Case study The construction of the West Rail Tsing Kwai Tunnel from Mei Foo to Tsuen Wan

Similar documents
HUDSON TUNNEL PROJECT

introduction Introduction to Bridge and Tunnel Engineering Characteristics of ideal bridge Ideal location Factors affecting bridge type Classification

From Colonia Jardín to Cuatro Vientos

Case examples for the construction of complex basement

Preferred Elevated Tank Site

Ironton Russell Bridge Project

D7: TUNNEL CONSTRUCTION AND METHODOLOGY

Ironton Russell Bridge Project

TBM Selection and Specification

COMMUNITY BOARD EIGHT

COMPETITIVENESS OF PIPE-JACKING TUNNEL LININGS

LARGE-SCALED BRIDGE PROJECTS IN RECENT HONG KONG. Raymond W M Wong, Division of Building Science & Technology, City University of Hong Kong

13/05/2016. Introductions of Pipe Roof. Focuses. Application of Rectangular Shield Jacking

Pipe Jacking/Microtunnelling. Dr. Mark Knight. Centre for Advancement of Trenchless Technologies (CATT) University of Waterloo.

Introduction to Tunnel Construction

CROSSRAIL INFORMATION PAPER D8 TUNNEL CONSTRUCTON METHODOLOGY

Ironton Russell Bridge Project

4th International Engineering and Construction Conference - July 28, 2006

An indicative program for works to be conducted within the Sydney Park construction compound is provided in Table 6-20.

Topic: Site Formation

Pump storage hydro power plant (PSKW) Reißeck

Venice Pumping Plant Dual Force Main Project Draft EIR

Large-scale site formation for a residential development at Sheung Shing Street, Ho Man Tin

Ironton Russell Bridge Project

Topic: Site Formation

ATHABASCA RIVER BRIDGE REHABILITATION PROJECT

PAUL ZICK, PE NORTH SHORE CONSTRUCTORS JV

TUNNEL WIENERWALD ABSTRACT

SPECIAL CONDITIONS FOR PIPE JACKING (PJ) October, 2006

The Aizhai Suspension Bridge is

An introduction to. pipe jacking

Rock Tunnel Engineering INTRODUCTION. Tunnel a hole in the ground to provide for desired movement or as mobility channel.

Hardrock Tunnel Boring Machines

Semmering Base Tunnel Large Caverns in Challenging Conditions

Diaphragm wall Construction

King County Uses Trenchless Methods to Construct a Large Siphon Under Seattle s Ship Canal

The Technical and Contractual Matters of Bored Piling Works. By Wallace Yeung Vibro (H.K.) Ltd.

Horizontal Directional Drilling

Indirect and Cumulative Effects

Trenchless Technology

ILC ASIAN DRAFT SCHEDULE

2.0 PROJ ECT D ESCRI PTION

USE OF MICROTUNNELING TO INSTALL PIPES IN AN ENVIRONMENTALLY SENSISTIVE AREA. Miranda Roman D. *, LaFaso Edward

The Chief Estimator Software. Item Cost Summary Bridge & Overpass Projects

Hamilton Rapid Transit Preliminary Design and Feasibility Study

Workshop Brief Notes on: Construction of Pipe Roof and Support System

Concrete Pipe Jacking

All Drill and Blast Tunnelling Works for Shatin to Central Link Completed

Design Data 4. Jacking Concrete Pipe

LARGE DIAMETER PIPE ROOF BOX EXCAVATION FOR PASSENGER LINKWAY TUNNEL

Tunnel Lining Design and Construction

Tunnels. Introduction in Shield tunnelling Pipe jacking & tunnelling Slurry & hydroshield Slurry versus EPB Principles of support pressure

Well Road Project Accelerated Bridge Construction Using Self-Propelled Modular Transporters (SPMT s) By: Mark Bucci, P.E.

SAFE WORK METHOD STATEMENT

Challenges in the Remediation of the Glatscheras-Railway-Tunnel, Bergün, Switzerland

There are several types of trenchless technology applications for new installations. The following are some of the most prominent applications.

