Non-Destructive Testing & Assessment of Concrete Structures Case Study: St. Mary Dam Low-Level Conduit

Similar documents
Inspection & Maintenance of Concrete Facilities By Cheyenne Wohlford CCS GROUP, LLC

Structural Assessment and NDT Procedures

FHWA Mobile Concrete Lab Program. Illinois Tollway Open House: Sustainable Concrete Paving Practices August 20, 2013

MURALT WALLS: VIANE AND SCHELPHOEK, NETHERLANDS

Restoration and Rehabilitation FRP Wrapping

USE OF GPR TO ESTIMATE DETERIORATION IN CONCRETE BRIDGE DECKS

NDT in Grouted PT Inspection for Bridges

Strengthening of Grinding Building Slab. Strengthening of Grinding Building Slab Batu Hijau Copper-Gold Mine

Fundamentals of Concrete

PRISM TEST, FLAT JACK TEST, REBOUND HAMMER, & MECHANICAL PULSE VELOCITY

Non-Destructive Assessment of the Historic World War Memorial Baseball Stadium, Greensboro, North Carolina

Application of Rebound Hammer Method for Estimating Compressive Strength of Bricks

SECTION PERMEABLE INTERLOCKING CONCRETE UNIT PAVEMENT

Non-Destructive Evaluation of Concrete using Ultrasonic Pulse Velocity

Course Concrete Technology Course Code Theory Term Work POE Total Max. Marks Contact Hours/ week

Reliability Of Non-Destructive Tests For Hardened Concrete Strength

Strength Evaluation of Existing Concrete Buildings

CTP STITCH-TIE AGAIN! Quick and easy way to re-anchor existing veneers to back-up structures.

CORROSION MONITORING IN REINFORCED CONCRETE BY ACOUSTIC EMISSION

CW 3615 RIPRAP TABLE OF CONTENTS

The Detection and Analysis of Reservoir Dam Crack Depth and Grouting Quality Analysis

CONTINUOUS FLIGHT AUGER (CFA) PILES QC/QA PROCEDURES. Preferred QC/QA Procedures

ITU-T L.74. Maintenance of cable tunnels SERIES L: CONSTRUCTION, INSTALLATION AND PROTECTION OF CABLES AND OTHER ELEMENTS OF OUTSIDE PLANT

Non-destructive Testing of Concrete - Methods of Test. Lecture No. 26

METHOD OF MAKING AND CURING CONCRETE TEST SPECIMENS IN THE FIELD FOP FOR AASHTO T 23

The choice of concrete as a building material in con-structing

Nondestructive evaluation of concrete dams and other structures. Larry D. Olson, P.E. (Presenter); Dennis A. Sack

Minimum Guidelines for the Design and Use of Underpins When Performing Foundation Stabilization and/or Supplementation UP-08

FHWA-NDE CENTER. Methods Available for Testing & Evaluation of Structures. NDE Center Federal Highway Administration

In situ non-destructive testing: the steel and concrete resistance assessment of ancient r/c structures

Condition Assessment and Repair/Strengthening of Reinforced Concrete Structures University of Cape Town, Dept. of Civil Engineering

MINERAL ADMIXTURES IN CONCRETE

Assessment of reinforcement corrosion in concrete façades

Mr. Paul Dunlap, California Department of Water Resources

KIM Best Practices Guide for Shotcrete Nov 2013

3/5/2014. Disclaimer and Waiver of Liability. Learning Objectives. Portland Cement Association

Sikafloor -161 is an economic, two part, solvent free, low viscosity epoxy resin, suitable for use under hot climate condition.

