PJM Technical Guidelines for. Installation of Synchrophasor Measurements at. Generation Facilities

Similar documents
Industry Solution. Real-time Historian for Synchrophasor Data Management

Standard PRC-002-NPCC-01 Disturbance Monitoring

Jetstream Certification and Testing

Introduction to Jetstream

International ejournals

Innovation & Grid Modernization at ComEd. Laura García García Grid Strategy & Analytics Commonwealth Edison

Information Document Service Proposals and Cost Estimating ID # R

Facility Interconnection Requirements

Siemens Power Technologies International. Bridging the Gap Enterprise Model Management for Operation and Planning

Enhancing Power Grid Reliability through Synchrophasor Measurements

SCHEDULE 12 Transmission Enhancement Charges. Establishment of Transmission Enhancement Charges.

POTOMAC ELECTRIC POWER COMPANY

PJM Manual 14A: New Services Request Process Revision: 20 Effective Date: October 1, Prepared by Interconnection Planning Department

COST ALLOCATION POLICY FOR VICTORIAN TERMINAL STATIONS NEGOTIATED TRANSMISSION SERVICES

Energy Processing for Smart Grid (4.4)

Generator Assessment & Roles During A Restoration

Energy Management System (EMS)

Peak Time Demand Management Using Distributed Solar Inverters

Collaborative Approach for Wind Power Plant Model Data and Validation

Transmission Competitive Solicitation Questions Log Question / Answer Matrix Delaney to Colorado River 2014

Hydro-Quebec s experience with HYPERSIM Real-time Power System Simulator

Con Ed/PSEG Wheel Replacement Proposal A joint white paper from the New York Independent System Operator and PJM Interconnection

TPL Transmission System Planned Performance for Geomagnetic Disturbance Events

Minimum Transmission Design Standards f or Competitive Upgrades Rev 2

MOD Data for Power System Modeling and Analysis

Standard EOP System Restoration from Blackstart Resources

Planification du réseau, exploitation et gestion : nouvelles approches dans la recherche

Technology, Innovation and Information at Fingrid Kari Suominen, CIO

Lesson Learned Loss of Wind Turbines due to Transient Voltage Disturbances on the Bulk Transmission System

Protection Settings: Calculating, Administering and Testing ADMO at Energinet.dk

FRCC 2007 SYSTEM OPERATOR TRAINING SEMINARS. Reliability Coordinator Processes and Tools

Fixed Demand (Block Demand) The utility company sends a signal to synchronize the start of the Maximum Demand period.

Requirements for the Provision of Load Shedding Service for Import Version 4.0

PSS E. High-Performance Transmission Planning Application for the Power Industry. Answers for energy.

Paper No: 14PESGM1876. Prof. James A. Momoh, PhD, FIEEE, FNSE, FNAE, FAS Howard University

Water & Energy Consulting Lon W. House, Ph.D.

PJM Transmission Replacement Processes Senior Task Force COST ALLOCATION & COST RECOVERY Educational Session. June 3, 2016

California Independent System Operator Corporation Fifth Replacement Electronic Tariff

Analytics Are Just the Tip of the Iceberg How the PI System Revolutionizes Asset Management

2B. Performance Advantages of Alerton BACnet. 1. Alerton Overview

Frontier Telephone Companies TARIFF FCC NO. 13 Original Page 18-1 ACCESS SERVICE

Top Five Reasons to Implement Distributed Bus Protection

Enterprise Asset Management for Power System Protection. Enterprise Protection Information System

PRESENTS A RFID THE JANUS* GATE: RFID TERMINAL SYSTEM FOR CONTAINERS CCCCCONTAINERS CONTAINERS RFID NEPTUNESEAL * CONTAINER BOLT SEAL

MOD Steady-State and Dynamic System Model Validation

ONCOR INTERCONNECTION APPLICATION AND PROCESS FOR DISTRIBUTED RESOURCES

Fundamentals of Transmission Operations

Frontier Telephone Companies TARIFF FCC NO. 14 Original Page 16-1 FACILITIES FOR INTERSTATE ACCESS

Committed Offer: Offer on which a resource was scheduled by the Office of the Interconnection for a particular clock hour for the Operating Day.

