Schedule Margin. Contingency for Schedulers. John Owen, Product Manager Schedule and Risk, Deltek

Similar documents
Estimating Project Schedule-Time and Cost

Deltek Acumen 7/15/16. Learning Objectives. Introduction to Project Risk Analysis. Planning, Risk, Acceleration. The 5 steps. Worked examples Q&A

For the PMP Exam using PMBOK Guide 5 th Edition. PMI, PMP, PMBOK Guide are registered trade marks of Project Management Institute, Inc.

SCHEDULE RISK ANALYSIS ESSENTIALS FOR PROJECT SUCCESS

Consulting Newsletter

Course Outline. TEC D 205 Engineering Tech Project Planning Olympic College Bremerton, WA. Week 1 Chapter 4: DEFINING THE PROJECT

Principles of Schedule Contingency Management

Project Time Management

PMI Scheduling Professional (PMI-SP)

Colorado Springs PMI Risk Management in Five Easy Pieces Colorado Springs, Colorado May 8 th, 2008

COST LOADED CONSTRUCTION SCHEDULES PART 1 - GENERAL

Project Management. Kristian Sandahl

Guten Tag. (good day)

PMP Sample Questions Click here for PMP Questions. Question No : 1 Which of the following is an output of Define Scope?

The Differences Between CPM and Resource-Loaded Scheduling and How They Applied to The Martinez Tesoro Refinery Flare Header Replacement Project

1.0 BASIS OF ESTIMATE (BOE) HOW TO

Downloaded from Integrated Master Plan and Integrated Master Schedule Preparation and Use Guide

Integral Risk Management for DBFM Tenders and Contracts in the Netherlands

5 Essential Legal Project Management Metrics Every Law Firm Should Track

Presented by. H. Wynnlee Crisp

Document No: SB002-P3 Revision No: Last Updated: April

SPECIFICATIONS - DETAILED PROVISIONS Section Project Control Schedule C O N T E N T S

Even though Benjamin Franklin first voiced this wellknown

Why SLAs Fail and How to Make Yours Succeed

DCC Business Case for DCC activities during the Transitional Phase of the Switching Programme

Responding to RFPs. Slide 1 Responding to RFIs and RFPs Welcome this module on responding to RFIs and RFPs.

Lean Production Management In Design

Project Planning and Estimating DJ

PS.08. Let s Scrap the Precedence Diagramming Method

Planning & Scheduling

Lessons Learned Schedule Updating and Maintenance using Primavera P6 Hannah Schumacher, PSP, PMI-SP, LEED AP Hill International

Planning & Scheduling CSTM 102

Managing a complaint at work A step-by-step guide

Schedule Health-Killing Project Predictability. Darryl Townsend, PMP January, 2017

ASSIGNMENT BUFFER CONTROL FOR CONSTRUCTION PROJECTS

AACE Planning and Scheduling Professional (PSP) Certification Preparation Training Course Brochure and Competency Matrix

1.Which of the items listed below is not one of the software engineering layers?

P6 Instructors Sample Presentation

Section M: Evaluation Factors for Award HQ R LRDR Section M: Evaluation Factors for Award For HQ R-0002

A Project Management Approach to Improve on Time Delivery Performance in Manufacturing Industry

As part of the tasks and responsibilities of project control, the aspect of (time) control during the course of a project can be applied in many ways.

Earned Value Management Training Program Course Brochure and Competency Matrix

GLOSSARY AND INDEX. Glossary Index Project Management Institute, 130 South State Road, Upper Darby, PA USA 155

Information Technology Project Management,

PMI-001 Questions & Answers

LEANING YOUR ORGANIZATION

Errata 1 st Printing. Errata 2 nd Printing

Advantages and Disadvantages of. Independent Tests. Advantages. Disadvantages

STO Navigator Canada Best-Practices Manual

THE CONTRACTS GROUP LTD. THE SOCIETY OF CONSTRUCTION LAW DELAY & DISRUPTION PROTOCOL 2 nd Edition

Administration. Welcome to the Eastwood Harris Pty Ltd MICROSOFT PROJECT AND PMBOK GUIDE FOURTH EDITION training course presented by.

