Flygt Advanced Low Pressure Sewer System Package

Similar documents
C. Foundation stabilization for pipe and utility structures.

TYPICAL INSTALLATION INSTRUCTIONS

Fabrication and Installation Table of Contents

Minimum Guidelines for the Design and Use of Underpins When Performing Foundation Stabilization and/or Supplementation UP-08

SITE SERVICES GUELPH TRANSIT OPERATIONS & MAINTENANCE SECTION WATSON ROAD FACILITY PAGE 1 OF 6 WATER RECLAMATION PROJECT JUNE 2013

SECTION 820 PUMP STATION DEMOLITION AND SITE RESTORATION

SECTION 19 - TRENCH EXCAVATION, BEDDING AND BACKFILL TABLE OF CONTENTS

SOLID WALL PVC SEWER PIPE

SECTION UTILITY MANHOLES AND STRUCTURES

Design Manual: Gravity Wall. Section 1

1. Cast-in-place concrete is specified in Section

SOLID WALL PVC SEWER PIPE

B. Subsurface data is available from the Owner. Contractor is urged to carefully analyze the site conditions.

SECTION 19 - TRENCH EXCAVATION, BEDDING AND BACKFILL TABLE OF CONTENTS

SEWER FORCE MAIN HDPE PIPE

BASED ON DFD MASTER SPECIFICATION DATED 2/24/2014

Gainesville Technical Center 5399 Wellington Branch Drive Gainesville VA Phone (703)

In preparation for constructing buildings on a property, the builder. Site Preparation CHAPTER

See the IRC for additional information. See CPD-DS Information Bulletin 100 for Requirements for 1 & 2 Family Dwelling plan submittals.

SLIDE RAIL SHORING SYSTEMS

Anchor bolts ASTM F1554, Gr. 36 Wide flange beams ASTM A992, Fy = 50 ksi Misc. structural steel ASTM A36, Fy = 36 ksi

DIVISION 31 EARTHWORK 2006 Edition, Published January 1, 2006; Division Revision Date: January 31, 2012

Section [ ] Storm Water Treatment Device

PHILADELPHIA GAS WORKS SPECIFICATION BOOK For Common Trenching For Natural Gas Mains and Services

File No Supplemental November Geotechnical and Environmental Consulting Engineers

VERTI-BLOCK - DESIGN MANUAL

DIVISION 03 CONCRETE SPECIFICATION : FORMS AND FORMWORK

RETAINING WALL LEVEL BACKFILL

SPECIFICATIONS FOR PRECAST MODULAR BLOCK RETAINING WALL SYSTEM (revised 5/8/7)

SECTION FACILITY SANITARY SEWERS

Tabulated Data Waler Rails

THE ADVANTAGES HDPE MANHOLES

BAYFILTER SPECIFICATIONS

INDEX FOR SPECIFICATIONS FOR JACKING CULVERTS THROUGH EMBANKMENTS SCOPE... 2

PRECAST CONCRETE ON-SITE WASTEWATER TANKS

Sample Bid Specification Revision 2 PVC Expanded-in-Place Pipeline Reconstruction

STANDARD SPECIFICATIONS SECTION TUNNELING. A. Section includes requirements for constructing tunnels 48-inch and larger diameter.

SECTION BASIC ELECTRICAL MATERIALS AND METHODS

B. Backfill and compact utility bedding and fill placed in the utility trenches between the top of the utility bedding and the subgrade elevation.

The better way to build TM. Installation Manual FOUNDATION SIPs & FROST WALLS SIPs

TCC/SHORE TRANSIT BUS MAINTENANCE FACILITY - PHASE II

A Design Review of Waterproofing Codes

SECTION RIPRAP, BOULDERS, AND BEDDING

Excavation and Trenching

ITEM 6 CONCRETE CURBS, GUTTERS, AND SIDEWALKS

Design Data 6. Loads and Supporting Strengths Elliptical and Arch Pipe. Values of B d

MS-2A LINER SPECIFICATIONS: for STRUCTURAL REPAIR and SEALING of MANHOLES

A. Product Data: Submit manufacturer s product data, with complete general and specific installation instructions, recommendations, and limitations.

TYPES OF SEWAGE PUMPS. Solids Handling Pumps: Grinder Pumps: Effluent Pumps:

Foundation/Site Work Code Requirements

Table of Contents AQUA-SWIRL 2

SECTION Stabilizer Apache Warning Track Mix for baseball or softball field surfacing

SECTION HIGH DENSITY POLYETHYLENE PIPE AND FITTINGS (PRESSURE PIPE)

STANDARD SPECIFICATIONS SECTION BORING AND JACKING. A. Section includes requirements for boring and jacking casing pipe.