Durability Assessment Techniques

SPECIFICATION FOR THE RUBBER SPEED HUMPS

Study on Estimated In-situ Cube Strength from Cores and Cube Strength

SECTION CAST-IN-PLACE CONCRETE

Introduction of a Japan Concrete Institute Guideline: Practical Guideline for Investigation, Repair and Strengthening of Cracked Concrete Structures

GPR Application Case Studies

Module 8: Composite Testing Lecture 36: Quality Assessment and Physical Properties. Introduction. The Lecture Contains

Destructive and Non- Destructive Testing for Concrete in Sudan - A Comparative Study

ALKALI AGGREGATE REACTIVE MORTAR CYLINDERS PARTLY RESTRAINED BY EXTERNAL CFRP FABRIC EXPANSION AND CONFINEMENT

In Service Replacement of Box Girder Bottom Slab

BIO-AQUIFER STORM SYSTEM

GHD Materials Technology

Liquid applied polyurea hybrid membrane

Concrete. Chapter 10 Properties of Fresh Concrete. Materials of Construction-Concrete 1. Wikipedia.org

Construction. SikaTop 111 Plus. Application Instructions. Sika Corporation

Construction. 3-part cement and epoxy combination micro mortar for surface sealing. Product Description 1 1/5. Tests

CHEMICAL /4" 3/8" to 5/8" /8" 3/4" to 1-1/4" 1 10

September 1, 2003 CONCRETE MANUAL SPECIAL TYPES OF CONCRETE

DETECTION OF INCLINED CRACKS INSIDE CONCRETE STRUCTURES BY ULTRASONIC SAFT

Geotech Services, X-18, MIDC, Hingna, Nagpur, Maharashtra. Discipline Mechanical Testing Issue Date

PRECAST CONCRETE ON-SITE WASTEWATER TANKS

IN SITU MONITORING OF REINFORCEMENT CORROSION BY MEANS OF ELECTROCHEMICAL METHODS

TAMDID PIPES GRP MANHOLE BROCHURE

INDEX FOR SPECIFICATIONS FOR JACKING CULVERTS THROUGH EMBANKMENTS SCOPE... 2

A.2.a Random Riprap... Table

STANDARD SPECIFICATION FOR CRIBLOCK CONCRETE CRIBWALL

Measurement and Documentation for Structural Integrity Assessment of an In-Service School. Building at Risk

The Long Term Performance of Three Ontario Bridges Constructed with Galvanized Reinforcement

TECHNICAL ASSISTANCE REPORT EFFECT OF CONCRETE REMOVAL EQUIPMENT AND METHODS ON THE CONDITION OF DECK CONCRETE LEFT IN PLACE

Structural Evaluation and Strengthening Strategy for a Reinforced Concrete Commercial/Residential Complex in Northern Beirut

5th Pan American Conference for NDT 2-6 October 2011, Cancun, Mexico

KOSTER AMERICAN CORPORATION

Section COATING RESTORATION

APPLICATION OF GROUND PENETRATING RADAR (GPR) AS A DIAGNOSTIC TECHNIQUE IN CONCRETE BRIDGES INSPECTION

High Strength Epoxy Tested in Accordance with ICC-ES AC308

Narrow Modular Pavers (NMP) for Sand-Set Installations

Satish Sharma, B.S. Rao. Adarsh Kumar NS, Rizwan Anwar, Ankit Sharma National Council for Cement and Building Materials, India

Pulsed Eddy Current Testing (PECT) Inspection Technique

Specified Tests for Concrete Quality

Kinds of Mortars. Mortar. Specifying Mortar. Proportion Specifications. M a S o N w O r K. Specification for Mortar Cement

February 1, 2016 PARTIES INTERESTED IN EXTERIOR ULTRA-HIGH PERFORMANCE CONCRETE THIN WALL CLADDING PANELS

Changing Needs In Sulfur Capacity For In- Ground Reinforced Concrete Sulfur Pits

Construction. 2-part epoxy primer. Product Data

Protective Coatings for Underground Utility Concrete Structures. By: John E. Davis Inside Sales & Marketing Specialist: Sauereisen, Inc.

