Renewable sources of energy, dispatching priority and balancing the system, facts and options: Part I

Similar documents
Pilot projects for storage: the Italian experience

CURRENT STATUS AND PERSPECTIVES OF RES DEVELOPMENT IN THE REPUBLIC OF MOLDOVA.

Integrating High Penetrations of Variable Renewable Generation Lori Bird and Debra Lew, NREL NCSL Webinar March 28, 2012

Making the Electricity System Work

CUC s Response to Alternative Energy

SPP at a Glance. Located in Little Rock. Approximately 600 employees

La regulación del incierto futuro de los sistemas eléctricos

Interconnection capacity and regulation

INDEPENDENT SYSTEM OPERATORS (VI + Access Rules vs. ISO vs. ITSO)

New England States Committee on Electricity

The Impact of Wind Generation on System Services in Ireland

Gas Natural Fenosa s Experiences on Renewable Energy Integration

Egyptian Renewable Energy plan

Where is moving the electricity sector and how are Electric. Industry Investment Decisions Influenced by Potential

Wind Power in Denmark. Steffen Nielsen Head of Section Danish Energy Authority Ministry of Climate and Energy

Flexibility in Indian Power System

Tucson Electric Power 2017 Integrated Resource Plan. Southern Arizona Regional Solar Partnership Jeff Yockey, PE

Methodology for calculating subsidies to renewables

FUEL OPTIONS NATURAL GAS VS. LPG VS. COAL

20 MW Flywheel Energy Storage Plant

Integrating Variable Renewable Energy into the Grid: Sources of Flexibility Best Practices and Case Studies

CHAPTER THREE. Load Curves The curve showing the variation of load on the power station (power plant) with reference to time is known as load curve.

Executive summary OECD/IEA Executive Summary

Development of Renewable Energies in Tunisia

Demand Response as Flexibility Provider: what are the challenges to achieve its full potential?

Generation in Germany under Decarbonisation: The German Energiewende Bangkok, November 2013

Flexible power generation and interconnection capacity needs of the Italian power system using PLEXOS LT plan.

Green+ ELECTRICITY AUTHORITY OF CYPRUS. NER 300 European Program 2 nd call of proposals Zero Energy Mountains of Cyprus. Green

Glossary of Terms in Sustainable Energy Regulation

The value of storage. Chris Elliott Senior Hydropower Engineer. 8 th November 2016

1st International Conference on Large-Scale Grid Integration of Renewable Energy in India Durgesh Manjure, MISO Energy September 6, 2017

Simulatie van het EU-wijde elektriciteitsysteem. Modellering van de elektriciteitsmarkt en de hierin gebruikte elektriciteitsinfrastructuur

The new role of DSO. David Trebolle Trebolle Manager, Active Networks and Network Analysis Applications Gas Natural Fenosa

Slide 1. ABB August 23, 2016

Medium Term Renewable Energy Market Report Michael Waldron Senior Energy Market Analyst Renewable Energy Division International Energy Agency

X Accept as requested X Change to Existing Practice Accept as modified below Decline

Integrated Planning Model (IPM ) Overview

New power bridges between Germany and Scandinavia

Cost of Service and Public Policy. Ted Kury Director of Energy Studies, PURC

Remuneration of RES and conventional power: Convergence or continued divergence?

Power to Gas. Bedeutung und Wirtschaftlichkeit verschiedener Power to Gas Umwandlungsketten , DGMK, Hannover

Renewable Portfolio Standards

1.818J/2.65J/3.564J/10.391J/11.371J/22.811J/ESD166J SUSTAINABLE ENERGY. Prof. Michael W. Golay Nuclear Engineering Dept.

Gas-Electric Coordination in PJM: Trends, Issues, Interactions, and Looking Ahead

Roadmap for Solar PV. Michael Waldron Renewable Energy Division International Energy Agency

Study of Using Energy Storage to Mitigate the Impact of High Renewable Energy Penetration to the Grid

Electricity tariff structure Spanish experience

Developing a Regional Roadmap on Energy Connectivity. China Electric Power Planning & Engineering Institute Bangkok

Integrating variable renewables: Implications for energy resilience

Relevant Energy Sectors in Portugal. Chapter 1

Solar Power Realities

IEA-DSM Task XVII: Country Report Austria

OVERVIEW OF THE ENERGY SECTOR IN ZAMBIA: CASE OF RENEWABLE ENERGY

The German Market Promotion Initiatives for Renewable Energies

ESP ENERGY SYSTEM PLANNING (PTY) LTD COMPANY EXPERIENCE (PROJECTS) Cons ulting Group

Variable Renewable Energy Sources in Distribution Networks Martin Braun Fraunhofer IWES & Universität Kassel

Framework conditions and public regulation for wind turbines in the Øresund Region Hansen, Kenneth; Mathiesen, Brian Vad; Connolly, David

