B. Provide liquid-filled secondary substation transformers as indicated on drawings.

Similar documents
SECTION to 5000 AMPERE PLUG-IN AND FEEDER BUSWAYS - SPECTRA. A. Low-Voltage Plug-in Busway to 5000 ampere, 600 VAC

SECTION SECONDARY UNIT SUBSTATIONS

SECTION SECONDARY UNIT SUBSTATIONS

NORTHWESTERN UNIVERSITY PROJECT NAME JOB # ISSUED: 03/29/2017

Houston First Corporation Package 1 SECTION MEDIUM VOLTAGE FUSED SWITCH INTERRUPTER

A. Section includes busway and fittings including plug-in units.

SECTION MEDIUM VOLTAGE TRANSFORMERS

SECTION SECONDARY UNIT SUBSTATIONS SECONDARY LESS THAN 1000 V

SECTION LOW-VOLTAGE TRANSFORMERS

SECTION ENCLOSED BUS ASSEMBLIES

PRIMARY UNIT SUBSTATIONS SECONDARY 1000 V AND ABOVE SECTION SECTION

SECTION BUSWAYS

Capital Projects Group Liquid Filled Transformer Specification

SECTION METAL-ENCLOSED BUS MEDIUM VOLTAGE

A. This Section includes the following types of dry-type transformers rated 600 V and less, with capacities up to 1000 kva:

SERIES 800 / 810 SPECIFICATION 15KV & 25KV PADMOUNTED LIQUID-INSULATED VACUUM LOAD INTERRUPTER ASSEMBLIES

SECTION ENCLOSED BUS ASSEMBLIES

1 29SEP03 ALL General update with miscellaneous changes in entire document.

FIELD TEST AND OPERATIONAL CHECK SECTION A. Refer to Section 16010, Electrical General Requirements.

BUSWAY LOW VOLTAGE (POW-R-WAY III) SECTION SECTION 16466

Unit Substation Transformer Construction Checklist (under 500 kva)

SECTION MOTOR CONTROL CENTER

SECTION 16496A MTS MANUAL TRANSFER SWITCH (MANUAL CONTROL ONLY) Note to Spec Writer: { } Denotes EATON Feature reference number

A. Provide a complete Distribution Panelboard system as indicated on the drawings, and as specified herein.

roduct Scope: Substation

POWER TRANSFORMER INSTALLATION

SUGGESTED SPECIFICATION for Low Voltage (600V) Generator Paralleling Switchboard

A&E Standards Electrical Substations & Transformers Division 26 Electrical

Point Eight Power, Inc. Switchgear Specification Low Voltage UL 1558 Metal-Enclosed Switchgear

UFGS (August 2010) UNIFIED FACILITIES GUIDE SPECIFICATIONS

UNIFIED FACILITIES GUIDE SPECIFICATIONS

ADDENDUM NO. 1 BID AND CONTRACT DOCUMENTS FOR. BID No. 2019PW299

SECTION REQUIREMENTS FOR ELECTRICAL INSTALLATIONS

DISTRIBUTION TRANSFORMER SPECIFICATION #

56-SDMS-01 REV. 01 SPECIFICATIONS FOR

Low Voltage Switchgear Construction Checklist (under 500 kva)

MANUFACTURING TECHNICAL INSTRUCTIONS SAFETY Subject: DESIGN, MAINTENANCE AND INSPECTION OF SECONDARY ELECTRICAL DISTRIBUTION SYSTEMS

UNIFIED FACILITIES GUIDE SPECIFICATIONS

Equipment Specifications Low Voltage. Active Harmonic Filter

SECTION HEAT TRACING FOR PLUMBING PIPING

SECTION HEAT TRACING FOR PLUMBING PIPING

Important Considerations for Specifying MV Mining Switchgear Western Mining Electrical Association Edmonton, Canada June 13, 2008

UNIFIED FACILITIES GUIDE SPECIFICATIONS. Use for Southeast projects only **************************************************************************

