Medium Term Scenarios for Electricity Supply/Demand Balance

Similar documents
Medium Term Scenarios for Electricity Supply/Demand Balance

Update on the Power System and the Build Programme: A Presentation to the Media

Dose reduction initiatives at the Koeberg Nuclear Power Station ISOE ALARA Symposium. Marc Maree Corporate Specialist (Radiation Protection)

State of the Power System. Mr Paul O Flaherty Finance Director 16 February 2012

State of the Power System Current Situation and Future Prognosis

INTEGRATED RESOURCE PLAN FOR ELECTRICITY REPORT

4 NEED AND DESIRABILITY FOR THE PROJECT

Medium-term System Adequacy Outlook 2017 to 2021

State of the Power System Quarterly Update. Winter Outlook. 5 June Collin Matjila Interim Chief Executive

MEDIUM-TERM SYSTEM ADEQUACY OUTLOOK to 2021

Role of Eskom in SA context

Eskom Power Plant Engineering Institute (EPPEI) Prof Louis Jestin EDF EPPEI Senior Manager EDF-Eskom France

1. Background. 2. Introduction

System Status Briefing

Eskom Briefing Parliament s Portfolio Committee on Energy. 16 September 2014.

Future wind deployment scenarios for South Africa

Ian Curry Managing Director BR Energy South Africa

ESKOM S FINANCIAL CRISIS AND THE VIABILITY OF COAL-FIRED POWER IN SOUTH AFRICA

Residential Heat Pump Rebate Programme

7-8 NOVEMBER 2018 CAPE TOWN, SOUTH AFRICA

THE FUTURE OF COAL: EXISTING POWER STATIONS CONSIDERATIONS FOR NEW STATIONS. Brett Cohen sti!s Power Sector Workshop 5 March 2013

AHTR Project Status (PBMR Restart)

Feasibility of the WWF Renewable Energy Vision South Africa

NERT Update. October2009

STRATEGIC CONTEXT FOR ENERGY PLANNING CHAPTER 2

GOVERNMENT NOTICE DEPARTMENT OF ENERGY REQUEST FOR COMMENTS: DRAFT INTEGRATED RESOURCE PLAN 2018

The cost and greenhouse gas emissions implications of the coal IPP procurement programme

OVERVIEW OF ELECTRICITY DEMAND AND SUPPLY SITUATION. Public meeting 29 November 2004 Braamhoek Road EIA

Eskom Revenue Application. Multi-Year Price Determination (MYPD 4) FY2019/ /22

SOUTH AFRICA. IEA DSM 41 st EXCo Meeting. 25 April 2013

Eskom Holdings Ltd. Coal Presentation: A Presentation to the Portfolio Committee on Public Enterprises. 28 January 2010

The Future of Electricity: A Market with Costs of Zero? Marginal

South African IPP Procurement Programme. December 2016

The Greening of Energy. Eskom s role in the Renewables Industry in South Africa

DURBAN INVEST Presentation by Eskom

The Future of Electricity: A Market with Costs of Zero? Marginal

SOUTH AFRICAN COAL ROADMAP

Transmission Ten-Year Development Plan (Public Version)

Impact of stranding power and coal mining assets in South Africa. Tara Caetano Date: 15 June 2016 TIPS Annual Forum: Energy Utilisation

Are Eskom s concerns relating to Renewable Energy Independent Power Purchase Agreements valid?

PLANNING FOR TODAY, TOMORROW, AND THE FUTURE. P. 1

INTEGRATED RESOURCE PLAN UPDATE ASSUMPTIONS, BASE CASE RESULTS AND OBSERVATIONS REVISION 1

Title of presentation

Strategic Grid Network Study

Electricity generation technology choice: Costs and considerations

Towards a New Power Plan

Concentrating solar power and renewable energy policy instruments

Contribution of Renewables to Energy Security Cédric PHILIBERT Renewable Energy Division

Maximising the potential of Energy Efficiency and Demand Side Management in South Africa

High-renewables scenarios Thought experiments for the South African power system

Economic impacts of South Africa s energy mix

Financial Costs and Benefits of Renewables in South Africa in February 2015

Source: regional government planning documents, official forecasts

International trade what lies in store for global hard coal trade & what fundamentals will drive developments?

