RS32 Multi-Section Skylight System under/over seam clip double diverter

Similar documents
INSTALLATION INSTRUCTIONS for MP-RC1 TWO PIECE CONSTRUCTION TO BE INSTALLED ON COMPLETED ROOF DECK

YCW 250 I-Beam Curtain Wall System Installation Manual

KS SERIES - VERTICAL INSTALLATION

238T and 138T Panel and Accessories Price List 9/29/2017 (price good for shipments through 11/31/2017) Customer Job Date Sales Rep 238T PANEL ITEM #

SWING DOOR SPECIFICATION

CEILING & WALL SYSTEMS

Kingspan Day-Lite Klick

200 / 300 SERIES PANELS COLD STORAGE

Assembly Instruction wedi Fundo Floor element

Pella 250 Series. Wood Frame Construction with Vinyl Siding... V250-ID-888 Wood Frame Construction with Brick Veneer...

NUCOR VR 16 II STANDING SEAM ROOF SYSTEM TABLE OF CONTENTS

Roof Accessories. Division Roof Hatches Roof Safety Rails Safety Posts. Division Smoke Vents

Roof Replacement. Notes: T-1 (Title Sheet) Roof Key Plan Russell House Student Union 1400 Greene Street Columbia, South Carolina 29208

Duracast Pressure Plate Installation Instructions

TEST REPORT. Rendered to: ALL WEATHER ARCHITECTURAL ALUMINUM Vacaville, California. SERIES/MODEL: 6000 PRODUCT TYPE: Aluminum Awning Window

Assembly Instruction. wedi Fundo Primo Shower System

BioPrism Solid Surface

General. 2. Design. 3. Anchor Bolts And Foundations. 4. Drawings. 5. Structural Framing. 6. Roof Covering Nucor Classic Roof Panel

Architectural Single-Hung Aluminum Window Series L701T SH-AW130 GUIDE SPECIFICATION

ARCHITECTURAL TESTING, Inc. Code Compliance Research Report #0774 CCRR-0131

Prior to ordering and installing materials, all dimensions should be verified by field measurements.

Canopy Assembly Instructions: Post-Supported Super Lumideck (2 3/4" Interlocking deck, 6" Fascia)

ATI Evaluation Service A Division of Architectural Testing Certification Services

Casement Windows Montecito New Construction Window

Assembly Instruction. wedi Fundo Primo Steam Shower System

NOVABRIK MORTARLESS CONCRETE BRICK VENEER SPECIFICATION. MASTERFORMAT SECTION (Mortarless Concrete Brick Veneer)

SECTION SLOPED TRANSLUCENT METAL SKYLIGHT SYSTEM

Awning Windows Montecito New Construction Window

ELEVATION FOR DETAIL REFERENCE ONLY

Trench Duct Class Catalog 5230CT9601R10/08

AXIOM Indirect Light Coves

3275 & 3275U, 3285 & 3285U Vertical Sliding, Double-Hung Windows

Smarter. Safer. Leaner.

Louis Armstrong New Orleans International Airport NOAB Project # North Terminal Development Program Phase 1

B. Polyethylene samples shall be submitted for Owner approval of color and quality.

Thin Brick Façade. Façades Installation Guide

SECTION DIRECTORIES

OmniFlex 300 Plus Installation Instructions

Se incluyen las instrucciones en español

Maximum thermal performance ISOLEREN INSULATED METAL PANELS INSTALLATION GUIDE

Modular CABANA Kit 16 x 16 (6x6) Lumber: Western Red CEDAR #1 (Cabinet) Shingles: 5X / 16" long / 1/2" thick or 16 oz. copper

YES SSG TU Vent Window System

Lithia Dodge East 5500 L St. Omaha, NE

7520 Casement Windows

ASTM C 1363 Thermal Performance Test Report

Liner Replacement Instructions:

How do you install yours?

Picture/Radius Windows Montecito New Construction Window

SECTION MANUFACTURED ROOF EXPANSION JOINTS

PRE-ENGINEERED METAL BUILDINGS

Guardian-Lok. Standing Seam Roof System THIS MANUAL APPLIES TO GUARDIAN-LOK SYSTEMS. GUARDIAN-LOK REQUIRES PANEL SIDELAPS TO BE MECHANICALLY SEAMED.

