Application & Management of CPM Schedules

Similar documents
SPECIFICATIONS - DETAILED PROVISIONS Section Project Control Schedule C O N T E N T S

COST LOADED CONSTRUCTION SCHEDULES PART 1 - GENERAL

Document No: SB002-P3 Revision No: Last Updated: April

Managing Schedule Change

Views and Layouts for Program Management

THE CONTRACTS GROUP LTD. THE SOCIETY OF CONSTRUCTION LAW DELAY & DISRUPTION PROTOCOL 2 nd Edition

Principles of Schedule Contingency Management

Jacksonville District Master

A Structured Approach to Minimum Cost Recovery Scheduling

The Differences Between CPM and Resource-Loaded Scheduling and How They Applied to The Martinez Tesoro Refinery Flare Header Replacement Project

Consulting Newsletter

Richard J. Long, P.E.

Lessons Learned Schedule Updating and Maintenance using Primavera P6 Hannah Schumacher, PSP, PMI-SP, LEED AP Hill International

Guten Tag. (good day)

Presented by. H. Wynnlee Crisp

Retained Logic and Progress Override in Primavera P6

Project Management Concepts, Tools & Techniques

IBM TRIRIGA Application Platform Version Introduction to the Gantt Scheduler

Planning & Scheduling CSTM 102

Chapter 12. Sample Surveys. Copyright 2010 Pearson Education, Inc.

Cashflow. Total price. Total cost. Contract completion. Predicted revenue (2) Total price. Total price. Total cost. Total cost. Contract completion

Risk Analysis Overview

For the PMP Exam using PMBOK Guide 5 th Edition. PMI, PMP, PMBOK Guide are registered trade marks of Project Management Institute, Inc.

EN T. How Clear is Your Talent Strategy?

Project Management Casey Lucius, Ph.D. Oct 16, 2017 AGENDA. Introductions 8/31/2017

Ronald J. Rider, MBA

Project Engineers and Supervisors Conference. CPM Scheduling

Sample Case Studies. i2c world Inc. 59, West 37 th Street, New York, NY Phone: Fax:

An Introduction to SupplyPro

Welcome to the Eastwood Harris Pty Ltd Primavera P6 Versions 8.2 EPPM Web Tool 2 day training course Enterprise Portfolio Project Management

Sales Order Processing

Project Cost Management

Topic # 12. CIS Project Management: an overview

Developing a Project Plan

2017 LOSS PREVENTION / RISK MANAGEMENT SEMINARS APRIL 20, 2017 DALLAS, TEXAS

Your Trading Plan Windsor Advisory Services

Estimating Project Schedule-Time and Cost

The Agile PMP Teaching an Old Dog New Tricks

Copyright 2012, Business Directors New Zealand Limited, Graeme Owen,

P6 Instructors Sample Presentation

Your easy, colorful, SEE-HOW guide! Plain&Simple. Microsoft Project Ben Howard

1/4/2014. Alternative Project Delivery Methods 1. Agenda

Exam Code: Number: Passing Score: 800 Time Limit: 120 min File Version: 35.4.

Design Like a Pro. Boost Your Skills in HMI / SCADA Project Development. Part 3: Designing HMI / SCADA Projects That Deliver Results

It All Starts Here. WEB WORK v.7 USER MANUAL Chapter 8 Preventive Maintenance (PM) Module Maintenance section of Azzier. Tero Consulting Ltd.

Mobile Storage "One of the fastest growing business opportunities!"

3-Day Oracle Primavera P6 Professional Fundamentals - Training Outline -

2007 ALLDATA LLC. All rights reserved. ALLDATA is a registered trademark of ALLDATA LLC. ATI is a mark of Automotive Training Institute.

How to Cost Load a schedule. OR Understanding the SDEF

SMALL CONTRACTORS INITIATIVE ASSESSMENT TOOL USER S GUIDE

Average worker wastes 2 hours a day

FORENSIC PLANNING DELAY ANALYSIS, EXPERT WITNESS, CLAIMS AND CONTRACT ADMINISTRATION SERVICES

Andrew Avalon, P.E., PSP

LONG INTERNATIONAL. Richard J. Long, P.E., Andrew Avalon, P.E., PSP and Ronald J. Rider, MBA

The new Uber for Business. How to make the most of the new features

Facilities Planning and Construction (FP&C)

REQUEST FOR PROPOSAL FOR CONSTRUCTION MANAGEMENT SERVICES NOT AT RISK FOR THE. St. Charles County Ambulance District

TenStep Project Management Process Summary

Deeper. Deeper. Deeper. Deeper. Deeper. Deeper. What is the advantage of breaking a project down into tasks and sub-tasks?