Impact of localised Energy Efficiency (EE) and Renewable Energy (RE) on Ekurhuleni s finances over the next 10 years Report.

Impact of localised Energy Efficiency (EE) and Renewable Energy (RE) on City of Cape Town s finances over the next 10 years Report.

Operating High Variable, Renewable Generation Power Systems Lessons Learned from Ireland and Northern Ireland

ELECTRICITY SUPPLY INDUSTRY OF SOUTH AFRICA

(How) can the European power market be decarbonized to 2050, without CCS? Lasse Torgersen CenSES årskonferanse Oslo 7/

Eskom Interim Results for the six months ended 30 September 2011

Title of presentation

Technical considerations for integration of distributed renewables on the grid

Large-scale rollout of Concentrating Solar Power in South Africa

Meeting the Challenge of Climate Change

Overview of the South Africa s Independent Power Producers Procurement Programme

How much more renewable energy should we aim for? Philip Lloyd Professor Energy Institute, CPUT Cape Town, South Africa

UK Future Energy Scenarios. Richard Smith Future Transmission Networks Manager

SOUTH AFRICA POWER MARKET OUTLOOK TO MARKET TRENDS, REGULATIONS AND COMPETITIVE LANDSCAPE

The changing African utility landscape - African Utility Week

Capacity reserves until 2025: declining, but sufficient

The Kendal May to September 2015 monthly reports show specific instances, 37 in total, of violations of licenced PM 10 limit values.

Hydropower as Flexibility Provider: Modeling Approaches and Numerical Analysis

ERCOT Public LTRA Probabilistic Reliability Assessment. Final Report

F e b Des Muller Chairman for NIASA Supply Chain Development Subcommittee

POWER-SYSTEM-WIDE ANALYSIS OF THE BENEFITS OF RESERVE PROVISION FROM SOLAR PHOTOVOLTAICS IN SOUTH AFRICA

Advanced Power Plant Flexibility

Power System Status Update

African Utility Week Eskom s s Cogeneration Project. Thursday 31 st May, 2007

Powering the Future. Knowledge, Technology, Interaction African Utility Week. Silas Mzingeli Zimu C.E.O. Suzlon Wind Energy SA

Revenue Application FY2018/19

Challenges. Operational excellence back to basics in the operation and maintenance of power plants

Evolution of the Grid in MISO Region. Jordan Bakke, David Duebner, Durgesh Manjure, Laura Rauch MIPSYCON November 7, 2017

Increasing renewables share in Turkey s power system

ELECTRICITY AND MINING IN SOUTH AFRICA

The Integrated Resource Plan (IRP) was promulgated in March 2011;

The post-2020 Cost-Competitiveness of CCS Cost of Storage. Dr. Wilfried Maas Carbon Capture Manager Shell

I 5 Corridor Analysis Phase 1 Report

Positioning Nelson Mandela Bay for Renewable Energy Manufacturing Opportunities

ERLN Meeting. Renewable Energy and Energy Efficiency. Wolfgang Böhmer. Eskom: Grid Access Unit

RESEARCH REPORT. An assessment of new coal plants in South Africa s electricity future

The South African Renewable Energy Independent Power Producers Procurement Programme (REIPPPP) Lessons Learned

ESKOM S FINANCIAL CRISIS AND THE VIABILITY OF COAL-FIRED POWER IN SOUTH AFRICA IMPLICATIONS FOR KUSILE AND THE OLDER COAL-FIRED POWER STATIONS

COULD LOAD SHEDDING REOCCUR?