Section Safety Section Cleanup. None Required

Stabilization of Running Granular Soils in TBM Alignment with Sodium Silicate Grout

Finnish Underground Lab

THE GOTTHARD BASE TUNNEL PROJECT IN SWITZERLAND CONSTRUCTION OF THE WORLD S LONGEST RAILWAY TUNNEL. Jens Classen

Trenchless Pipeline Crossings

Design and Construction of the SH58 Ramp A Flyover Bridge over IH70. Gregg A. Reese, PE, CE, Summit Engineering Group, Inc.

Design and development of a decline shaft through poorly consolidated Kalahari deposits at Ghaghoo Diamond Mine.

Field trips 7, 14, 15. Brenner Base Tunnel

Purple Line Extension Section 1 Construction Community Meeting September 26, 2017

THE GROUNDBREAKING TUNNEL

Membrane for tunnels and underground construction

Collation between Underground and Elevated Metro System

Immersed Tunnels. Richard Lunniss and Jonathan Baber. CRC Press. Taylor & Francis Group. Taylor & Francis Group, A SPON BOOK

Design Data 4M. Jacking Concrete Pipe

ITR CONCESSION COMPANY LLC

TRENCHLESS TECHNOLOGY. Department of Civil Engineering.

INFRASTRUCTURE TUNNELS

Excavation Safety Program

Introduction. General Description

I-94/I-69 Interchange Bridge Construction

12 Oct Virama Karya presentation on South Coast Highway. Therefore require a new route expressway

Pipe Jacking. Japan Sewage Works Association

Funding was provided by the City of New York via the Hudson Yards Infrastructure Corporation and Hudson Yards Development Corporation.

Western Rail Link To Heathrow

Rowa Customers Day. Gotthard Base Tunnel Sedrun, Lot 360. Speaker: Heinz Jenni 07 September 2004

STANDARD SPECIFICATIONS SECTION TUNNELING. A. Section includes requirements for constructing tunnels 48-inch and larger diameter.

Finnish Underground Lab

The Use of the Roof The Upper Level Company

Hydraulic Excavators

Getting. Dodge. in and outa

AlpTransit Gotthard and Lötschberg Rowa s Contribution

Slope Stabilisation and the Beauty Of Shotcrete AN OVERVIEW

Underground Construction Technology

3 rd Edition of the ITA Tunnelling Awards - the winners 2017!

Summary, Conclusion and Outlook

District Department of Transportation ABC in DC (Accelerated Bridge Construction in Washington, DC) Paul Hoffman October 26, 2016

Operations and Civil Engineering Services Construction Operations (Construction)

6.2.2 Environmental Consequences and Mitigation Measures

Rossio Railroad Tunnel Surveillance and Analysis of the Rehabilitation Works

DIVISION 33 - UTILITIES SECTION UTILITY PIPE BORING AND JACKING DIVISION 33 UTILITIES SECTION UTILITY PIPE BORING AND JACKING

Feasibility of Underground Short-Haul Freight PipelinesApplication to the DFW Airport

Highway and Rail Transit Tunnel Inspection

STANDARD SPECIFICATIONS SECTION BORING AND JACKING. A. Section includes requirements for boring and jacking casing pipe.

Transcription:

Case study The construction of the West Rail Tsing Kwai Tunnel from Mei Foo to Tsuen Wan

West Rail Tsing Kwai Tunnel Location of major Tunnel Portal

West Rail Tsing Kwai Tunnel Construction Features - Total length about 3.6 km - The 1 st section from Mei Foo to Lai King, about 1.7 km long, constructed using drill-and-blast method - The 2 nd section from Lai King to Tsuen is Wan about 1.8 km long, constructed using a 8.4m dia. mixmould tunnel boring machine (TBM) - A 50m dia. access shaft is provided at Lai King to facilitate the dismantling of the TBM upon its completion of the drilling from Tsuen Wan direction. - The TBM has been used twice, forming the east and south bound tube in two separated journeys from Tsuen Wan direction to Lai King