Innovative Marketing Ideas That Work

PURCHASING AND JOB COSTING FOR CONTRACTORS. Leslie Shiner Owner, Principal of The ShinerGroup

WORKING WITH TEST DOCUMENTATION

Part Seven: Program Assessment & Evaluation


NW Region Tribal Transportation Symposium March 6-9, PROJECT DOCUMENTATION for Tribes Administering Construction Projects

Preferred status. Platinum service. Personal attention. Get ready to take business to the next level.

Co-Managed IT Services: The IT Executive s Best Friend

S O Seminar Objective

A Media Buyer s Guide to Clients & Profits

Main Building Auditorium

Microsoft Dynamics GP. Manufacturing Core Functions

Marketing Automation: One Step at a Time

Operations Management, 11e (Heizer/Render) Chapter 3 Project Management. Section 1 The Importance of Project Management

Welcome to the Eastwood Harris Pty Ltd Primavera P6 Version 7 and Earlier Versions 3 day training course

PS.08. Let s Scrap the Precedence Diagramming Method

Errata 1 st Printing. Errata 2 nd Printing

Just like QUALITY Good Project Management Practices start with an Internal Kick-Off Meeting. It is the Project Managers job to communicate:

Deltek Acumen 7/15/16. Learning Objectives. Introduction to Project Risk Analysis. Planning, Risk, Acceleration. The 5 steps. Worked examples Q&A

PMI Scheduling Professional (PMI-SP)

CEB-BLOCK STARTER KIT START SINGLE SPARK. Your business-in-a-box!

Exam Code: Number: Passing Score: 800 Time Limit: 120 min File Version: 35.4.

Managing People and Projects: What You Need to Know to Get Started

Post Remediation Warranty

Increasing Value Add by: Sheila Julien, Senior Associate

RB8 Training Orientation Essential Training overview 1 Recommended Lesson Plans By Department 1

worldwide O 2 Worldwide Compensation Plan

Job Shop Scheduling. Introduction (Seminar 7) ManuDyn Seminar 7 Job Shop Scheduling

Proposal Pricing with Deltek MPM TM

Project Risk Analysis (with Pertmaster)

PeopleSoft Enhancement Project

Millennials are crowdsourcingyouhow companies and brands have the chance to do

Govt. Contracting, Dynamics 365 Operations Implementing Dynamics 365 Operations for Govt. Contractors PVBS

Mindset Of The Millionaire Traders

I Have My Sales Data, Now What? Developing GSA Commercial Sales Practices Disclosures

Anytime Adviser New Car Buying Coach

The Hard Truth about Effective Performance Management

The Starting Your Business Checklist ebook

As part of the tasks and responsibilities of project control, the aspect of (time) control during the course of a project can be applied in many ways.

VIDEO 1: WHY IS A STRATEGY PLAN IMPORTANT?

Schedule Health-Killing Project Predictability. Darryl Townsend, PMP January, 2017

Transcription:

Application & Management of CPM Schedules Matthew Milliet James Construction Group, LLC 2009 Louisiana Transportation Conference Session 60 Project Scheduling

DISCLAIMER The following is intended to outline a general approach to Project Schedule Updating. It is intended for information purposes only. Any representations made here in are not to be construed as procedures, guidelines, recommendations, requirements, or directives by James Construction Group, LLC and may not be incorporated into any contract. Nothing in this presentation is intended to bind James Construction Group, LLC to the content herein. All Rights and Reservations to the content of this presentation is reserved by James Construction Group, LLC.

CPM ~ Skipping the Basics Does everyone know what a CPM Schedule is? Has everyone created or seen a created Schedule? Key Phrases: Longest Path Critical Float Resource Calendar Logic Basic Process: Monitor Progress Update Progress Modify as Needed Report Progress Agree / Approval Repeat

Case Study EXAMPLE Driving Down I-10 towards Lafayette 9:00 a.m. You have a blow out. Left rear tire of your company vehicle. 2 Able bodied people in the car. Your meeting starts at 3:00 p.m. Create a Schedule showing what happens next. Take about 3 to 5 minutes Ready Go!

