Med (3) Locator Information/GPS GPS shows 16 ft accuracy Lat: Impact Rating

Similar documents
Lyon Creek Cedar Way Stormwater Detention Dam Operation and Maintenance Manual

PART 1 GENERAL REQUIREMENTS

U.S. ARMY CORPS OF ENGINEERS. Little Rock District

Temporary Watercourse Crossing: Culverts

Straw Bale Barrier. - Along the face and at grade breaks of exposed and erodible slopes to shorten slope length and spread runoff as sheet flow

Straw Bale Barrier. Parallel to a roadway to keep sediment off paved areas

Item Name Description Unit of Measure Mobilization Per WSDOT Lump Sum

Brush layering construction

MOA Project # Golden View Drive Intersection & Safety Upgrades

Sediment Basin. Fe= (Depends on soil type)

Filter Tube Barriers (Instream)

Standards for Soil Erosion and Sediment Control in New Jersey May 2012 STANDARD FOR RIPRAP. Conditions Where Practice Applies

Erosion and Sediment Control Plan for a Timber Harvesting Operation

TECHNICAL CONTENT PROPOSED STEEP SLOPE REGULATION

901 - TEMPORARY EROSION AND POLLUTION CONTROL SECTION 901 TEMPORARY EROSION AND POLLUTION CONTROL

Erosion & Sedimentation Control Policy

A.2.a Random Riprap... Table

SPECIFICATIONS FOR PRECAST MODULAR BLOCK RETAINING WALL SYSTEM (revised 5/8/7)

CITY OF TROY CONSTRUCTION SPECIFICATIONS PREPARED BY: F-7587

Understanding Stormwater Pollution Prevention Plans (SWPPPs) (SWPPPS)

ITEM 506 Temporary Erosion Control

Unit E: Basic Principles of Soil Science. Lesson 7: Understanding Soil Erosion and Management Practices

KDOT TEMPORARY EROSION - CONTROL MANUAL

SECTION TRENCHING & BACKFILLING

Niagara Falls Storage Site Safety Measures During Remediation

Construction of Dariali HEPP. Reinstatement Plan

Coal Combustion Facility Assessment Report. October 20, 2010

LOW WATER CROSSINGS, fords, or drifts, as they

Town of Essex, Vermont January, 2017 Standard Specifications For Construction CHAPTER 3 EROSION AND SEDIMENT CONTROL

Table of Contents for Guide Specifications

APPENDIX D: COST ESTIMATES FOR STUDY REACHES

Storm Drain Inlet Protection

Standards for Soil Erosion and Sediment Control in New Jersey May 2012 STANDARD FOR SLOPE PROTECTION STRUCTURES. Definition

Ponds. Pond A water impoundment made by excavating a pit, or constructing a dam or an embankment.

Nevada Contractors Field Guide for Construction Site BMPs

SECTION RIPRAP, BOULDERS, AND BEDDING

T-WALL & STONE STRONG

NEW CASTLE CONSERVATION DISTRICT. through. (Name of Municipality) PLAN REVIEW APPLICATION DRAINAGE, STORMWATER MANAGEMENT, EROSION & SEDIMENT CONTROL

Economics of Implementing Two-stage Channels

Ohio Department of Transportation Division of Production Management Office of Geotechnical Engineering. Geotechnical Bulletin

Method of Measurement for Road Works Series MM Earthworks

C. This project shall be designed to meet LEED Silver design criteria. Construction activity pollution prevention is a mandatory requirement.

ODOT Design & Construction Requirements for MSE Walls

10:00 AM, Wednesday, April 8, 2015

GUIDELINES FOR INSTALLATION OF ON-SITE SEWAGE SYSTEMS

Storm Drain Inlet Protection for Construction Sites (1060)

Applying landforming to reclamation: A case study in Central Appalachia

Prepared for Urban Drainage and Flood Control District

CHAPTER 15 - GABIONS, EROSION PROTECTION

TOWN OF GREENWICH, CONNECTICUT WILLIAM STREET BALL FIELD REMEDIATION WILLIAM STREET WEST, GREENWICH, CONNECTICUT

Final Report: 1999 South Fork Garcia River Watershed Erosion Control and Prevention Project, SB271 Road Upgrading and Decommissioning Project

10.1 INTRODUCTION 10.1 DRAINAGE

28 February 2017 ATTENTION: MR HENNIE WOOD AND MS MAGGIE VON RONGE NORTHAM BOOYSENDAL CC: AMANDA PYPER AMEC FOSTER WHEELER NOTE FOR THE RECORD

