US Army Corps of Engineers. Permitting Process. Chad Konickson. Chief, Southwest Section St. Paul District Regulatory Branch.

Similar documents
THE CORPS REGULATORY AUTHORITY

Navigating the U.S. Army Corps of Engineers Regulatory Process

WILMINGTON DISTRICT US ARMY CORPS OF ENGINEERS REGULATORY DIVISION. US Army Corps of Engineers BUILDING STRONG

Nationwide Permit General Conditions

Instructions for the South Pacific Division Nationwide Permit Pre- Construction Notification (PCN):

Regulatory Guidance Letter 93-02

NATIONWIDE PERMIT 32

US Army Corps of Engineers and Stream Restoration Permitting

Public Notice Charlestown Road New Albany, Indiana 47150

Department of the Army Permit Application

Public Notice. Applicant: City of Dallas Project No.: SWF Date: April 18, Name: Chandler Peter Phone Number:

Public Notice. Applicant: Lennar Homes Project No.: SWF Date: October 29, Name: Mr. Darvin Messer Phone Number:

Information for File #MVP MVM

Joint Public Notice. LOCATION: In Salmon Bay, Lake Washington Ship Canal, at Seattle, Washington.

ACTIVITIES AUTHORIZED BY 2012 NATIONWIDE PERMIT

J O I N T P U B L I C N O T I C E

SOLID WASTE DISPOSAL FACILITY CONSTRUCTION/DEMOLITION LANDFILL PERMIT APPLICATION PACKAGE. ADEM Form

Notice No Closing Date: May 12, 2017

6. The following paragraphs provide further interim guidance where the ACHP regulations are not specific to the Corps Regulatory Program:

COMPENSATORY MITIGATION AND THE MITIGATION RULE. USACE, Jacksonville District

New Developments in Federal Wetlands Permitting

J O I N T P U B L I C N O T I C E

DEPARTMENT OF THE ARMY GENERAL PERMIT FOR THE STATE OF MAINE

Public Notice ISSUED: August 11, 2015 EXPIRES: September 10, 2015

Information for File # PRH

I THOUGHT IT WAS JUST WET LAND: A GUIDE TO ENVIRONMENTAL PERMITTING FOR AIRPORTS ROAD SCHOOL 2018 SIMON DAVIES, SENIOR SCIENTIST MARCH 7, 2018

General Permit No: NAE Final Effective Date: August 18, 2017 Applicant: General Public in NH Expiration Date: August 18, 2022

PUBLIC NOTICE. REPLY TO: Denver Regulatory Office 9307 South Wadsworth Blvd 30 DAY NOTICE Littleton, CO FAX (303)

APPENDIX H Guidance for Preparing/Reviewing CEQA Initial Studies and Environmental Impact Reports

Public Notice of Application for Permit

US Army Corp of Engineers

Public Notice. This notice announces an application submitted for a Department of the Army (DA) Permit, subject to Section 404 of the Clean Water Act:

CESAM-RD-C April 24, 2013 PUBLIC NOTICE NO. SAM AFM JOINT PUBLIC NOTICE SAM AFM U.S. ARMY CORPS OF ENGINEERS

Effective: April 1, 2012 Expiration: April 1, 2017 Authority: 33 U.S.C. 401 et seq.; 33 U.S.C A. Introduction

Effective: April 1, 2017 Expiration: April 1, 2022 Authority: 33 U.S.C. 401 et seq.; 33 U.S.C A. Introduction

Environmental Information Worksheet

MEMORANDUM OF UNDERSTANDING Between UNITED STATES ARMY CORPS OF ENGINEERS And BNSF RAILWAY COMPANY

US Army Corps of Engineers

Public Notice ISSUED: June 29, 2017 EXPIRES: July 31, 2017

PUBLIC NOTICE. Dredging with ten-years maintenance, return flow to the waterway and upland placement. Georgica Cove, tributary of Georgica Pond

Department of the Army General Permit State of Rhode Island

DEPARTMENT OF THE ARMY GENERAL PERMIT STATE OF MAINE

Project Overview. Northwest Innovation Works LLC and the Port of Kalama propose to develop and operate

J O I N T P U B L I C N O T I C E

ATTACHMENT (12509-SPD EIS SOP) Statement of Responsibilities (Template)

APPENDIX F. SECTION 404(B)(1) EVALUATION SHORT VERSION. Herbert Hoover Dike Dam Safety Modification Study

INSTRUCTIONS FOR USING THE GENERAL PERMIT...i A. GENERAL DESCRIPTION AND FEES

Oregon Department of State Lands. Protecting Natural and Fiscal Resources to Support Schools

J O I N T P U B L I C N O T I C E

Construct and Operate a Rail Line Between North Pole, Alaska and Delta Junction, Alaska

The project will be conducted in partnership with the Nez Perce Tribe.