STANDARD SPECIFICATION FOR CRIBLOCK CONCRETE CRIBWALL

RESIDENTIAL HARDWOOD WARRANTIES

HIGH DENSITY CROSSLINKED POLYETHYLENE STORAGE TANKS WITH OXIDATION RESISTANT LINING SYSTEM (NSF/ANSI 61)

SECTION 19 - TRENCH EXCAVATION, BEDDING AND BACKFILL TABLE OF CONTENTS

Section 3 Fusible PVC Pipe Connections

SECTION TRENCHING & BACKFILLING

SPECIFICATIONS FOR STREET CONSTRUCTION WITHIN THE TOWN OF PLAINVILLE

(c) Presentation of Information. Information is presented in several forms as follows:

CANTILEVER RACK SPECIFICATIONS PART 1 GENERAL 1.1 SCOPE 1.2 APPROVED MANUFACTURER 1.3 REGULATORY ORGANIZATIONS AND GROUPS 1.4 QUALITY ASSURANCE

PERMA-PIPE Prefabricated Manholes. Installation Manual

SECTION MANHOLES AND STRUCTURES. A. Section Includes: 1. Manholes for water, storm drain and sanitary sewer systems.

SECTION DUCTILE IRON FITTINGS. A. This section includes materials, installation, and testing of ductile iron fittings 48 inches and smaller.

Curlex High Velocity EROSION CONTROL BLANKET SPECIFICATION

BIO-AQUIFER STORM SYSTEM

Rural Servicing Guidelines

SECTION GRADING AND SITE PREPARATION CITY OF LEE S SUMMIT, MISSOURI STANDARD SPECIFICATIONS

Click on image to enlarge.

STANDARD PRACTICE INSTRUCTION

Underground Piping for Private Hydrants & Sprinkler Supply Line

SEPTIC TANK CONSTRUCTION GUIDELINES

PVC Fittings & Laterals for Solid-Wall PVC Sewer Pipe

SECTION CAST-IN-PLACE CONCRETE

SECTION HIGH DENSITY POLYETHYLENE PIPE AND FITTINGS

SECTION PIPE & PIPE FITTINGS PART 1 GENERAL

CW 3615 RIPRAP TABLE OF CONTENTS

MODULAR CONCRETE RETAINING WALL

LS 2519 CONCRETE PAVER PAVEMENT RECONSTRUCTION

HYDROGRID SUBSURFACE IRRIGATED HARTRU TENNIS COURTS

SECTION CHAIN LINK FENCES AND GATES (GALVANIZED) A. Fence framework, fabric, gates, and accessories.

E. Section Polymer Modified Cement Waterproofing. K. Section Sub drainage: Foundation perimeter drainage.

16. Design of Pipeline Structures.

This guide can be used to prepare a specification for incorporating free standing jib cranes into a competitively bid construction project.

Specifications for Electrical Underground Residential Distribution Systems

Permit Requirements: Building Codes: The City of Clanton has adopted the following codes which are enforced by the Building Department:

Detached Garages and Building Permits. 1 and 2 Family Dwellings

AEC Premier Straw Double Net Quick Mow EROSION CONTROL BLANKET SPECIFICATION

Read Only Copy Not For Distribution. Chapter 17. Private Potable Water Supply Systems 17.1 GENERAL REGULATIONS 17.2 QUANTITY OF WATER REQUIRED

SPECIAL CONDITIONS FOR PIPE JACKING (PJ) October, 2006

TRENCHING AND EXCAVATION

SUBSURFACE INFILTRATION SYSTEM DESCRIPTION. Alternative Names: Sump, Drywell, Infiltration Trench, Infiltration Galleries, Leach Fields

DESIGN & CONSTRUCTION CONSIDERATIONS OF REINFORCED CONCRETE STRUCTURES FOR WATER UTILITIES

STANDARD SPECIFICATIONS SECTION JACKED CASING

SpaVault TM Installation Guide for Bullfrog Spas (7-10 x 7-10 x 38 )

TECHNICAL PROCEDURE TABLE OF CONTENTS

American Metal Specialties, Inc.

