Audit of the Management of Projects within Employment and Social Development Canada

Similar documents
Audit of Entity Level Controls

Audit of the Delegation of Authorities for Select Human Resources Processes

Audit of Occupational Health and Safety (Canada Labour Code, Part II)

Audit and Advisory Services Integrity, Innovation and Quality

Assessment of the Design Effectiveness of Entity Level Controls. Office of the Chief Audit Executive

Audit of Departmental Security

Audit of Human Resources Planning

Audit of Shared Services Canada s Information Technology Asset Management

Justice Canada. Audit of Cost Recovery Process Improvement (CRPI) Initiative Phase 1. Audit Report. Internal Audit Services.

Internal Audit of Compensation and Benefits

Audit of Canada s Participation in the World Exposition Shanghai China 2010 (Expo 2010)

System Under Development Review of the Departmental Financial Management System Renewal Project

Corporate Risk Management Audit

Audit of the Office of the Correctional Investigator. A report by the Public Service Commission of Canada

ARCHIVED Audit of Risk Management

Office of Learning Technologies (OLT) Program

Aboriginal Affairs and Northern Development Canada. Internal Audit Report. Management Practices Audit of the Treaties and Aboriginal Government Sector

Open Government Implementation Plan (OGIP)

Integrated Business Planning Audit

Auditor General s Office REVIEW OF THE CITY SAP COMPETENCY CENTRE APPENDIX 1. June 1, 2010

POSSE System Review. January 30, Office of the City Auditor 1200, Scotia Place, Tower Jasper Avenue Edmonton, Alberta T5J 3R8

Audit and Advisory Services Integrity, Innovation and Quality. Audit of Internal Controls over Financial Reporting

Horizontal Audit of the Acquisition Cards Process

AUDIT REPORT NOVEMBER

Audit of Cultural Industries Branch

Review of Information Technology Service Delivery. The Audit and Evaluation Branch

Internal Audit Management of IST Taxi Voucher Usage

Audit of the electronic Common Information Management System (ecims) Development Project

PHASE TWO FOLLOW-UP REPORT ON THE AUDIT OF CONTRACTS (2008)

Strategic Direction #7 Business Operations. Final Report

Sole and Single Source Audit

36th Board Meeting Prioritized Action Plan (PAP) to Accelerate Management for Impact For Board Information

Auditor General s Office APPENDIX 1 REVIEW OF INFORMATION TECHNOLOGY TRAINING. October 30, 2009

PART THREE: Work Plan and IV&V Methodology (RFP 5.3.3)

Re: Response to Audit of the Application Services Section Report No

Compliance Monitoring and Enforcement Program Implementation Plan. Version 1.7

Aboriginal Affairs and Northern Development Canada. Internal Audit Report. Audit of the Additions to Reserve Process. Prepared by:

Office of the Superintendent of Financial Institutions

Canada AUDIT OF DIGITIZATION OF SERVICE AND HEALTH RECORDS. March Audit and Evaluation Division. Page i

REPORT 2014/115 INTERNAL AUDIT DIVISION. Audit of information and communications technology management at the United Nations Office at Geneva

AUDIT OF KEY FINANCIAL PROCESSES AT THE SOUTHWESTERN ONTARIO FIELD UNIT AND THE GEORGIAN BAY FIELD UNIT FINAL REPORT. Prepared by:

Passit4Sure.OG Questions. TOGAF 9 Combined Part 1 and Part 2

Internal Oversight Division. Internal Audit Strategy

This charter defines the purpose, authority and responsibility of News Corporation s (the Company ) Corporate Audit Department.