Managing Strategic Initiatives for Effective Strategy Execution

Performance Management: Giving and Receiving Feedback

Chapter 4 Software Process and Project Metrics

Retained Logic and Progress Override in Primavera P6

Exam Code: Number: Passing Score: 800 Time Limit: 120 min File Version: 35.4.

IT Project Management. Essentials of IT project management 25 Sep 2017

Multiple-Prime Top 10 Concerns Especially when

#1 Misalignment of internal and external resources

TickITplus Implementation Note

Giving and Receiving Feedback

Agenda. Last Module Handling Objections. Creating a Sense of Urgency. Best Way to Create a Sense of Urgency 4/13/2015

Topic # 12. CIS Project Management: an overview

Tikuhao ᦤկϧϮ,7䅸䆕㗗䆩乬ᑧ ᙼ䕏ᵒ䗮䖛㗗䆩 ІЗ߃Ҳ ޏ߆ԇ NZZV ]]] ZOQ[NGU IUS

Introduction to Software Engineering

Project Scope Management

Resource Allocation Optimization in Critical Chain Method

PMI EXAM PgMP Program Management Professional (PgMP)

Effective Personal Productivity

Planning Optimized. Building a Sustainable Competitive Advantage WHITE PAPER

The Technology-Driven of. Project Management. Capitalizing on the Potential Changes and Opportunities

7/26/2016 ARETE-ZOE, LLC 1

Ronald J. Rider, MBA

Volume 8, No. 1, Jan-Feb 2017 International Journal of Advanced Research in Computer Science RESEARCH PAPER Available Online at

The Agile PMP Teaching an Old Dog New Tricks

Understanding Agile from a PMP s Perspective! Exploding the myth that Agile is not in the PMBOK

MANAGE PROJECTS CANDIDATE RESOURCE WITH SIMULATED ONLINE BUSINESS ASSESSMENT BSBPMG510A

Testkings PMP 705q. PMI PMP. Project Management Professional v5

7. What is planning? It is an act of formulating a program for a definite course of action. Planning is to decide what is to be done.

RAISING THE STANDARD THE NEW ISO RISK MANAGEMENT STANDARD

2017 LOSS PREVENTION / RISK MANAGEMENT SEMINARS APRIL 20, 2017 DALLAS, TEXAS

Ir. Herwin Rubijono Hotel Ambhara 19 September Manajemen Proyek. Pengelolaan Waktu, Pengelolaan Biaya Pengelolaan Resiko, Pengelolaan Klaim

Views and Layouts for Program Management

Software Engineering II - Exercise

For Portfolio, Programme, Project, Risk and Service Management. APMP for PRINCE2 Practitioners Graham Williams, Principle Consultant, GSW Consulting

Saving for a Rainy Day

FORENSIC PLANNING DELAY ANALYSIS, EXPERT WITNESS, CLAIMS AND CONTRACT ADMINISTRATION SERVICES

IN THE ABSENCE OF GOOD DATA ONE CANNOT MAKE GOOD BUSINESS DECISIONS

Introduction to Project Management 1Day Seminar

Warning: Academics complain that there is no theory in Theory of Constraints John A. Ricketts (p. 9)

Delivering End-to-End Supply Chain Excellence

Sagar Khadka, MBP, Fairfax, VA Tom Hyland, Ohio DOT, Garfield Heights, OH. Tuesday, October 27, :00 AM 11:30 AM

Managing Schedule Change

3.1 Edition APMP Syllabus APMP

Staff Guidelines for Conducting Impact Assessment

Information Guide & FAQs PROFESSIONAL MENTORING PROGRAM CPHRBC.CA

Copyright 2012, Business Directors New Zealand Limited, Graeme Owen,

Welcome to the Eastwood Harris Pty Ltd Primavera P6 Version 7 and Earlier Versions 3 day training course

Welcome to the Eastwood Harris Pty Ltd Primavera P6 Versions 8.2 EPPM Web Tool 2 day training course Enterprise Portfolio Project Management

A summary of the principles from The Speed of Trust Book:

Transcription:

Schedule Margin Contingency for Schedulers John Owen, Product Manager Schedule and Risk, Deltek

Contingency / Management Reserve Let s start with a question Have you ever seen a project without any Contingency (for known unknowns) or Management Reserve (for unknown unknowns)? Hopefully the answer is No however, sometimes the answer is Yes. For those occasions where the answer is yes (there is no identified contingency/mr) my contention is that there is indeed contingency but it s been buried in a fee or some other overhead because some clients and regulatory authorities fear such reserves will be included in project baselines and may impact reliable Performance Measurement So most everyone would agree that Contingency or Management Reserve funding exists to deal with the cost of risks and uncertainties associated with our projects. 2/10/2013 2

Schedule Contingency/Reserve You have probably heard the suggestion that The only certain thing about a project completion date calculated by Critical Path Method is that it will be wrong So if we have contingency funds to deal with cost variances, why don t we also hear about a Schedule Contingency/Reserve to deal with the time impacts of those same risks and uncertainties? We may even be doing Schedule Risk Analysis to quantify those possible impacts but what, if anything, do we do with that information? Unfortunately, many projects do build contingency for schedule uncertainty into the plan in the form of padded durations,but this technique has several serious flaws. Contingency is spread across the project without any way for project managers to identify or control when it is being utilized Parkinson s Law (Work Expands so as to Fill the Time Available for its Completion) 2/10/2013 3

Schedule Margin So we need a way to model schedule reserves in our projects without simply hiding it in overstated durations and addressing the concerns of our customers and the regulatory authorities regarding performance measurement. Schedule Margin is one such way Schedule Margin is an approach for calling out a reserve in our schedules to protect both contractors and customers from unplanned delays. Key features are: The purpose of the Schedule Margin is to protect project deliverables Various mechanisms to determine an appropriate amount of reserve A way to manage/approve the utilization of the reserve A mechanism to track remaining reserve 2/10/2013 4

How does it work? Schedule Margin is simply a buffer between when you expect to complete the work and when you will commit to have finished to your customer The margin buffer goes between your work tasks and your contract deliverable It can be used both for Interim and Contract Completion Deliverables The size of the buffer is related to the uncertainty surrounding the work to be completed. It may either be based on manager estimates or calculated using techniques like Schedule Risk Analysis. The more uncertainty, the bigger the buffer It is important that the buffer and its purpose is clearly identified The exact implementation can vary depending on what your client or industry will allow 2/10/2013 5

This sounds like Critical Chain Critical Chain (derived from Goldratt s Theory of Constraints) does have some similar fundamental concepts to Schedule Margin. Similarities Both techniques encourage realistic unpadded duration estimates Both techniques create buffers/margins/reserves/contingency to protect project deliverables. Differences Critical Chain determines buffer size/location based on key resources and percentages of duration. Buffers can occur anywhere in the schedule Schedule Margin places margin to protect project deliverables and the size of those margins is often calculated using Schedule Risk Analysis So Schedule Margin is NOT Critical Chain Note to self: Stop calling the Margin a Buffer! 2/10/2013 6

What do the Experts say? Industry Bodies such as the PMI suggest that Contingency Funds and Management Reserve are indeed a best practice both for Cost and Schedule. It s a prudent risk mitigation strategy but we unfortunately still hear comments like: A schedule must accurately reflect critical and driving paths in the project. Whenever I see schedule margin applied I will work that much harder to understand how it s being used or misused. Schedule Margin feels like schedule management reserve which better be clearly justified and understood. So it s a good idea but there s still some resistance 2/10/2013 7

What about contracts? Federal Contracts DID: DI MGMT 81861 TITLE: Integrated Master Schedule (IMS) Approval date: 20120620 Schedule Margin. A management method for accommodating schedule contingencies. It is a designated buffer and shall be identified separately and considered part of the baseline. Schedule margin is the difference between contractual milestone date(s) and the contractor s planned date(s) of accomplishment. This is not new! The previous IMS DID (DI MGMT 81650) from 2005 contained the same language 2/10/2013 8

