Coal Sub committee meeting at Cagliari, Italy April Strategies for promoting CMM project development in India

Similar documents
Research Compendium. Coal Sector in India 2013 A comprehensive data and information update

Welcomes. H.E. Milan Hovorka, Ambassador, The Czech Republic to India & Czech Business Delegation. 09 th Nov 2017 CIL HQ, Kolkata

Analysis and evaluation of CDM prospects for coal bed methane (CBM) projects in India

METHANE TO MARKETS PARTNERSHIP COAL SUBCOMMITTEE MEETING MINUTES

Global Overview of Policies Affecting Coal Mine Methane (CMM) Recovery and Utilization

MINING IN INDIA 2016

Unconventional Gas E&P : Essar Approach

Disclaimer. The U.S. Environmental Protection Agency does not:

CBM AND CMM DEVELOPMENT IN MONGOLIA NEW POLICIES TO STIMULATE CLEAN ENERGY PROJECTS

Examining the Technology of CBM Multiple-lateral Horizontal Well

METHANE TO MARKET PARTNERSHIP Coal Mine to Market Subcommittee Country Profile: ITALY 1. INTRODUCTION OR SUMMARY OF COAL INDUSTRY AND CMM RECOVERY/USE

H.R.6. Energy Independence and Security Act of 2007 (Enrolled as Agreed to or Passed by Both House and Senate) Subtitle B--Geothermal Energy

CMM Development at the Amasra Mine, Turkey

Review of Mine Safety Regulations UNECE Ad Hoc Group of Experts on CMM. Victoria Burn Associate Norton Rose LLP 16 October 2008

Unconventional Gas Market Appraisal


An Overview of Offsets from Mine Methane Capture and their Role in California Cap-and-Trade. June 19, 2014

Coal Sector Reforms in India Analysing from the Lens of Competition & Regulatory Architecture

INFRASTRUCTURE PROJECTS IN PIPELINE

Energy Procedia 4 (2011) Energy Procedia 00 (2010) GHGT-10. Status of CCS Development in Indonesia

Shouyang CBM Project Design for Production

Methane Control Technology for Improved Gas Use in Coal Mines in China. Report No. COAL R257 DTI/Pub URN 04/1019

CRIRSCO Best Practices

Enhanced Coalbed Methane (ECBM) Field Test at South Qinshui Basin, Shanxi Province, China

Options of Post-Mine Utilization of Hard Coal Deposits

COAL. Hasan Hüseyin ERDOĞAN. Chief of Section General Directorate of Energy Affairs Ministry of Energy and Natural Resources TURKEY

Shivee Energy integrated energy complex

International Methane Partnership Fighting Climate Change

ASIAN DEVELOPMENT BANK

Electricity Supply of Naryn Sukhait Coal Mine using Coal Bed Methane ULAANBAATAR

Numerical Modelling and Prediction of Abandoned Mine Methane Recovery: Field Application from the Saar Coalfield, Germany

PER13 PPP. Terms of Reference for consultancy on Public Private Partnerships in the Transport sector

COALBED METHANE IN THE UNITED STATES: A GIS STUDY

SNA News Number 28 May 2009

Thar Coal & Energy Board Government of Sindh

ENERGY OPTIONS & COAL

Volume 3, Issue 5, May 2015 International Journal of Advance Research in Computer Science and Management Studies

Economic Statistics Division Central Statistics Office (CSO) India

COAL RESOURCES INCREASE TO 79Mt AT KATINGAN RIA, INDONESIA

File No.23014/4/2017-CLD Government of India Ministry of Coal <C» OFFICE MEMORANDUM

INTERGOVERNMENTAL PANEL ON CLIMATE CHANGE

PLus. Power COALNOMICS POWER PLUS CONSULTANTS State-wise

SPE Copyright 2003, Society of Petroleum Engineers Inc.