REPORT 2016/033 INTERNAL AUDIT DIVISION

Waterloo Region District School Board

GATU Webinar Part 1 March 2017 Presented by Carol Kraus, CPA

ARCHIVED - Evaluation Function in the Government of. Archived Content. Centre of Excellence for Evaluation Treasury Board of Canada Secretariat

Project and Process Tailoring For Success

IT PROJECT ANALYST/MANAGER

Final Report Evaluation of Translation Bureau Programs Volume 2: Translation and Other Linguistic Services Program

INTERNAL AUDIT DIVISION REPORT 2017/022. Audit of knowledge and records management at the United Nations Framework Convention on Climate Change

Research & Benchmarking Services

CABINET DIRECTIVE ON STREAMLINING REGULATION

Conseil des écoles publiques de l Est de l Ontario

AUDIT OF EARNINGS LOSS

CANADA REVENUE AGENCY

Competitive Procurement Evaluation Process Audit

Program Management Professional (PgMP)

THE POWER OF ENTERPRISE- FILE: PROJECT MANAGEMENT

Chapter 4 Department of Government Services

Quality Management as Knowledge Sharing: Experiences of the Napa County Health and Human Services Agency

Internal Audit Report. Toll Operations Contract Management TxDOT Office of Internal Audit

Information Technology Services Project Management Office Operations Guide

REPORT 2014/148 INTERNAL AUDIT DIVISION. Audit of the recruitment process at the Office of the High Commissioner for Human Rights

Article from: CompAct. April 2013 Issue No. 47

Evaluating and Building Portfolio Management Maturity

GUIDELINES FOR IMPLEMENTING A PRIVACY MANAGEMENT PROGRAM For Privacy Accountability in Manitoba s Public Sector

Certificate IV in Project Management Student Assessment Guide

Main points Background Our audit objective and conclusions Managing for results key findings...243

Centralizing Your Energy Supply Spend

INTERNAL AUDIT DIVISION REPORT 2017/058

SOLUTION BRIEF RSA ARCHER AUDIT MANAGEMENT

3.13. Supply Chain Ontario and Procurement Practices. Chapter 3 Section. 1.0 Summary

Her Majesty the Queen in Right of Canada, represented by the President of the Treasury Board, 2011 Catalogue No. BT22-89/2012E-PDF ISBN

Financial Services Job Summaries

An Overview of the AWS Cloud Adoption Framework

Performance, evaluation, risk and audit framework (PERAF)

Monthly Independent Verification and Validation Assessment Report

Internal Audit of ICT Governance in WFP. Office of the Inspector General Internal Audit Report AR/15/11

CIP 2017 Project Outline

Conseil scolaire de district du Grand Nord de l Ontario

PROMPT OAS Assessment Process

Report. Quality Assessment of Internal Audit at <Organisation> Draft Report / Final Report

ITS STRATEGIC PLAN. ITS Strategic Plan

Agenda. Enterprise Risk Management Defined. The Intersection of Enterprise-wide Risk Management (ERM) and Business Continuity Management (BCM)

Realizing Business Value through Collaborative Document Development

ACOA Internal Audit Directorate

INFORMATION SERVICES FY 2018 FY 2020

Dynamic Reallocation of Portfolio Funds

NCDOT Project Delivery Study

Oilpocalypse Now: Weathering the Storm with Integrated Project Management Samarth Jain Andrew Lavinsky

US Business Continuity Safeguarding Your Business from a Disaster

Monthly IV&V Assessment Report (December 1 31, 2015)

Enterprise Technology Projects Fiscal Year 2012/2013 Fourth Quarter Report

Supreme Audit Institutions Performance Measurement Framework

Guidance Note: Corporate Governance - Audit Committee. March Ce document est aussi disponible en français.

SharePoint Governance at BMO. How we took action to curb the sprawl of sites

INTERNAL AUDIT DIVISION REPORT 2017/071. Audit of recruitment of staff in the United Nations Interim Security Force for Abyei

GUIDANCE NOTE FOR DEPOSIT TAKERS (Class 1(1) and Class 1(2))

Transcription:

Unclassified Internal Audit Services Branch Audit of the Management of Projects within Employment and Social Development Canada February 2014 SP-607-03-14E

Internal Audit Services Branch (IASB) You can download this publication by going online: http://www12.hrsdc.gc.ca This document is available on demand in multiple formats (large print, Braille, audio cassette, audio CD, e-text diskette, e-text CD, or DAISY), by contacting 1 800 O-Canada (1-800-622-6232). If you use a teletypewriter (TTY), call 1-800-926-9105. Her Majesty the Queen in right of Canada, 2014 For information regarding reproduction rights, please contact via e-mail Employment and Social Development Canada at droitdauteur.copyright@hrsdc-rhdcc.gc.ca PDF Cat. No.: Em20-3/2014E-PDF ISBN/ISSN: 978-1-100-23420-5