Key Parts of a Schedule Activity Description Detailed enough to know item of work WBS-Area-Resp.-Mile-Step-Other Activity ID Unique number assigned Activity Duration Original Duration based upon original K Remaining Duration based upon balance % Complete Quantity Complete Activity Resources Can be Money Better as Manpower / Equipment Activity Budgets Cost / Qty / Earnings P3 / P6 Offer Contractors and Owners 100 s of options

CPM SCHEDULE OVERVIEW Create the Original Schedule Sounds Simple but is far from it. Flat Tire Example Update the Schedule: Monitor Progress Update Progress Modify as Needed Report Progress Agree / Approval Repeat

Update the Schedule In Lump Sum or Fixed Price Contracts Experience shows having Contractor Responsible for creation and maintenance works best. Other Options Owner Creates and Updates Schedule GC or Construction Manager Updates Whomever Does it Monitor Progress Daily Reports Time Sheets Quantity Installed Reports Major Vessels / Procurement Objects Subcontractors Progress Reports

Need to Update Schedule Construction Projects are Dynamic Plans / Estimates are bound to change Unusually Bad Weather Strikes / Acts of God / Public Convenience Material Shortages Unforeseen Subsurface Conditions Change Orders Labor Shortages Many Many others

Definition The Periodic review and assessment of the project s plan, schedule, and progress is UPDATING. Updating the Network of Activities their logic, physical progress, & changes is critical to accurate reporting. Without this, Delays Encountered and the ability to deliver the Project as intended is impossible.

Preparing to UPDATE Updates should take place Monthly at a minimum. Higher frequency should be determined by the project team. Turn Around Documents A listing of Activities with Blank locations for reporting Start & Finish Dates Support Dates with factual reports from records. Started Activities Need to have projected remaining durations evaluated. Activities that Need Resequesnced, Added, Deleted, or Modified. Fragnets (mini schedules) that need to be incorporated into the Schedule Small units to reflect delays, change conditions, etc

What about Recovery? If after Updating you find yourself behind What can you do? Many options Need to be Evaluated Look for Preferential vs. Actual Logic Look for Additional Resources Look for Multiple Shifts Look for Dovetailing tasks (lug nuts & lower) Extend the work week if required Some of these are free others cost $$

Approval Joint efforts should be made during the update process. Ultimately there needs to be concensus on the Schedule with each update. Be willing to spend the time needed to Support you contentions in the Schedule.

Submission Every update should include a Detailed Project Narrative Narrative should be PROBLEM / SOLUTION oriented philosophy. Every Change in the Schedule should be recorded for Historical Reference. Finally, it should include an analysis of the CRITICAL Path and the other float variances of consequence.

REPEAT After Approval of the Submission and Documentation for that update is complete file it and monitor it. Move on to the NEXT Update Start the Process over again.

PITFALLS #1 The Computer #2 Forcing the Software to say what we want. Adding Constraints Modifying Calendars Not enough Detail Starting too Soon to look good #3 Laziness in the Update Not keeping up with logic revisions

#1 - The Computer Just because the computer prints it out doesn t make it right. Increased power and Access Makes Scheduling a more sophisticated process. (See Peter s presentation to follow on the NEW Direction of the Software) Left to the uninformed, GIGO is a problem in Schedule Updates

#2 - Forcing the Software Advanced Scheduling Software offers Many Features. Constraints, Lags/Leads, Calendar Manipulation, Customizable Reports, Resource Constraints, Huge Databases Not Understanding those is Disastrous. Too much Preferential Logic Forcing Cost Loading Completion activities for Billing & Starting too soon. Setting of Constraints is almost always Bad.

#3 Laziness in Update or Review The single biggest culprit to a BAD schedule is BAD LOGIC Out of Sequence activities can give false impressions of the Project Progress override and Retained Logic are both BAD. Try to fix your logic by increasing detail, or modifying it to reality. Lags & Leads can mask this problem.

#3 Laziness in Update or Review The second worst offender BAD Dates Starting a Task before you really begin work. Dropping off forms doesn t = FORM Footer Leads to elongated activity durations More out of Sequence work Non-consistent pursuit of activity = False Paths Not Completing a Task just as Bad Not picking up cure blankets doesn t mean the deck isn t 100% complete. See above consequences

Conclusion & Summary CPM Schedules are becoming more & more sophisticated. (See Peter s presentation to follow.) Accurate Updates are essential. Open & honest reporting of updated progress is ONLY way to achieve success. 10 Experts = 10 opinions. Settle your fights as they happen and have competent persons perform your updates and reviews. Share your RESULTS. If everyone knows the Goal and Critical activities you will have a good project.

Questions & Comments Matthew Milliet Senior Contract Manager James Construction Group, LLC (225) 241 3253 or (225) 295 4830 mmilliet@jcgllc.com