TAMDID PIPES GRP MANHOLE BROCHURE

Transcription:

PURPOSE Xylem The purpose of this document is to provide a brief reference to the recommended methods and procedures for installing Flygt's underground sump and sewage basins to ensure that damage or premature failure of the basin does not occur. Studies conducted by both environmental regulatory agencies and trade organizations demonstrate that the most significant source of leaks and failures in underground storage systems is improper handling and installation. Proper handling and installation requires practical experience combined with strict adherence to proven methods and procedures. This guide is not intended to serve as a basin instructional manual. The installation of our sump and sewage basins is a specialized skill. It is assumed that the individuals who install our products and refer to this guide will have a basin understanding of such procedures as excavating, backfilling, pipe fitting and electrical work. No amount of written instruction by a manufacturer or a regulatory agency will convert an inexperienced, under supervised laborer into a skilled, experienced mechanic. The ability to recognize and correctly respond to abnormal conditions during a basin installation requires field experience as well as mechanical aptitude. In addition to proper system engineering and competent manufacturing, the use of basin installers who have both practical experience and integrity to insist that the basin be installed properly constitutes the greatest protection from catastrophic basin failure and liability exposure. DISCLAIMER Every reasonable effort has been put forth by Flygt and its agents to ensure the accuracy and reliability of the information contained in this reference guide. However, neither Flygt, its agents, or its consultants make any representation, warranty, or guarantee in connection with the publication of these recommended methods and procedures. Flygt hereby disclaims any liability for loss or damage resulting from their use; for the violation of any federal, state, county or municipal regulations with which these recommended methods and procedures may conflict; or for the infringement of any patent resulting from the use of these recommended methods and procedures These handling and installation instructions are not intended to preclude normal safety procedures, which should be followed to prevent injury to personnel. SAFE INSTALLATION PROCEDURES SHALL BE ENTIRELY THE RESPONSIBILITY OF THE INSTALLER. MATERIAL HANDLING General Handling. Although the exterior surfaces of our fiberglass reinforced plastic (FRP) sump and sewage basins are designed to withstand normal handling, they can be damaged during transportation and installation. Basins must not be dropped, dragged or handled with sharp objects and with the exception of the minimal movement involved in a visual inspection, should not be rolled. If the basin or its shell is damaged, installation should be suspended until a determination of the extent of damage can be made by Flygt or its agent. Any repairs must be first authorized in writing by Flygt and then be done in accordance with Flygt instructions. Page 1 of 5

Unloading, Lifting and Lowering. The proper way of moving a basin is by lifting it, using chains or cables with the optional lifting lugs (not more than 30 included angle) or by using a non-marring sling around the basin. Before any attempt is made to move the basin, it should be established that all the equipment and accessories have sufficient capacity and reach to lift and lower the basins without dragging and/or dropping. Basins should be maneuvered with guide ropes attached to the sides. WARNING! Under no circumstances is the use of chains or cables around the basin shell permitted. Storage. Basins should be stored in a secure, controlled area where the potential for accidental damage or vandalism will be minimized. The storage area should be free from sharp objects, rocks and any other foreign solutions or materials that could cause damage to the basins. Chock the basins until they are needed for installation and if windy conditions are possible, secure the basins with non-marring restraints of a size and number adequate for securing the basin. Pre-installation inspection. Basins, valves, equipment and piping materials should be physically and visually inspected prior to installation. Adherence to the project s specifications should also be confirmed before installation. If the basin or any of its internal components are damaged, installation should be suspended until a determination of the extent of damage can be made by Flygt or its agent. Any repairs must be first authorized in writing by Flygt and then be carried out in accordance with Flygt's instructions. EXCAVATING Excavating. The excavation should provide adequate space for the basin, piping and other buried equipment and for the placement and compaction of backfill materials particularly around the basin walls. The size, shape and wall slope of the excavation should be determined by soil conditions, depth of excavation, shoring requirements, and, if workers are required to enter the excavation, safety considerations and federal, state, county and municipal regulations. WARNING! Locate all overhead and underground utilities before excavating. Location of Excavation. Excavation for an underground basin should be made with due care to avoid undermining foundations of existing structures and contact with underground utilities. In the absence of building codes or regulations, maintain a minimum distance of five feet plus a slope of 45 from the bottom of the compacted sub-base to the bottom of the adjacent structures, foundations, footings and property lines (as shown in the attached illustration). Additional distances may be required to assure that any loading carried or created by the foundations and support cannot be transferred to the basins. Maximum Burial Depth. If burial depth is greater than the basin height, contact Flygt to determine if additional wall reinforcement is required and secure written authorization. Handling of Excavated Materials. Excavated materials, which cannot be removed from the job site, should be carefully stored as far from the edge of the basin excavation as possible. Unless approved for use as backfill, excavation materials should be securely stored separate from approved backfill materials. Page 2 of 5