STREAMBANK RESTORATION DESIGN

Alternative No. 1 Total Cost DRAFT

Recommended Resources: The following resources may be useful in teaching this lesson:

Extended Detention Basin Maintenance Plan for [[== Insert Project Name ==]]

Open Trench Construction Plan Review The open trench construction plan review involves the following general investigative elements:

Design and Installation Guidelines for Retaining Walls. 1 P age. Geo Products, LLC 8615 Golden Spike Lane Houston, TX Phone:

REROUTING DRAINAGE SYSTEMS

C. Foundation stabilization for pipe and utility structures.

Attachment D-1: Civil/Structural Scope of Work

MODEL Stormwater Local Design Manual. City of Centerville

BASED ON DFD MASTER SPECIFICATION DATED 2/24/2014

B. Subsurface data is available from the Owner. Contractor is urged to carefully analyze the site conditions.

Preface. MNR # Queen s Printer for Ontario, 2012 ISBN (PRINT) ISBN (PDF)

City of Bozeman. Construction Site Management Program

Erosion Control for Home Builders

File No Supplemental November Geotechnical and Environmental Consulting Engineers

Departments of Agronomy C709 Conservation Farming and Biological and Agricultural Engineering. Permanent grass cover

SOIL EROSION CONTROL PERMIT APPLICATION

AEC Premier Straw Double Net Quick Mow EROSION CONTROL BLANKET SPECIFICATION

A. C-I ROAD RULES APPENDIX C: 14 CCR DEFINITIONS.

Stormwater Local Design Manual For Houston County, Georgia

MSE WALLS CASE STUDIES. by John G. Delphia, P.E. TxDOT Bridge Division Geotechnical Branch

Topic: Site Formation

DAM INSPECTION CHECKLIST Department of Environmental Protection Bureau of Waterways Engineering Division of Dam Safety

iv) Alberta fish weirs

LANDSCAPE RETAINING WALLS

Greenfield Pond B Rehabilitation

Block or Log forms of PAM and PAM blends are manufactured for specific use in drainage waterways to remove suspended particulates from runoff.

SACHSE EROSION CONTROL GUIDELINES

DIVISION 31 EARTHWORK 2006 Edition, Published January 1, 2006; Division Revision Date: January 31, 2012

Curlex High Velocity EROSION CONTROL BLANKET SPECIFICATION

TYPE "A" CATCH BASIN

PERVIOUS PAVEMENT. Alternative Names: Permeable Pavement, Porous Concrete, Porous Pavers

Rural Roads: A Construction and Maintenance Guide for California Landowners

Constructed Wetland Pond T-8

W. Goodrich Jones State Forest. Best Management Practices Virtual Demonstration Tour

Curlex II EROSION CONTROL BLANKET SPECIFICATION

Project Photo Tour Updated July 15, Tom Blackman Project Lead. Gary Cambre Senior Communications Manager 1

E. STORMWATER MANAGEMENT

f) Culverts in series shall be spaced at least 20 feet between each other. 2.7 C Culverts

Section Soil Erosion Protection Tender No. [ ] Page 1

Austin Technical Manuals - Standard Specifications Preservation of Trees and Other Vegetation (610S) 03/27/2000

CATCH BASIN ST-1 ENGINEERING DEPARTMENT PLATE NUMBER 3.33' 3.0' 2.0' 4.33' 3.0' 4.0' 1.00' TO BACK OF CURB LINE

Watershed size and name: The drainage area is acres. The pond is located within the Ohio River watershed. (2016 Inflow Design Plan)

LEVEE DEFICIENCY CORRECTION PROCEDURES

APPENDIX A EARTHEN EMBANKMENT. VERSION 1.0 March 1, 2011

CHAPTER 2 EROSION CONTROL

Transcription:

(FERC 1927) Erosion Control Plan Site Remediation/ Assessment Form Site # Med (3) LM2-25 Priority Ranking Locator Information/GPS GPS shows 16 ft accuracy Lat: Long: Impact Rating 5 Start Project Development: Lemolo 2 Risk Rating 1 Reference Point 43' 21.226" 122' 16.203" Nearest Project Feature: Waterway Structure Type: Canal, Access Road End Description of Concern: Slope 20 to 30 ft high above canal, includes isolated boulders that could roll into canal and cause damage. Site includes Helen Creek crossing. Proposed Remediation: Mitigate damage potential through installation of drainage pipes at selected locations along waterway so that canal can be drained in 30 minutes. Monitor slope for signs of failure and implement additional mitigation measures if required. Replace culvert under access road embankment only if culvert analysis indicates that it is undersized. Remediation Task Breakdown: Approx. units unit Estimated Additional Comments/Sketches quantity price Costs (2001$) Helen Creek crossing. Aquatic connectivity site L15 lies within the NA area of this site. Issues related to future modifications planned to restore aquatic connectivity have not been taken into account in evaluating erosion mitigation measures. Final design of aquatic connectivity measures at this site may result in modifications to the dimensions and limits of the proposed treatments Proposed location for 30-minute waterway drainage pipe. Additional engineering investigations and designs to be completed for drainage pipes. Design process will include review of draft designs by agency personnel as part of the normal implementation process. Final designs may include additional erosion control measures. (Cont. on next page) Data Collection Information: Mass Bal Borrow CY Team: Hanek, Moen, Hansen Weather: Overcast, 45 degrees Excess Fill CY Date: 16-Nov-01 Time: 9:00am Waste CY Printed: 03/11/2004 Revised: 3/4/2004