SAN LUIS VALLEY PUBLIC LANDS CENTER

Will be modified map from GIS 6/16 EOD

ILF Program Audit Methodology. James McElfish Senior Attorney Environmental Law Institute April 12, 2016

U.S. Army Corps of Engineers

RECORD OF DECISION I. INTRODUCTION

DRAFT GREATER MOOSES TOOTH TWO (GMT2) DEVELOPMENT PROJECT PERMITTEE RESPONSIBLE WETLANDS MITIGATION PLAN NATIONAL PETROLEUM RESERVE-ALASKA

October 19, 2017 Community Engagement Panel Meeting #4 Overview of Environmental Effects

Public Notice. East Kentucky Power Cooperative (EKPC) 4775 Lexington Road Winchester, KY

COST-BENEFIT ANALYSIS. Categorical Exclusions for Oil and Gas Exploration and Development Activities. USDA Forest Service

Department of the Army. Record of Decision

U.S. ARMY CORPS OF ENGINEERS BUILDING STRONG LOS ANGELES DISTRICT

JOINT PUBLIC NOTICE. April 14, 2014

3-13 Other Required Findings and Regulatory Compliance

PROSPECTS FOR COMPREHENSIVE, INTEGRATED WATERSHED MANAGEMENT UNDER EXISTING LAW

DEPARTMENT OF THE ARMY Wilmington District, Corps of Engineers 69 Darlington Avenue Wilmington, North Carolina April 24, 2017

Decision Notice and Finding of No Significant Impact

Cross-Cutting Environmental Laws A Guide for Federal/State Project Officers

S.O.P. No. HMD

Mississippi River/Gulf of Mexico Watershed Nutrient Task Force Timeline for Reassessment Revised 9/5/06. Revised 9/5/06. Symposia.

PUBLIC NOTICE PROJECT: Jack McNamara Field Airport (CEC) Runway Safety Area (RSA) Project

Remaining Wetland Acreage 16,194,500 8,784,200 7,410,300-46%

An Overview for Wetland Conservation & Management

Overview of the Clean Water Act and Water Quality Standards

NOTICE OF PREPARATION

~ ~ US Army Corps of Engineers Louisville District RECORD OF DECISION FOR INDIANAPOLIS NORTH FLOOD DAMAGE REDUCTION PROJECT MARION COUNTY, INDIANA

SAN FRANCISCO DISTRICT PUBLIC NOTICE PROJECT: San Francisco Marina West Harbor Maintenance Dredging

DECISION DOCUMENT NATIONWIDE PERMIT 12

Permitting Handbook. A guide to the permit process for activities that affect Indiana s waters. Indiana Department of Environmental Management

PUBLIC SCOPING MEETING AGENDA

Oil and Gas Energy. Transforming Ideas for the Energy We Use. gaiconsultants.com/energy

AGENCY: Department of the Army; Corps of Engineers; and Texas Commission on Environmental Quality

Seven years ago, the Federal Energy Regulatory

APPROVED JURISDICTIONAL DETERMINATION FORM U.S.

JOI NT PUBLIC NOTICE

REQUEST FOR INFORMATION REPORT (RFI) Contractor's Request for Information

APPROVED JURISDICTIONAL DETERMINATION FORM U.S. Army Corps of Engineers

Navigating the Environmental Compliance Process in Coastal California

Public Notice ISSUED: January 25, 2018 EXPIRES: February 24, 2018

Public Notice. This notice announces an application submitted for a Department of the Army (DA) Permit, subject to Section 404 of the Clean Water Act:

Stormwater Management Studies PDS Engineering Services Division ES Policy # 3-01

APPROVED JURISDICTIONAL DETERMINATION FORM U.S. Army Corps of Engineers

Distribution Restriction Statement

Notice of Availability of the Final Environmental Impact Statement for the Monument

Florida Department of Environmental Protection. Bureau of Mining and Minerals Regulation. Regulation of Mines. Howard J. Hayes, Program Administrator

APPROVED JURISDICTIONAL DETERMINATION FORM U.S. Army Corps of Engineers

DECISION DOCUMENT NATIONWIDE PERMIT 40

SRF 101 SRF Cross Cutters: Understanding the Environmental

STATE OF LOUISIANA NATIONWIDE PERMIT (NWP) REGIONAL CONDITIONS FEBRUARY 2012

US Steel/Spirit Lake Sediment Cleanup Update for River Corridor Coalition

Transcription:

US Army Corps of Engineers Permitting Process Chad Konickson Chief, Southwest Section St. Paul District Regulatory Branch May 7, 2013 US Army Corps of Engineers BUILDING STRONG

Outline St. Paul District Organization and Staff Statutory Authorities and Jurisdiction Permit Mechanisms for Transportation Projects Permit Evaluation Process Permit Application Completeness Requirements Information Needed for Project Analyses Issues Challenges Progress Factors that Lead to Longer Review Times How to Shorten Review Times Questions 5/14/2013 2

St. Paul District Organization and Staff 5/14/2013 3

Rivers & Harbors Act Oldest Federal environmental law in the U.S. Prohibits unauthorized obstruction or alteration of navigable waters (Section 10 RHA) Listed waters, such as Mississippi River, Minnesota River, Lake Superior, and many other rivers and lakes Structures or work in, over, or under navigable waters, or affecting the course, condition, or location of navigable waters Piers, wharfs, breakwaters, bulkheads, jetties, transmission lines, etc.

Clean Water Act Restore and maintain the chemical, physical, and biological integrity of the Nation s waters Waters of the United States (WOUS) Typically include navigable waters, their tributaries and most wetlands. Types of Activities: Discharges of dredged or fill material into WOUS (Section 404 CWA)

Permit Mechanisms for Transportation Projects General Permit (~3500/yr) RGP-003-MN: Impacts < 1/2 acre Individual 401 certification NOT required Letter of Permission (~ 150/yr) LOP-05-MN: Impacts < 5 acres Individual 401 certification NOT required Standard Permit (~50/yr) Impacts > 5 acres or activities not covered by GP/LOP Individual 401 certification IS required 5/14/2013 6

Overall Permit Evaluation Process Determine Jurisdiction Determine scope of review and type of permit required Solicit input/comment on proposal EPA, FWS, Tribes, state agencies often comment Prepare NEPA EA or EIS and make finding Public Interest Review (weighing and balancing) For Section 404 permits, must comply with CWA 404(b)(1) Guidelines (pass/fail) Comply with all other applicable federal laws, regulations, executive orders Permittee must obtain Section 401 Water Quality Certification/Waiver to obtain a valid Section 404 permit. Decision (Issue or Deny Permit) 5/14/2013 7

General Permit Process Complete application? Request more info if needed Confirm that proposal meets GP requirements Generally, no coordination with resource agencies Determine mitigation requirements Project Manager issues GP letter Individual 401 water quality certification NOT required (already granted with GP) National Performance Goal: 75% in < 60 days (2012 = 91%) 5/14/2013 8

Letter Of Permission Process Pre-application consultation recommended Complete application? Request more info if needed Confirm that proposal meets LOP requirements Post public notice on internet (10 days) Coordination with resource agencies Determine mitigation requirements Prepare decision document and LOP letter Individual 401 water quality certification NOT required Section Chief signs LOP letter with conditions National Performance Goal: 50% in < 120 days (2012 = 75% LOP/SP) 5/14/2013 9

Standard Permit Process Pre-application consultation recommended Complete application? Request more info if needed Issue public notice (30 days) Coordinate with resource agencies Tribal consultation Determine mitigation requirements Prepare environmental assessment, public interest review, 404(b)(1) analysis Individual 401 water quality certification required Branch Chief signs permit decision National Performance Goal: 50% in < 120 days (2012 = 75% LOP/SP) 5/14/2013 10

Information Needed for Complete Permit Application Name (POC), address, signature and date Purpose and need for project Description of project & location Drawings/plans showing ALL proposed activities Name/address of adjoining property owners Description of fill - type, quantity, locations List of all authorizations required for proposal, including all approvals received/denied Statement addressing avoidance and minimization measures and compensatory mitigation Source: 33 CFR 325.3

Purpose and Need Purpose and need statement describes the transportation problem It is the foundation for decisionmaking It drives the alternatives analysis Possible Source: CATEX, EA, project memo

Information for Permit Decision Waters/wetlands accurately identified (boundary concurrence) Thorough analysis of alternatives to avoid/minimize impacts Dismiss alternatives if: - they do not meet project purpose or - are not practicable or - are more damaging to the natural environment Demonstration of no practicable alternative to placing fill in wetlands Compensatory mitigation plan for unavoidable losses

404(b)(1) Guidelines Alternatives analysis (40 CFR 230.10) No discharge of dredged or fill material shall be permitted if there is a practicable alternative to the proposed discharge which would have less adverse impact on the aquatic ecosystem (LEDPA) Least damaging to aquatic resources Practicable alternatives: available and capable of being done considering cost, existing technology, and logistics in light of overall project purpose Applicant required to submit necessary information for Corps to determine compliance with the guidelines.