Enabling GIS in Distribution Utility for Energy Audit and Load flow analysis

Standard TPL Transmission System Planning Performance Requirements

TOGAF - The - The Continuing Story Story

POLOPOLY V9 TECHNICAL OVERVIEW. System Architecture Templates and Presentation Modules

Modeling of the Dynamic Behavior of the Island Power System of Cyprus

The STS Prepayment Standard TID rollover in 2024 managing the change

Volatility Prediction and Management by Active Network Management & Future Generation Management. Siemens, Sept 8 th 2017

Manual No. 010 Business Practices Manual Network and Commercial Models

Smart Grid Concept, Applications and Lessons Learned from Recent Deployments

LOAD SERVING ENTITIES PJM REGION

Multi-Agent Model for Power System Simulation

Job Descriptions. Title & Job Functions: Transmission Function Employees

WEBINAR SERIES #4 EPC/RFID STANDARDS AND RFID STUFF YOU NEED TO KNOW

Analyzing Event Impacts using PI Event Frames and Versify

C2-304 INTEGRATED INFORMATION SYSTEM FOR THE SIEPAC REGIONAL ELECTRICITY MARKET

n Real-world Case Study of how LIPA are using a Model-Driven approach, leveraging an Enterprise Semantic Model (ESM) to:

Public Policy and Multi-Driver Projects. RPPTF August 10, 2012

Incremental Black Start RFP Response Template & General Information

PRODUCT CONFORMITY CERTIFICATE

safe reliable affordable GENERATOR COMPLIANCE MONITORING PROGRAM REQUIREMENTS 1 21 September 2015 TITLE: PREPARED BY: SYSTEM ANALYSIS & SOLUTIONS

Improving Protection System Reliability With Automatic NERC PRC-005 Testing and Reporting

Analysis of Three Recent Blackouts

The Alcatel-Lucent Integrated Control and Management System

Section 1 : About the Resource Database

The Smart Grid UTILITY CONTROL CENTER UTILITY CUSTOMER T H E S M A R T G R I D. data management. utility communications.

SENTRON Powermanager. SENTRON Powermanager. Identifying hidden potential for energy optimization and savings. Answers for industry.

EMS of the Future. EMS Users Conference Chicago, Illinois. John McDaniel September 20, Proprietary 1 Experience you can trust.

Two Settlement PJM /06/2016

Effects of Wide-Area Control on the Protection and Operation of Distribution Networks

Image-Based Item Processing Solution

Reference report Oil & Gas

Smart Metering End-to-End Solutions from the Meter Data Management System to the Meter

PRINCE2 - Project Initiation Documentation

Oracle Siebel CRM On Demand Integration Pack for JD Edwards EnterpriseOne (Opportunity to Cash)

Queue Management. A look at queue reform and. Jennifer Heintz and Janet Wheeler June 12, 2012

DA concept for higherquality. supplies. 24 ABB Review 4/1996

Totalflow software systems

Power Technologies International. Industry Perspective on GIS Integration: Challenges, Solutions, Benefits and Case Studies

Session Number: 5 Proactive Remote Service Support

Asset Optimization and Condition-Based Maintenance (CBM) Improving Reliability and Quality

Power Plant Model Verification using PMUs

HYDRO AND ELECTRIC ENERGY REGULATION

Laboratory Information Management System Index

the most promising locations for new renewables in the Imperial CREZ.

Restoration of the Besor-Hebron-Be'er Sheva Stream. A Transboundary Project Supported by the JNF Parsons Water Fund

Understanding Your Enterprise API Requirements

Research and Application Study on Accident-Based 3D Power Station Simulation Technology

First Data EFTPOS. User Guide. 8006L2-3CR Integrated PIN Pad

AdvOSS Interconnect Billing

Business Practice. Contents

PJM ARR and FTR Market

Transcription:

PJM Technical Guidelines for Installation of Synchrophasor Measurements at Generation Facilities

Introduction The technical requirements and guidelines presented here are for reference to aid new generation facilities in early planning to design and install synchrophasor measurement system that is compliant and interoperable with PJM. The requirements are consistent with the governing text in the PJM Tariff 1 and PJM Manuals 2. These requirements and guidelines can be used for initial plans, which should then be shared and reviewed with PJM during the Interconnection process. This document is comprised of three main sections: 1. Technical Specifications, which detail the required measurements, networking, protocols, data storage, and other details pertinent to the design of the synchrophasor system. Items that are preferred but not strictly required are identified as preferred. The preferred items are in addition to the base requirements, not a replacement of the requirements. 2. Example One-line Drawings and Point Lists, which illustrates a typical generation electrical drawing indicating PMU measurement location for a traditional generator and solar farm facility. Required and preferred measurements and related equipment are color coded. Additional guidance is also provided. 3. Naming Convention, which explains the PJM naming convention for the phasor data station and channel naming. The resulting names will be configured into the site PMUs. The PMU registry template will typically be provided as part of this package. The registry template will be filled out by the site with PJM s assistance, and included in the PJM Phasor Registry, which will make future maintenance and administration easier. 1 PJM OPEN ACCESS TRANSMISSION TARIFF, Effective Date 12/28/2013, Section 8.5.3 2 PJM Manual 01: Control Center and Data Exchange Requirements, current R30, Section 3.3