SECTION LOW-VOLTAGE SWITCHGEAR

SECTION GENERAL MOTOR REQUIREMENTS FOR HVAC AND STEAM GENERATION EQUIPMENT

UNIFIED FACILITIES GUIDE SPECIFICATIONS

ELECTRICAL INSPECTION BULLETIN (Effective )

PLANNING GUIDE FOR SINGLE CUSTOMER SUBSTATIONS SERVED FROM TRANSMISSION LINES

SECTION PARK NON-SEGREGATED BUS SPECIFICATION

16300 HIGH VOLTAGE DISTRIBUTION

UNIVERSITY OF WASHINGTON Facilities Services Design Guide. Electrical. Medium Voltage Switchgear. Basis of Design.

NORTHWESTERN UNIVERSITY PROJECT NAME JOB # ISSUED: 03/29/2017

SPECIFICATION FOR SIMPLEX SWITCHBOARDS

CONSOLIDATED EDISON COMPANY OF NEW YORK, INC. 4 IRVING PLACE NEW YORK, NY DISTRIBUTION ENGINEERING NETWORK SYSTEMS SECTION

B. Accept materials on site in original factory packaging, labeled with manufacturer s identification.

SECTION AIR TERMINAL UNITS

SECTION A. NEC Compliance: Comply with NEC as applicable to installation and construction of electrical power/distribution transformers.

ENGINEERING SPECIFICATION

LOW-VOLTAGE SERVICE ENTRANCE SWITCHBOARDS SECTION D

1.0 In addition to the requirements previously presented herein, each specification shall contain the following general information:

Title: YALE OFFICE OF FACILITIES PROCEDURE MANUAL Chapter: 01 - Yale Design Standard Division: Electrical Standards

SECTION GROUNDING AND BONDING FOR ELECTRICAL SYSTEMS

PIKES PEAK PARKING RESTORATION TABLE OF CONTENTS

S. C. Electric Cooperative s Specification for a Single-Phase, Two Bushing Overhead Distribution Transformer (Revised 10/2013)

SPECIAL SPECIFICATION 6499 Environmentally controlled Communications Building

NORTH HARRIS COUNTY REGIONAL WATER AUTHORITY. Section AUTOMATIC CONTROL VALVE INSULATED ENCLOSURE (HOT BOX)

CLARK PUBLIC UTILITIES TECHNICAL SPECIFICATIONS SINGLE-PHASE PADMOUNTED TRANSFORMERS

This section applies to the requirements for electrical Inspection, calibration, and testing.

SECTION AUTOMATIC TRANSFER SWITCH

SECTION PART 1 GENERAL

SECTION FIBERGLASS REINFORCED PLASTIC (FRP) ENCLOSURE

SECTION ELECTRIC FOUR FOLD DOORS MODEL 46 FLAT SHEETED

37-SDMS-01 REV. 03 SPECIFICATIONS FOR

SECTION GROUNDING

DIVISION MEDIUM VOLTAGE VAULT DESIGN Contents MEDIUM VOLTAGE VAULT DESIGN... 2 DIVISION LIST OF FIGURES...

DIVISION MEDIUM VOLTAGE VAULT DESIGN Contents

SECTION FIELD PANELS

SECTION (16071) - VIBRATION AND SEISMIC CONTROLS FOR ELECTRICAL SYSTEMS

SECTION PACKAGED, SUBMERSIBLE, DRAINAGE PUMP UNITS

SECTION WIRE, CABLE AND BUSWAYS. A. This section specifies providing wire, cable and busways.

Section 70 Airport Transformer Vault and Vault Equipment (FAA L-109)

Bus Facility

SECTION COOLING TOWER

A. All materials shall be tested and listed by an OSHA approved Nationally Recognized Testing Laboratory (NRTL).

This guide can be used to prepare a specification for incorporating wall bracket jib cranes into a competitively bid construction project.