ASX RELEASE BY METROCOAL LIMITED (ASX-MTE) $30 MILLION JOINT VENTURE SIGNED WITH CHINA COAL

Energy Efficiency Policy in Uzbekistan

Coal Mine Gas. Utilization Principles

Supplying Key Resources into Expanding Asian Markets COMPANY PRESENTATION

Telephone Lake project

6. Cross-Cutting Issues Indicators

Cyprus Scientific and Technical Chamber ( ETEK) A brief presentation

Potential for CCS in India: Opportunities and Barriers

Revenue-Positive Incentives to Accelerate Deployment of EOR Using CO 2 Captured from Coal Generation and Other Industrial Sources:

MANGANESE ORE, CHROME ORE, FERRO ALLOYS

Paper Presented on Renewable Energy Sources Policies of India. Author- Rucha Korhale

Wage and Employment of Bharat Coking Coal Limited

PPIAF Assistance in Tunisia

India s Market Readiness Proposals (MRP) Country: India Responsible agency: MoEFCC, GOI Date of submission: 28th February, 2017

No /47/2008 CA I(Pt.) Government of India Ministry of Coal NOTICE

Policy Dialogue on PPP Infrastructure Development in South Asia

Global Geothermal Development Plan Roundtable

Underground Mining for Meeting Environmental Concerns A Strategic Approach for Sustainable Mining in Future

The Impact of the Kyoto Protocol on the Global Coal Mine Methane Market

PRESENTATION ON DEVELOPMENT OF NEW POWER PROJECTS APPROACH & WAY FORWARD

REDD + ANNUAL COUNTRY PROGRESS REPORTING (with semi-annual update) COUNTRY: [Bhutan] PERIOD: [Jan-June 2015]

Conseil des écoles publiques de l Est de l Ontario

Welcome to Elkview; Visitor Presentation September 11, 2014 Don Sander, GM, Elkview

Armenia RECENT AND ONGOING ACTIVITIES. Greening economies in the EU Eastern Partnership countries. COUNTRY UPDATES SERIES winter 2014 / 2015

Research Internship at the Reserve Bank of India

RECLAMATION OF COAL MINE VOID

MSW Subcommittee Progress Report

Sardar Sarovar Narmada Nigam Ltd (A wholly owned company of Govt. of Gujarat) (

Deliverable 1.2 Detailed risk management plan

Country profile. More from less material resource efficiency in Europe overview of policies, instruments and targets in 32 countries.

MINING REGULATIONS IN FOREST AND ECO-FRAGILE AREAS A PRESENTATION BY RAJEEVA, IFS, ADDITIONAL PRINCIPAL CHIEF CONSERVATOR OF FORESTS.

Joseph S. D Amico PE

3 Responsibility Centre COS - CenPEEP 4 Brief scope of work The engagement with NTPC will be in the following steps:

Coal mining industry at the crossroads: Towards a Coal policy for liberalising India 1

Logging solutions for optimizing field development. Well Evaluation for Coalbed Methane

Sustainable Development Policy of NHDC Ltd

GUIDELINES OF THE MINISTÈRE DE L ÉNERGIE ET DES RESSOURCES NATURELLES IN THE AREA OF SOCIAL ACCEPTABILITY

Tender Specifications for subcontracting external expertise

RWE Power International. Bankable Feasibility Study Thar Lignite Mine Work Progress

ARGENTINA S PROGRESS ON ADAPTATION PLANNING

ASX Release ASX Code: YTC

CDM Developments in India & Challenges Ahead. Pamposh Bhat Head, GTZ CDM - India Indo German Energy Programme Bureau of Energy Efficiency

Overview of the current status of CCS deployment in Indonesia

Presentation on current status of or plan for nuclear HRD programs Country: Lao PDR

Outline. Anderson Mining Company Ltd. Peel Region - Yukon s Mineral Wealth Wind River Energy Project The Future Planning Issues

The Unconventional Oil and Gas Market Outlook

Global Methane Initiative Biogas Subcommittee Meeting

Enefit s oil shale projects in Jordan

34011/2/2004-CRC CPAM Ministry of Coal CPAM Section ORDER

Terms of Reference. Pilot Program for Climate Resilience and Forest Investment Program in Rwanda. Scoping Mission

Implementing Clean Coal Technology Through Gasification And Liquefaction The Indian Perspective

Evaluation and Classification of Hydrocarbon Resources

Petrotechnical Expert Services. Multidisciplinary expertise, technology integration, and collaboration to improve operations

For personal use only

Majuba Underground Coal Gasification

Template for ToR for Transaction Advisory Services

Transcription:

Coal Sub committee meeting at Cagliari, Italy 29-30 April 2008 Strategies for promoting CMM project development in India 1. Broad National Initiative: India is vigorously pursuing clean coal technologies and is one of the founder member countries of Methane to Markets. Activities for CBM development were taken up in early 90 s. However, the main thrust on development of CBM came with formulation of CBM policy in 1997 by Govt. of India. Under this policy, 26 VCBM blocks have so far been allotted for commercial development to different operators through global bidding. The ultimate production potential of the allotted blocks is 38 MMSCMD having electricity generation capacity of 6700 MW. With utilization of CBM, there is potential of reduction of 27 mt/year of CO2 if compared with coal-fired power plants. Development of CMM is on high agenda of Indian coal mining industry and steps are being taken up for its commercialization. A mine related demonstration project under UNDP/GEF/Govt. of India funding is under implementation in 2 underground mines of BCCL. 2. Development of country specific strategy: For developing a meaningful strategy for development of CMM, participation of Governmental agencies, Mine Planning Department, Mine Safety Department, Environmental Protection Agency, Coal industries representatives and operators of CMM recovery may be associated. The representatives of following organizations may be involved for development of strategies for CMM development: a) Govt. Organizations: i) Ministry of Coal (MoC) ii) Ministry of Environment and Forest iii) Directorate General of Mines Safety (DGMS) b) Coal Industry Sector: i) CIL/CMPDI ii) Singareni Collieries Co. Ltd. (SCCL) iii) Neyveli Lignite Corporation (NLC). c) CMM operators: Representative from private sector interested in CMM CMPDI may act as a nodal agency for coordinating various activities.

Overview of Coal Sector Description of Country s Coal Sector Annual production 431 Million Tonnes (2006-07) Description Coal reserves 257 Billilion Tonnes (As on 1 st April, 2007) Percentage of coal mined from underground mines Number of underground mines considered gassy: Status of regulatory Framework CMM/CBM Project Status Commercial-scale CMM projects About 15% D-III mine: 18 (>10 m 3 of gas per tonne of coal produced) D-II mine: 102 (>1 to 10 m 3 of gas per tonne of coal produced) D-I mine: 222 (up to 1 m 3 of gas per tonne of coal produced) Coal mines: Available CBM: Regulated through CBM policy of Govt. of India formulated in 1997. CMM: Regulatory framework under formulation by Govt. of India. Description Presently there is no commercial scale CMM project in India. Pilot or demonstration CMM project. One UNDP/GEF/Govt. of India funded CBM/CMM demonstration project for Recovery and Utilization of methane is under implementation in Sudamdih and Moonidih mines of BCCL. The 23.11 million USD project is being jointly implemented by CMPDI and BCCL. The aim of the project is to acquire experience in: CBM production from virgin seams ahead of mining Recovery of methane from Gob areas Recovery of methane through long hole in-seam underground drilling Utilization technique of captured methane 2

Present status of the demonstration project: a. Moonidih Hydro fracturing in 2 vertical wells completed Dewatering in 1 well under progress Laying of surface gas pipeline completed Production of methane likely to commence from June 08. The produced gas will be utilized to generate 1 MW electricity b. Sudamdih Long-hole in seam drilling likely to commence soon Commercial scale CBM production Commercial production of CBM has started since June 2007 from Raniganj South CBM block operated by M/S GEECL. The annual production is reportedly 23.7 million cubic metre. Barriers to CMM Project Development Rank Barriers (1 st, 2 nd, 3 rd ) Description Technical 1 Resource assessment technique and technoeconomic evaluation Resource assessment technique in destressed condition Techno-economic evaluation of identified project area. Utilization of recovered methane Since this expertise is not available, international experts help from partner countries would be required. 3

Legal/regulatory/own ership for CMM development 2 Legal/regulatory/ownership for CMM development Legal/safety framework under which CMM prospects can be developed. Simultaneous and harmonious exploitation of CMM and coal. This issue is under consideration of a duly appointed government committee. Contract & Fiscal Matter (Commercial Issues): Ownership issue of recovered gas/ Carbon credits Market 3 The economy of India is growing at a rate of about 9%. Further, there is a gap in the demand and supply of natural gas. As such, market is available for produced CMM. However, there is a lack of infrastructure for transportation of the produced CMM. 4