(FERC 1927) Erosion Control Plan Site Remediation/ Assessment Form Site # Med LM2-25 Priority Ranking Locator Information/GPS GPS shows 16 ft accuracy (Cont.) Impact Rating 3 Start Lat: Long: Project Development: Lemolo 2 Risk Rating 1 Reference Point 43' 21.226" 122' 16.203" Nearest Project Feature: Waterway Structure Type: Canal, Access Road End Remediation Task Breakdown: Approx. units unit Estimated Additional Comments/Sketches quantity price Costs (2001$) 21' 15' 40' Approximate embankment dimensions Data Collection Information: Mass Bal Borrow CY Team: Hanek, Moen, Hansen Weather: Overcast, 45 degrees Excess Fill CY Date: 16-Nov-01 Time: 9:00am Waste CY Printed: 03/11/2004 Revised: 3/4/2004

LM2-25 Site Photos Helen Creek Medium priority site No remediation planned other than mitigation through installation of 30-minute drainage pipes View of access road crossing and culvert outlet. Replace only if culvert undersized for 100 yr event. Monitor slopes above canal to observe erosion pattern and evaluate if there is need for additional measures in the future View of trestle on upstream side of creek crossing 03/11/2004 Revised: 6/28/2002

(FERC 1927) Erosion Control Plan Site Remediation/ Assessment Form Site # High LM2-26 Priority Ranking Locator Information/GPS GPS shows 22 ft accuracy Lat: Long: Impact Rating 3 Start Project Development: Lemolo 2 Risk Rating 2 Reference Point 43' 21.286" 122' 16.021" Nearest Project Feature: Waterway Structure Type: Access Road End Description of Concern: Access road embankment has oversteepened D/S side, drainage from road surface onto D/S face. Drainage down access road from east approach, also seepage in ditch on north side of road with potential to reach road surface and cause additional erosion. Areas of oversteepened sidecast to east of stream crossing, with little or no vegetation present. Proposed Remediation: Rebuild downstream side of embankment fill with gabion wall or engineered fill. Regrade road surface, excavate ditch on north side of road and line with rock to prevent downcutting. Remove sidecast fill from areas east of stream crossing and construct 60-ft long gabion wall, 12-ft high to maintain road surface and prevent further erosion of access road. See sketch. Remediation Task Breakdown: Approx. units unit Estimated Additional Comments/Sketches quantity price Costs (2001$) Sidecast Removal Beverly Creek crossing. This site is also a proposed location for 30- Excavation Use as padding material (or stockpile) Waste disposal Gabion Walls 9'x40' & 12'x60' 290 CY 260 CY 30 SF minute waterway drainage pipe. Design process may evaluate feasibility of using existing 30-inch diameter waterway drain pipe for 30-minute drainage. Additional engineering investigations and designs to be completed for drainage pipes. Design process will Excavate for tie backs Spread compact backfill Use as padding material (or stockpile) Place wire mesh tie-backs Place gabion baskets 9' high Place gabion baskets 12' high Stone fill in baskets Regrade Road & Establish Ditch on 80' 390 CY 340 CY 50 CY 2,500 SF 40 LF 60 LF 120 CY include review of draft designs by agency personnel as part of the normal implementation process. Final designs may result in modifications to the dimensions and limits of the proposed treatments Areas where ground is disturbed by construction will be protected with jute mats or other comparable erosion control measures until vegetation planting or other ground cover is provided in accordance with the VMP. Grader Small excavator Rock Uner 30" Drainage Pipe 4HR 4HR Riprap 1.5'-3' rock 5 CY (Cont. on next page) Data Collection Information: Mass Bal Borrow CY Team: Hanek, Moen, Hansen Weather: Overcast, 45 degrees Excess Fill 310 CY Date: 16-Nov-01 Time: 10:00am Waste 30 CY Printed: 03/11/2004 Revised: 3/4/2004