EDF and Integration of Distributed Energy Resources

Energy Storage in a Grid with Fluctuating Sources : the German Perspective

Renewables, Smart Grids

The Electric Power System

Renewable energy in Europe. E-turn 21 workshop Cologne, 10 May 2006

28/09/16 1. Challenges for wind energy projects in. World Wind Energy Association. Legal Working Group. Eoin Cassidy. Ireland. Mason Hayes & Curran

Solar PV in ASEAN Challenges and Opportunities. Peerapat Vithayasrichareon Centre for Energy and Environmental Markets (CEEM), UNSW Australia

Electricity generation, electricity consumption, system integration, production and consumption balance

IV Riunione IU.NET. Towards the Internet of Energy A pathway to electric revolution. Paolo Tenti, Tommaso Caldognetto

Storage Solutions in Developing Countries A Case Study on the Market Potential for Battery Storage in Tanzania

DEMAND SIDE WATER ELECTROLYSIS COMPROMETIDOS CON SU FUTURO

Setting the Stage for Microgrid Discussions NGA Energy Resilience Retreat June 29, 2017

Generation Technology Assessment & Production Cost Analysis

Medium voltage products. Technical Application Papers No. 17 Smart grids 1. Introduction

CHAPTER 1 EXECUTIVE SUMMARY

RENEWABLE POWER GENERATION COSTS IN 2014

BEAST PROJECT. Energy Planning of Island Systems for Maximum Renewable Energy Penetration

1. Is there a preference between MW and MWh? RPS need for San Diego Gas & Electric is based upon a percentage of retail sales, which is in MWh.

Policy and Regulatory Approaches to Grid Integration of Renewable Energy in the US

ECONOMIC TRENDS OF ITALIAN ELECTRICITY SECTOR SHORT TERMS STATISTICS

2013/2014 RPM Base Residual Auction Results

August 22, 2014 FIRE ISLAND WIND

Market design What changes the winter package brings?

COGENERATION: Opportunities in Today s Power Markets

The Husker Power Plan: A New Energy Plan for Nebraska

Hydropower as Flexibility Provider: Modeling Approaches and Numerical Analysis

Presentation Overview

Renewable Integration at ERCOT

Grid-interactive Electric Thermal Storage (GETS) provides economic and environmental benefit

Workshop on photovoltaics, grid Integration and funding of the next wave of PV expansion in Cyprus, 13 December 2016.

Lebanese National Renewable Energy Grid Code

Impact of small solar PV on the NSW wholesale electricity market. Approved for Public Release 12 October 2017

Con Edison. Evolution of Con Edison efforts in Energy Efficiency and Demand Management:

ENABLING EMBEDDED GENERATION

SEIRP Technical Conference

Oman Energy and Water Conference May 2016

How to achieve Security of Energy Supply: The need for flexibility

Efficienza energetica, smart grid e fonti rinnovabili: la strada maestra per un Europa elettrica

Eastern Wind Integration and

The Role of Microgrids in Grid Modernization Initiatives Sima Seidi Principal Consultant, Microgrids and Distributed Energy Resources Tetra Tech

Support Schemes for PV in Europe

Status Quo - Storage systems and PV in a global context

BEFORE THE PUBLIC UTILITIES COMMISSION OF THE STATE OF CALIFORNIA CALIFORNIA INDEPENDENT SYSTEM OPERATOR CORPORATION DETERMINISTIC STUDIES

Transcription:

Renewable sources of energy, dispatching priority and balancing the system, facts and options: Part I Matteo Leonardi 22 May 2013

Liberalized markets versus monopolies Production Transmission distribution M o n o p o l y Natural monopoly Rules for third party access Sale

Connection to the grid Third Party Access right to the grid has to be regulated In a vertically integrated electricity system independent producers need to be protected with clear and transparent rules. In liberalized markets, the TSO is normally not used to RES, and SPP: a specific regulation needs to be introduced. Connection regards two stages: The line from the PP to the substation The grid enforcement requirement after plant/plants connection

From the PP to the substation Normally the power producer pays full cost of connection. The producers need to know the costs in advance and need to be sure about the timing of connection The regulator may Introduce standard connection costs: Connection cost may be defined in lump sum (according to km, aerial or underground line), for LV and MV connection, and be accurate for HV lines Introduce a maximum time for quotation and a maximum time for final connection

Grid reinforcement The producer may be asked to pay the necessary grid reinforcement (deep connection charge) The reinforcement costs are paid by the TSO and socialized into electricity tariff The regulator may introduce incentive for the TSO to reinforce the grid by allowing a higher remuneration on invested capital The TSO should follow the renewable planning and act accordingly. There is often a time lag between plant commissioning time and grid reinforcement.

Grid access When natural resources are concentrated in specific areas grid bottlenecks often occurs. Access may be given on an non-constrained approach or on a restricted queue-approach Curtailment rules need to be defined especially in countries with fragile grids. In case of queue approach the connection right may be given on First time first served Tendering of connection rights In case of first come first served maximum commitment time has to be introduced. This is often difficult to coordinate with licensing and planning permission.