Audit of Management of Projects within ESDC Table of Contents Executive Summary... 1 1.0 Background... 3 1.1 Context... 3 1.2 Audit Objective... 3 1.3 Scope... 4 1.4 Methodology... 4 2.0 Audit Findings... 5 2.1 A Project Management Framework is not sufficiently established to support project management... 5 2.2 The Stage-Gate process is not consistently followed by project stakeholders... 7 2.3 Project progress reporting needs to be improved... 8 2.4 The PMIS is not consistently used by project stakeholders... 10 3.0 Conclusion... 12 4.0 Statement of Assurance... 12 Appendix A: Audit Criteria Assessment... 13 Appendix B: Glossary... 14

Internal Audit Services Branch (IASB)

Audit of Management of Projects within ESDC Executive Summary Employment and Social Development Canada (ESDC) is currently managing a significant investment portfolio, with 87 projects estimated at over $500 million. 1 The Department has initiated projects that respond to the government priorities to modernize service delivery, implement new policies, and increase effectiveness and efficiency of operations. In order to effectively manage these projects, ESDC had developed an Investment Management Process (IMP) which included the approval and review of projects throughout their life cycle. The department-wide process provides oversight to all large projects and procurements in ESDC in order to deliver value for money to Canadians. Audit Objective The objective of the audit was to assess the adequacy and effectiveness of the Department s Project Management Framework. Summary of Key Findings Over the course of the audit, major findings relevant to the assessment of the Project Management Framework emerged from document review, consultations, interviews and case studies. The key findings are summarized as follows: ESDC has established some components of a Project Management Framework but a complete framework has not been developed to support project management across the Department; The Department adopted an industry standard gating process to prioritize, select and approve projects through decision gates throughout the life cycle of a project but it was not consistently followed by project stakeholders. Documentation was available to guide project stakeholders through the process but stakeholders were attempting to work outside the departmental gating process. A formal mandate to enforce the gating process has not been established; Progress reporting to track the status of large projects relies on information provided by project stakeholders but it is incomplete to accurately track progress. The rating system to provide progress on projects is interpreted in an inconsistent manner by project stakeholders. The Enterprise Project Management Office (EPMO) does not have a formal mandate to monitor the completeness of the project information that is reported to them, nor do they have the tools that would allow them to assess the accuracy of project information; and 1 Source: The ESDC Project Portfolio Report for the fourth quarter of 2012 2013 and the first quarter of 2013 2014, September 9, 2013. 1

Internal Audit Services Branch A Project Management Information System (PMIS) has been developed but the full functionality is not used by project stakeholders. The capacity of the system has not been leveraged to generate reliable and accurate project reports, as well as to share knowledge and best practices among project stakeholders. The PMIS is being upgraded and needs to be mandatory to resolve the inconsistent use by project stakeholders. Audit Conclusion The audit concluded that the Department has not developed and articulated a consistent enterprise level framework to manage its investment projects. Although the Department has implemented some components that are part of a Project Management Framework, there is a lack of project stakeholder buy-in and compliance with the established processes. A comprehensive approach is required to establish a framework that will support reliable project delivery and oversight. Recommendations The Chief Financial Officer (CFO) should: Develop and communicate to the Department a comprehensive Project Management Framework with formal accountability, roles and responsibilities; Assign the accountability to enforce the gating process as part of the development of the Project Management Framework; Redesign the project progress reporting to include baseline data and develop a follow-up system to escalate projects of concern; and Establish the PMIS as the mandatory departmental system to be used for project management. 2

