Root Cause Analysis Report

Similar documents
Root Cause Analysis Report

Conformity Assessment. Dan Cheetham BPV Requirements 4/12/16

EFFECTIVE ROOT CAUSE ANALYSIS

CPEA. Certified Professional Environmental Auditor.

CQR-1. CONTRACTOR QUALITY REQUIREMENTS for CONSTRUCTION SERVICES Revision Date: 6/8/2015

QUALITY ASSURANCE SPECIFICATION WELDING HEAT TREATMENT PAGE 1 OF 6

Guide for AWS Visual Weld Inspection

AS9102 Frequently Asked Questions

A brief history of welding

Quality Management Review. MoDOT Dave Ahlvers P.E. Dennis Brucks P.E. Josh Kincaid P.E.

Conformity Assessment. Dan Cheetham BPV Topics of Interest 2016 Certification 360

Quality Management System

"Welder Certification"

Stretch Your Shrinking Budget with RCA

SUPPLIER QUALITY SYSTEM SURVEY

NR CHECKLIST Rev. 1. QAM IMP References NBIC Part 3, 1.8 Y N Y N a. Organization. Company Name/Certificate Number: Page 1 of 26

Welcome. Mission. About Us. to Sharjah Steel Corporate Portfolio

SUPPLIER QUALITY REQUIREMENTS

KOPETZ BUSINESS PROCESS MAP LEVEL 1 INQUIRY TO DELIVERY

Facilities Planning and Construction (FP&C)

Pipeline Systems PIP PLSC0013 Non-Destructive Examination of ASME B31.4 and B31.8 Metallic Pipelines

Manufacturing Company, Inc Tanner Road Phone: (713) Houston, Texas Fax: (713)

SAMPLING AND ERROR EVALUATION RSM US LLP. All Rights Reserved.

Bituminous Percent Within Tolerance (PWT)

APPENDIX B Corrosion Management System Framework and Guidance

TECHNICAL SPECIFICATIONS for 100Ci Ir-192 source projector(exposure device /Camera )

Vendor Qualification Survey

UNIFIED FACILITIES GUIDE SPECIFICATIONS

General Document or OQE Comments SAT UNSAT

Flooring Contractor QA/QC Plan Sample Selected pages (not a complete plan)

MEC-QW-E-2005 Senior QA/QC Inspector / Test Package Coordinator PERSONAL DATA LANGUAGES COMPUTER SKILLS TRAINING COURSES AND CERTIFICATIONS

Introduction. Al-Rook Engineering Services Company (est. 2002) based in Baghdad-Iraq with offices in Basra and Erbil.

DOT-FHWA QA/QC Plan Sample Selected pages (not a complete plan)

AECON POWERS THE INDUSTRY

D. All distributors shall be reviewed and approved as per company procedure.

There is an inspection report prepared after the Digester cleaning was carried out.

How ISO/TS Developed

Quality Assurance in the Amusement Industry CLARK WESTERFIELD

By Ginger Bailly 18 Feb For Official Use Only

Lean Project Delivery Operating System

Quality supervision (QS) and material testing

GLOBAL INTERNATIONAL SERVICES MATERIAL INSPECTION CONTROL

) ) ) ) ) ) ) ) ) ) II.

Supplier Quality Survey

Quality Assurance The Rest of the Story

SECTION QUALITY REQUIREMENTS

AxiomLogics. Auditing Consulting Staffing Training. One Stop QUALITY

NAPCA Workshop August 19, 2010 Houston, Texas Kenneth Y. Lee Office of Pipeline Safety

CONSTRUCTION MANAGEMENT

Coating Application Specialist (CAS): The New Standard for Quality, Safety, and Reliability in Industrial Painting. White Paper. v2.

EA-7/04 Legal Compliance as a part of accredited ISO 14001: 2004 certification

ZODIAC INTERCONNECT US ZODIAC AEROSYSTEMS SEGMENT ZODIAC INTERCONNECT DIVISION

Industrial Services. Minimizing Downtime. Maximizing Performance. LDAR. Leak Detection and Repair (LDAR) Services

MASTER AGREEMENT FOR BRIDGE DESIGN SERVICES SCOPE OF WORK

REQUEST FOR PROPOSAL. Construction Management Services Not at Risk

Corrosion Under Insulation Detection Methods and Inspection

Presented by: Gary Scribner Manager of Technical Services. August The National Board of Boiler and Pressure Vessel Inspectors