NCMA TEK TEK 19-5A FLASHING DETAILS FOR CONCRETE MASONRY WALLS

SOLAR SHADING SYSTEMS - Manual Solar Shade SECTION ROLLER WINDOW SHADES

Pittsburgh Corning ProVantage Glass Block Installation System Assembly Instructions

ROOF MOUNT KIT OWNERS MANUAL

SECTION (Master Template Final-05) ELECTRICAL BOXES. A. Provide boxes for electrical equipment and wiring devices as follows:

PRODUCT SPECIFICATION SERIES 9000 WINDOW WALL THERMALLY BROKEN ALUMINUM CASEMENT / AWNING / FIXED WINDOW

Modular Buildings. Installation Manual

VELUX America Inc. SPECIFICATION FOR MODEL FS NO LEAK FIXED SKYLIGHT SECTION UNIT SKYLIGHTS

PROJECT LOCATION SECTION COPPER METAL PLATE WALL PANELS

B. Shop Drawings: For metal lockers. Include plans, elevations, sections, details, and attachments to other work.

Senergy Platinum CI Stucco Typical details for an impact resistant cement plaster stucco system featuring Neopor GPS Plus Rigid Insulation Board

ELEVATION FOR DETAIL REFERENCE ONLY

5. AMCA 301 Method of Publishing Sound Ratings for Air Moving Devices. 6. AMCA 500 Test Methods for Louver, Dampers, and Shutters

WARRANTY PROVIDER ACCEPTED A REFERENCE GUIDE OF TYPICAL RAINSCREEN WALL AND WINDOW DETAILS

Axiom Building Perimeter System

Brava Spanish Tile. Installation Manual. Brava Roof Tile Phone: Fax:

This Installation Guide uses the following symbols to indicate important information. Always observe the instructions indicated by these symbols.

STEP UP SHOWER BASE INSTALLATION GUIDE FOR TIMBER AND CONCRETE FLOORS

Architectural Testing ASTM E283, ASTM E330, ASTM E331 TEST REPORT. Report Number: C Rendered to: Tubelite Inc.

INSULATED PANEL OVERVIEW

Planning and installation instructions

Series 510-I Thermal Heavy Commercial Projected Window

Metal Roof Panels

PRODUCT CONTROL SECTION DEPARTMENT OF REGULATORY AND ECONOMIC RESOURCES (RER)

Alply CLASSIC WALL Architectural Insulated Panel Wall System

MAKE ROOFS LAST LONGER

SHEET METAL ROOF TEST REPORT

GroundTrac. Installation Manual

TRIAD CORRUGATED METAL, INC.

DIVISION: SPECIALTIES SECTION: DEMOUNTABLE PARTITIONS REPORT HOLDER: KRUEGER INTERNATIONAL, INC.

Insulating systems used in agricultural and industrial buildings

DRY SEAL INSTALLATION GUIDE

PLATON RUGGED, DIMPLED HIGH-DENSITY POLYETHYLENE (HDPE) MEMBRANE THAT KEEPS FOUNDATIONS AND FLOORING DRY ADVANCED TECHNOLOGY EASY INSTALLATION

Cladding Attachment Solutions for Exterior Insulated Commercial Walls

Vinyl Windows and Doors

PATENTS ARE PENDING. Building Dimensions. Exterior Dimensions Roof Edge to Roof Edge

Attached Solar Greenhouse Plans for a solar heated greenhouse attached to your home

ACCESSORIES TABLE OF CONTENTS

Central Dartmouth Section Exterior Envelope Renovations METAL-CLAD WOOD DOORS Page 1 of 5 Dartmouth, NS

Fusion Welded, Maintenance Free, All Vinyl Frame and Sash Construction Energy Efficient ¾ Insulated Glass Standard Available Sizes: (Tip to Tip Frame

Product Data Sheet. Product: Benchmark Wall Liner System

SECTION EXPANSION CONTROL

INSTALLATION INSTRUCTIONS. Wall Sleeve Kit. For Use With MGE/MCE/MHP Series Magic-Pak Unit

ALLMET CONTINENTAL INSTALLATION GUIDE

GOWANDA, NEW YORK SEPTEMBER 18, 2008 ARCH PROJECT NO

Reflective Insulation Specification & Application Guide for Post Frame and Metal Building Construction

Proper Installation of Insulated Metal Wall Panels

Mounting instructions. novotegra for trapezoidal metal - roof parallel

Shower & Spa System Solutions. Innovation. System. Quality.