6. SECONDARY SERVICES (under 600 volts) 6.1 AVAILABILITY For the electrical characteristics of available secondary services see Section 3.4.

CONTENTS. B. System Design and Performance Requirements

MIRUS International Inc.

1.05 Power System Fault and Coordination Study with Arc Flash Calculations

Ground Fault Protection. Medium Voltage Artificial Neutrals

SECTION BASIC ELECTRICAL REQUIREMENTS

1. Telecommunications mounting elements. 2. Backboards. 3. Telecommunications equipment racks and cabinets. 4. Grounding.

SECTION The specification section is organized by placing information in three standard parts:

SECTION AIR COILS

DIVISION 16. Electrical Specifications

The Next Step In The World Of Transformers

SECTION INFLUENT EQUALIZATION TANK PUMPS

SECTION METAL FRAMED SKYLIGHT. A. Engineering, preparation of fabrication drawings and structural calculations for the entire skylight system.

The Medical Center Company Electrical System Installation Requirements

Transcription:

SECTION 26 12 13 PART 1 - GENERAL 1.01 WORK INCLUDED A. Comply with the provisions of Sections 26 05 00. B. Provide liquid-filled secondary substation transformers as indicated on drawings. 1.02 RELATED SECTIONS A. Division 03: Concrete B. Section 26 05 13: Medium Voltage Cable C. Section 26 13 19: Medium Voltage Vacuum Interrupter Switchgear D. Section 26 13 16: Medium Voltage Fusible Interrupter Switchgear E. Section 26 24 13: Switchboards F. Section 26 23 00: Low Voltage Switchgear G. Section 26 25 00: Enclosed Bus Assemblies H. Section 26 24 19: Motor Control Centers 1.03 REFERENCES A. The integral distribution center liquid-filled secondary substation transformer and protection devices in this specification shall be designed and manufactured according to latest revision of the following standards (unless otherwise noted). B. ANSI/IEEE C57.12.00, Distribution, Power, and Regulating Transformers, General Requirements for Liquid-Immersed. C. ANSI/IEEE C57.12.90, Test Code for Liquid-Immersed Distribution, Power and Regulating Transformers and Guide for Short-Circuit Testing of Distribution and Power Transformers. D. ANSI/IEEE C57.98, Impulse Tests, Guide for Transformer (Appendix to ANSI/IEEE C57.12.90). E. ANSI/NFPA 70, National Electrical Code. F. ASTM D877 - Test Method for Dielectric Breakdown Voltage of Insulating Liquids Using Disk Electrodes. G. DOE Part III 10 CFR 431, Energy Conservation Program for Commercial Energy: Distribution Transformers Energy Conservation Standards. 1.04 SUBMITTALS A. Comply with Division 01. B. Product data and spare parts list. Include all ratings, weights, sound ratings, and cable terminal data. 26 12 13 - Page 1

C. Outline, nameplate, connection diagrams and other shop drawings on transformer. Include front elevations, plan views, dimensions, and conduit entry/exit locations. D. Installation and operating instructions, maintenance, troubleshooting and repair procedures and technical literature pertaining to all components or instruments provided. E. A certified test report containing minimum information per IEEE C57.12.91 Appendix. F. DOE Part III 10 CFR Part 431 compliance certificate 1. Dimensioned Outline Drawings of Equipment: Identify center of gravity, and locate and describe mounting and anchorage provision. 2. Anchorage Devices: Detailed description of equipment anchorage devices on which the certification is based and their installation requirements. 3. Qualification Data: for Professional Engineer and Testing Agency. Professional Engineer must be registered in the state of [ ]. G. Where applicable, provide the following additional information: 1. Busway connection data. 2. Connection details between close-coupled assemblies. 3. Composite plan view and elevation view of close-coupled assemblies. 4. Kick interlock scheme drawing and sequence of operation. 1.05 SYSTEM DESCRIPTION A. Transformers that supply predominately loads with VFDs or other highly harmonic type loads shall be "K" factor type of the proper rating. B. Transformer shall be [indoor] [outdoor] secondary unit substation type from incoming line terminals to outgoing feeder terminals. C. Primary terminations shall be side-wall mounted for [close-coupling to medium voltage switchgear.] [cable connections in air-filled terminal chambers.] D. Secondary terminations shall be side-wall mounted for [close-coupling to low voltage switchgear.] [busway or cable connections in air-filled terminal chambers.] 1.06 PROJECT RECORD DOCUMENTS A. Maintain an up-to-date set of above documents. Note any and all revisions and deviations that are made during the course of the project and provide record copy to the owner. 1.07 OPERATION AND MAINTENANCE DATA A. Comply with Division 01. B. Provide installation, operation and maintenance procedures to owner. C. Submit operation and maintenance data based on factory and field testing, operation and maintenance of specified product. 1.08 QUALITY ASSURANCE (QUALIFICATIONS) A. Manufacturer shall have specialized in the manufacture and assembly of integral distribution center liquid-filled secondary substation transformer for 20 years. 26 12 13 - Page 2