Data collection/information products: 1. On going activities: Table 2: Assessment of Ongoing and Potential Activities One UNDP/GEF/Govt. of India funded CBM/CMM demonstration project for Recovery and Utilization of methane is under implementation in Sudamdih and Moonidih mines of BCCL. The 23.11 million USD project is being jointly implemented by CMPDI and BCCL. 2. Potential activities: Development of CMM within CIL command area: Five Damodar valley coalfields namely Raniganj, Jharia, East & West Bokaro and South Karanpura with a CMM resource potential of 150 BCM have been identified for commercial development of CMM. These blocks are to be awarded for commercial development of CMM through global bidding. 3. CMM Projects associated with the opencast mine: Pre-drainage of methane in the deeper projectisedm opencast mining area is considered. In this context, Moher sub-basin and Korba coalfields were considered for development of CMM. Templates in the flyer format on these likely projects were displayed in the M2M Expo at China. 4. Establishment of CBM/CMM clearinghouse: A MoU has been signed between GoI and USEPA to establish CBM clearinghouse in India under the aegis of M2M. As per the Govt. decision, the clearinghouse is to be established at CMPDI, Ranchi with the following purposes: To contribute to legislation improvement with an aim of attracting foreign investment. To support governmental and non-governmental organizations involved in the implementation of global climate change prevention projects; To encourage collaboration between governmental and commercial organizations through the development and implementation of joint projects; To contribute to training of qualified local specialists and broad dissemination of information concerning environmental protection problems; and To contribute to development of a new fuel and energy industry sector, establishing projects for utilization of India s deposits of coalbed and coal mine methane. 5

The clearinghouse is scheduled to carryout following tasks: Establish a website which will post useful data and reports. Conduct workshops and training programs for the Indian mining community and government officials to promote technology transfer and the exchange of ideas. Participate in technical, financial, and managerial training programs or conferences in the US, India, or another country to enhance the Clearinghouse s services. Study geological survey materials of coal and coal mine methane in the main coal basins and deposits of India. Identify project opportunities among the gassy coal basins and facilitate development of CMM projects. Publish a semi-annual newsletter on CMM/CBM. Prepare a coalbed and coal mine methane database. Promote investment in CMM projects and prepare an investment guide 6

Specific Activity (A) Has the activity already been undertaken? (Yes/No) (B) If already undertaken describe/list extent (e.g., number of workshops per year) (C) If already undertaken, does it need to be modified, updated, or expanded? (Yes/No) (D) Can it be implement ed in the near term? (Yes/No) (E) How much would it cost? (Estimate $/year, or indicate High, Medium, Low) (F) Are there any policy initiatives already promoting this activity? (Yes/No) (G) Would this be a recommend ed activity for this country? (Yes/No) Inventory gassy mines on a national scale Database of country-specific opportunities/project sites Database of CMM related businesses Technical reports addressing specific issues Other? Yes 120 Yes Yes Low Yes Yes, it requires to be seen in context of CMM Preliminary assessment for 5 coal fields and 2 opencast projectised areas carried out No Technoeconomic feasibility needs to be worked out Yes Medium Yes Yes No No Yes Medium No Yes No No No Yes 7

2) Capacity-building (general) Information center, clearinghouse, or organization to coordinate and disseminate information A clearinghouse is proposed to be open shortly. Details of activities furnished above. 3) Targeted information exchange Web site dedicated to CMM issues Newsletters Roundtable workshops, conferences, Web-based seminars, etc. 4) Specific training Intensive training (e.g., study tour, orientation visit) on technical, legal, policy, financial issues 5) Prefeasibility studies of potential CMM projects at specific sites 6) Feasibility studies of CMM projects at specific sites 7) Technology demonstrations at coal mines Envisaged in the proposed clearinghouse Envisaged in the proposed clearinghouse Workshop /seminar envisaged in the proposed clearinghouse Required Required Required Yes (stated earlier) Yes, needs expansion 8

Table 3: Prioritizing Recommended Activities Priority Recommended Activities From Table 2 1 top priority Know how for Techno-economic feasibility studies of the CMM sites 2 second priority Data base of country specific opportunities 3 third priority 4 fourth priority Training/study tours on technical/legal/policy/financial issues including sharing of carbon credits Pre-feasibility/feasibility studies of potential CMM projects at specific sites including preparation of data dossiers. 9

Table 4: Implementation Plan for Recommended Activity (used in Step 6) (Consider completing one individual table for each recommended activity) Recommended activity name: (e.g., technical training) Implementation Plan Essentials Resources required (e.g., funding, equipment, training) Description Sponsored Intensive training in Techno-economic feasibility studies Hands on training at a running CMM project for 2/3 months to geologist/mining engineers and finance persons Personnel/organization/agency to lead effort (Name, affiliation) MoC, CIL/CMPDI Expected opportunities/outcomes (e.g., tonnes CMM abated, training materials) Milestones/progress indicators (e.g., emission reductions, draft documents) 5 CMM projects and 2 methane drainage projects associated with OC mines can be soon implemented Availability of DPR for projectisation. Implementation timeline (day, month, year include milestones) Plan for communicating results (description) 18 months Quarterly 10

