US-101 CORRIDOR ADVISOR S UPDATE 19 MARCH 2015

Similar documents
PROJECT CHARTER South Coast 101 HOV Lanes Project Design Decision Phase

Members of the Board of Directors. Laurena Weinert, Clerk of the Board

ALTERNATIVE PROJECT DELIVERY DIVISION

ADOT Yuma District. Alvin Stump, P.E. ADOT Yuma District Engineer Rural Transportation Summit January 20, 2012

Alder Drive / Blair Road Bridge Replacement Projects

PROJECT STATUS REPORT April June 2017

PROJECT STATUS REPORT January March 2017

Interchange Workshop Report (August 2004)

South Sounder Capital Improvements Program

THE PROJECT. Executive Summary. City of Industry. City of Diamond Bar. 57/60 Confluence.

Route 7 Corridor Improvements Project Reston Avenue to Jarrett Valley Drive Public Hearing

Geometric Design: Past, Present, and Future

Metro Blue Line Improvements & Project Update

Appendix B. Benefit-Cost Technical Memorandum

I-495 HOT LANES PROJECT VIRGINIA CONCRETE CONFERENCE CONCRETE: LEADING THE WAY. Dan Staron, P.E. HNTB Corporation MARCH 4, 2010

Statewide Acceleration Transformation (SWAT)

LOCATION AND DESIGN DIVISION

PROFESSIONAL SERVICES REQUEST FOR PROPOSALS Moffat Collection System Siphon 1 River Crossing

WELCOME IL 47. Community Advisory Group Meeting #5 Waubonsee Community College Wednesday, May 31, 2017

IH 820 Corridor Improvement Study Randol Mill Road To North SH 121 Interchange. Public Meeting. Thursday April 4, 2013

Selecting Projects for Accelerated Bridge Construction

LOCATION AND DESIGN DIVISION

Appendix B Highway 407 Interchange Review - Cochrane Street Area

SIXTH STREET VIADUCT REPLACEMENT PROJECT MONTHLY EXECUTIVE MEETING REPORT JULY 2013

Re: EX8.12 F.G. Gardiner Expressway Strategic Rehabilitation Plan Procurement Strategy

AGENDA COMMITTEE OF THE WHOLE COUNTY OF KANE

Interstate 66 Widening from. RFQ Information Meeting. January 4, 2012 Christiana Briganti-Dunn, P.E. District Project Manager

Barrington Road. at Jane Addams Memorial Tollway (Interstate 90) Interchange Improvement Study. Community Advisory Group Meeting #1

S.P TH 65 (3rd Avenue Bridge) Industry Informational Meeting October 31, 2017

extent feasible. Per the and low constructability,

Phase 2 Exposition Metro Line Project

TRANSMITTAL LETTER. Design Manual Part 1C Transportation Engineering Procedures November 2015 Edition

Chapter 2: Alternatives

National Governors Association

summary report West Texas Rail Feasibility Study Texas Department of Transportation Cambridge Systematics, Inc. HNTB August 2011

2017 Highway Safety Improvement Program Call

2 Purpose and Need. 2.1 Study Area. I-81 Corridor Improvement Study Tier 1 Draft Environmental Impact Statement

Michael Gillam Deputy Program Director - Southern California

All Aboard Florida Project Status Update TREASURE COAST REGIONAL PLANNING COUNCIL

Central Phoenix Transportation Framework Study

CHAPTER 2B - PHASE I, INITIAL ROADWAY INVESTIGATION & PRELIMINARY FIELD INSPECTION

Design-Build. Authorization. Criteria Selection/Award Process. Design-Build Construction Engineering and Inspection

FY STATEWIDE TRANSPORTATION IMPROVEMENT PROGRAM New Jersey Department of Transportation Project Descriptions ($ millions)

Project Steering Committee April 14, 2015

Railyard Enterprise Project (REP) Supplemental Scoping

3.0 CUMULATIVE PROJECTS SCENARIO

FINDINGS CALIFORNIA DEPARTMENT OF TRANSPORTATION FINDINGS FOR THE INTERSTATE 10 CORRIDOR PROJECT SAN BERNARDINO AND LOS ANGELES COUNTIES, CALIFORNIA

PROJECT SCOPING PHASE ~ SCOPE OF SERVICES MAIN STREET BRIDGE OVER WINOOSKI RIVER CITIES OF BURLINGTON & WINOOSKI VERMONT

APPENDIX A TIER 1 ANALYSIS

Performance Based Practical Design (PBPD)

LONE HILL TO WHITE DOUBLE TRACK STUDY Community Open Houses May 16 & 17

COUNTY OF SUFFOLK STEVEN BELLONE SUFFOLK COUNTY EXECUTIVE DEPARTMENT OF PUBLIC WORKS

I-10 Master Plan Escambia and Santa Rosa Counties TPO Meetings. Tier II June 11 th & 13 th, 2012

Notice of Preparation For Link Union Station (Link US) Project. Joint Environmental Impact Statement and Environmental Impact Report

Strategic Transportation Plan. Presented to: ECO-Rapid Transit Board of Directors Presented by: Gill V. Hicks, Cambridge Systematics, Inc.