Work Area Safety. Safe installation procedures shall be the sole responsibility of the basin installer. Work safety requirements are defined in U.S. Department of Labor 29 CFR part 1926, subpart P, Excavations. BACKFILLING General. Careful selection, placement and compaction of approved backfill material are critical to a successful basin installation. Among common problems associated with basin leaks and premature failures are: Use of an incorrect backfill material. Inadequate or improper placement or compaction. Rocks, clods or debris left in the excavation or basin. Voids under or around the perimeter of the basin. Failure to prevent the migration of backfill materials. Placement of Basin. The bottom of the basin excavation should be covered with suitably graded, leveled and compacted backfill material to a depth of at least 12 inches (compacted sub-base). If a concrete hold-down/anti-floatation pad is required, this bedding can be reduced to a depth of at least 6 inches. The basin should then be carefully lowered into the excavation and centered on the compacted backfill or concrete pad (see attached illustration). WARNING! Placement of a basin on a concrete pad or compacted sub-base smaller than the total basin bottom area or on intermediate supports (saddles) will cause uneven distribution of loads. This may contribute to structure failure and is never permitted. Backfill Material. Backfill material should be clean, well granulated, free flowing, non corrosive and inert. It should be free of ice, snow, debris, rock, or organic material, all of which could damage the tank and interfere with the compaction of the backfill material. The largest particles should not be larger than ¾ inch. Not more than 3 percent (by weight) should pass through a #8 sieve, and the backfill material should conform to ASTM C-33, Paragraph 9.1 requirements. Approved backfill materials include: Pea Gravel, naturally rounded particles with a minimum diameter of 1/8 inch and a maximum diameter of ¾ inch. Crushed Rock, washed and free-flowing angular particles between 1/8 inch and ½ inch in size. Placement and Compaction of Backfill. Compaction of backfill materials should be adequate to ensure the support of the tank and to prevent movement or settlement. Backfill materials should be placed in 12 inch lifts and compacted to a minimum soil modulus of 700 pounds per square foot (psf). Supporting Piping, Equipment and Accessories. Support for piping, equipment and other accessories must be provided during backfilling. Using the basin to support piping, equipment, cribbing, bracing or blocking is never permitted. During backfilling, temporary supporting materials must be carefully installed and removed to prevent damage to the basin, piping or equipment. WARNING! Using the basin to support any loading carried or created by piping, equipment, cribbing, bracing or blocking is never permitted. Page 3 of 5

ANCHORAGE Xylem General. When basin installations are located in areas subject to high water tables or flooding, provision should be made to prevent the basins, either empty or filled, from floating. The buoyancy force to be offset is determined primarily by the volume of the basin. The principle offsetting factors include: Backfill materials. Concrete hold-down pad. Friction between the tank, backfill materials and the surrounding soil. Methods of Anchoring. All methods of anchoring basins use the weight of the backfill materials to offset the buoyancy forces. The use of supplemental mechanical anchoring methods (a concrete hold-down pad) increases the amount of backfill ballast which is mechanically attached to the basin. The recommended method of attachment is to pour concrete grout over the basin s anti-floatation flange and concrete hold-down pad (see attached illustration). Anchorage Requirements. Requirements for anchorage, thickness of concrete hold-down pads, as well as the size of anchors and reinforcement must be calculated for each installation based on the environmental conditions of that specific installation. WARNING! Use submerged material weights when calculating anchorage requirements. Example: weight of concrete (150 pounds per cubic foot) minus the weight of the water (62.4 pounds per cubic foot) equals a submerged weight of 87.6 pounds per cubic foot. Page 4 of 5

CAUTION: Handle with care Do not drop Do not impact 30 Maximum Do not roll Do not wrap cable or chain around basin Lifting Cable or Chain Spreader Bar Finish Grade Sloped and size of excavation as per OSHA and engineer's specification. In the absence of these consider condition of soil, depth of excavation and safety considerations. Compacted sub-base minimum 12" or 6" when used with concrete hold-down pad Optional Lifting Lugs Basin anti-floatation flange Compacted sub-base and /or concrete slab as per engineer's specification. Adjacent structure, foundation, footing or property line 12" minimum backfill compacted to a minimum soil modulus of 700 lbs. per square foot Finish Grade 5'-0" Minimum 45 Minimum Fiberglass basin as required per engineer's specification Backfill Material In the absence of building codes, or regulations, maintain a minimum distance of five feet plus a slope of 45 from the bottom of the compacted sub-base to the bottom of the adjacent structure's foundation, footing or property line. Concrete grout as required per engineer's specification Pea Gravel Crushed Rock BACKFILL MATERIAL REQUIREMENTS NOTE: The intent of these installation instructions and illustrations is to ensure that damage or premature failure to the basin will not occur. These installation instructions and illustrations are NOT intended to preclude normal safety procedures which should be followed to prevent injury to personnel. SAFE INSTALLATION PROCEDURES SHELL BE ENTIRELY THE RESPONSIBILITY OF THE INSTALLER. Page 5 of 5