Transcription:

INSTALLATION INSTRUCTIONS RS32-x RS32 Multi-Section Skylight System under/over seam clip double diverter www.rnssales.com sales@rnssales.com 805.375.3980 Fax 805.375.3981

SKYLIGHT ACRYLIC skyline series 32 vertical standing seam roof RS32-X 0.070 Extruded Aluminum Frame Shim One Piece Aluminum Curb FIGURE 1: CROSS SECTION Neoprene Gaskets 10 x 3/4 Fastener White Impact Modified Acrylic Prismatic Inner Dome Oversized Condensate Gutter Optional Fall Protection Screen Poured & De-bridged Thermal Break Clear Impact Modified Acrylic Prismatic Outer Dome 12 x 1-1/4 Fastener 14 x 1-1/2 Fastener Shim Bright White Metal Liner Vertical Seam Roof Panel Downslope 15-1/16 33-1/8 15-13/16 Double Dome Prismatic Glaze-Clear over White 64 SEAM PATTERN A Optional Fall Protection Screen 15-13/16 33-1/8 64 15-1/16 Upslope Edge of Flange Slides Under Roof Upslope Diverter Backer Plate FIGURE 2: RS32 KIT SEAM PATTERN B CONSTRUCTION 0.080 Aluminum Under/Over Fully Welded & Assembled Curb 0.070 Extruded Aluminum Thermally Broken Skylight Frame 2 Rigid Vertical Insulation with Liner 1/8 x 1 Neoprene Gasket Seals Skylight Frame Clear, 100% Impact Modified Acrylic Prismatic 0.177 Outer Dome White, 100% Impact Modified Acrylic Prismatic 0.118 Inner Dome 2-1/2 Triple Bead Mastic Tape, Polyurethane Sealant #5 Tek Shoulder Screws Long-Life Self Drillers w/ Washers: 12-14 x 1-1/4 & 14 x 1-1/2 Long-Life Self Drillers w/o Washers: 12 x 1-1/4 & 10 x 3/4 Expansion Joint Covers with 1/4 Flanged Shoulder Spacers PERFORMANCE 70% Visible Light Transmittance with 100% Haze Factor 0.50 Solar Heat Gain Coefficient 0.65 U Factor or 1.54 R Value AAMA/WDMA/CSA 101/I.S.2/A440-08 OPTIONS 4 x 4 x 3/16 galvanized steel fall protection screen RS24 Custom Length Increments of 5 : Panel Offset Height: 3/8, 1-3/8, Custom Liner Height: 5-7/8, Custom Liner Base: 3, Custom Customer Date Model Quantity Project Name Roof Panel Panel Seam Pattern A or B Panel Offset Height 3/8 or 1-3/8 www.rnssales.com sales@rnssales.com 805.375.3980 Fax 805.375.3981

SKYLIGHT POLYCARBONATE skyline series 32 vertical standing seam roof RS32-X FIGURE 1: CROSS SECTION Clear Polycarbonate Outer Dome 0.070 Extruded Aluminum Frame Neoprene Gaskets 10 x 3/4 Fastener White Polycarbonate Inner Dome Oversized Condensate Gutter Poured & De-bridged Thermal Break 12 x 1-1/4 Fastener Shim One Piece Aluminum Curb Optional Fall Protection Screen 14 x 1-1/2 Fastener Shim Bright White Metal Liner Vertical Seam Roof Panel 15-1/16 33-1/8 15-13/16 64 Double Dome Glaze- Clear over White Downslope Backer Plate SEAM PATTERN A Optional Fall Protection Screen 15-13/16 33-1/8 64 15-1/16 Upslope Edge of Flange Slides Under Roof Upslope Diverter Backer Plate FIGURE 2: RS32 KIT SEAM PATTERN B CONSTRUCTION 0.080 Aluminum Under/Over Fully Welded & Assembled Curb 0.070 Extruded Aluminum Thermally Broken Skylight Frame 2 Rigid Vertical Insulation with Liner 1/8 x 1 Neoprene Gasket Seals Skylight Frame Clear, Polycarbonate 0.118 Outer Dome White, Polycarbonate 0.118 Inner Dome 2-1/2 Triple Bead Mastic Tape, Polyurethane Sealant #5 Tek Shoulder Screws Long-Life Self Drillers w/ Washers: 12-14 x 1-1/4 & 14 x 1-1/2 Long-Life Self Drillers w/o Washers: 12 x 1-1/4 & 10 x 3/4 Expansion Joint Covers with 1/4 Flanged Shoulder Spacers PERFORMANCE 70% Visible Light Transmittance with 100% Haze Factor 0.50 Solar Heat Gain Coefficient 0.65 U Factor or 1.54 R Value AAMA/WDMA/CSA 101/I.S.2/A440-08 OPTIONS 4 x 4 x 3/16 galvanized steel fall protection screen RS24 Custom Length Increments of 5 : Panel Offset Height: 3/8, 1-3/8, Custom Liner Height: 5-7/8, Custom Liner Base: 3, Custom Customer Date Model Quantity Project Name Roof Panel Panel Seam Pattern A or B Panel Offset Height 3/8 or 1-3/8 www.rnssales.com sales@rnssales.com 805.375.3980 Fax 805.375.3981