Audit of Management of Projects within ESDC 1.0 Background 1.1 Context In 2007, the Treasury Board (TB) of Canada introduced the Policy on Investment Planning Assets and Acquired Services and the Policy on the Management of Projects. These policies introduced a significant change in how government carries out investment planning and project management. The successful implementation of these policies by April 1, 2012, was intended to support improved accountability and strengthen management practices across government. ESDC implemented the IMP in 2008 to meet the requirements of the Policy on the Management of Projects and since that time has embarked on a journey to continuously improve the Department s project management practices. In compliance with the policies and standards, 2 ESDC prepared the 2011 2016 Investment Plan, which was approved by TB in 2012. As part of the policy requirements, ESDC also completed a self-assessment of their organizational capacity in 2011 using the TB Organizational Project Management Capacity Assessment (OPMCA) tool. Based on the results of the self-assessment, ESDC prepared an OPMCA Action Plan to address areas needing improvement, which became the Streamlining Plan to improve project management practices in the Department. The OPMCA self-assessment was approved by TB in 2012 and resulted in an organizational capacity class rating of Level 2 Tactical of five potential levels. 3 The rating established the expenditure authority granted to the Department for the approval of projects, which is to be reviewed every three years. In December 2012, the ESDC Major Projects and Investments Board (MPIB) presented a Streamlining Plan to the Corporate Management Committee (CMC) to address weaknesses in the Project Management Framework and to improve departmental project management practices. The Department also identified key priorities to advance the Project Management Framework. However, the audit team noted that the Streamlining Plan to address the areas targeted for improvement had not been implemented. 1.2 Audit Objective The objective of the audit was to assess the adequacy and effectiveness of the Department s Project Management Framework. 2 TB Secretariat Standards: Enterprise Resource Planning Systems, Organizational Project Management Capacity, Project Complexity and Risk and Electronic Documents and Records Management Solutions. 3 The five levels are: Level 0 Limited, Level 1 Sustaining, Level 2 Tactical, Level 3 Evolutionary and Level 4 Transformational. 3

Internal Audit Services Branch 1.3 Scope The audit examined the components of ESDC s Project Management Framework. This included governance, roles and responsibilities and processes established as part of the framework. 1.4 Methodology This audit used a number of methodologies to assess the Project Management Framework within ESDC including: Document review and analysis; Interviews with project managers and other project stakeholders within the Department; and A random sample of nine project case studies from the departmental Investment Plan. 4

Audit of Management of Projects within ESDC 2.0 Audit Findings 2.1 A Project Management Framework is not sufficiently established to support project management A Project Management Framework defines the roles and responsibilities, establishes the processes to be followed, and provides the tools to be utilized by project stakeholders in order to support the consistent management of projects across an organization. Our audit expected that ESDC established and articulated a Project Management Framework for all departmental project stakeholders to follow. The audit found that ESDC has established some components of a Project Management Framework but the Department has not articulated a complete framework to guide project stakeholders through the project life and control cycles. The audit team noted that the Department developed a draft document describing the Project Management Framework for ESDC but it was not completed for approval or communicated to the Department. Our review of the draft framework identified that it was insufficient as a Project Management Framework as it focused primarily on the gating process. The Department has adopted the industry standard Stage-Gate 4 process as an integral part of the Project Management Framework. This structured gating process is used to prioritize, select, and approve projects through five management decision gates as well as to prescribe the activities required in each stage to develop the project from idea through to close. Although a key element of a Project Management Framework, a project approval process alone is not sufficient to support project management across an organization. For example, a comprehensive Project Management Framework would include: A definition of the type of projects subject to follow all aspects of the framework and the minimum project management standards for all large and small projects; Performance management of projects to support informed decision making; Prioritization and resource management processes to achieve business objectives; A quality assurance process for project outputs to comply with standards; Processes for communication, change management and continuous improvement to support the framework; Defined roles and responsibilities for project life and control cycle management; and Fundamental information on all processes, tools and techniques stakeholders are required to use in carrying out their respective roles and responsibilities. 4 Stage-Gate TM divides the effort into five distinct management decision gates: Gate 1 Opportunity Identification, Gate 2 Concept Initiation, Gate 3 Plan, Gate 4 Develop and Build, and Gate 5 Deploy, Install and Stabilize. 5