AAPA Facilities and Engineering Seminar. Robert Tolsma PE, PPM, D.PE Division Manager Atkins North America San Diego, CA Oct 22, 2015

ASSESSING CREEP DAMAGE IN CAST MATERIAL FOR REFORMER TUBES UTILIZING MULTI-PARAMETER APPROACH

Pulsed Eddy-Current (PEC) Inspection through Insulation

***********************************************************************************

Pre-Sloped Drain System

Section Fluid Applied Waterproofing

High Strength Epoxy Tested in Accordance with ICC-ES AC308

SECTION STAY-IN-PLACE INSULATED CONCRETE FORMING SYSTEM

CITY OF FARGO SPECIFICATIONS AGGREGATE BASES

DETERMINING THE STRENGTH OF SOLID BURNT BRICKS IN HISTORICAL STRUCTURES


SECTION I FLEXIBLE PIPE VS. RIGID PIPE (GENERAL)

The Wing Sang Building at 51 East Pender

100-YEAR SERVICE-LIFE BRIDGE DECKS USING LOW-SHRINKAGE HIGH-PERFORMANCE CONCRETE

Tile on Existing. Viewpoint

Giuseppe Giunta, Giuseppe Calloni EniTecnologie SpA Via Maritano 26, I San Donato Milanese, Italy

Maryam Nasser AlHarthy Student, Department of Built and Natural Environment, Muscat, Sultanate of Oman Corresponding author:

Transcription:

Non-Destructive Testing & Assessment of Concrete Structures Case Study: St. Mary Dam Low-Level Conduit Presented By: Clayton Weiss, P.L.(Eng.) ESRD Operations Infrastructure, Oldman Basin

St. Mary Dam - Background Constructed 1946-1951, 65 years old, high risk Low-level concrete riparian conduit, 646 meters long (426 m easy access via catwalk left side at 3m), 6m (20 ) inside Dia., 0.6-0.75m thick walls, sub-grade under 50 meters fill.

Management & Optimization of Aging Infrastructure Challenge: approaching end of theoretical design service life. How to determine actual remaining life, justify need for high priority funding? Extreme high costs to repair or replace. Limited funding, many competing high priority projects: What is the Level of Risk??!! Dictates when is action is required PROVE IT Design & Construction will take many years due to size and unique challenges start planning now.

Management & Optimization of Aging Infrastructure Current monitoring strategy: Standard Methods: Visual surface inspections, crack monitoring, leakage/seepage monitoring, Schmidt hammer testing. Very effective and essential to continue, but has limitations: Limited to surface only, no way to identify and map internal defects Limited precision, requires confirmation & quantitative data No early warning of internal degradation.

Management & Optimization of Aging Infrastructure How to increase level of scrutiny beyond the surface, and gather quantitative data, including: Directly measure internal quality and overall uniformity of the concrete Identify red flag defects. i.e. voids, delamination, honeycombing Confirm actual rebar arrangement (concerns regarding 1940 s construction standards). More inputs for identifying Level of Risk

Non-Destructive Testing Methods - Options? - 1) Schmidt Hammer Test lower precision for internal defects, needs confirmation - 2) Hammer Sounding - lower precision for internal defects, subjective, needs confirmation - 3) Ultra-Sonic Pulse Velocity (UPV) Used to assess structural integrity of concrete members in bridges, and to map extents of defects. Limitation requires 2-sided access, not possible in the case - 4) Impact-Echo Scanning LOW COST, FAST - collect ASTM approved measurements of thickness in concrete and identify and map location and extents of defects ex. Cracks, Delaminations, Voids, Honeycombing. Limited to 1 meter thickness, requires only 1-sided access YES - 5) Ground Penetrating Radar LOW COST & FAST - Identify and map first layer of rebar - YES - 6) Coring and Laboratory testing by far the most detailed, complete & precise information, but HIGH COSTS and LONG TIMELINES in concrete of questionable quality, destructive testing can be risky until condition is first assessed with methods such as #4 and #5 above.

