Regional Expansion SB 350 Implementation Timeline Special Study Portfolios

Similar documents
Interregional Transmission Project Evaluation and 50% RPS Out-of-state Portfolio Assessment Study Plan

Anchor Data Set (ADS) Definition, Benefits, Implementation and Management Ver. 6-Aug 15 th DRAFT Proposal only

Jan Strack and Huang Lin March 14, 2017

Utility Scale Integration of Wind and Solar Power

Regional Coordination in the West: Benefits of PacifiCorp and California ISO Integration

Fred Stoffel. Tri-State Generation and Transmission Association, Inc. May 19, Utility Resource Planning Fundamentals

California s Renewable Portfolio Standard

CCA Terms Glossary. Valley Clean Energy Alliance. i CCA Terms Glossary

Imperial County Transmission Consultation Current Resource Deliverability Capabilities from Imperial Valley

Exploring the Impacts of California s Renewable Portfolio Standard

2016 Fall Reliability Conference MRO

Business Practice Manual for the Transmission Planning Process

Business Practice Manual for Reliability Requirements. Version 34

Renewables Portfolio Standard (RPS) Sara Kamins April 2, 2008

SPP at a Glance. Located in Little Rock. Approximately 600 employees

California s Energy Storage Mandate

Transmission Planning Strategies to Accommodate Renewables

Generator Interconnection Driven Network Upgrade Cost Recovery. Draft Final Proposal

May 9, This presentation will summarize some key takeaways from the most recent Pacificorp Integrated Resource Plan (IRP) filed in April 2017

CAISO s Flexible Resource Adequacy and Must Offer Obligation Phase 2 Revised Straw Proposal Public Generating Pool and Public Power Council Comments

The CCA Handbook. A Guide to Conducting Business with Southern California Edison under Community Choice Aggregation. Version 3.

February 15, Mr. Steve Berberich President and Chief Executive Officer California Independent System Operator P.O. Box Folsom, CA 95763

Introduction to the Energy Imbalance Market (EIM Module 1)

March 17, 2017 BOARD APPROVED

Benefits for Participating in EIM February 1, 2016

Transmission Planning Process Unified Planning Assumptions and Study Plan March 31, 2017 FINAL

California ISO Public

EAGLE MOUNTAIN Hydro Electric Pumped Storage Project

Flexible Resource Adequacy Criteria and Must Offer Obligation Phase 2. Revised Straw Proposal Short Term Solutions

Rice Solar Energy Project

Northwest Power and Conservation Council NW Power Markets Symposium Products & Transactions

EVALUATION OF MIDWEST ISO INJECTION/WITHDRAWAL TRANSMISSION COST ALLOCATION DESIGN. Prepared by Scott Harvey and Susan Pope

PacifiCorp 2017R Request for Proposals. Pre-Issuance Bidders Conference May 31, 2017

Oregon Department of ENERGY

Transmission Planning Process Unified Planning Assumptions and Study Plan. March 31, Final

BEFORE THE PUBLIC UTILITIES COMMISSION OF THE STATE OF CALIFORNIA

Transmission Planning Process Unified Planning Assumptions and Study Plan. February 22, Draft

Capturing the Benefits of Energy Efficiency Through Target Setting

Best Practices in Conducting Grid Integration Studies

Load Serving Entity Definition Refinement Draft Final Proposal

ENERGY COMMISSION PUBLIC UTILITIES COMMISSION

Tucson Electric Power 2017 Integrated Resource Plan. Southern Arizona Regional Solar Partnership Jeff Yockey, PE

Transmission Planning at the Midwest ISO. Mr. Eric Laverty Senior Manager of Transmission Access Planning Midwest ISO June 26 th, 2008

SB 838: Oregon Renewable Energy Act Establishing an Oregon Renewable Energy Standard

Stakeholder Comments Template

Portland General Electric 2016 Integrated Resource Plan. OPUC Public Meeting December 20, 2016

High Voltage Direct Current

UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION

the most promising locations for new renewables in the Imperial CREZ.