U.S. 101 / San Mateo County Smart Corridor Project

1-7 Deliverables. OSFP Information and Procedures Guide. 1-7 Deliverables December Deliverable Distribution List

FY STATEWIDE TRANSPORTATION IMPROVEMENT PROGRAM New Jersey Department of Transportation Project Descriptions ($ millions)

Exhibit A Scope of Work and Deliverables

Performance Based Practical Design. An FHWA Perspective

Climate Change Adaptation Strategies for Infrastructure Managers

TECHNICAL MEMORANDUM

Request for Proposals No ; Various On-call Professional Design and Engineering Services Addendum No. 1 Page 2

Summary. S.1 Introduction

Scope of Work. Project Approach and Understanding. Task 1: Study Initiation and Administration

State Route 8 Bridge Replacement Project

EXHIBIT A. TRANSIT AND MULTIMODAL DEVELOPMENT SUPPORT CONTINUING SERVICES SCOPE OF SERVICES FM No

City of Denton On-system Project Status Report Prepared by ITS

HIGHWAY 14 NEW ULM TO NICOLLET 4-Lane Expansion Open House

SR 9/I-95 Interchange at 45th Street PD&E Study Palm Beach County, Florida FPID No.: FAP No.: ETDM No.

I-11 Project Nevada Transportation Conference. Ryan Wheeler, P.E. NDOT, Senior Project Manager. Nevada Department of Transportation

I-35W Retaining Wall Design Exhibit A - Draft Scope of Work

GEOMETRIC DESIGN CRITERIA for Non-freeway Resurfacing, Restoration, and Rehabilitation Projects

Memorandum. FROM: Jim Ortbal Rosalynn Hughey Barry Ng TO: HONORABLE MAYOR, CITY COUNCIL. DATE: June 16, 2017

Airport Road from 1 km North of Mayfield Road to 0.6 km North of King Street Public Information Centre #1

CHAPTER 4 GRADE SEPARATIONS AND INTERCHANGES

Since the Vision 2000 effort under taken in 1995, ODOT has operated under a Mission,

TEMPORARILY SUSPENDED

Project Alignment Appendix A

TCATS October 12-Michigan Works 5:30-7pm. NATS October 19-Niles District Library 6-7:30pm

SH 35 Public Meeting

FLORIDA DEPARTMENT OF TRANSPORTATION Planning and Environmental Management Office INTERCHANGE MODIFICATION REPORT

Overall project. The $288 million Phase 2 DesignBuild project starts construction. this spring, with completion by December 31, 2016

CITY OF CLOVIS Traffic Impact Study Guidelines

MEETING DATE: March 22, 2017 PREPARED BY: DEPT. DIRECTOR: Jim Gilliam, Arts Administrator. Jennifer Campbell

3D Engineered Models at Florida Department of Transportation

Qualitative Hot Spot Analysis for PM2.5 February 4, 2008

Cold Foam In-Place Recycling (CIR)

THE COMMONWEALTH OF MASSACHUSETTS NON-NHS BRIDGE R&R POLICY

California High-Speed Train Program FEIR/EIS

Report to INFRASTRUCTURE SERVICES Committee for decision

U.S. DEPARTMENT OF TRANSPORTATION Federal Highway Administration. RECORD OF DECISION June 2014

Interstate 10/605 Transition Connector from SB I-605 to EB I-10

I-15 South, MP 0 to MP 16 Environmental Assessment. Public Hearing. August 7, :00 PM to 7:00 PM

Creek) Bridge Replacement with environmental, survey, and bridge design. Geotechnical work will be performed by ODOT.

Agenda. PRE-CONSTRUCTION PUBLIC MEETING September 18, 2014

Drainage Report for US-50 Camino Corridor Safety Project

Concept, Feasibility & Mobility Studies. Southport Connector Expressway

Rail 101 Highway-Rail Crossing Program & Project Coordination

SAN RAFAEL CITY COUNCIL AGENDA REPORT

Transcription:

US-101 CORRIDOR ADVISOR S UPDATE 19 MARCH 2015 1

DELIVERY RECOMMENDATION GOALS Project Readiness: Enhance Funding pursuits Corridor Related Projects Coordination Develop Information to: Resolve Questions Evaluate Alternate Delivery Methods Maintain & Increase Public Support 2

PROJECT DELIVERY RECOMMENDATIONS HOV Implementation Proceed with Design (combine with Rehab) Corridor-wide Tasks Corridor Related Projects Clarify Roles and Advance to Next Phase Coordinate with HOV Develop Corridor Charter with Caltrans & MOUs with City & County of Santa Barbara 3

HOV IMPLEMENTATION Initiate Design for Entire Corridor City of Carpinteria / County of Santa Barbara to north of Padaro Lane IC County of Santa Barbara from north of Padaro Lane IC / City of Santa Barbara Construction Segments TBD with input from: 35% Design (HOV & Rehab) Corridor Tasks Funding Available Alternate Delivery Method Evaluation Related Projects Status Clarification 4