Primary Issues Increasing complexity of regulatory standards Shrinking fiscal resources Timeliness 5/14/2013 15

Challenges Federal Mitigation Rule published 2008 Rapanos Guidance (JDs) 2008 Regional Delineation Supplements 2008-2012 St. Paul District Mitigation Policy - 2009 Designated critical habitat for Canada Lynx - 2009 Increased emphasis on Tribal Consultation - 2009 National minimum standards for permit decision documentation - 2010 Compliance issues: NHPA Section 106 and ESA Section 7 2010 National Wetland Plant list 2012 Staff Turnover: Corps, FWS, SHPO 5/14/2013 16

Progress Corps/MnDOT/USFWS Agreement - 2004 Corps/MnDOT/SHPO Agreements - 2004, 2012 Preliminary Jurisdictional Determinations - 2008 MnDOT SALT/Corps Permit Guide Published summer 2012, on line Joint BWSR/Corps Outreach Training MnDOT/Corps Shared Historian Established Fall 2012 Application Checklist Developed in 2012, released update Jan 2013 Application Acknowledgement Card, March 2013 5/14/2013 17

More Progress? Update joint permit application form to aid in complete applications Opportunity to incorporate permit process earlier in project development schedules Increased Corps use of other environmental analyses for permit authorizations Potential GP for routine road work? Corps Transportation Liaison/Project Manager? In-Lieu-Fee Mitigation (LGRWRP)? 5/14/2013 18

Factors that Lead to Longer Review Times Presence of endangered species or critical habitat Historic properties or archaeological resources Inadequate delineations, particularly when submitted outside the growing season Incomplete description of impacts to aquatic resources Unclear Purpose and Need Lack of detail on project plans Lack of detail regarding avoidance and minimization measures Lack of detail regarding compensatory mitigation Missing or insufficient alternatives analysis 5/14/2013 19

How to Shorten Review Times Read the Minnesota Local Road Authority Reference Guide to US Army Corps of Engineers Permits Use the US Army Corps of Engineers Permit Application Checklist 5/14/2013 20

How to Shorten Review Times Coordinate early and often with the Corps Schedule a review of the next 2-5 years of planned projects Start the permit process early (including the delineation) Communicate the planned start date ask for a permit process timeline 5/14/2013 21

How to Shorten Review Times Request a pre-application meeting early in the planning process Determine who has jurisdiction and what will be regulated Identify permit category Identify potential issues Discuss additional information that may be needed for permit review 5/14/2013 22

How to Shorten Review Times Identify federally listed species, critical habitat, or state or tribal sensitive species early in the planning process Identify and begin consultation regarding historic properties and archaeological resources early in the planning process Hire experts when needed 5/14/2013 23

Delineations How to Shorten Review Times Prepare them early; you don t have to wait until you apply for a permit Plan for Corps review during the growing season Follow the current delineation guidance (May 2013) Use the correct delineation method NWI alone is not sufficient Delineate ALL aquatic resources Submit detailed delineation reports 5/14/2013 24

How to Shorten Review Times Submit a complete application so a Public Notice can be published as quickly as possible Provide detailed purpose and need of the proposal 5/14/2013 25

How to Shorten Review Times Provide a complete and legible tabulation and depiction of all impacts to aquatic resources By type of impact Fill Cut Conversion Drainage (lateral effect) By resource affected Wetland type Tributary By permanence Permanent Temporary 5/14/2013 26

How to Shorten Review Times Provide project plans that clearly and accurately illustrate: Project location Existing and proposed conditions Location and type of aquatic resources Location and type of impacts Plans must be at a scale that is both legible and reproducible 5/14/2013 27

How to Shorten Review Times Provide details regarding specific avoidance and minimization measures Provide specific compensatory mitigation plan LGRWRP GPs: Identification of bank and proof of debit required prior to work LOPs/SPs: Identification of bank required prior to permit issuance; proof of debit required prior to work 5/14/2013 28

How to Shorten Review Times Provide detailed alternatives analysis Alternative ways to achieve project purpose with fewer impacts Detail commensurate with degree of impacts Share any environmental analysis or coordination already done (EA, CATEX, Project Memo) 5/14/2013 29

How to Shorten Review Times Provide detailed alternatives analysis Alternative ways to achieve project purpose with fewer impacts Detail commensurate with degree of impacts Share any environmental analysis or coordination already done (EA, CATEX, Project Memo) 5/14/2013 30

Questions? More Information and Resources: http://www.mvp.usace.army.mil/missions/regulatory.aspx Telephone: 651-290-5525 Email: mvp-reg-inquiry@usace.army.mil 5/14/2013 31