Direct Access to Renewables The Greening of Choice

SB 350 Study: The Impacts of a Regional ISO-Operated Power Market on California

PACIFICORP DEMAND-SIDE RESOURCE POTENTIAL ASSESSMENT FOR

MON TANA M EAN S BU SINE SS MONTANA TRANSMISSION FOR AMERICA CLEAN ENERGY AND TRANSMISSION DEVELOPMENT IN MONTANA AND THE WEST

Energy Imbalance Market Year 1 Enhancements Phase 2. Draft Final Proposal

INTEGRATED TRANSMISSION PLANNING MANUAL

Renewable Portfolio Standards

Wind Power Transmission Case Studies Project National Wind Coordinating Committee

1. Is there a preference between MW and MWh? RPS need for San Diego Gas & Electric is based upon a percentage of retail sales, which is in MWh.

CALSEIA 2017 Legislative Session Wrap-Up October 16, 2017

PJM Manual 14A: New Services Request Process Revision: 20 Effective Date: October 1, Prepared by Interconnection Planning Department

Review Transmission Access Charge Structure. Straw Proposal

WWSIS - 3: Western Frequency Response and Transient Stability Study

Acreage Needed in 2050 for Renewable Generation to Meet California s GHG Emission Reduction Goals California Energy Commission May 9, 2011

Briefing on 2018 Policy Initiatives Roadmap and Annual Plan

Wind energy resource development along the Baja California-U.S. Border: progress and potential hurdles

Final Flexible Capacity Needs Assessment for 2018

SB 838: Oregon Renewable Energy Act Establishing an Oregon Renewable Energy Standard

2011 Update Of the San Francisco Electricity Resource Plan (2002 ERP)

April 28, Filing of CAISO Rate Schedule No. 90 Docket No. ER

Bad News and Good News

Final 2014 Flexible Capacity Needs Assessment

APPENDIX B: WHOLESALE AND RETAIL PRICE FORECAST

DATA ASSUMPTIONS AND DESCRIPTION OF STUDIES TO BE PERFORMED 2014 EGSL & ELL Integrated Resource Plans

Bad News and Good News

California Independent System Operator Corporation Fifth Replacement Electronic Tariff

ERCOT ISO: Current Market and Trends in Future Market Design

Draft Whitepaper to Platte River Board of Directors

Distributed Energy Resources Integration

Temporary Shutdown of Resource Operations. Straw Proposal

Ruby Pipeline Project

2017 Integrated Resource Plan. February 2017

The Implementation of California AB 32 and its Impact on Wholesale Electricity Markets

2011 Congestion Assessment and Resource Integration Study

Western EIM Benefits Report Second Quarter 2017

MEMORANDUM. January 6, Power Committee. Maury Galbraith. Draft Sixth Plan Electricity Price Forecasts

A New Market for Energy Regulation: Advancing the Clean Energy Revolution

NCSL Transmission Policy Institute Denver, CO

SMUD. Renewable Energy. Resources Eligibility Guidebook. First Edition October 2008 SACRAMENTO MUNICIPAL UTILITY DISTRICT

Executive Summary MQRI-OPS 2

Table of Contents CHAPTER 5 - RECOMMENDATIONS THAT EMPOWER SAN FRANCISCO TO INFLUENCE PROCUREMENT OF ELECTRIC RESOURCES AT THE WHOLESALE LEVEL...

Can IOU Demand Response Programs Facilitate Integration of Wind and Solar Energy Needed to Achieve California s 33% Renewables Portfolio Standard?

Dynamic Transfers Revised Draft Final Proposal

Water & Energy Consulting Lon W. House, Ph.D.

Impact of EIM Imports on Carbon and REC accounting. Clare Breidenich Western Power Trading Forum Regional Issues Forum September 7, 2017

SCE Background PG&E LADWP SDG&E

BEFORE THE PUBLIC UTILITIES COMMISSION OF THE STATE OF CALIFORNIA CALIFORNIA INDEPENDENT SYSTEM OPERATOR CORPORATION DETERMINISTIC STUDIES

Decarbonizing California: What is required & what are the options to get it done?