2017 Long-term Outlook. Information Session July 25, 2017

Electricity Supply. Monthly Energy Grid Output by Fuel Type (MWh)

CONCENTRATED SOLAR POWER POTENTIAL OVERVIEW

Observations on variations in grid carbon intensity

Transcription:

Medium Term Scenarios for Electricity Supply/Demand Balance The Sustainable Energy Seminar Corrie Visagie 6 October 2010

Table of Contents Key assumptions : Demand & Supply Medium Term Outlook: Demand vs Supply MYPD2 Additional Contingencies Defining the Problem : Quantification of the Energy Gap Nature of the Problem : Demand vs. Energy The Impact of Price Elasticity Implications if GAP not closed Proposed solutions to close the GAP Key Messages 2

Best Renewable Energy? Time magazine of 12 January 2009 claimed that it does not seem as if the most obvious, perfectly clean, remarkably cheap, surprisingly abundant and immediately available renewable energy resource is properly embraced yet in the world (and particularly in South Africa.) 3

Best Renewable Energy? The Time Magazine report continues. This resource has outstanding potential to reduce carbon emissions that threaten the planet, and unlike coal and petroleum, it doesn t pollute; unlike solar and wind, it doesn t depend on the weather, unlike nuclear, it doesn t raise uncomfortable questions on radioactive waste storage, It doesn t take a decade to build and it has been proven. This energy source is called ENERGY EFFICIENCY! 4

The Case for Energy Efficiency Security of Supply Challenges Energy Efficiency is a Common Solution Renewables major challenge is on the financials Financial Challenges Environmental Challenges 5

Background Current reality In recent years, South Africa s electricity supply system has come under severe pressure: Due to limited new generation capacity, the power system reserve margin has reduced to unacceptable levels The availability of generation plant has reduced because of the requirement to run them harder and the lack of space for essential maintenance The power system will remain under pressure until new baseload power stations come on line. The recent economic slowdown has provided temporary relief However electricity demand has recovered to 2008 levels There is no clear industry acceptance on the extent of the problem There still seems be some level of apathy amongst key stakeholders Lack of urgency from policy/decision makers to deal with the problem New Inter-Ministerial Committee structure may be better equipped to deal with the challenges Joint Emergency Response and Business Continuity technical task team set up recently between business/industry/eskom/doe to support IMC 6

SUPPLY VS DEMAND ANALYSIS

Key Assumptions Demand The demand projection excludes the effects of: - Demand Side Management - Co-Generation - Solar Water Heating Price elasticity will have a delayed impact on demand which will not significantly reduce demand over the critical next 3 years Demand is based on a GDP ranging from 3 to 5% for the period 2010 to 2014 There is an additional recovery of demand in 2010 due to smelters ramping up to full capacity after the economic recession Unconstrained growth allowed for new connections 20 MVA

Key Assumptions Supply ESKOM Build Country Options Grootvlei Komati Medupi Kusile Ingula Sere MSBLP Nuclear Regional DoE OCGT OCGT MTPPP1 REFITT Wind REFITT Other Other Total New Build System Capacity MW MW MW MW MW MW MW MW MW MW MW MW MW MW MW MW MW 2009 570 202 0 0 0 0 0 0 0 0 0 0 0 0 0 772 44157 2010 380 303 0 0 0 0 0 0 0 0 0 168 0 175 30 1056 45213 2011 0 404 0 0 0 0 0 0 0 0 0 168 200 150 55 977 46190 2012 0 0 738 0 0 100 0 0 0 1020 0 84 200 0 0 2142 48332 2013 0 0 738 0 666 0 0 0 0 0 0 0 0 0 0 1404 49736 2014 0 0 1476 723 666 0 0 0 1858 0 0 0 0 0 0 4723 54459 Base Load Coal Energy Availability Factor : Scenario s of 86% and 84% Expensive Base Load Station Load Factor : 50% Open Cycle Gas Turbines Gross Load Factor : 6% Energy Utilisation Factor : 95%