Internal Audit Services Branch Our audit confirmed that ESDC has established governance for project management in the Department. The MPIB is the enterprise-wide governance body responsible for investment planning and project oversight. MPIB, as per its Terms of Reference, is mandated to support rigorous and transparent project planning, project management, and investment decisions. MPIB is supported by the Director General-level Major Projects Review Committee (DG MPRC). Within the direction set by MPIB, the DG MPRC is responsible to review the initial phases of all large projects prior to MPIB s review of the final phases of the project. In support of governance, the IMP Team, within the Chief Financial Officer Branch (CFOB) is responsible for maintaining the Investment and Project Management Frameworks. As per the investment plan, the IMP Team has been designated as the EPMO and the Project Management Centre of Excellence (CoE) for the Department. The IMP Team coordinates the investment planning exercise, prepares the departmental investment plan, and monitors and reports on project investments. The IMP Team collaborates with Branch Project Management Offices (BPMO) to coordinate investment planning and project management activities. The BPMO within the Innovation, Information and Technology Branch also provides additional information technology (IT) support to project stakeholders for projects that are IT-enabled. Although there is an active governance structure in place, the audit revealed that the IMP Team s role as the EPMO and CoE is broadly defined and the roles and responsibilities are not formalized. Project stakeholders across the Department did not understand the role of an EPMO and did not always follow the guidance provided by the IMP Team. For example, it was not clear to project stakeholders as to the degree of control and influence that the IMP Team had on projects within the Department. As a result, the IMP Team could not consistently enforce the application of standards when providing guidance to project stakeholders. Within a Project Management Framework, the EPMO requires a mandate with sufficient resources to provide support and control functions to project stakeholders across the Department. This would allow for the consistent application of standards, mentoring, resource development, reporting and technology to manage project outcomes on a portfolio basis within the Department. A comprehensive Project Management Framework with clear roles and responsibilities is needed to implement standard project management approaches to keep projects on-track, on-time and within budget. Recommendation The CFO should develop and communicate to the Department a comprehensive Project Management Framework. This includes establishing formal accountability to enforce the application of the framework and clearly defining the mandate, roles and responsibilities of all project stakeholders. 6

Audit of Management of Projects within ESDC Management Response Agree. The CFOB will finalize and communicate a comprehensive Project Management Framework taking into consideration policy obligations, stakeholder input and sound project management practices. The estimated completion date is March 2014. 2.2 The Stage-Gate process is not consistently followed by project stakeholders A Project Management Framework provides a consistent process for the required approvals throughout the life cycle of a project. Our audit expected that the Department implemented a project management process which is followed by project stakeholders to prioritize, select, and approve projects through decision gates as well as to prescribe the activities required in each stage to develop the project from idea through to close. As per the departmental Investment Plan and the MPIB Terms of Reference, all investment projects greater than $1 million or deemed sensitive must use the Department s standard Stage-Gate Process. The audit revealed that although the Department has adopted a standard process, gating is not followed consistently by project stakeholders. The audit team randomly selected nine projects as case studies and of the nine selected, five projects had not scheduled their next management decision gate and four were not gating as expected. Of the four projects that did not gate we noted the following: The first project was cancelled after Gate 2 without any evidence of cancellation; The second project was completed without gating; The third project stopped gating after Gate 2; and The fourth project was almost completed without gating and has since returned to gate. Some of the reasons mentioned by project stakeholders for inconsistent gating were a lack of awareness of the gating process and that project guidance and tools were not sufficient to navigate the project life cycle. MPIB has identified that improvements to the gating process and tools and templates are required through the Streamlining Plan. However, the audit team determined that guidance provided by CFOB on the gating process, as well as the project list approved as part of the annual Investment Planning exercise, were available to all project stakeholders on the Department s Intranet site under the IMP. The audit team noted that there was a lack of buy-in to gating and that project stakeholders were attempting to work outside of the gating process. Without consistent gating, senior management does not have the opportunity to assess how a project is performing against planned goals at all stages. Although MPIB provides departmental oversight for project management, a formal mandate to enforce gating has not been assigned. This, coupled with the need to develop a comprehensive Project 7