Evaluate New Methods for Monitoring & Assessment of Concrete Structures Pilot Project: Evaluate the Effectiveness of Non-Destructive Testing Techniques as a useful Infra. Management Tool augment existing methods. May, 2013 Request for Proposals for Non-Destructive Testing, Impact Echo and GPR Awarded to AMEC Materials Group, Calgary. July, 2013 Field Testing program begins

Field Testing Program GPR Rebar Locates - 5 Sample Locations

Field Testing Program GPR - 5 Sample Locations

Field Testing Program GPR - 5 Sample Locations Results Red Flag concerns/deficiencies Reinforcing bar highly variable pattern/orientation, vertical and horizontal spacing far too wide, not close to conforming to current standards Not installed as per record drawings, record information incorrect!! Very deficient in spacing, orientation, consistency, and cover

Field Testing Program Impact-Echo - Sample Locations

Field Testing Program Impact-Echo - Sample Locations

Field Testing Program Impact-Echo - Sample Locations

Field Testing Program Impact-Echo - Results Sound Concrete Suspect/Low Quality Concrete Defective Area

Field Testing Program Impact-Echo - Results Defective Concrete Multiple Defective Areas

Field Testing Program Impact-Echo - Results Summary of Results Strong correlation with visual and hammer sounding results, >50% areas sampled were red flag concerns Sound/Good: 50% Suspect or Defective: 50% Delaminated Areas: 56% Interpretation? Next Steps? Consultant recommended collecting Core Samples for Lab Analysis to calibrate readings, Impact-Echo Proof-of-Concept, increase confidence Also Collect additional Lab data: Compressive Strength & Hardened Density, Air entrainment, Permeable void analysis Alkali-aggregate reactivity

Confirmation of Non-Destructive Tests - Core Sampling & Laboratory Analysis Jan., 2014 10 Cores Collected & Analyzed at AMEC s Lab» 3 diameter, Min. depth 200 mm

Concrete Coring for Lab Analysis

Concrete Coring for Lab Analysis

Concrete Condition Core Laboratory Findings and Conclusions Overall, highly variable concrete with many reasons for concern: Consistently High/Good Compressive Strength, Avg. >50 Mpa Absorption and Permeable Voids Good Consolidation Air Content Very Poor, not air-entrained, Evidence of stress due to prolonged moisture, sulphate attack, weakening structure, Poor No evidence of Alkali-aggregate reactivity, Good Evidence of expansive distress, physical defects including cracking, delamination and voids consistent with Impact Echo findings, Poor Rebar orientation, spacing and depth of cover Very Poor

Evaluation of Methods - Conclusions Ground Penetrating Radar Rebar Location Method Effective method for mapping rebar and cover, confirming asconstructed records, id new deficiencies. No other equivalent substitute method Fast Real-Time Results, Cost Effective

Evaluation of Methods - Conclusions Testing Results: Strong correlation between A) Existing Visual & Hammer Surveys, B) Impact Echo and C) Actual lab test results

Evaluation of Methods - Conclusions Evaluation of Method - Impact Echo Testing Method: Reliable, Effective, Immediate Results in Real Time, No Waiting, Low Cost, much cheaper than core & lab test Low Impact No Destruction and can quickly access tight spots Confirmed results from current/past methods, i.e. areas of defect Expanded scrutiny into interior of concrete, confirmed thickness Provided quantitative data to add credibility and confidence to conclusions i.e. Current Level of Risk, Remaining Service Life Limitations - Not a standalone solution for concrete evaluation, but is complementary & adds value to a comprehensive program.

Conclusions When used in combination with existing surface monitoring, spot core sampling and lab tests for calibration, Impact Echo and GPR are very fast, cost effective testing methods for concrete structure assessment and early detection of problems. Not a standalone solution, limitations must be understood Particularly valuable for buried sub-grade structures Adds credibility to current monitoring program and directly supports maintenance & Capital Planning processes.

Next Steps Expand scope of testing & evaluation: Gather more data from more locations, including bottom and top of conduit with access issues Uniformity? Areas of more severe defect, first point of failure? Risk? Continue to refine service life estimates, support Capital Planning Process Track change over time Retain a Structural Engineer to analyze the data in detail, 3 rd party opinion on current level of risk and remaining life

Questions?? and Thank You: Mr. Shaun Radomski, M.Sc., P.Eng. Materials Engineer AMEC Environment & Infrastructure Calgary, AB Clayton Weiss, P.L.(Eng.) ESRD Operations Infrastructure, Oldman Basin clayton.weiss@gov.ab.ca 403-381-5984