(FERC 1927) Erosion Control Plan Site Remediation/ Assessment Form Site # High (4) LM2-26 Priority Ranking Locator Information/GPS GPS shows 22 ft accuracy (Cont.) Impact Rating 5 Start Lat: Long: Project Development: Lemolo 2 Risk Rating 3 Reference Point 43' 21.286" 122' 16.021" Nearest Project Feature: Waterway Structure Type: Access Road End Remediation Task Breakdown: Approx. units unit Estimated Additional Comments/Sketches quantity price Costs (2001$) (Cont.) Slope Revegetation Jute Matting Revegetation 2,400 SF 2,400 SF Data Collection Information: Mass Bal Borrow CY Team: Hanek, Moen, Hansen Weather: Overcast, 45 degrees Excess Fill 310 CY Date: 16-Nov-01 Time: 10:00am Waste 30 CY Printed: 03/11/2004 Revised: 3/4/2004

LM2-26 Site Plan Beverly Creek N Double wall concrete flume Seepage area beneath steel flume Existing 30 dia. waterway drainage pipe, possibly used as a 30-minute waterway drainage pipe Enlarge 80-ft of existing drainage ditch on N side of road to 3-ft width and line with rock. Regrade existing road surface so that surface drainage flows into ditch and not along road. Access road New 60 ft long approximately 12 high gabion wall, wall continues approximately 20 ft further east than shown on sketch Steel flume on trestle Riprap Existing surface drainage on road Trees Existing gabion wall to remain Remove typical sidecast section North Umpqua River Timber crib (existing) Access road Rock wall at toe of fill (existing) Rebuild downstream face of existing embankment with gabion wall or engineered fill 0 Scale in feet 60 03/11/2004 Revised: 6/28/2002

LM2-26 Site Photos Beverly Creek Looking East at Beverly Creek Crossing Looking West upstream of Beverly Creek Crossing Existing Gabian Wall Areas for typical side cast removal on either side of existing Gabion wall Looking West at Beverly Creek Crossing 03/11/2004 Revised: 6/28/2002

(FERC 1927) Erosion Control Plan Site Remediation/ Assessment Form Site # High High LM2-27 Priority Ranking Locator Information/GPS GPS acc. 38' (S) and 138' (E) Lat: Long: Impact Rating 3 3 Start 43' 21.310" 122' 15.972" Project Development: Lemolo 2 Risk Rating 3 3 Reference Point Nearest Project Feature: Waterway Structure Type: Canal, Access Road End 43' 21.316" 122' 15.852" Description of Concern: Potential rockfall hazard from slopes above canal. This site includes Flume 2 failure site. Oversteepened sidecast fill on downslope side of access road. Two major failure areas caused by Flume 2 failure have bare oversteepened slopes immediately above North Umpqua River. Proposed Remediation: Place excess fill and regrade failure areas to stable slopes. Provide protection of toe of slope through placement of natural boulders present on site. Place rockfall mesh over 200-ft section of upslope area to mitigate potential for large boulders to bounce as they move down slope. Provide erosion control measures during regrading of eroded areas. Remediation Task Breakdown: Approx. units unit Estimated Additional Comments/Sketches quantity price Costs (2001$) Erosion Control Silt Fence Straw Bales 450 LF 450 LF Site Regrading Bulldozer & Operator Excavator& Operator Laborer Borrow Fill From Stockpile Rockfall Fence Rockfall Fence 200' long x 70' high Anchors (2 per 10' mesh section) Slope Revegetation Jute Matting Revegetation 24 HR 24 HR 24 HR 30,000 CY 14,000 SF 41 EA 30,000 SF 30,000 SF Site contains two erosion treatments listed in the Settlement Agreement: (1) Spoil piles and erosion & sediment control. Priority Rating: High (5) w/ impact (5), Risk (5) (2) Breccia slope over canal, and Priority Rating: High (5) w/ impact (5), Risk (5) Use excavator and bulldozer to establish track that will allow placement of spoil from other areas of project to rebuild slope. Pull exsisting oversteepened slopes to 1:1.5 grad. Push larger rock and boulders to toe of slope to improve stability, reduce erosion at toe and facilitate drainage. (Cont. on next page) Data Collection Information: Mass Bal Borrow 30,000 CY Team: Hanek, Moen, Hansen Weather: Overcast, 45 degrees Excess Fill CY Date: 16-Nov-01 Time: 11:00am Waste CY Printed: 03/11/2004 Revised: 3/4/2004