Internal Audit Services Branch Management Framework, has left a void to enforce consequences for project stakeholders who choose not to follow the gating process. Formal accountabilities to enforce gating are required so that project stakeholders acquire the discipline and rigour needed to manage large investment projects in a consistent manner. A fully defined and functioning Project Management Framework will require project stakeholders to proceed through the departmental gating process. Recommendation The CFO, in consultation with members of the MPIB, should assign the accountability to enforce the gating process as part of the development of the Project Management Framework. Management Response Agree. The Project Management Framework and Directive will outline the project gating requirements and assign accountability to the Project Sponsors to support mandatory compliance. The estimated completion date is March 2014. 2.3 Project progress reporting needs to be improved Progress reporting is essential to monitor the achievement of project outcomes against planned results, identify issues and make necessary course corrections. Our audit expected that the Department established a reporting approach as part of the Project Management Framework to assess results against planned activities. Our audit observed that the IMP Team established a reporting approach to track the status and progress of large projects within the Department. The approach consists of preparing two key reports, the Executive Dashboard and the ESDC Project Portfolio Report. The Executive Dashboard contains details on the progress of individual projects and is periodically updated by project stakeholders. Using the Executive Dashboard, the IMP Team creates the ESDC Project Portfolio Report on a quarterly basis. The Project Portfolio Report contains key project information and uses project health indicators consisting of a green, yellow and red rating system to identify if projects are on track, are experiencing challenges, or have major concerns related to budget, schedule, scope, risks and issues. The IMP Team also prepares a quarterly progress report to provide MPIB and CMC an overview of project progress. As the IMP Team does not have a formal mandate to monitor the accuracy or completeness of the project information, they rely on and report data provided by project stakeholders. The audit team reviewed the project status reports and observed that the information provided by project stakeholders was incomplete to accurately track progress. For example: 8

Audit of Management of Projects within ESDC Some approved projects with a value of more than $1 million were not included in the project status report; Baseline data, such as the actual start date, was not captured in order to assess and report on project progress; Some projects did not provide a status update; and Projects that identified issues provided minimal information regarding the cause or mitigating actions. Our analysis of the reports also confirmed that the Executive Dashboard rating system of green, yellow and red is not interpreted in a consistent manner by project stakeholders. For example: Some projects identified changes in scope, delays in meeting the original timeline, or a missed scheduled gate, yet these projects reported their status as green. Explanations were not provided for the scope change or for the delays. Resulting impacts on other projects were also not identified; Some projects were rated yellow for the overall project health indicator and included a red rating for risk. An explanation of the risk or the mitigating strategy was not provided; and Dates to identify the next decision point for some projects were identified as TBD, which indicated that the date was to be determined. Follow-up information was not provided to indicate a specific date for future monitoring. The fidelity of the reporting needs to be improved by project stakeholders to provide MPIB with information in order to measure objectively how well a project is accomplishing its deliverables. There is also an opportunity for the EPMO to revise the reports to include baseline data related to cost, schedules, and resources. This would allow MPIB the capability to monitor projects of concern, identify project interdependencies, and determine if further corrective action is required. Currently, the EPMO does not have monitoring tools that would allow them to compare or assess the accuracy of project information provided by stakeholders. As such, the EPMO does not have the capability to identify discrepancies and bring them to the attention of MPIB. Recommendation The CFO should redesign the project progress reporting to include baseline data as part of the development of the Project Management Framework and develop a follow-up system to escalate projects of concern to MPIB. 9