By Jasmine Gilmore, Quality Analyst

BULLETIN 15 (Publication 35) Qualified Products List for Construction

Case Report from Audit Firm Inspection Results

Maine Turnpike Authority Construction Resident Engineer/Inspector SCOPE OF WORK July 14, 2014

SUPPLIER QUALITY ASSESSMENT

Internal Audit Quality Analysis Evaluation against the Standards International Standards for the Professional Practice of Internal Auditing (2017)

VIRGINIA DEPARTMENT OF TRANSPORTATION MATERIALS DIVISION MEMORANDUM. Charles A. Babish, PE State Materials Engineer Approved:

LONE STAR PIPE TRACKING SYSTEM

COMPANY PROFILE INNOVATION EMIRATES GENERAL CONTRACTING L.L.C.

FAA/HSAC PART 135 SYSTEM SAFETY RISK MANAGEMENT SAFETY ELEMENT REQUIRED INSPECTION ITEMS (RII) JOB AID

Contractor Management and Purchasing

DALAIR LIMITED QUALITY MANUAL

ISO 9001 Quality Management Systems

Quality Management Manual

Instructions for Supplier Survey

A Total Solution for Semiconductor / WEEE RoHS Laboratory

TENDER FOR INSPECTION AND RADIOGRAPHIC TESTING OF WELDING JOINTS

LEED for Homes Sampling Protocol for Multi-family Projects 2011 Version

2

INNOVATION BEYOND TECHNOLOGY

Quality Assurance Program for CDA / Design-Build Projects with a Capital Maintenance Agreement with Three Optional 5-Year Terms.

Private Side Sewer Inspections for Sources of Inflow & Infiltration Frequently Asked Questions

Special Inspections Instructions

Janitorial QA/QC Manual Sample

How to use the TNI standards to meet essential QC elements in the MUR

Company Introduction & Overview

Project management and engineering solutions for the global pipeline industry

MONTACHUSETT REGIONAL TRANSIT AUTHORITY (MART) BROKERAGE DEPARTMENT QUALITY ASSURANCE AND INTEGRITY PLAN FY2015

UPPLIER ANUAL. Issued: 01 Aug 13

Audit Report No: QE /12 - S. Hooks Industrial, Inc. Contact Person: Mr. John Valentine Phone: « »

GxP Auditing, Remediation, and Staff Augmentation

Pressure Piping Construction Requirements

ISO General Requirements for Competence of Testing Laboratories Procedure

REQUEST FOR PROPOSAL FOR CONSTRUCTION MANAGEMENT SERVICES NOT AT RISK FOR THE. St. Charles County Ambulance District

Reach optimal revenue by maximizing every opportunity in your Service Department.

Section [ ] Storm Water Treatment Device

3 rd PARTY MATERIALS TESTING MANUAL

PURPOSE To establish a quality requirements and guidelines for Suppliers doing business with Orchid Monroe

Subcontractor / Supplier Pre-Bid Qualification All fields must be filled out unless otherwise noted.

SECTION HIGH DENSITY POLYETHYLENE PIPE AND FITTINGS (PRESSURE PIPE)

Manufacture of welded products - Welding workshop

Transcription:

Page 1 \ 10 RCA Name Pipeline weld non-conformance Report Number 2012-001 Report Date 7/27/2012 Root Cause Analysis Report Problem Statement Focal Point Near miss-almost had to replace 5 miles of 6" underground oil pipe When Start Date 7/8/2012 Unique Timing After discovering QC was not performed on installation Where Component Oil Pipelines Porter Creek interstate network Actual I mpact Cost Cost Cost Customer Service Cost Excavation & inspection of 5 weld joints $95,000.00 Radiography $25,000.00 Risk Assesment $21,000.00 Damaged reputation with client $0.00 Actual I mpact Total: $141,000.00 Frequency 1 times overall Frequency Notes Have missed other inspection points but this is the first time an entirely new installation had all inspections points missed. Potential I mpact Cost Environmental Revenue excavate and replace pipeline $9,000,000.00 New environmental impact study $130,000.00 potential loss of customer $15,000,000.00 Potential I mpact Total: $24,130,000.00 Report and chart generated by Sologic s Causelink software. www.sologic.com