ZONE A LFO 50MW 150 /MWh 20MW 20MW ZONE B LFO 100MW 130 /MWh

Integrating renewables DIESEL NATURAL GAS COAL RES NON COMPETITIVE HYDRO RES (Incentive or competitive)

Daily load

Load duration curve

DIESEL NATURAL GAS COAL HYDRO

Unpredictability and dispatching priority means that Unpredictable RES are better represented on the load curve rather than on the capacity one. The grey area represents the input from non predictable Renewable source of energy Source IEA worldenergyoutlook

Integration of PV system in Italy impact on pool prices (Italy 18july 2007-2012; Sicily 16 may 2007-2013

Wind cut-in and cut out

50kW PV system in cloudy conditions

Capacity credit Capacity credit is the peak demand less the peak residual demand, expressed as a percentage of the variable renewables installed. As a general rule low capacity credit renewables should not exceed 20-30% of load in order to guarantee acceptable standards for security of supply. 0% 100%

Integrating renewables into electricity market There are a number of instruments to regulate the integration of res into electricity market with particular reference to the unpredictable nature of the system. - Improve communication between the TSO and RES producers (weather forecast, monitoring) - Increase and improve interconnection - Increase storage (hydro or batteries) - Introduce economic signal to price fluctuation - Curtail RES or load to balance the system - Increase generation capacity with higher flexibility (NG)

Increase interconnection Highly interconnected systems are more stable then small ones. Denmark has met 100% of hour demand with wind power without security of supply concerns given the large availability of interconnection. Reinforcing interconnection is probably the most efficient solution for RES integration. Possible regulatory instrument to increase interconnection are: higher cooperation at regional level; higher remuneration on capital given to new transmission lines; Fluctuation will be transferred to neighbor countries. This may cause regional problems.

Storage Storage infrastructure (hydro or batteries) may be considered as reserve capacity. They can be directly managed by the TSO. Storage can be remunerated as a transmission infrastructure. Development costs are hence transferred into final tariff independently from the time of use. In isolated contexts the installation of storage batteries poses additional regulatory complication in setting tariffs. Block tariff can be used as a component for the remuneration of battery storage systems.

Regulating storage in off-grid systems Battery life span changes according to number of discharge cycles and depth of discharge. The deeper the discharge the shorter the life span of the battery. This can be transferred into a block tariff system.

Off grid / peripheral areas Electric systems that can accept lower levels of overall reliability may be able to manage the integration of RE into electrical power systems at lower costs than systems that demand higher levels of reliability, creating a trade-off that must be evaluated on a case-by-case basis.

Introducing peak hour incentive only Time of production FIT/premium may be introduced in order to orient programmable RES to produce during peak load Year kwh generation Peak hours Base load Up to 1 million (28,39-Pp)/P+Pp Pp Over 1 up to 2 millions (21,80-Pp)/P+Pp Pp Over 2 up to 3 millions (19,94-Pp)/P+Pp Pp Over 3 up to 4 millions (18,87-Pp)/P+Pp Pp Over 4 up to 5 millions (17,94-Pp)/P+Pp Pp Over 5 up to 10 millions (16,49-Pp)/P+Pp Pp Over ten millions (15,01-Pp)/P+Pp Pp Pp is the pool price P = 0.409 (ratio of peak hours / 8760) Autorità per l energia elettrica e il gas

Curtailments When non programmable renewable inputs exceed the capacity of the system to provide adequate reserve, curtailments rules have to be introduced. This can happen even if the renewable incentive scheme has posed a % cap over the development of non prog. RES. For instance if a technology reaches the grid parity, or if the natural resource (wind) is concentrated in some areas with a weak grid (bottle necks). Zone slots of MW may be allocated. In some cases curtailment occurs because of grid outages. Curtailment may significantly reduce the load factor of a technology. A specific regulation should be in place to reduce investment risk.

Possible compensation for curtailments In case of grid outages a compensation may be given to the renewable producer, this increase overall costs. Alternatively the incentive period/ppa may be extended for a period long enough to compensate the avoided production. (ie: Compensation = time of curtailment* 8760/average technology load factor) In case of excess of capacity not all RES plants need to be curtailed. The incentive may be reduced for those dispatching electricity and savings assigned to curtailed ones as compensation. It is also possible to introduce compensation for voluntary curtailments of final consumer (high load ones) who accept to be curtailed at a given price.

Natural gas Combined Cycle Gas Turbines are efficient and have short ramping time. They are a flexible technology with relatively low capital costs. CCGT are the ideal companion to respond to RES fluctuation

Hydro and other RES MW

Balancing cost + Balancing costs can be socialized, they can be paid by the TSO or by public utilities and then transferred to final tariff. Incentive/fine mechanisms may be introduced in order to stimulate accurate weather forecast and plant management to reduce as much as possible avoidable fluctuations. Cost are transferred to renewable producers through a balancing cost mechanisms. Cost may varies according to balancing services offered by other operators and by the overall balance of the area.

Balancing cost for renewable producers Sign of the area + - Renewable producer balance + the producer is supposed to pay full balancing service - The producers is compensated as his mistake has improved the overall balance + The producers is compensated as his mistake has improved the overall balance - the producer is supposed to pay full balancing service