(FERC 1927) Erosion Control Plan Site Remediation/ Assessment Form Site # High (5) High (5) LM2-27 Priority Ranking Locator Information/GPS GPS acc. 38' (S) and 138' (E) Lat: Long: (Cont.) Impact Rating 5 5 Start 43' 21.310" 122' 15.972" Project Development: Lemolo 2 Risk Rating 5 5 Reference Point Nearest Project Feature: Waterway Structure Type: Canal, Access Road End 43' 21.316" 122' 15.852" Remediation Task Breakdown: Approx. units unit Estimated Additional Comments/Sketches quantity price Costs (2001$) Aquatic connectivity sites L11, L12 and L13 lie within the area of this site. Issues related to future modifications planned to restore aquatic connectivity have not been taken into account in evaluating erosion mitigation measures. Final design of aquatic connectivity measures at this site may result in modifications to the dimensions and limits of the proposed treatments. Data Collection Information: Mass Bal Borrow 30,000 CY Team: Hanek, Moen, Hansen Weather: Overcast, 45 degrees Excess Fill CY Date: 16-Nov-01 Time: 11:00am Waste CY Printed: 03/11/2004 Revised: 3/4/2004

LM2-27 Site Plan Approximately 200 of rockfall mesh above canal to prevent boulders impacting outside flume wall. 4230 N 4460 4360 L13 4055 L12 Distance in feet from access road canal crossing at upper end of Lemolo 2 canal Existing gabion wall to remain Temporary access for equipment to allow slope restoration L11 Existing gabion wall to remain North Umpqua River Eroded basin in slope, approximately 50 ft maximum depth, restore natural slope contour using excess sidecast fill from other erosion sites, revegetate restored slope Eroded basin in slope, approximately 60 ft maximum depth. Resotre natural slope contour using excess sidcast fill from other erosion sites, revegetate restored slope Place boulders at base of slope for toe protection Place silt fence and straw bail erosion protection at base of slope to prevent fine eroded material from entering river. 300 Scale in feet 0 Base map from Project Boundary maps Exhibit G of license application 03/11/2004 Revised: 9/9/2002

LM2-27 Site Plan 2 by 2 Anchoring Stakes FLOW 4 Vertical Face Typical Straw Bale 03/11/2004 Revised: 9/9/2002

LM2-27 Site Plan 3 Post or Equal Follow Specifications as per Section 02370 Erosion & Sediment Control Geotextile Fabric Staples or Wire Rings (Typ.) FLOW 3 Backfill or Bury Bottom of Filter Fabric with Native Material 6 2-6 1 8 4 O.C. Typical Silt Fence 03/11/2004 Revised: 9/9/2002

LM2-27 Site Photos Looking East at western erosion gully resulting from failure of Flume 2. 03/11/2004 Revised: 9/9/2002

LM2-27 Site Photos Silt fence and straw bail erosion control at base of slope Place boulders at outer edge of fill for toe protection Looking East at eastern erosion gully resulting from failure of Flume 2. 03/11/2004 Revised: 9/9/2002

(FERC 1927) Erosion Control Plan Site Remediation/ Assessment Form Site # High LM2-28 Priority Ranking Locator Information/GPS GPS - 26' (End) accuracy Lat: Long: Impact Rating 3 Start 43' 21.286" 122' 15.789" Project Development: Lemolo 2 Risk Rating 2 Reference Point Nearest Project Feature: Waterway Structure Type: Access Road End 43' 21.272" 122' 15.727" Description of Concern: Oversteepened sidecast with 80% slopes. Proposed Remediation: Remove sidecast from two segments of access road. Removal areas are from 3390 to 3500 ft (measured from access road bridge over canal at LM2 diversion point) and 3560 to 3740 ft. See sketch. Remove 'typical' sidecast prism: 15 ft horizontal distance, cut to 1.5:1 slope with flatter toe area, as shown on sketch. Remediation Task Breakdown: Approx. units unit Estimated Additional Comments/Sketches quantity price Costs (2001$) Sidecast Removal Excavation Excess fill to stockpile Waste disposal Slope Revegetation Jute Matting Revegetation 1,000 CY 900 CY 100 SF 8,700 SF 8,700 SF Areas where ground is disturbed by sidecast removal will be protected with jute mats or other comparable erosion control measure until vegetation planting or other ground cover is provided in accordance with the VMP. Leave 6" and larger diameter trees and their roots undisturbed during sidecast removal. Data Collection Information: Mass Bal Borrow CY Team: Hanek, Moen, Hansen Weather: Overcast, 45 degrees Excess Fill 900 CY Date: 16-Nov-01 Time: 12:00am Waste 100 CY Printed: 03/11/2004 Revised: 3/4/2004