Western Wind & Solar Integration Studies

Marin Clean Energy Applicant Analysis for the County of Napa

The Interaction of Complementary Measures and the Cap & Trade Program under in AB32

Transcription:

Comments of TransWest Express LLC on Topics Discussed during the CPUC and ISO June 20, 2016 Telephone Call to discuss the California ISO 2016-2017 Transmission Planning Process, 50% RPS Special Study Introduction TransWest Express LLC (TransWest) appreciates the efforts of the CPUC and the California ISO in getting the 2016-2017 Transmission Planning Process (TPP) 50% RPS Special Study organized and sharing the objectives, scope and methodology with the stakeholders. We also appreciate the opportunity to provide these comments for consideration in augmenting and completing this very important study. The study, although for information purposes only, is very important because it will help inform various agencies and market participants about the potential solutions to the integration challenges associated with supplying over half of California s electric energy needs with renewable resources. The study is also important due to the compressed timeframe to reach the incremental 40% target in 2024, 45% in 2027 and the 50% RPS in 2030. The 40% target is well within the 10-year 2016-2017 TPP planning horizon. Transmission solutions, especially longdistance lines, take many years to develop and place in service, hence the 10-Year planning horizon. The adoption of Senate Bill 350 (SB350) with its 50% RPS mandate in late 2015 has required the CPUC and the ISO to conduct a three annual TPP cycle prior to approval of any transmission solutions to meet the SB350 Policy Transmission needs. In the 2015-2016 TPP the 50% RPS special study provided useful information to improve the information the CPUC needs to inform their policy decisions. The 2016-2017 study needs to take this analysis further and tee up the required information for the CPUC and ISO to consider in their respective 2017-2018 Needs Assessments for the 2018 to 2028 planning horizon. In addition, Market Participants, particularly load serving entities with RPS obligations, will need to have the information from this study to inform their procurement and integrated resource planning activities.

Page 2 Regional Expansion TransWest notes that SB350 also included provisions for the regional expansion of the ISO. Since passage in late 2015 an enormous amount of work and effort has gone into this initiative. TransWest supports the regional expansion and suggest that the provisions of an expanded ISO in to the PacifiCorp regions be incorporated into the 2016-2017 TPP 50% RPS Special Study. The Special Study should look at both solutions that provide direct access between OOS resource areas and California load as well as solutions that only require access between the OOS resource areas and non-californian load centers within the expanded market regions. Given the amount of resources dedicated to regional expansion initiative since the passage of SB350, the TPP Special Study should consider an expanded region as a possibility. The ability to approve any Policy Transmission following the 2017-2018 TPP Needs Assessment will need to be informed on how that transmission investment may be impacted by the regional expansion. Once again, agencies and load serving entities could use this information to better plan and implement investment and transaction activities to reach their respective policy obligations. SB 350 Implementation Timeline TransWest appreciates the timelines provided by the CPUC and the ISO to outline the sub-tasks within the Special Study. We agree the key objective of the study is to update the RPS Calculator with information on transmission to help inform the 2017 Assumptions and Scenarios for the TPP and Long Term Procurement Planning (LTPP). TransWest has developed the attached timeline based on our understanding of the ongoing processes in California and regionally that are looking at transmission solutions to meet the increasing RPS needs of California and the region. The arrows between the processes show the key data flows between the processes. The duration from the completion of the Special Studies in February 2017 to the start of the 2017-2018 TPP provides the CPUC and ISO very little time to use the information and for the public to review and comment on the data before it is used. TransWest would like to suggest that the ISO reconsider its methodology for the Special Study so that critical and less analytically demanding information be provided prior to February 2017. We outline these suggestions on methodology below. The Integrated Resource Plan (IRP) process required by SB350 will not be in place to inform the 2017-2018 TPP, although output from the 50% special study and from subsequent TPPs will likely be required to inform the development of IRPs. RETI 2.0 will be completed in time to help inform the 50% RPS TPP and LTPP in 2017. Special Study Portfolios TransWest is not certain why the ISO felt the need to request alternative portfolios from the CPUC to conduct the 50% RPS. We see some improvements over the portfolios provided in the 2016 Assumptions and Scenarios and we have some questions to better understand the reason for the alternative set of portfolios. As long as these portfolios will serve to improve the RPS Calculator with the transmission information that needs to be reviewed and revised for the most