Internal Audit Services Branch Management Response Agree. CFOB will review current reporting requirements and tools to identify opportunities for enhancements to escalate projects of concern to MPIB. The estimated completion date is June 2014. 2.4 The PMIS is not consistently used by project stakeholders The use of a PMIS has been found to contribute to the successful delivery of projects. Our audit expected that the Department established a PMIS to be used by all project stakeholders to collect, store and distribute project information to support decision making and monitor progress. The Department has a PMIS that was previously used exclusively for IT and projects that were IT-enabled. However, in 2011 2012 the Department began expanding the use of this system to include all investment projects. The PMIS contains information essential to initiating, planning, executing and closing a project. The audit did not include an assessment of the PMIS as we were advised that the Department is currently upgrading to Microsoft (MS) Project Server 2010 from the 2003 version. The Department is also implementing the SAP Enterprise Resource Planning System planned for 2014, which will include a Project Module to manage project financial information. Microsoft Project Server 2010 and the SAP Module are intended to form the future PMIS. The audit team noted that project stakeholders were working in a somewhat manual environment. For example, project stakeholders were: Storing project documents on branch common drives, which limits access to project stakeholders who may need the information and contributes to version control issues; Using MS Word and Excel derived templates, which required users to input information and data multiple times; and Submitting project status information manually to the IMP Team rather than entering the information directly into PMIS. The full functionality of PMIS is not being used by project stakeholders. The automated tools available within PMIS are used inconsistently and project information is not captured nor consolidated so that interdependencies between projects can be managed. In addition, the capacity of PMIS has not been leveraged to generate reliable and timely reports that would allow MPIB to monitor progress of projects. Transition to an updated version of PMIS will not resolve the inconsistent use of the system by project stakeholders. The PMIS will need to be aligned to the Project Management Framework with mandatory use to maximize the functionality and value for money of a single system. Additionally, the development of a change management strategy would help identify gaps, possible points of resistance, and a strategy to address issues before they emerge. A centralized information system also provides opportunities for project stakeholders to share project management knowledge, experiences and best practices. These lessons learned would provide all project teams with the opportunity to benefit from the experiences of others and apply this knowledge to their own projects. 10

Audit of Management of Projects within ESDC Recommendation The CFO should establish the PMIS as the mandatory departmental system to be used for project management in order to facilitate accurate information and knowledge sharing across the Department. Management Response Agree. The Project Management Framework and Directive will identify the PMIS as the mandatory departmental tool to support projects and will assign accountability to Project Sponsors to ensure it is used. The estimated completion date is March 2014. 11

Internal Audit Services Branch 3.0 Conclusion The audit concluded that the Department has not developed and articulated a consistent enterprise level framework to manage its investment projects. Although the Department has implemented some components that are part of a Project Management Framework, there is a lack of project stakeholder buy-in and compliance with the established processes. A comprehensive approach is required to establish a framework that will support reliable project delivery and oversight. 4.0 Statement of Assurance In our professional judgement, sufficient and appropriate audit procedures were performed and evidence gathered to support the accuracy of the conclusions reached and contained in this report. The conclusions were based on observations and analyses at the time of our audit. The conclusions are applicable only for the assessment of the departmental Project Management Framework. The evidence was gathered in accordance with the Internal Auditing Standards for the Government of Canada and the International Standards for the Professional Practice of Internal Auditing. 12

Audit of Management of Projects within ESDC Appendix A: Audit Criteria Assessment It was expected that the Department s Project Management Framework is working effectively to demonstrate that: 1. The Department has the capacity to manage its investments through: A collaborative project portfolio environment; Efficient systems and processes; Project prioritization; The allocation of resources to support top priorities; Interdependency management; Project managers with the necessary knowledge, skills and experience; and Clear and consistent information, tools and training. 2. Project delivery is on time, on budget and on scope as a result of timely and appropriate: Project oversight supporting decision making; Management of project issues, risks and change requests; Project tracking and reporting; and Access to real-time data on costs, benefits, and schedules. 3. The Project Management Framework supports project delivery by: Understanding the current state of project management and developing an action plan that addresses weaknesses; Executing strategies to address the identified weaknesses; Ensuring that lessons learned improve project management governance and oversight mechanisms; and Clearly communicating best practices and lessons learned to all stakeholders. 13

Internal Audit Services Branch Appendix B: BPMO CFO CFOB CMC CoE DG MPRC EPMO ESDC IMP IT MPIB MS OPMCA PMIS TB Glossary Branch Project Management Office Chief Financial Officer Chief Financial Officer Branch Corporate Management Committee Centre of Excellence Director General Major Projects Review Committee Enterprise Project Management Office Employment and Social Development Canada Investment Management Process Information Technology Major Projects and Investments Board Microsoft Organizational Project Management Capacity Assessment Project Management Information System Treasury Board 14