Build Programme Project Summaries: Medupi, Kusile & Ingula JOH-ESK021-20100118-YB-P1 Medupi Kusile Ingula Project Summary Greenfields Project Lephalale (Limpopo Province) 6 Unit Coal Fired Power Station Planned capacity 4,764MW Financial & Economic Impact Projected project cost to completion ~R125.5bn Estimated 95% impact on Lephalale town GDP ~ 70% contracts awarded Project Schedule Construction commenced March 2007 First Unit planned to be handed over April 2012 Subsequent Units at 8 month intervals thereafter Last Unit planned for handover during August 2015 Project Summary Greenfields Project Delmas (Mpumalanga Province) 6 Unit Coal Fired Power Station Planned capacity 4,800MW Financial & Economic Impact Projected project cost to completion ~R141.5bn Estimated 25% impact on Delmas town GDP ~ 41% contracts awarded Project Schedule Construction commenced Mid 2008 First Unit planned to be handed over June 2014 Subsequent Units at 8 month intervals thereafter Last Unit planned for handover during October 2017 Project Summary Greenfields Project Ladysmith (KwaZulu Natal Province) 4 Unit pumped storage power station Planned capacity 1,352MW Financial & Economic Impact Projected project cost to completion ~R21.8bn Estimated 1% impact on Ladysmith town GDP ~ 75% contracts awarded Project Schedule Construction commenced Mid 2006 First Unit planned to be handed over January 2013 Subsequent Units at 3 month intervals thereafter Last Unit planned for handover during November 2013 SOURCE: Eskom Build Programme; 30 April 2010 Project Assurance Reports 10

Build Programme Project Summaries: RTS, Transmission & Other JOH-ESK021-20100118-YB-P1 Return to Service Transmission Other Projects Summary Refurbishment and return to service of previously moth-balled coal fired power stations in Mpumalanga. Camden (8 units total 1,600MW), Komati (9 units 1,000MW), Grootvlei (6 units - 1,200MW) Financial and Economic Impact Projected RTS cost to completion ~ R26.8bn Project Schedule All 8 units at Camden power plant are now in commercial operation 2 units, each rated at 125MW, have been commissioned at Komati power station. Last unit (unit 1) planned for handover August 2012. 3 units, each rated at 200MW (total 600MW) have been commissioned at Grootvlei. Last unit (unit 6) planned to be completed end August 2010. Project Summary Transformers 20 600 MVAs: 765kv (Planned: 12,000 MVAs) Cape Grid (Planned: 1,500 MVAs) Northern Grid (Planned: 3,500 MVAs) Central Grid (Planned: 3,600 MVAs) Transmission Lines 3,977.5 Km: 765kv (Planned:1,689.9 km) Northern Grid (Planned: 1,253.6 km) Cape Grid (Planned: 621 km) Central Grid (Planned: 413 km) Project Schedule (Projected completion dates) 765kv: (Mar 2012) Northern Grid: (Nov 2016) Central Grid: (Sept 2012) Cape Grid: (Dec 2012) Projects Summary - Refurbishment Major refurbishment of existing and operational power stations in Mpumalanga, comprising Duvha, Matla, Kriel and Arnot (300MW capacity increase) Project Summary - Tubatse Greenfields 1,500MW pumped storage scheme near Steelpoort (Limpopo Province) Project on hold subject to funding being obtained Project Summary Majuba Rail Rail infrastructure for coal supply for the operational Majuba power station in Mpumalanga Awaiting revised schedule as per the outcome of the World Bank decision. Project Summary Sere Greenfields pilot windfarm project on the West Coast (WC province) Awaiting revised schedule as per the outcome of the World Bank decision. SOURCE: Eskom Build Programme; 30 April 2010 Project Assurance Reports 11