CORRIDOR TASKS Advance Specific Tasks Mapping & Surveys Drainage Studies Geotechnical, Hazardous Waste, Materials, Pavement Permitting Coordination (Coastal Permit Related Only) Corridor Aesthetics Coordination (Utilities/Right of Way, Community Involvement, Agency) Project Management Support & Oversight Engineering Peer Review / Value Analysis Constructability Assessment (Included in design scope of work) 5

WHAT IS MEANT BY 35% DESIGN? Final Design, Right of Way / Utilities requirements, Construction Cost, Input for Construction Segments Deliverables: Roadway & Structure Plans & Estimate Alignments and Intersection/Interchange Design Design Exception Fact Sheets and Updates Drainage Study Technical Memorandum Right of Way / Utilities Requirements Drawings Coastal Development Permits & Local Coastal Plan Amendment Technical Data 6

IMPLEMENTATION LEAD Design South Segment Caltrans North Segment SBCAG Consultants Corridor Tasks Mapping & Surveys - Caltrans District 5 Drainage Studies - SBCAG Consultants Geotechnical, Hazardous Waste, Materials, Pavement - Caltrans District 5 Permitting - SBCAG Consultants Corridor Aesthetics - Caltrans Coordination - SBCAG Consultants Project Mgt. Support & Oversight SBCAG Consultants Engr. Peer Review / Value Analysis SBCAG Consultants 7

US-101 REHABILITATION State Highway Operation Protection Program funding opportunity Project Study Report completed Total Cost approx. $150 M SHOPP Funding - $34 M Pavement Rehab, Shoulder Improvements, etc. Preliminary Engr. / Environmental next step Opportunity - Sharing of Cost & Funding with HOV Project 8

COST & FUNDING HOV (100% Design) $ 39 M Rehab (100% Design) $ 14 M Design generally 10-15% of Construction Cost Recommendations Estimated Cost Design North Segment $ 8.2 M Design South Segment $ 7.7 M Corridor Tasks $ 6.4 M Total $ 22.3 M Proposed Funding STIP $ 6.7 M SHOPP $ 5.7 M Measure A $ 9.9 M Total $ 22.3 M 9

FUNDING APPROACH SCOPE FUND SOURCE North Segment (Caltrans) STIP / SHOPP South Segment (SBCAG) Measure A Rehab Environmental (Caltrans) SHOPP Corridor Tasks (Caltrans / SBCAG) Combination Caltrans performed activities funded by STIP / SHOPP SBCAG Consultants performed activities funded by Measure A 10

CORRIDOR CHARTER Design Phase HOV Rehab Corridor Management Structure Executive Committee Corridor / Deputy Corridor Managers Project Development Teams Deliverable Management / Schedule Issue Resolution 11

CORRIDOR PROJECT ORGANIZATION SBCAG Board of Directors Corridor Advisor US 101 Executive Team SOUTHERN SEGMENT Project Manager (Caltrans) Corridor Manager (Caltrans) & Dep. Corridor Manager (SBCAG) NORTHERN SEGMENT Project Manager (SBCAG Consultant) Southern Segment Project Mainline 101 Improvements between Carpinteria Crk and Padaro Ln PM 2.0 to PM 7.5 35% PS&E Corridor Task Services (Caltrans) Topographical Surveys and Base Mapping Geotechnical Design, Hazardous Waste Analysis, Pavement Design, Materials, and Preliminary Foundation Reports Corridor Aesthetics Concept Plan Corridor Task Services (SBCAG Consultant) Floodplain Analysis Utility, Railroad, and Right of Way Coordination Community Involvement / Local Agency Coordination / Graphics, 3D Modeling Coastal Permitting Coordination Project Management Support and Oversight Engineering Peer Review / Value Analysis Northern Segment Project Reconstruct Interchanges at Cabrillo-Hot Springs and Sheffield and Mainline 101 Improvements between Padaro Ln and Cabrillo Blvd. PM 7.5 to PM 11.9 35% PS&E 12

CORRIDOR RELATED PROJECTS UPDATE Local Agencies / SBCAG / Caltrans Coordination MOU Approach Recommended Objective: Advance Projects (Clarify Scope, Cost, etc. through Feasibility Study and / or PSR) Local Agency Implementation Lead Role Recommended 13

CABRILLO/UPRR UNDERPASS Working to Complete MOU Requirements Cost estimated at approx. $28.5 M City prepared draft feasibility study Planning Commission Updated 3/5/15 City Council Updated 3/17/15 Revised Design to be submitted to UPRR Estimated Timeline for UPRR response (2016) 14

OLIVE MILL ROAD INTERSECTION City prepared roundabout concept Current Cost Estimate ($6m - $10m) Planning Commission Updated 3/5/15 City Council Updated 3/17/15 Recommended Next Step MOU Project Study Report and/or Project Report 15

SAN YSIDRO INTERCHANGE County prepared conceptual improvements - signals, roundabouts & bridge replacement Recommended Next Steps MOU PSR 16

NEXT STEPS April 2015 Board Agenda Item SBCAG / Caltrans Corridor Charter Consultant Procurement Documents Draft SBCAG / Caltrans Co-Operative Agreement Corridor Project Organization Implementation Corridor Related Projects MOUs 17