Parts List RS32 Skylight Domes & Screens 10 with normal frame 10 with batten frame one side 10 with batten frame two sides 5 with batten frame one side 10 safety screen 5 safety screen Skylight Curbs 10 complete curb 10 up slope curb section 10 down slope curb section 5 down slope curb section 10 intermediate curb section curb expansion joint cover pairs Curb Insulation & Liners 10 complete curb insulation set 10 intermediate curb insulation set 5 intermediate curb insulation set 10 complete curb insulation liner set 10 intermediate insulation liner set 5 intermediate insulation liner set Backer Channels & Battens Curb up slope backer channel Curb down slope backer channel Skylight frame batten channel Fasteners #5 1/4-14 x 1-1/4 Shoulder TEK 2 5/16 Hex Washer Head #12-14 x 1-1/4 TEK Longlife Hex Integral- Washer Head #14 x 7/8 TEK Longlife Hex Integral- Washer Head #12 x 1-1/4 TEK Longlife Hex Head Washered #10 x 3/4 TEK Longlife Hex Head Washered 1/4 Nylon Shoulder Spacer for Expansion Joint Safety Screen Clip Spaced 12 o/c Sealants 2-1/2 Triple Bead Tape Mastic Polyurethane Sealant 10 OZ Cartridge www.rnssales.com sales@rnssales.com 805.375.3980 Fax 805.375.3981

The Batten style system is dependent upon the seam orientation. There are two possible seam patters. Looking from the ridge, seam pattern A or seam pattern B. The system is not symmetrical, so it is important that the correct seam pattern is specified prior to ordering the skylights. SEAM PATTERN A 15-1/8 33-1/8 15-13/16 64 SEAM PATTERN B 15-13/16 33-1/8 15-1/8 64

The RS32 Skylight System is designed to be installed after the roof has been put in place. Do not remove roof clips where skylights cross purlins. The skylight system must be able to expand and contract with the roof sheeting. 1 The curb upslope flange is located near the upslope purlin. Reference the center line of the purlin top web for center of the opening. Remove 8 of the roof panel where the skylight will be installed. Purlin 2 For single 10 skylights, remove 116-1/2 of roof sheeting as shown below. For multiple skylight installations up to 50, follow the schedule below. For skylights exceeding 50, leave approximately 12 of sheeting in place (to be removed at a later time) to allow for coordination of ultimate curb and skylight lengths. Do not remove roof clips when crossing purlins. Clean the sheeting area and remove metal shavings. RS10 116-1/2 RS15 176-1/2 RS20 236-1/2 RS25 296-1/2 RS30 356-1/2 RS35 416-1/2 RS40 476-1/2 RS45 536-1/2 RS50 596-1/2 3 Purlin 2

3 Place the steel upslope backer channel, with the 1 notch facing into the opening as shown below, under the roof sheeting and onto the purlin. Fasten the channel with six #5 shoulder tek screws to allow for roof movement. UPSLOPE DIVERTER CRICKET 3 3 7 7 BACKER CHANNEL ALLOWS FOR ROOF MOVEMENT WHEN US- ING #5 SHOULDER TEK SCREWS IN SLOTS #5 SHOULDER TEK SCREW DOWNSLOPE BACKER CHANNEL ALLOWS FOR ROOF MOVEMENT WHEN USING #5 SHOULDER TEK SCREWS IN SLOTS

4 When installing a skylight greater than 10, secure the upslope curb, and side rails in place with locking pliers. Preserve a 1/4 nominal gap between all adjoining sections. Continue the process until all side rails have been secured. Mark a line matching the outline of the curb and siderails. DOWNSLOP UPSLOPE CURB ASSEMBLY UNDER ROOF PANEL MODEL RS32-20 ILLUSTRATED UPSLOPE

5 Remove the curb and clean the sealing surfaces. Place 2-1/2 of butyl sealant over the panel within the outline drawn in step 4. Place another 2-1/2 of butyl sealant over the leading edge of the curb. Run a 3/8 bead of polyurethane over all mastic surfaces. Prepare the seam clips and expansion joint face with mastic and polyurethane sealants and as shown below. DOWNSLOP UPSLOPE POLYURETHANE AROUND PERIME- 2-1/2 MASTIC SPLICE PLATE MASTIC & POLYURETHANE MODEL RS32-20 ILLUSTRATED