Medium term outlook MYPD2 Baseline Energy Supply /Demand Balance on 86% and 84% EAF with Alcan excluded 300 Energy in TWh 290 280 270 260 Forecast Energy Demand (Alcan excluded) Forecast Energy Demand (Alcan excluded, SWH included) Forecast Energy Demand (Alcan excluded, 5 yr DSM included) Original MYPD 86EAF Supply 250 240 Forecast Energy Demand (Alcan excluded) Forecast Energy Demand (Alcan excluded, SWH included) Forecast Energy Demand (Alcan excluded, 5 yr DSM included) 250.42 258.58 265.44 273.17 279.75 249.61 257.35 263.74 271.14 277.72 249.59 256.40 261.38 266.96 270.97 Original MYPD 86EAF Supply 257.46 263.60 265.73 280.61 296.10 Revised MYPD 86EAF Supply 257.23 262.58 264.53 273.71 290.28 Revised MYPD 84EAF Supply 254.92 258.58 259.87 270.06 285.08 * Multi-Year Price Determination, December 2009 2010 2011 2012 2013 2014 Year Revised MYPD 86EAF Supply Revised MYPD 84EAF Supply 12

Additional contingencies to MYPD2 Baseline Demand Management solutions need to provide sufficient contingency in the supply / demand forecast to mitigate risk associated with: - Reduced performance levels of current generation plant - Possible delays in the delivery of the new large power stations (Medupi & Kusile) - Higher than anticipated demand - Possible delays in the delivery of non-eskom generation options In addition, the contingency will ensure opportunities for: - Additional space for maintenance of generation plant - Minimising the overall cost to the consumer by avoiding excessive usage of OCGT s - Growth in electricity consumption, including large new projects Although there is a current 5TWh annual energy surplus, the system remains tight. It will therefore be appropriate to ensure that this buffer be maintained and planned for into the future

Additional contingencies to MYPD2 Baseline The following are key supply and demand assumptions that on aggregate will ensure sufficient contingency over and above what was allowed for in the MYPD2: - Allow for extended delivery dates of Eskom base load stations : assume delivery dates of 2013 and 2015 for Medupi and Kusile respectively - Plan for an energy availability factor of 84% (rather than 86%) to allow for sufficient space for maintenance - Apart from MTPPP, exclude all other non-eskom generation options in the period until 2014 - Postponement of the 1020MW DoE OCGT from 2012 to 2014 - The MYPD2 sales assumptions allow for sufficient contingency and remains as-is - Maintaining the current 5TWh annual energy buffer into the future Sufficient contingency will reduce the risk to the systems and build buffer to manage future pressure on the system

Defining the Problem Quantification of the Energy Gap MYPD2 Additional Contingencies 300 300 290 290 280 Demand: Reference 285.08 280 Demand: Reference 279.75 273.17 279.75 273.17 270 260 250.42 258.58 258.58 265.44 259.87 270.06 270 260 250.42 258.58 265.44 Additional Buffer Energy Gap 258.63 270.31 250 254.92 Supply: 84% EAF 250 249.69 252.25 250.86 Supply: 84% EAF Delay 240 240 2010 2011 2012 2013 2014 2010 2011 2012 2013 2014 2010 2011 2012 2013 2014-4.5 0 5.6 3.1-5.3 Initial Gap (TWh) 2010 2011 2012 2013 2014-4.3 1.3 9.6 9.5 4.4 Gap 0.7 6.3 14.6 14.5 9.4 + Buffer 15

Defining the Problem Nature of the problem: Energy vs Demand 300 Energy 55 Capacity 290 280 270 260 250.42 250 249.69 240 2010 Energy Required 258.58 252.25 265.44 Additional Buffer 2011 250.86 2012 273.17 Energy Gap 258.63 279.75 270.31 Supply Available 2013 2014 GW 50 45 45.58 45.01 46.50 41.36 40 40.23 38.84 35 Capacity Required 47.17 51.45 Capacity Reserve 44.78 42.83 Supply Available 2010 2011 2012 2013 2014 2010 2011 2012 2013 2014 Gap -1.7% 0.5% 3.6% 3.5% 1.6% +Buffer 0.3% 2.4% 5.5% 5.3% 3.4% Initial Gap (Reserve) 2010 2011 2012 2013 2014 15.9% 13.3% 12.4% 10.1% 14.9% Energy Availability rather than Capacity is the challenge! 16

