Competitive bidding of solar and wind projects 11th Dec 2017
About SECI Incorporated on 20th September 2011, as a not for profit organization. Converted to a Commercial Company on 9th Nov, 2015; Scope widened to cover all Renewable Energy. Authorized capital is Rs. 2,000 Cr. Paid up is Rs. 304 Cr. SECI Financials (Rs. Cr.) 779 60 579 50 49.7 Income after Tax 40 Turnover 30 10.59 20 10-2.33 0-4.77-2.84 6.1 0.8 19.1 40-10 18-Apr-16 2011-12 2012-13 Solar Energy Corporation of India limited 2013-14 2014-15 2015-16 2016-17
Organization Structure Employee Strength Regular: 71 Contractual: 62 Solar Energy Corporation of India
SECI s Business Areas Preparation of feasibility and detailed project reports, resource assessment, cost engineering, technical and financial due diligence Consulting Mini/micro grid projects Solar street lights Supplying 600,000 solar lanterns in the rural areas CSR support Power Trading Power trading licensee Trading solar power from Solar projects of 680 MW capacity Trading across 15 states: 1500+ MU transferred Scheme Implementation SECI activities PMC 9000+ MW VGF schemes 20,000 MW Solar parks 700+ MW Rooftop schemes 100 MW Canal top/canal banks scheme PMC for several prestigious PSUs- BEL, BDL, GAIL, CIL,IREDA, THDC Capacity of almost 2000 MW under PMC work in pipeline Project Development SECI has operational power generation assets Project pipeline of 8 almost 200 MW May 2016
National Solar Mission Solar Energy Corporation of India
INDIAN ENERGY SCENARIO One of the fastest growing economies in the world Ranks third in total electricity generation after China and USA Low Per capita daily electricity consumption (2.76 kwh) compared to Canada (51.5kWh), USA (39.25kWh) and other developed countries. Third largest coal producer after China and USA, yet net importer of coal More than 25% of primary energy needs met from imports mainly crude oil and gas Accelerated development of energy sector to meet sustainable growth aspirations Endowed with vast renewable energy resources
Introduction to India s Power Scenario Overview Growth of Installed Capacity across India India s installed capacity is 319 350000 (As on April 2017). 300000 250000 India s RE capacity has exceeded 200000 52 (as on April 2017) which 150000 100000 accounts for 15% of the installed 50000 power capacity 0 Jän.08 Jän.09 Jän.10 Thermal Jän.11 Jän.12 Nuclear Jän.13 Hydro Jän.14 Jän.15 Jän.16 Jän.17 Current share of renewable (in Renewables energy produced) is ~7.5% Gas 7.75% Diesel Contribution of RE in total power mix 0.26% Nuclear Hydro Wind 2.07% 13.61% 9.89% Close to 65% of the installed RE Andere 17.52% SPV 12288.83 3.76% Gas Diesel Nuclear Hydro RES Wind SHP terms of yearly additions Waste to Energy 114.08 0.03% Biopower Strictly private and confidential PwC expected to overtake wind in Biopower 8182 2.50% Coal 58.80% Coal Capacity from Wind, but solar is SHP 4346.85 1.33% Waste to Energy SPV May 2017 4
India s Energ Challenge In ne t ears India s electricity requirement to grow 2.5 times Electricity shortage estimated at 25-35 Demand Climate Change is also an important issue Shortage Climate Change Access Security India is dependent on oil imports for 80% of its demand Millions of people still without proper access to electricity
India's 175 Solar Target by 2022 Contnts Targets Source Solar Power Wind power Biomass Power Other RE TOTAL Solar landscape in India PwC Targets till 2022 () 100 60 10 5 175 Strictly private and confidential May 2017 8
Policy Support
Potential of Solar and Wind Power in India 111 Solar Potential India has potential for 748 34 3 (considering deployment on 3% 17 9 of wastelands) 5 11 11 142 23 14 9 18 36 62 2 6 18 26 64 20 38 25 6 18870 MW 84431 MW 10484 MW 55857 MW 2869 MW 4422 9 MW 1700 33880 MW MW 18 Strictly private and confidential PwC Wind Power Potential Potential of over 302 (at 100 meter above ground level) May 2017 7
Revised target of Solar Power 100 by 2022 Cumulative solar capacity targets (MW) Solar Power Capacity (MW) 120000 100000 100000 75000 80000 50000 60000 40000 20000 3500 5000 8000 12000 2013-14 2014-15 2015-16 2016-17 20000 30000 0 2017-18 2018-19 2019-20 2020-21 2021-22 Year Category 1. Rooftop Projects (< 1 MW per project) Category 2. Large scale Grid connected (1 MW 500 MW project) Category 3. Ultra Mega Power Projects (>500 MW) 40,000 MW 20,000 MW 40,000 MW May 2016