Table 5: Summary Template for Presenting Country-Specific Strategies in the CMM Sector [INDIA] Eight Steps Step 1) Reference broader national-level initiatives Step 2) Agencies proposed to be involved for developing strategies for CMM development Short Description India is vigorously pursuing clean coal technologies and is one of the founder member countries of Methane to Markets initiatives. Activities for CBM development were taken up in early 90 s. Govt. of India formulated CBM policy in 1997. 26 VCBM blocks have so far been allotted for commercial development to different operators through global bidding. The ultimate production potential of the allotted blocks is 38 MMSCMD having electricity generation capacity of 6700 MW. With utilization of CBM, there is potential of reduction of 27 mt/year of CO2 if compared with coal-fired power plants. Development of CMM is on high agenda of Indian coal mining industry and steps are being taken up for its commercialization. A mine related demonstration project under UNDP/GEF/Govt. of India funding is under implementation in 2 underground mines of BCCL. The representatives of following organizations may be involved for development of strategies for CMM development: Govt. Organizations: iv) Ministry of Coal (MoC) v) Ministry of Environment and Forest vi) Directorate General of Mines Safety (DGMS) Coal Industry Sector: iv) CIL/CMPDI v) Singareni Collieries Co. Ltd. (SCCL) vi) Neyveli Lignite Corporation (NLC). CMM operators: Representative from private sector interested in CMM CMPDI may act as a nodal agency for coordinating various activities. 11

Step 3) Summarize country s coal sector in relation to CMM/CBM projects Coal production Coal mine types Gassy mines 431 Million Tonnes (2006-07) Opencast (Producing about 85%) and Underground (Producing about 15%) D-III mine: 18 (>10 m 3 of gas per tonne of coal produced) D-II mine: 102 (>1 to 10 m 3 of gas per tonne of coal produced) D-I mine: 222 (up to 1 m 3 of gas per tonne of coal produced) Regulatory framework (Ownership of coal/gas) Status of regulatory Framework: Coal mines: Available CBM: Regulated through CBM policy of Govt. of India formulated in 1997. CMM: Regulatory framework under formulation by Govt. of India. Are there commercial scale CMM recovery and use projects? Are there commercial-scale CBM production projects? Barriers to CMM Project Development No Yes Resource assessment technique and technoeconomic evaluation Legal/regulatory/ownership for CMM development Contract & Fiscal Matter (Commercial Issues Lack of infrastructure for transportation of the produced CMM. 4) Describe ongoing activities promoting incountry CMM/CBM recovery and use Data collection information products Capacity building Targeted information exchange Specific technical training Pre-feasibility assessments Feasibility assessments Yes for promoting VCBM Yes by operators of the allotted VCBM block A CBM/CMM related clearing house is to be opened soon which will cater to the needs of information exchange For VCBM and CBM blocks Ongoing in several allotted VCBM blocks 12

Technology demonstrations In both VCBM and CMM blocks Other activities Creation of base line data for CBM Preparation of data dossiers for award of VCBM blocks Step 5) Recommend appropriate activities to further promote CMM/CBM project development Know how for Techno-economic feasibility studies of the CMM sites Data base of country specific opportunities Pre-feasibility/feasibility studies of potential CMM projects at specific sites including preparation of data dossiers. Sponsored Intensive training in Techno-economic feasibility studies Hands on training at a running CMM project for 2/3 months to geologist/mining engineers and finance persons Prioritize activities Know how for Techno-economic feasibility studies of the CMM sites Data base of country specific opportunities Pre-feasibility/feasibility studies of potential CMM projects at specific sites including preparation of data dossiers. Sponsored Intensive training 13

Step 6) Outline implementation plan for each recommended activity Resources required Personnel/organization/agency to lead effort Expected opportunities/outcomes Milestones/progress indicators Sponsored Intensive training in Techno-economic feasibility studies Hands on training at a running CMM project for 2/3 months to geologist/mining engineers and finance persons MoC, CIL/CMPDI 5 CMM projects and 2 methane drainage projects associated with OC mines can be soon implemented Availability of DPR for projectisation Implementation timeline (Start to finish; milestones) Plan for communicating results 18 months Quarterly Step 7) Create a plan for updating and communicating the strategy to key individuals, organizations, and incorporating it into nationallevel initiatives, if present Updation and communication may be made through: Web site Newsletter Individual communication and newspaper 14