Tunnel alignment from Mei Foo Direction Ching Cheung Road West Rail Tsing Kwai Tunnel at Mei Foo Portal Forming a access ramp into the tunnel portal

Forming a access ramp into the tunnel portal

Temporary ramp being formed Forming a access ramp into the tunnel portal

The purposes of tunnel portal 1. As temporary ramp entering into the tunnel 2. As a working space for the assemble or dismantling of tunnelling equipments 3. As exit to allow excavated spoil be removed from the tunnel interior 4. Setting up and stationing of supporting services such as ventilation or equipment storages 5. As an approach section leading to other tunnel servicing areas, such as equipment depot or spoil/material storage

West Rail Tsing Kwai Tunnel Portal at MF Inside the portal seeing the preparation and entrance arrangement into the tunnel

A tunnel working gantry is being assembled at the portal on Mei Foo side Setting up arrangement at the tunnel portal

Works in Drill and Blast Tunnel (for rock tunnel) 1. Layout the tunnel alignment and start drilling holes for placing explosive charges along the side of the tunnel section. Each time about 5m (depth of hole). 2. Place in explosive and do the blasting. 3. Use excavating machine to remove the loosened rock 4. Removal the excavated using suitable equipment, such as by conveyor or by dumper truck. 5. Temporary stable the exposed tunnel surface by shotcrete, girder beam or rock nail where required. 6. Construct tunnel lining to cover up the tunnel interior permanently.

The drilling machine usually can operating 3 to 4 hole drilling operation at one time using computer controled drilling arm. Boring machine to form holes for placing of explosive

Tunnel surface temporary protected by shotcrete Erection of the waterproofing membrane before the placing of tunnel lining Formwork for placing tunnel lining

Lai King Hill Road West Rail Tsing Kwai Tunnel Service Shaft at Lai King Kwai Chung Road

The purposes of tunnel shaft at Lai King 1. As an emergency access at the mid-way of a long tunnel. 2. As an access point for the delivery of materials such as concrete, precast lining segment or rail track into the tunnel tube for the required works 3. To serve as a work station to dismantle and remove the tunnel machine drilling from Tsuen Wan direction.

West Rail Tsing Kwai Tunnel Portal at Tsuen Wan Waterside Plaza Wing Shun Street Diversion Alignment of cut-andcover tunnel

West Rail Tsing Kwai Tunnel Tunnel Boring Machine & Tunnel Lining

The shielding units and some pieces of precast tunnel lining segments storage at the portal

Tsing Kwai Tunnel - Tunnel Boring Machine Assembling the shield of the tunnel boring machine

West Rail Tsing Kwai Tunnel Portal at Tsuen Wan Assembly of the tunnel drilling machine inside the shaft of Tsuen Wan portal Shield of the TBM

The Tunnel Boring Machine being first assembled for testing and commissioning in the depot

Portal setting up in mid 1999 Portal arrangement in mid 2000 Portal for the Tsing Kwai Tunnel at Tsuen Wan

Acoustic cover to control dust and noise from disturbing the neighbourhood

Spoil removal system for the tunnel construction during boring and excavation process

Tunnel tube with the precast lining segments forming the final tunnel lining

The hydraulic jack system inside the boring machine. The jacks can provide the anchoring, pushing and turning ability for the machine to facilitate the boring process

Another example of TBM of smaller size used in forming a service tunnel for water supply pipeline

Construction of the Interchanging Section at Ching Cheung Road, Mei Foo - where a section of tunnel crossing a busy roadway without interrupting the surface traffic

Tunnel alignment from Mei Foo Direction Ching Cheung Road at in Dec 1999 Ching Cheung Road

Ching Cheung Road in Dec 2000 Ching Cheung Road in Dec 2001

Construct the tunnel section using cut-and-cover manner in 3 sections, with temporary closure of one section at a time and reinstate afterward, follow by the next section.

Detail showing the arrangement of a cutand-cover section and the provision of the soil support system

The final reinstatement of the completed section