Energy vs Demand Eskom Power System Hourly Demand 35000 30000 Demand (MW) 25000 20000 15000 10000 Actual Sent out 23 March 2010 Actual Sent out 16 March 2010 Actual Sent out 09 March 2010 Very flat profile during the day indicating energy rather than peak demand problem (Tuesdays selected) 5000 0 Note: Winter profile is more peaky 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24

Implications if the Gap is not closed National Implications The electricity supply system will be under severe pressure, posing a risk to Security of Supply Using open cycle gas turbines to mitigate the risk is expensive, ultimately increasing the price of electricity It will not be possible to connect large customers, negatively affecting economic development South Africa s sustainability, reputation and competitiveness will be negatively affected Pressure to reduce supply to neighbouring countries could have negative political implications Further reputational damage to government and the electricity industry Lost opportunity to unlock economic efficiencies through more efficient use of electricity 18

Proposed Solutions to close the GAP Most Supply-side solutions are being pursued, but they are Too late Expensive Not enough money allowed for in the approval of Eskom s price application (MYPD2) Demand-side solutions are more readily available in the Short term Less expensive Strong business case Strong case for both as they complement each other

The Impact of Price Elasticity What is Price (&Income) Elasticity Price elasticity of electricity demand measures the sensitivity of consumption to changes in price Income elasticity of electricity demand measures the sensitivity of consumption to changes in income Key Findings* Electricity demand is fairly inelastic to price changes in the short term, but will see a longer term impact Electricity demand is sensitive to short term changes in income/commodity prices Likely Impact on Eskom The MYPD2 price increases could reduce demand for electricity, but probably not immediately and will most likely be delayed beyond the critical period of 2012/13 Favourable economic conditions could result in a quick increase in demand prior to the critical period, neutralising the impact of price elasticity Price elasticity will not provide demand reductions over and above the current demand management initiatives such as DSM - Initiatives such as DSM are enabling mechanisms to realise the price elasticity reductions Resolution There is a high level of uncertainty regarding the impact of price elasticity It should not be seen as a bankable solution for the critical period in 2012/13 The long term implications need to be carefully monitored *Refer to study performed by Eskom Treasury, 2009 20

Suite of Energy & Demand Related Solutions Options Savings : Energy Savings : Demand Easy Implementation Bankability Economic Implications Eskom Control Cost to Eskom External Dependencies Risks Focus Mass Market DSM Individualised Customer Energy Management DSM (Solar Water Heating) Communications (incl Power Alert) Energy Efficiency and behavioural change initiatives provide deep energy solutions Internal Energy Efficiency Demand Market Participation Utility Load Manager Advanced Metering Infrastructure Predominantly Demand Response initiatives with secondary energy efficiency benefits ECS : Energy Conservation Scheme Risk Mitigation solution Favourable Problematic/Negative Impact Intermediate 21

Remaining Gap If all the Demand related solutions are successful, there will still be a remaining gap over the next 3 to 5 years. The only remaining workable solution that has the ability to close the gap with the least impact on the economy, is the Energy Conservation Scheme (ECS) There is growing support that ECS be positioned as a safety net for the industry The ECS will provide the appropriate pricing signal for investment in energy efficiency and supply options with customers, such as co-generation, self generation and renewable generation

Key Messages South Africa has moved from a period of abundant, cheap electricity to a situation of looming shortages of supply and rising electricity prices The shortage of electricity will probably last for at least 5 years and urgent decisions need to be taken to address this potential crisis All generation options have largely been identified and are expensive, however need to be pursued for MT and LT solutions Demand management options, specifically energy conservation and efficiency is the least cost, best environmentally friendly short term solution to address a number of challenges facing South Africa Creation of space for generation maintenance and new connections More time available for new generation decisions Positive impact to contain electricity price increases Positive impact on the environment All South Africans need to focus on energy efficiency to contribute to the solution 23

Thank you The cheapest kwh is the one that you don t t use!