6 Install the curb with the leading edge under the roof panel and with the sides and downslope over the panel. Locate the downslope backer channel under the roof panel and downslope flange. The downslope mounting location must be within 12 of a purlin. If the curb is in multiple sections, the expansion joints should be set with a 1/4 gap. Secure all parts in place with locking pliers. Upslope and downslope flanges are secured with #12-14 1-1/4 long life integrated washered head self drilling fasteners at 4 centers so that the sealing washer is flat on the outside surface. Secure sufficiently so a small amount of sealant is exposed along the sides. Attach the seam clips and side rails with #14 7/8 long life integrated washered head self drilling fasteners, 6 on center on both sides of the seam clips. Caulk (with mastic and polyurethane) and secure splice plates if provided. Splice plates are secured using #14 7/8 self-drilling shoulder screws and flanged shoulder spacers to enable movement from roof expansion or contraction. DOWNSLOPE BACKER PLATE #14 7/8 HWHSD SPLICE PLATE SHOULDER SPACER UPSLOPE MODEL RS32-20 ILLUSTRATED

7 Remove the fiberglass insulation on the inside area, leaving a 2-3 perimeter The facing remains in place. Cut the insulation facing as shown below. INSULATION CUT LINE INSULATION FACING 8 Terminate the exposed facing in any of the following ways. Tape the exposed facing if necessary.

RS32 Skylight System 9 Install the side wall insulation and liner panels as shown. The insulation is notched to surround the remaining roof panel. The liner panel is placed over the insulation and fastened with self-drilling screws in the pre-punched holes. If safety screen is included, position as shown in step 10, and use the self drilling fasteners to secure the liner and safety screen assembly at the same time using the same pre-punched holes. GASKET #10 x 3/4 FASTENER SAFETY ALUMINUM CURB SHIM 10 LINER PANEL SAFETY SCREEN #14 x 1-1/2 FASTENROOF PANEL If the safety screen option is included, align the screen over the opening as shown. Using the clips, gasket, and fasteners provided, fasten a clip every 12 around the perimeter. See detailed clip positioning above. MODEL RS32-20 ILLUSTRATED

RS32 Skylight System 11 With the first two lengths of curbing installed, the first upslope skylight may be set. Starting at the upslope diverter, install the first RS32 skylight so it is centered on the curb and so it compresses the foam rubber gasket to the curb. If there is a 5 section, it is placed at the downslope position. The first skylight in the sequence is constructed with one short side having a reverse batten frame facing up. Position the skylight with the reverse batten facing downslope. Secure the upslope and sides of the skylight frame to the curb in pre-drilled holes with #12 1-1/4 self-drilling fasteners, shimming to avoid excessive stress on the skylight frame. Do not over tighten the fasteners. The first batten assembly centerline should be aligned with the curb splice centerline. If it is off center, add or subtract to the expansion joint gap (minimum gap is 1/8 ) on the next curb rail assembly as necessary. Once the first skylight is secure, another section of curb should be installed as described earlier in steps 4 thru 10. The next skylight module will be fitted with an upslope batten frame, and possibly a downslope frame (unless it is the last section). In preparation of installing the next skylight module, clean the batten surfaces, place 1-1/2 wide tape mastic over one batten, and apply a 1/4 bead of polyurethane sealant over both faces along the outboard perimeter as shown below. Butt the surfaces together assuring that some sealant emits from the joints. Use locking pliers to secure the bottom 1/2 of each batten. REVERSE BATTEN FRAME 1-1/2 TAPE MASTIC POLYURETHANE SEALANT

12 Fill the batten channel with a 1/2 bead of polyurethane, and place over the batten channels insuring the assembly is fully seated. With locking pliers squeezing the batten flanges in place, secure the assembly with four # 14 x 7/8 self drilling screws as illustrated below. Starting at the upslope diverter, install the RS32 skylight(s), centering the assembly, if multiple skylights are being installed. Secure the skylight frames to the base curbs with #12 x 1-1/4 selfdrilling fasteners provided. The screws should be located in the pre-drilled skylight frame holes and shimmed as necessary so as not to stress the frame. Do not over tighten the fasteners. For cold climate installations, you may place three strips of 1/4 x 1-1/2 neoprene over the exposed frame under the battens for interior condensate control. These are installed from inside the building after the skylight is fully secured. POLYURETHANE SEALANT BATTEN SEALANTS 1-1/2 NEOPRENESTRIPS BATTEN TEK SCREW TEK SCREW BATTEN FLANGE LOCKING PLIER PLACEMENT