B. Transformer shall comply with all referenced documents and standards listed within this section. C. Installation shall comply with National Electrical Code, National Electrical Safety Code, EPA regulations, and all local and state codes and regulations. 1.09 DELIVERY, STORAGE, AND HANDLING A. Deliver, store, protect, and handle products in accordance with recommended practices listed in manufacturer's Installation and Maintenance Manuals. B. Inspect and report concealed damage to carrier within specified time. C. Store in a clean, dry space. Maintain factory protection or cover with heavy canvas or plastic to keep out dirt, water, construction debris, and traffic. (Heat enclosures to prevent condensation.) 1.10 PROJECT CONDITIONS (SITE ENVIRONMENTAL CONDITIONS) A. Follow industry standard practices before, during and after liquid filled secondary substation transformer installation. B. Liquid-filled secondary substation transformer shall be located in areas away from hazardous materials. Ambient temperature of area will be between minus 30 and plus 40 degrees C. 1.11 WARRANTY A. Manufacturer warrants equipment to be free from defects in materials and workmanship for greater of 1 year from date of installation or 18 months from date of delivery. 1.12 FIELD MEASUREMENTS A. Make all necessary field measurements to verify that equipment shall fit in allocated space in full compliance with minimum required clearances specified in National Electrical Code. PART 2 - PRODUCTS 2.01 MANUFACTURER A. Approved manufacturers are: 1. Eaton 2. Siemens 3. Square D 4. Cooper Power Systems 5. ABB 2.02 EQUIPMENT A. Refer to drawings for: actual layout and location of equipment and components; current ratings of devices, bus bars, and components; voltage ratings of devices, components and assemblies; and other required details. 26 12 13 - Page 3