Growth of Solar Capacity in India Installed capacity (MW) 12200 The sector has been registering exponential growth 8626 3002 1684 2101 936 3 11 36 2008-09 2009-10 2010-11 2011-12 2012-13 2013-14 2014-15 2015-16 2016-17 Four pillars of scale up of solar power plants: Land, Production capacity, PPA, Financing 18-Apr-16 Solar Energy Corporation of India limited
Evolution of Bidding Processes Solar Energy Corporation of India
Solar Projects evolution in India Jawaharlal Nehru National Solar Mission was launched on the 11th January, 2010 by the honourable Prime Minister of India. Initial target was 20000 MW 2022. Rooftop PV & Small Solar Power Generation Programme (RPSSGP) was launched in 2010. Generation based Incentive scheme based on CERC bench mark tariff was provided. Rs. 17.0 (~ $0.33) Bundling mechanism with Cheaper Thermal Power was also launched based on reverse bidding on CERC tariff. Renewable Energy Certification (REC) Mechanism implemented through imposing Solar Renewable Power Obligation (RPO) to Utilities
Status of Phase-I RPSSGP scheme -78 projects of cumulative capacity of 98 MW allocated 68 projects of 89 MW commissioned. Bundling scheme, batch 1 150 MW ( 30 projects allocated)-130 MW commissioned (26 projects) Tariff 10.95 to Rs 12.76 470 MW(7 projects ) of solar thermal projects allocated 200 MW (3 projects) commissioned. Tariff Rs.10.49 to Rs. 12.24 Bundling scheme batch -2 350 MW(28 projects) allocated- 330 MW(26 projects commissioned). Tariff Rs. 7.49 to Rs 9.44 Around 20 MW projects were developed under REC mechanism.
Status of phase-ii Viability gap funding Scheme launched in phase -2 of the mission. Fixed tariff of Rs.5.50 offered with Rs 25 Million grant support per MW. The VGF support quoted was ranging from Rs1.7 million Rs22 million with average of ~Rs12 million / MW 750 MW capacity allocated for 46 projects. 680 MW capacity has been commissioned. REC market was lost attraction - trading reduced drastically due to rapid tariff reduction.
Status of phase-ii Batch 2 to 6 are is under process in both VGF and bundling schemes. Target 10000MW under bundling scheme by NTPC 20000 MW under VGF schemes by SECI VGF scheme- Tariff- Rs.4.43 Support Rs 10 million/mw Zero VGF bids received. Tariff quoted 2.42/kWh Bundling scheme- Tariff of Rs 3.15 quoted
Bidding in wind power projects Wind power was mainly developed through FIT schemes by various states. The tariff of wind used to vary from Rs. 4.5 to 6.0/ kwh. With The success low tariff s in Solar, MNRE decided to go for reverse bidding on tariff for wind power projects. SECI recently concluded 2000 MW wind power auctions. Received the record low tariff od Rs. 2.63/kWh. Another 2000 MW tender is about to release. May 2016
Govt of India Schemes implemented by SECI VGF Schemes under JNNSM Phase II 750 MW scheme: 680 MW commissioned 2000 MW scheme: RfS for 2425 MW; PPA for 2295 MW. Projects under execution. 5000 MW scheme: RfS for 2900 MW; PPA for 970 MW. Projects under execution. Record low tariff of Rs. 2.44 per kwh discovered. Indo-Pak Border Solarization Scheme: 5 MW commissioned 100 MW Canal-top and Canal-bank Scheme; 300 MW scheme for Defence /Para military forces; 1000 MW scheme for CPSUs Grid connected Rooftop Schemes: 1000 MW, About 100 MW commissioned. 40,000 MW Solar Parks Schemes: 34 solar parks in 21 States 4000 MW scheme for Wind power plants: Record-low tariff of Rs. 2.63/ kwh discovered. Another NIT for 2000 MW brought out.
Factors Impacting Solar & Wind Tariff Project Structuring Contract Structuring External Conditions Stakeholder s Risk Assessment Ring fencing of risks Creditworthiness of the off-takers EPC Vs PackageWise Contracting Managing commercial risks Mitigation of Technical Risks Policy Visibility Change in Law Economic conditions of the Host Country (inflation, growth) Geo-political conditions
SECI s Tendering Process Industry standard open, transparent bidding process e-bidding platform Reverse Auction platform. Project specific elaborated technical specifications. Continuously updating the technical specs along with market trends and best practices. Solar Energy Corporation of India
Other Factors Bankability of PPA: Tri-patriate Agreement between, Sate Govts, RBI and SECI. FDIs: Number of foreign investors are investing aggressively. Solar Parks: Development of solar parks reduced number of issues. Solar Energy Corporation of India
SOLAR PARKS Solar Energy Corporation of India
Solar parks Enabling environment for developers. Quick turnaround time for projects. Common infrastructure and support services. Shared development costs. Lesser losses in evacuation. Can establish local manufacturing and support facilities. Local employment and generation.