Technical Specifications The technical requirements and guidelines below are for reference to aid new generation facilities in early planning to design and install synchrophasor measurement system that is compliant and interoperable with PJM. The requirements are consistent with the governing text in the PJM Tariff 1 and PJM Manuals 2. These requirements and guidelines can be used for initial plans, which should then be shared and reviewed with PJM during the Interconnection process. Specifications noted as required must be satisfied, specifications noted as preferred are not required but add additional operational value and should be satisfied wherever possible. Measurement Point Required: PMU(s) shall measure at the Customer Facility low-side of each generator step-up transformer, unless it is a non-synchronous generation facility in which case the PMU(s) shall measure at the Customer Facility side of each Point of Interconnection. Preferred: Additional measurement point at any Point of Interconnection (usually high-side of a main step-up transformer). Note: With both low-side and high-side measurements, the impact of GMD on the transformer (reactive power as a function of GIC flow) can be monitored. Measured Phases Required: Voltage and current Signals are required to be streamed to PJM as the Positive Sequence component. Actual measurement of all 3 phases is required for calculation of Positive Sequence. Preferred: Separate phase current and voltage measurements (each phase as a separate Signal), stored locally. Note of Interest: Separate phase measurements are valuable for handling power phase balance problems. Signals Measurement Coordinate System Scan Rate Required: For each measurement point: Voltage, Current, Voltage Angle, Current Angle, Frequency, df/dt (rate of change of frequency). Required: All phasors must be reported in polar coordinates. Required: 30 samples per second, streaming to PJM PDC client. Preferred: 60 samples per second, only stored locally (per the Local Storage Compression preferred storage). Note of Interest: The accuracy of PMU-based Generator Model Validation improves significantly with 60 samples/sec data. 1 PJM OPEN ACCESS TRANSMISSION TARIFF, Effective Date 12/28/2013, Section 8.5.3 2 PJM Manual 01: Control Center and Data Exchange Requirements, current R30, Section 3.3

Network Interface Required: TCP/IP traffic. Configurable IP address (or equivalent NATing) and listening port number. Firewall to allow connection from PJM client. Note of Interest: At some Facilities the PJMnet circuit that supports the ICCP SCADA or DNP SCADA data between PJM and the Facility will also support the C37.118 Synchrophasor data. If there is a Market Operation Center or Control Center separate from the Facility that already has a PJMnet circuit installed, then the customer may be required to connect between the site PMU/PDC and a Market Operation Center or Control Center PDC. Network design should be part of the review process with PJM Interconnection Coordination. Data Protocol Required: C37.118-2005 communicating via TCP/IP. Preferred: C37.118.2-2011 communicating via TCP/IP. PDC Required: A local PDC for data concentration, data storage, and support of PJM C37.118 connection. Note: A PDC is often useful for data concentration, ease of data storage, and as a gateway for applications using phasor data. The PDC may be located at the facility or at the corresponding control center. A control center that operates more than one facility with PMUs would concentrate all facility PMUs at the CC PDC. Other architectures are considered on a case by case basis. Local Storage Amount Required: Storage amount - 30 days-worth of rolling local data storage of all Signals. Preferred: Storage amount additional storage up to 90 days-worth of rolling local data storage of all Signals. Local Storage Compression Required: Storage compression - data storage preserving lossless 30 samples per second. Preferred: Storage compression data storage with additional granularity preserving lossless 60 samples per second.

Example One-Line Drawing and Point List, Synchronous Generation To Utility Preferred Required Bus POI 10 9 6 8 5 7 GPS Antenna Main GSU Main GSU Clock Aux Load Aux Load 2 4 PMU PMU 1 3 Gen Unit 1 Gen Unit 2 Site Data Network Site or MOC/CC PDC to PJM PDC over PJMnet

# Measurement Description Signal 1 Unit 1 low side Current Magnitude and phase angle (positive seq.) 2 Unit 1 low side Voltage Magnitude and phase angle (positive seq.) 3 Unit 2 low side Current Magnitude and phase angle (positive seq.) 4 Unit 2 low side Voltage Magnitude and phase angle (positive seq.) 5 Unit 1 high side Current Magnitude and phase angle (positive seq.) 6 Unit 1 high side Voltage Magnitude and phase angle (positive seq.) 7 Unit 2 high side Current Magnitude and phase angle (positive seq.) 8 Unit 2 high side Voltage Magnitude and phase angle (positive seq.) 9 Site POI line Current Magnitude and phase angle (positive seq.) 10 Site POI line Voltage Magnitude and phase angle (positive seq.)