Page 3 likely resource areas to be viewed as high potential areas to meet the 50% RPS requirements. We assume this confirmation has already taken place between the CPUC and ISO. The Special Study portfolios include CA-only and WECC-wide portfolios. This differs from the product content category requirements in SB350 and the 2016 Assumptions, Scenarios and portfolios that were all based on WECC-wide renewable resources with sufficient transmission to schedule delivery to the ISO system. It is not clear why CA-only portfolios were requested by the ISO. Transmission considerations for any areas that show up only in the CA-only portfolios should have a lower priority than the other areas. The Out-of-State (OOS) portfolios make reference to a set aside amount of resources in Wyoming and New Mexico. The term set aside implies that these resources had to be specially treated, set aside, to appear within the portfolio outcome. We understand this is most likely the case with the RPS Calculator. However, we point out that the metrics for these OOS portfolios with these set asides are all better than the CA-only portfolios. These resources may not be selected by the RPS Calculator without setting them aside. However, this should be more an indication of the limitation on the RPS Calculator and not the resources. It isn t clear how the 2,000 MW figure was selected for these two resource areas. The typical rating of new 500 kv AC line solutions are approximately 1,500 MW and for new DC line solutions can range from 1,500 MW to 3,000 MW or more. Since 4,000 MW of OOS resources provided better economics it may make sense to extrapolate that even more OOS resources would improve the metrics more. The ISO s SB350 study assumes 6,000 MW of OOS resources and the 2016 Assumptions and Scenarios document includes a scenario with 3,000 MW of Wyoming wind. The 2015-2016 TPP 50% Special Study found over 2,000 MW of capacity at the assumed entry points for these OOS resources. TransWest believes different ranges of OOS resources from Wyoming and New Mexico will make sense to analyze in the 50% special study. TransWest appreciates that the ISO and CPUC have provided portfolios for all cases that produce the same level of non-curtailed renewable energy. This was a deficiency in the 2016 Assumptions and Scenarios that was not accounted for in the metrics. Study Scope and Methodologies The Study scope should include a review and revision if required of the existing and potential new transmission capacity values to the highly likely resource areas. This seems to be the main focus of the scope. In addition, the capital cost estimates to realize the new transmission capacity levels should be reviewed and revised along with other basic information required in the RPS calculator for miles, voltage level, etc. With respect to the potential transmission solutions to meet the needs of the potential wind resources in Wyoming and New Mexico, RETI 2.0 has already catalogued a wide range of