2.03 PRIMARY (INCOMING / LINE) SECTION A. Where indicated on the drawings, the transformer shall have one integrally mounted air-filled primary terminal compartment with [pothead] [clamp-type terminals] [compression type terminals]. Refer to the drawings for specific wire size and type. The terminals shall be [radial feed] [loop feed] [a combination of radial feed and loop feed]. 1. A set of [station] [intermediate] [distribution] class, [3.0] [6.0] [9.0] [15] [18] KV surge arrestors shall be mounted inside terminal compartment. 2. A set of surge protection capacitors sized by manufacturer for optimum performance with surge arrestors shall be mounted inside terminal compartment. B. Where indicated on the drawings the transformer shall have an air-interrupter switch with [pothead] [clamp-type terminals] [compression type terminals]. Refer to the drawings for specific wire size and type. The terminals shall be [radial feed] [loop feed] [a combination of radial feed and loop feed]. 1. A set of [station] [intermediate] [distribution] class, [3.0] [6.0] [9.0] [15] [18] KV surge arrestors shall be mounted inside terminal compartment. 2. A set of surge protection capacitors sized by manufacturer for optimum performance with surge arrestors shall be mounted inside terminal compartment. 3. The primary switch shall be kirk key interlocked to the secondary main device such that access to fuses is prevented unless secondary main is open. C. Where indicated on drawings the transformer shall have a double air-interrupter switch with [pothead] [clamp-type terminals] [compression type terminals]. Refer to the drawings for specific wire size and type. The terminals shall be [radial feed] [loop feed] [a combination of radial feed and loop feed]. 1. A set of [station] [intermediate] [distribution] class, [3.0] [6.0] [9.0] [15] [18] KV surge arrestors shall be mounted inside terminal compartment. 2. A set of surge protection capacitors sized by manufacturer for optimum performance with surge arrestors shall be mounted inside terminal compartment. 3. The primary switch shall be kirk key interlocked to the secondary main device such that access to fuses is prevented unless secondary main is open. 2.04 TRANSFORMER SECTION A. Furnish liquid filled secondary substation transformers as indicated in drawings. 1. Standard transformer oil meeting requirements of ANSI C7.106 and ASTM D-3487, with a high dielectric strength, free from impurities, and with a high flash point. 2. Fire Resistant Hydrocarbon Fluid, (FRHF) which is non-toxic. It shall be listed as a lessflammable fluid meeting the requirements of National Electrical Code 450-23 and the National Electrical Safety Code Section 15. It shall have a minimum fire point of 300 degrees C. It shall be R-TEMP or equivalent. 3. The insulating fluid shall be BioTemp, Envirosafe or EnviroTemp or equal environmental friendly type fluid. It shall be listed as a less-flammable fluid meeting the requirements of National Electrical Code 450-23 and the National Electrical Safety Code Section 15. It shall have a minimum fire point of 300 degree C. 4. Silicone liquid polymer with a viscosity of 50 centistokes at 25 degree C, a minimum fire point of 300 degree C, and an oxygen index of 21. It shall meet the requirements of the National Electrical Code 450-23 and the National Electrical Safety Code Section 15. B. General Construction 1. Transformer shall be liquid-filled construction. It shall be designed and manufactured in accordance with ANSI C57.12.00 latest revision. 2. Transformer shall be constructed of high-grade, grain oriented, silicon steel laminations, with high magnetic permeability. Magnetic flux density is to be kept well below the 26 12 13 - Page 4

saturation point. Core construction shall include mitered joints to keep core losses, excitation current and noise level at a minimum. 3. Coils shall be neatly wound under tension, utilizing adhesive-coated electrical grade insulating paper between LV and HV layers and between LV and HV windings. 4. Sealed tank construction shall be furnished, with cooling radiators welded or bolted to tank walls. Tank shall be leak tested after vacuum filling. 5. Secondary substation transformer tanks shall have side wall mounted bushings with flanges for connection to switchgear or air terminal compartments. 6. For units 750 KVA and above, the tank size, radiators and bushings shall be sized for the future forced air cooled rating. C. Ratings 1. Transformers shall be rated as indicated on the drawings. 2. The average winding transformer temperature rise shall be [65 degree C] [55 degree C] [55/65 degree C]. 3. The transformer primary Basic Impulse Rating shall be as indicated on the drawings and at a minimum of 60 KV BIL for 5 KV system voltages and a minimum of 95 KV BIL for 15 KV system voltages. 4. Fan cooling [OA Rating only] [Provide provisions for installation of future fan cooling, OA/FFA Rating] [shall consist of 120/240 VAC cooling fans with automatic control] for increased capacity of 15 percent {750-2000 KVA} or 25 percent {2500 KVA and larger} - OA/FA Rating {includes liquid temperature indicator}]. D. Standard features 1. Windings shall be [Copper] [Aluminum]. 2. Transformer primary shall have four 2-1/2 percent full capacity taps, two above and two below rated nominal voltage. Taps shall have an externally operated manual tap changer for use only when transformer is de-energized. Tap changer shall have provision for padlocking. 3. Corrosion resistant diagrammatic nameplate. 4. Provisions shall be provided for lifting and jacking the unit into place. 5. A base suitable for rolling and skidding parallel to centerline shall be provided. 6. A ground pad shall be located on the high voltage and low voltage end of enclosure. 7. The unit shall be a 60 hertz design. 8. [55] [65] [55/65] degrees C average winding rise ratings. 9. Pressure-vacuum gage 10. Hand hole on cover 11. Drain valve and sampling device 12. Top filling connection 13. Liquid-level gage (with alarm contacts) 14. Dial-type thermometer (with alarm contacts) E. Accessories 1. Pressure relief device 2. Fault pressure relay 3. [120 VAC Space Heaters] [120 VAC Space Heaters with Thermostat] [240 VAC Space Heaters] [240 VAC Space Heaters with Thermostat]. 4. Neutral grounding resistor rated as indicated on the drawings. F. Loss Evaluation 1. A loss evaluation report [is not required] [from the factory shall be provided] for each unit shall be provided and shall be factory certified as to the information]. 2.05 SECONDARY (OUTGOING / LOAD) SECTION 26 12 13 - Page 5