What does the DCMA Say? Defense Contract Management Agency Although the DCMA has not published formal guidance on the use of Schedule Margin, Deltek has received the following feedback: The NDIA Planning and Scheduling Excellence Guide V2.0 guidance regarding Schedule Margin was reviewed by the DCMA. Basically, schedule margin as a task is okay as long as it does NOT have any discrete successors anywhere down the logic chain, either directly or indirectly. DCMA prefers that schedule margin be represented as a calculated difference (i.e. float) rather than a task. 2/10/2013 9

Schedule Margin Calculation As mentioned earlier, the purpose of Schedule Margin is to protect project deliverables. So to calculate the margin we need to understand when we hope to finish versus a date we will commit to in our contracts. If there was no uncertainty then these dates would be the same but as uncertainty increases the margin should become bigger to afford the deliverable more protection. If you have experienced project managers they may simply be able to suggest a margin which they feel is adequate. For more complex or innovative projects Schedule Risk Analysis (SRA) can be used to suggest margins. Using Schedule Risk Analysis gives business managers an opportunity to define their appetite for risk since Schedule Margin is simply the difference between the deterministic (usually unrealistically favorable) completion suggested by Critical Path Method and the expected finish date suggested by Schedule Risk Analysis for a specific confidence factor. 2/10/2013 10

Schedule Margin Calculation If the deterministic (from Critical Path Method) completion for a project is calculated as September 26, 2012 and your company policy is for a 95% confidence that you can achieve deliverable dates you sign into contracts and Schedule Risk Analysis suggests you have a 95% chance of completion by October 2, 2012 Then the schedule margin that needs to be included in the project is 4 working days. This will protect the project deliverable from up to 4 days of slippage in the tasks preceding the contract deliverable. 2/10/2013 11

Schedule Margin Example 1 In this example we have introduced a Schedule Margin Activity immediately preceding the contract deliverable. The margin duration of 4 days in this example is based on the 95% confidence completion date calculated by Schedule Risk Analysis 2/10/2013 12

Schedule Margin Example 2 An alternative way to introduce the schedule margin is to use a target constraint date. The big disadvantage of this technique is the loss of visibility into the critical path unless additional logic/constraints are added. Margin consumption is also harder to monitor 2/10/2013 13

Does Schedule Margin affect Earned Value Management? In environments where strict Earned Value Performance Measurement is employed, it is still possible to use Schedule Margin provided no work activities are successors to Schedule Margin activities. Federal Agencies require that any margin activities applied to interim milestones are only used to drive the deliverable milestones. Real work successor activities can be controlled using Target/Constraint dates. 2/10/2013 14

Schedule Margin Example 3 The Margin after Phase 1 Complete is only driving the Customer Interim Deliverable. The start of Phase 2 is being constrained by a target date and is not connected to the Margin activity. 2/10/2013 15

Schedule Margin without changing durations or using target (constraint) dates Given the concerns regarding artificially introduced duration or target (constraint) dates how about using a technique that requires neither? How about using baselines or user fields to store the margin information and just use it for reporting? 2/10/2013 16

Worked Example The schedule has been defined and CPM is predicting a completion date of 9/27

Schedule Risk Assessment A Schedule Risk Assessment is performed (arrows show 95% confidence dates for activity completion).

Schedule Margin A baseline is used to capture and display the initial margin based on the 95% confidence results from SRA

After Status Update The project has started and progress has not gone according to plan. The slippage is highlighted as consumption of the margin

Standard CPM report The standard CPM reports show the slippage of the project forecast completion to 9/28

Summary Schedule Margin Protects both contractors and clients by offering visibility and control into risk and delays Can be used without causing federal agencies heartburn Has no impact on Performance Management

A little survey Do you use Schedule Margin? Do you use Schedule Risk Analysis? 2/10/2013 23

Previous Survey Results During a recent Projects at Work (www.projectsatwork.com) presentation on Schedule Margin the attendees were asked the following two questions: Do you use Schedule Margin? 22% responded Yes Do you use Schedule Risk Analysis? 52% responded yes So my question is: What are the 30% doing with the results from SRA? 2/10/2013 24

Thank You! johnowen@deltek.com http://forums.deltek.com http://kona.com