20 Solar parks 34 Parks (21 states) with capacity 20,000 MW approved Himachal Pradesh 1000 MW J&K 100 MW Haryana 500 MW Rajasthan Arunachal Uttarakhand 100 MW 50 MW Assam UP 69 MW 600 MW 680 + 1000 + 500 + 750 + 321 MW Nagaland 60 MW Gujarat Meghalaya 700 MW 20 MW MP WB 750 MW+ 500 MW+500 MW +500 MW +500 MW 500 MW Orissa Chattisgarh 1000 MW 500 MW Telangana Maharashtra 500 MW+500 MW +500 MW Karnataka Current status,2000 OutlookMW and opportunities MNRE Kerala 200 MW 500 MW AP: Anantapur, Kurnool, Kudappa 1500 MW + 1000MW + 1000 MW + 500 MW May 2016 Tamil Nadu 500 MW
Solar Parks Scheme Category A parks (Work in Progress) Andhra Pradesh- 4,000 MW Rajasthan- 680 MW (Bhadla Phase II) Rajasthan- 1500 MW (Bhadla Phase III, Phase IV) Uttar Pradesh- 440 MW Kerala- 200 MW Karnataka- 2000 MW Madhya Pradesh- 750 MW (Rewa Solar Park) Madhya Pradesh-500 MW (NeemuchMandsaur Solar Park) Category B parks (Work likely to start in 3-6 months) Maharashtra- 1500 MW Gujarat- 700 MW Chhattisgarh- 500 MW West Bengal- 500 MW Category C parks (DPR and Land Under Finalization) Odisha- 1000 MW Tamil Nadu- 500 MW Telangana- 500 MW Haryana- 500 MW Arunachal Pradesh100 Uttarakhand- 50 MW Assam- 69 MW Nagaland-60 MW J&K- 100 MW 1000 MW HP is under review 27
Solar Parks and SECI in JV in Phase-1 of Solar Park Scheme Solar Parks Approved Capacity : : 34 Nos. in 21 States 20,000 MW SECI in JV with State Designated Agencies: 1. Andhra Pradesh 2. Himachal Pradesh 3. Karnataka 4. Madhya Pradesh 5. Kerala 6. Uttar Pradesh *Total capacity sanctioned in above states is 10550 MW 28
ROOFTOP PROJECTS Solar Energy Corporation of India
Progress Status of Rooftop Solar in India State/UT Tamil Nadu Gujarat Maharashtra Punjab Karnataka Rajasthan (MW) 132 69 89 55 51 46 % 12.94% 6.76% 8.73% 5.39% 5.00% 4.51% Uttar Pradesh 33 Telangana Andhra Pradesh Haryana Delhi Chhattisgarh Others Total 27 3.24% 2.65% 32 57 35 16 378 1020 3.14% 5.59% 3.43% 1.57% 37.06% 100.00% Source: Bridge to India, as on 30th September 2016 Solar Policy notified by 30 states Net Metering Policy in 18 states Emphasis by GoI to set state-wise targets and direction to all Ministries to set up Rooftop on Government/PSU Buildings
Rooftop Solar Systems Pilot scheme was implemented in city specific: mode, through competitive bidding in 2013. 26.6 MWp scheme - Year 2013 50 MWp scheme - Years 2014 & 2015 50 MWp scheme for CPWD - Year 2015-16 500 MWp for residential and not for profit institutions Year 2016 500 MWp for Government buildings Year 2017 About 100 MW capacity installed. Project Cost (Rs./Wp) 100 90 80 87.96 90 89 84.5 90 75 83 70 60 50 40 30 63 58 63.8 53 44.8
Rooftop SPV projects under SECI schemes Pan India > 100 cities Implementing projects with from MNRE Rooftop subsidy Chandigarh (1) Mohali (1) Gurgaon (2.5) Upto 500kW capacity projects being set up in New Delhi (5) Jodhpur (.25) select cities Jaipur (3.75) Phase I: 5.5 MW (4 cities) Gwalior (1) Phase II: 11.3 MW (6 cities) Neemrana (.25) Bhopal (1) Phase III: 10 MW (9 cities) Gandhinagar (1) Phase IV -1:32.5 MW (29 cities) Vadodara (0.5) Phase IV -2: 24 MW (17 States) Surat (0.5) Nasik (0.5) Legend Phase I Phase II Phase III Phase IV Part 1 Phase IV Part 2 Multiple phases Nagpur (0.5) Mumbai (1) Pune (3) Tirupati (0.5) Bangalore (3) Coimbatore (1.5) Amritsar (0.5) Ludhiana (0.5) Lucknow (1.0) Noida/Greater Noida (3.5) Panchkula (1) Faridabad(0.5) Patna (2) Palatana (1) Ranchi (2) Kolkata (2) Durgapur (1) Bhubaneswar (1) Raipur (2.05) Vijaywada (0.5) Hyderabad (4) Chennai (6) Mysore (1) A & N (1) Madurai (0.5)
Solar Power Trading SECI is applying for a Category I trading license Trading solar power under VGF schemes Million Units of Power traded 2500 2400 Million Units 2000 1235 1500 954 1000 500 13.65 0 2014-15 2015-16 intra-state 2016-17 inter-state * 2017-18 figures are projected Solar Energy Corporation of India Total 2017-18*