LM2-28 Site Plan N 2-Wall Concrete Flume Steel Flume A GPS Ref. GPS Ref. Nancy Creek Canal access road 10 North Umpqua River Revegetate side cast removal slope in accordance with vegetation management plan t.b.d. 3740 Remove typical sidecast section See Section A A 3560 3500 No removal 3390 Remove typical sidecast section See Section A 300 Scale in feet Distance in feet from access road canal crossing 0 1.5:1 15 Section A NTS 5:1 Typical sidecast removal Do not remove 6 diameter or larger trees 3 Base map from Project Boundary maps Exhibit G of license application 03/11/2004 Revised: 6/28/2002

LM2-28 Site Photo View of eastern (upstream) end of LM2-28 looking towards Nancy Creek 03/11/2004 Revised: 6/28/2002

(FERC 1927) Erosion Control Plan Site Remediation/ Assessment Form Site # Med LM2-29 Priority Ranking Locator Information/GPS GPS shows 36' accuracy Lat: Long: Impact Rating 2 Start Project Development: Lemolo 2 Risk Rating 2 Reference Point 43' 21.277" 122' 15.680" Nearest Project Feature: Waterway Structure Type: Access Road, Culvert End Description of Concern: Nancy Creek crossing. Potential fill failure or debris flow plugging culvert, also sidecast fill failure potential, shotgun culvert outlet. Exisitng culvert is 36" diameter. Culvert under Nancy Creek is number 1075. Proposed Remediation: Replace culvert if culvert analysis indicates that it is undersized. Raise road surface on west end of approach approximately 2 ft to ensure proper surface drainage and to ensure that low spot in embankement is in area protected by gabion wall. Place rock on D/S slope of existing slope and fill in area under shotgun culvert. See sketch. Remediation Task Breakdown: Approx. units unit Estimated Additional Comments/Sketches quantity price Costs (2001$) Buttress Fill Clear slope Waste disposal Pitrun rockfill 10" minus Riprap 1.5'-3' rock 850 SF 5CY 80 CY 10 CY Regrade Road Fill material imported from other sites Grader Roadbed 1" minus pitrun 50 CY 4HR 10 CY Nancy Creek crossing. Proposed location for 30-minute waterway drainage pipe. Additional engineering investigations and designs to be completed for drainage pipes. Design process will include review of draft designs by agency personnel as part of the normal implementation process. Final designs may include additional erosion control measures. Method for placement of riprap on downstream face of embankment to be determined during final design, but may include benching and layer placement, end dumping, clamshell or other methods. Data Collection Information: Mass Bal Borrow CY Team: Hanek, Moen, Hansen Weather: Overcast, 45 degrees Excess Fill CY Date: 16-Nov-01 Time: 12:30am Waste 5 CY Printed: 03/11/2004 Revised: 3/4/2004

LM2-29 Site Plan Nancy Creek N A Steel Flume Possible location for 30-minute waterway drainage pipe. Existing surface drainage on road Canal access road Add 2 ft of fill to road surface on west side of embankment to shift dip in embankment to east so any surface drainage is onto area protected by gabion Culvert No. 1075 Riprap A Armor downstream face of existing embankment with rock Existing gabion wall to remain 0 Scale in feet 30 15 8 Rock placed on downstream face of existing embankment Section A NTS 1.5:1 6 Riprap 03/11/2004 Revised: 6/28/02

LM2-29 Site Photos Nancy Creek Armor downstream face of existing embankment with rock Existing gabion wall to remain 03/11/2004 Revised: 6/28/02