Page 4 potential solutions. Some of these solutions and a couple of new ones since the RETI 2.0 review in late 2015 have submitted Interregional Transmission Project submittals to the ISO and other regions. In addition, many of these projects (e.g. Gateway, SunZia, Southline have completed Phase 2 and TransWest and SWIP-N are in Phase 2) have already undergone intensive reliability review within the Path Rating Process with involvement by the ISO. A secondary review of these study plans and reports should help provide a general overview of the reliability assessment for these projects without the need to conduct production cost modeling and reliability studies. The ISO should develop a comprehensive list of these potential solutions along with key project details. WECC and West Connect have similar databases that can be used to inform this listing. There may be data the ISO needs to review to confirm or revise, however this work could be completed faster than PCM and reliability studies themselves. Once this information is compiled, the scope of the PCM and reliability studies to fill in the gaps will be less than starting from scratch. In addition the PCM and reliability assessments can be performed on a more refined level in the 2017-2018 Needs Assessment. The information from this listing will be helpful as well to inform the generic project information updated in the RPS Calculator as well as needed market information for LSEs. Out-of-state resources, especially ones located in remote areas in Wyoming and New Mexico that require transmission additions cannot file Generator Interconnection Requests with the ISO. Therefore market participants do not have a way to request or to understand the impacts of such a request on the evaluated cost for the resources without the ISO reviewing these within the Special Study. It is quite possible that the RETI 2.0 TTIG and/or the Western Interstate Electric Board will develop such a listing. However the constraints on that process and resources at hand will require the ISO s review and confirmation on the key data. Once again we appreciate the CPUC and ISO efforts on the Special Study to help inform the SB350 requirement s and we look forward to continuing to work with you on this very important study. Contact Information Any questions or responses to these comments should be directed to: David Smith Director, Engineering & Operations TransWest Express LLC 555 17th Street, Suite 2400 Denver, Colorado 80202 (303) 299-1545 david.smith@tac-denver.com

27% 27% 27% 29% 29% 29% 29% 31% 33% 36.5% 38.3% 40% 43.3% 45% California/Regional Resource and Transmission Planning Timeframes 5 Jul 16 27% 34.8% 2015 2016 2017 2018 2019 2020 2021 2022 2023 2024 2025 2026 2027 2028 2029 2030 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Market Drivers CA RPS Requirements (SB 2, SB 350) 25% 41.7% 46.7% Other RPS Requirements CO(30%) 2025 NV(25%), AZ(15%), UT(20% goal) Clean Power Plan (Stayed as of Feb. 2016) Clean Power Plan Interim Compliance Period PacifiCorp ISO Integration ISO PacifiCorp Integration Target timeframe 48.3% 50% Resource Planning Process RETI 2.0 (CPUC, CEC, ISO, BLM non regulatory) RETI 2.0 50% CAISO Utilities CPUC biennial LTPP [R13 12 010] Scenarios for TPP CPUC RPS Proceeding [R15 02 020] CPUC Biennial LTPP/IRP [R16 02 007] CPUC IRP [R16 02007] to commence in 2017 RPS Calculator, LCBF improvements LTPP 50% RPS authorization IRP 50% RPS authorization CA IOU Utility Procurement 1 Utility Initial SB350 Procurement 2 5 6 WestConnect Utilities CA Municipal Utility (WestConnect) IRP 7 CA Municipal Utility (WestConnect) Procurement AZ & NV Utility (WestConect) IRP AZ & NV Utility (WestConnect) Procurement Transmission Planning Processes ISO 2016 2017 Annual TPP (50% RPS Info. only) ISO 2017 2018 Annual TPP (50% RPS authorization) special study from R13 12 010 2017 18 TPP TWE Review 50% RPS Approval 2016 17 TPP Planning Horizon 2017 18 TPP Planning Horizon ISO 2018 2019 Annual TPP (expanded ISO) 2018 2019 TPP 2018 19 TPP Planning Horizon ISO 2019 2020 Annual TPP 3 4 2019/20 TPP 2019/20 TPP 2019 2020 TPP Planning Horizon 2020 2021 TPP Planning Horizon WestConnect 2016 2017 Biennial Regional Planning Reg. Needs & Opportunities Analyze & Develop Plan 8 Planning Year NTTG 2016 2017 Biennial Regional Plan Develop Draft Plan Develop Final Plan Planning Year NTTG & WestConnect 2018 2019 Regional Planning NTTG & WestConnect 2020 2021 Regional Planning NTTG & WestConnect NTTG & W/C Plan. Yr. Plan. Yr. Regional Energy Market (ISO expansion w/ PAC) SB350 studies SB350 Studies Governor, Legislative process Legislature Governance design Stakeholder Process Governance design TAC, GHG, RA, GMC, FERC Filings PacifiCorp State regulatory proceedings Go No Go PacifiCorp state proceedings Go/No Go Go Live Implementation Go Live Legend Link Number Established Links Potential Links x