A. Where indicated on the drawings, the transformer shall have one integrally mounted air-filled secondary terminal compartment with [clamp type terminals] [compression type terminals]. Refer to the drawings for specific wire size and type. B. Where indicated in the drawings, the transformer shall have an integral transition section which shall allow a close couple connection to the [secondary low voltage switchgear] [secondary switchboard] [secondary motor control center]. See appropriate specification section for equipment. C. The connection to the secondary low voltage equipment shall be made by [copper flex-braid] [aluminum flex-brand] [solid copper bars] [solid aluminum bars] [copper wire] [aluminum wire]. 2.06 FINISH A. The tank paint finish shall be neat clean and highly resistant to corrosion. Metal surfaces shall be thoroughly cleaned of all foreign matter prior to painting. Finish shall be ANSI 61 gray paint. 2.07 TESTING A. Each transformer shall receive all standard commercial tests in accordance with ANSI C57.12.90, latest revision, with test results available by transformer serial number upon request. B. Complete ANSI design test data shall be available on the transformer, including short circuit testing, available on request. C. The following special tests shall be performed on each transformer in accordance with applicable ANSI standards {indicate desired tests}: 1. Impulse test on the high voltage winding 2. Temperature test at self-cooled rating 3. Temperature test at maximum cooled rating PART 3 - EXECUTION 3.01 EXAMINATION A. Verify that liquid-filled secondary substation transformers are ready to install. B. Verify field measurements are as [shown on Drawings] [instructed by manufacturer]. C. Verify that required utilities are available, in proper location and ready for use. D. Beginning of installation means installer accepts conditions. 3.02 INSTALLATION A. Install per manufacturer's instructions. B. Install on concrete pad sized as recommended by the manufacturer. C. Install an oil spill containment system as required by EPA regulations. D. Install required safety labels including arc flash information. 3.03 FIELD TESTING 26 12 13 - Page 6

A. Field testing shall be performed as recommended by NETA, the manufacturer, and/or electrical testing specifications. B. Test dielectric liquid to ASTM D877, using 25,000 volts minimum breakdown voltage, after installing transformer and before energizing it from system. C. Inspect installed transformers for anchoring, alignment, grounding and physical damage. D. Check tightness of all accessible mechanical and electrical connections with calibrated torque wrench. Minimum acceptable values are specified in manufacturer's instructions. 3.04 ADJUSTING A. Adjust all circuit breakers, switches, access doors, operating handles, etc for free mechanical and/or electrical operation as described in manufacturer's instructions. B. Adjust primary taps so that secondary voltage is within 2 percent of rated voltage. 3.05 CLEANING A. Clean interiors of switchgear, switchboards, panels, MCCs, and separate enclosures to remove construction debris, dirt, shipping materials. B. Repaint scratched or marred exterior surfaces to match original finish. END OF SECTION 26 12 13 - Page 7