(FERC 1927) Erosion Control Plan Site Remediation/ Assessment Form Site # Med Med LM2-30 Priority Ranking Locator Information/GPS GPS acc. 31' (S) & 19' (E) Lat: Long: Impact Rating 2 2 Start 43' 21.315" 122' 15.575" Project Development: Lemolo 2 Risk Rating 2 2 Reference Point Nearest Project Feature: Waterway Structure Type: Canal, Access Road End 43' 21.311" 122' 15.118" Description of Concern: Breccia in slope above canal with potential to cause damage due to boulders rolling or bouncing into canal. Oversteepened sidecast in areas below access road. Patches in canal wall where past boulder impacts have damaged concrete and been repaired. Three or four noted. Poor drainage along access road surface - several areas of standing water. Proposed Remediation: Model upslope geometry to assess rockfall hazard and potential for additional damaging events. Place rockfall protection netting over 200 lineal ft of upslope area (60-ft high netting). Selectively remove sidecast from areas below road, as shown on sketch. Use sidecast to raise access road surface 3 to 4 ft and provide improved drainage. See sketch for areas of 'typical' sidecast removal and 'large volume' sidecast removal. Remediation Task Breakdown: Approx. units unit Estimated Additional Comments/Sketches quantity price Costs (2001$) Rockfall Fence Rockfall Fence 200' Long x 60' High Anchors (2 per 10' mesh section) 12,000 SF 41 EA Sidecast Removal Excavation Use as padding material (or stockpile) Waste disposal 4,500 CY 4,100 CY 400 CY Regrade Road Spread Material (from sidecast removal) Grader Roadbed 1" minus pitrun 1,300 CY 6 HR 100 CY Slope Revegetation Jute Matting (sidecast section) Revegetation (sidecast section) 26,000 SF 26,000 SF Aquatic connectivity sites L6, L7, L8, and L9 lie within the area of this site. Issues related to future modifications planned to restore aquatic connectivity at this site have not been taken into account in evaluating erosion mitigation measures at this site. Final design of aquatic connectivity measures at this site may result in modifications to the dimensions and limits of the proposed treatments In areas of sidecast removal, leave 6" and larger diameter trees and their roots undisturbed. Design efforts will include review of draft designs by agency personnel as part of the normal implementation process. Final designs may result in modifications to the dimensions and limits of the proposed treatments. Data Collection Information: Mass Bal Borrow CY Team: Hanek, Moen, Hansen Weather: Overcast, 45 degrees Excess Fill 2,800 CY Date: 16-Nov-01 Time: 1:00pm Waste 400 CY Printed: 03/11/2004 Revised: 3/4/2004

LM2-30 Site Plan N Placement area, See Detail 1 A Start Point GPS Ref. B L9 L8 End Point GPS L7 L6 No removal North Ump qu 2650 2245 2060 Remove large sidecast section See Section B Remove typical sidecast section See Section A 0 1000 No removal a Riv er 880 770 720 Remove typical sidecast section No removal 540 Remove typical sidecast section Base map from Project Boundary maps shown in Exhibit G of license application Scale in feet Canal access road 10 0 Distance in feet from access road canal crossing Canal access road Revegetate side cast removal slope in accordance with vegetation management plan t.b.d. 18 Revegetate side cast removal slope in accordance with vegetation management plan t.b.d. 15 1.5 :1 20 1. 5 :1 5:1 Section A 3 NTS Typical sidecast removal Do not remove 6 diameter or larger trees 03/11/2004 Section B 5:1 NTS 5 Large sidecast removal Revised: 6/28/2002

LM2-30 Site Plan N Approximate limit of sidecast placement area See Section C C C 0 540 Detail 1 North Umpqua River 300 Scale in feet 0 Sidecast used to raise access road grade Base map from Project Boundary maps shown in Exhibit G of license application Section C NTS Existing canal access road 03/11/2004 Revised: 6/28/2002 Place sidecast on top of existing road to depth of 3 to 5 ft, slope as needed to meet existing ground surface and maintain surface drainage

LM2-30 Photos Mudflow breccia above canal, potential for boulders falling into canal. View of over steep sidecast below road 03/11/2004 Revised: 6/28/2002