Example One-Line Drawing and Point List, Non-synchronous Generation (Solar, Wind, etc.) To Utility Bus POI 5 Preferred Required 6 4 3 Main GSU GPS Antenna Clock Aux Load 2 PMU Site or MOC/CC PDC Site Data Network 1 to PJM PDC over PJMnet

# Measurement Description Signal 1 Low side Current Magnitude and phase angle (positive seq.) 2 Low side Voltage Magnitude and phase angle (positive seq.) 3 High side Current Magnitude and phase angle (positive seq.) 4 High side Voltage Magnitude and phase angle (positive seq.) 5 Site POI line Current Magnitude and phase angle (positive seq.) 6 Site POI line Voltage Magnitude and phase angle (positive seq.)

Additional Guidance Many devices already incorporated in the typical generator facility design, for example protective relays, can often also serve as a PMU. These devices will often already be connected to the necessary Potential Transformers and Current Transformers. In some cases, only relatively minor changes will have to be made. These changes may include additional configuration of the device, installation of a PDC, and local data storage. The number of PMUs or physical location of the PMU is not strictly set by PJM requirements. A PMU can have one, many, or all of the required measurements, depending on the device capabilities and connected instrument transformers. First consider the required measurement points per these guidelines, and then select the best set of devices to obtain those measurements. For network Quality of Service (QOS), prioritize SCADA data over PDC data. Validate the final GPS coordinates of the PMU prior to providing the information to PJM. Ensure a strong GPS signal to the clock by using a shielded coax antenna and (for example) Schweizer SEL/Arbiter clock. Ensure firmware is kept up to date on all involved systems and assets. This helps prevent operational issues, such as logic on handling leap seconds, as well as provides the latest security enhancements.

Naming Convention The C37.118 data protocol used to send and receive synchrophasor data has specific built-in fields for identifying measurements. This naming and identification data will typically be configured in each PMU and automatically passed downstream to all PDCs and data clients. There are two configuration parameters; STN or Station Name and CHNAM or Channel Name. The Station Name is the name of substation and PMU identifier. A single substation can commonly have more than one PMU. Each PMU will generally have several data points, or CHNAM channels. All STN and CHNAM can be a maximum of 16 characters (bytes) long. The PMU owner must use appropriate one-lines, facility names, substation names, or identifying information to determine the STN and CHNAM names. The STN used should be based on the B1 station name in PJM s EMS model. This information can be provided by PJM. PJM has a naming convention for STN and CHNAM that defines all characters. That convention is detailed in this document and explained by example here, with two channels under a single station. STN, Station Name Example: AAG_GOODRIVR_01 AA is an example identifier of the transmission zone the asset is located in. The two-letter identifier for every transmission zone in PJM is provided in the Company Identifier in STN tab in the PMU registry template file. AAG_GOODRIVR_01 The G character designates that the PMU is owned by a generation company. The other option for this character is T, which designates that the PMU is owned by the Transmission Owner. AAG_GOODRIVR_01 GOODRIVR is an example STN name. STN names shorter than 9 characters are acceptable and should not be padded for length. The STN name should be based on the B1 value associated with this generator in the PJM EMS model. The STN name should begin and end with an underscore. AAG_GOODRIVR_01 A PMU identifier number, starting at 01 and increasing to the number of PMUs at the station. CHNAM, Channel Name Example: Frequency signals may simply be named Frequency, and Status signals may simply be named Status. For Voltage and Current signals, the following convention should be followed: T013GEN1_1V1 T06901BROADST_1I1 The first character designates the location of the measurement point and should be one of the following values:

Character A B D L T Description Non-phasor analog Bus Digital Line Transformer T013GEN1_1V1 T06901BROADST_1I1 The next three digits state the nominal voltage level at the measurement in kv, padded with zeroes at the front if below 100kV. Decimals should be rounded to the nearest whole number. For example, 12.5 kv should be rounded to 13 kv. T013GEN1_1V1 T06901BROADST_1I1 Up to the next 9 characters should describe the equipment being measured. For voltage signals and transformer current signals, this should be the B3 equipment name from the PJM EMS model. For line current signals, this should be the STN name representing the station at the opposite end of the line, and should be based on PJM s EMS model. STN names shorter than 9 characters are acceptable here and should not be padded. The STN name must be terminated with a single underscore character. T06901BROADST_1I1 Following the underscore, a single digit number must be included and will be an incremental counter number used to differentiate multiple signals that measure the same piece of equipment. For example, a single PMU monitoring the line current of two parallel transmission lines will use this identifier. In most scenarios, this will be 1. T06901BROADST_1I1 Finally, the type of measurement is identified here, with most importantly V1 and I1 meaning positive sequence voltage and positive sequence current respectively. Note that within the C38.118 protocol this will include magnitude and angle. There are other identifiers for generic digital or analog data, if needed.