Own Capex Projects 10 MW at Jodhpur, Rajasthan - Commissioned 1 MW Rooftop Solar at Andaman & Nicobar- Commissioned 150 MW Solar-wind Hybrid project in Andhra PradeshFeasibility assessment done 2.5 MW Solar-wind-battery hybrid tendering R&D project- Under 20 MW at DRDO, Karnataka- Feasibility assessment done 50 MW at DRDO, Hyderabad- Under discussion May 2016
Next Generation RE projects
Issues in high penetration of Solar power Solar power is intermittent/infirm in nature Scheduling of associated energy sources becomes quite difficult Prone to fluctuations due to nature. Cause instability in grid after exceeding some percentage of solar (especially in case of large installation and solar parks) Generation profile is not stable and not matches with load profile. Leads curtailment of generation of solar projects/ thermal projects. Viability of both the projects in trouble. Solutions?? Forecasting. Storage solutions Hybrid power plants 9-Jan-18 Proprietary & Confidential 36 09-01-2018
Solar storage projects Solar is intermittent source and the generated power can be Used locally Transmitted to other locations Local Use Generation not matches the load demand. Stability of the local grid after exceeding some percentage of solar. Source : Energypedia Solution?? Storage 9-Jan-18 Proprietary & Confidential 37 09-01-2018
Solar PV storage Projects SECI realized the issues and started working on projects with storage. Working on following pilot projects at potential locations of huge capacities in future. 2MW Solar and 0.5 wind hybrid power plant along with 1 MWh battery storage a Kaza, Lahaul spiti Dirtrict of Himachal Pradesh (Approved) Demonstrate the potential of large scale PV and wind power generation in Himalayan cold desert regions. Hybridization of renewable sources. Study the effectiveness of large scale battery storage. 1 MW solar projects with 3 MWh large scale storage facility at Chikten, Kargil To mitigate diesel consumption in the Localized diesel grid. To demonstrate the storage benefits in terms of stability of grid. 300 MW solar projects with storage are being developed for smooth solar power. Proprietary & Confidential 09-01-2018
Better land utilization more power generated per unit area and better utilization of unused land available adjacent to the wind turbine Better use of evacuation better utilization of transmission and shared electrical infrastructure Better power generation profile power output will be more stable compared to standalone generation. Peak Demand matching: Solar addresses morning peak and wind power meets evening peak. Lower operations and maintenance O&M of True H brid park more economical and easier due to common components and resources
Avg. annual hourly power gen comparison (1.5MW Wind + 0.75MW Solar) 1600 1400 POWER IN KW 1200 1000 800 600 400 200 0 00:00 02:24 04:48 07:12 09:36 12:00 14:24 HOUR OF DAY [HR] Wind only Solar only With Energy Storage out put can be firmed further 16:48 19:12 21:36 00:00 Hybrid Source : Regentech
SECI is planning to set up 150 MW solar+ wind hybrid projects The initiative is being supported by World bank. Firming projects sites, capacities is under progress in Andhra Pradesh. Procurement plans are being worked out. The project will employ Battery energy Storage system also.
Milestones Achieved Lowest ever solar tariff of Rs. 2.44 per Unit in Rajasthan bid without any VGF Introduction of competition in procurement of wind power and trend setting tariff of Rs. 2.63 per unit in a recently concluded CTU connected wind power scheme. Bringing in competitive mode in roof top solar projects from 2013 which is continuously driving down the cost and hence the benchmark cost of the MNRE Village electrification project for 895 villages through stand alone Solar Home Lighting Systems and 4923 nos. Solar Street lights in Arunachal Pradesh under DDGUY scheme Undertaking 150 MW solar-wind hybrid project with World Bank Support Very Good rating in its first MoU evaluation in 2015-16