(FERC 1927) Erosion Control Plan Site Remediation/ Assessment Form Site # CW2-1 Priority Ranking Med Locator Info/GPS GPS shows 18' accuracy Lat: Long: Impact Rating 2 Start Project Development: Clearwater 2 Risk Rating 2 Reference Point Nearest Project Feature: Waterway Structure Type: Double wall concrete flume. End 43' 15.583" 122' 23.716" Description of Concern: Basalt outcrop with unfavorable joint orientation above canal. Joint orientations vary along length of outcrop. Outcrop at eastern end of site is 80 to100-ft high, but generally massive and shows little evidence of past failures. Higher rockfall hazard is present at western end, where joint orientation creates potential for rock blocks sliding into waterway. Proposed Remediation: Provide protection against rockfall damage to flume through installation of rockfall netting along a 200-ft section of waterway at the western end of the concrete and rock flume section. Scale loose rock before placing netting. Net will be 60-ft in height. Also place 65-ft high, 155-ft long rockfall net at upper end of concrete and rock flume, beginning 80 ft downstream of transition from 2-wall concrete flume and continuing downstream. In addition, place rockfall padding along 90-ft section of 2-wall concrete flume, at location shown on sketch. Remediation Task Breakdown: Approx. units unit Estimated Additional Comments/Sketches quantity price Costs (2001$) Slope Scaling Cherry Picker Load and Haul Scaled Material Padding of Upslope Canal Wall w/ Fill Clean/Locate Risers at Padding Area Riser pipes 24" dia. 4' high (assumed) Pipe Bedding/Wall Drainage Rock (5CY/Riser) Fill Padding 90' (2CY/FT) Rockfall Fence Rockfall Fence 200' Long X 60' High Fence Anchors (2 Anchor per 10' Length) Rockfall Fence 155' Long X 65' High Fence Anchors (2 Anchor per 10' Length) 16 HR 20 CY 2EA 2EA 10 CY 180 CY 12,000 SF 41 EA 10,000 SF 33 EA Additional engineering investigations and designs to be completed for drainage pipes. Design efforts will include review of draft designs by agency personnel as part of the normal implementation process. Final designs may result in modifications to the dimensions and limits of the proposed treatments. Aquatic connectivity sites C23 and C24 lie within the area of this site. Issues related to future modifications planned to restore aquatic connectivity at this site have not been taken into account in developing proposed erosion mitigation measures at this site. Final design of aquatic connectivity measures at this site may result in modifications to the dimensions and limits of erosion treatments shown. Data Collection Information: Mass Bal Borrow 180 CY Team: Hansen, Moen, Denq Weather: Clear, cool Excess Fill CY Date: 7-May-02 Time: 8:00am Waste 20 CY Printed: 3/11/2004 Revised:3/04/2002

CW2-1 Site Plan A 2-Wall Concrete flume Place padding along 90- ft reach at upper end of 2-wall concrete flume N Scale loose rock and then place rockfall netting on slope above waterway. Net should be 60-ft in height, 200-ft in length, and cover area immediately upstream of end of concrete & rock flume. Concrete & Rock flume GPS Ref. C24 A Concrete & Rock flume Possible location for 30-minute waterway drainage pipe. Rockfall netting on slope above waterway. 65-ft in height, 155-ft in length, ends at point 80 ft downstream of transition from 2-wall concrete flume to concrete & rock flume. \ C23 0 2-Wall Concrete flume Concrete & Rock flume Scale in feet Rock flume 500 Remove rock knobs or place rockfall netting upslope of canal Canal access road Padding material on upslope side of 2-wall concrete flume to provide rockfall protection, if culverts exist under flume, add slotted risers to existing drainage culverts to maintain drainage Section A NTS Base map from Project Boundary maps Exhibit G of license application Printed: 3/11/2004 Revised: 6/28/2002

CW2-1 Site Photos View east along Clearwater 2 canal in area of concrete and rock flume at west end of site. \ Representative view north across canal at east end of site, in area where rockfall padding will be placed on upslope side of 2-wall concrete flume. Printed: 3/11/2004 Revised: 6/28/2002

(FERC 1927) Erosion Control Plan Site Remediation/ Assessment Form Site # CW2-2 Priority Ranking Med Locator Information/GPS Lat: Long: Impact Rating 2 Start Project Development: Clearwater 2 Risk Rating 2 Reference Point Nearest Project Feature: Waterway Structure Type: Double wall concrete flume. End 43' 15.312" 122' 23.412" Description of Concern: Mudflow Breccia with small slumps and wedges. Rockfall into waterway could cause partial blockage of flow. Proposed Remediation: Install drainage system that will allow canal to be drained within 30-minutes. Monitor slope above canal for signs of failure, however slope is only approximately 35-ft in height and failure of isolated blocks is unlikely to cause major blockage within canal. Daily canal inspections will identify any significant rockfall and develop plans for removal when needed. Remediation Task Breakdown: Approx. units unit Estimated Additional Comments/Sketches quantity price Costs (2001$) NA Data Collection Information: Mass Bal Borrow CY Team: Hansen, Moen, Denq Weather: Clear, cool Excess Fill CY Date: 7-May-02 Time: 2:20 Waste CY Printed: 3/11/2004 Revised: 3/4/2004

CW2-2 Site Plan N 2-Wall Concrete flume Monitor upslope areas for movement. Remove rockfall debris from flume to avoid overflow. Provide mitigation against any future flume failure through installation of drainage system to allow canal drainage within 30 minutes of any flume failure. A Rock flume A GPS Ref. 0 250 Concrete & Rock flume Scale in feet Canal access road Section A NTS Base map from Project Boundary maps Exhibit G of license application 3/11/2004 Revised: 6/28/2002

CW2-2 Site Photo Representative view north across canal showing concrete and rock flume. Mitigation to be provided through installation of drainage system that will allow canal to be drained within 30 minutes. 3/11/2004 Revised: 6/28/2002