Report Summaries Page 2 \ 10 Executive Summary In July of 2012, it was discovered that 5 miles of underground pipe that had been installed did not meet specifications due to out of spec welds and improper radiographic inspection. The client agreed to not replacing the entire pipeline if we repaired the out of spec welds, and if we completed an engineering assesment that included random inspection of 10 other welds, which was successfully completed to their satisfaction. The welds were out of spec because the wrong weld rod was used and the welds were not inspected. The wrong weld rod was used because the welder was not clear on the specs and he thought the rod used would meet the specs because he used that same rod on a previous job. The welds were not inspected because the weld inspectors were not notified to be there because the project manager didn't think it was necessary. The improper radiographic inspection was caused by using the wrong film and overexposed x-rays. The wrong film was used because the technician had multiple films available for use and he was unclear on which to use. The x-rays were over exposed because the wrong developing procedure was used. include but are not limited to: 1) Pre-scheduling of weld inspections at the beginning of jobs, 2) Have weld inspectors sign off on the weld rod container prior to first use, 3) Conduct pre-job review between welders and inspectors prior to the start of work, 4) Require certified x-ray techinicans and verify certification prior to commencing work. Cause and Effect Summary In July of 2012, we had a near miss where we almost had to replace 5 miles of pipe after it was discovered that the underground pipe did not meet specifications due to out of spec welds and improper radiographic inspection. The client agreed to not replacing the entire pipeline if we repaired the out of spec welds, and if we completed an engineering assesment that included random inspection of 10 other welds, which was successfully completed to their satisfaction The welds were out of spec because the wrong weld rod was used and the welds were not inspected. The wrong weld rod was used because the welder was not clear on the specs and he thought the rod used would meet the specs because he used that same rod on a previous job. The welds were not inspected because the weld inspectors were not notified to be there because the project manager didn't think it was necessary and he was trying to complete the job quickly. He was trying to complete the job quickly because they were nearing the end of the project and if they got done ahead of schedule, the team woudl receive a bonus. The improper radiographic inspection was caused by using the wrong film and overexposed x-rays. The wrong film was used because the technician had multiple films available for use and he was unclear on which to use. The technician was unclear on which film to use because he was new to the job and had not received much training. The lack of training was caused by technicians employer thinking he was qualified and because they didn't have the staff available to train or mentor him. The x-rays were over exposed because the wrong developing procedure was used because the technician was inexperienced in this area.

Page 3 \ 10 ID 1 Label Solution Cause Note Description Pre-schedule weld inspections at the begining of pipe installation Inspectors not told to be at inspection Assigned Brandon Prudent Due 8/8/2012 Status Selected Term Long Cost $0.00 2 Solution Cause Note Have welding inspector sign off on weld rod containers before use wrong welding rods used Assigned Chris Eckert Due 8/8/2012 Status Identified Term Long Cost $0.00 3 Solution Conduct pre-job review between welders and inspectors prior to the start of work. Assure welders have specs in the field and have reviewed them prior to starting. Cause Note Did not have weld spec available in field Assigned Cory Boisoneau Due 8/8/2012 Status Selected Term Short Cost $150.00 4 Solution Require certified X-ray technicians in the bid specs and followup to verify certification before technicians commence work Cause Note radiographer was inexperienced Assigned Cory Boisoneau Due 8/8/2012 Status Selected Term Medium Cost $0.00 5 Solution Implement Pre-job testing/checks to verify technician competency Cause Company did not audit for existing knowledge or skills

Note Assigned Due Term Choose Status Identified Choose Cost $1,500.00 Page 4 \ 10 6 Solution Cause Note When specific exposure, film and testing procedures exist, clearly include in bid specs. was unsure of what film to use Assigned Chris Eckert Due 8/8/2012 Status Selected Term Medium Cost $0.00

Team Page 5 \ 10 ID Label Description Label Description 1 First Name Brandon Last Name Prudent Phone (1) Phone (2) Role Group Email brandon.prudent@sologic.com 2 First Name Chris Last Name Eckert Phone (1) Phone (2) Role Group Email chris.eckert@sologic.com 3 First Name Cory Last Name Boisoneau Phone (1) Phone (2) Role Group Email cory.boisoneau@sologic.com

Page 6 \ 10 ID Label Description 1 Welding engineer statement pipeline weld standards exist wrong welding rods used 5 welds were out of spec Chris Eckert Direct Statement 2 Deficiencies were not addressed inspectors not present on job Inspectors not told to be at inspection no quality inspectors on site wrong welding rods used Pipe welds did not meet standards wrong film used welds not inspected used wrong developing procedures Improper radiography Installation specs' requred welds to meet standards previous weld xrays were overexposed Cory Boisoneau Direct Statement 3 welds not inspected welder choose to use them specific use truck not available inspectors not present on job truck was used for multiple types of welding

available on welding truck welder thought rod choice would meet specs Unclear direction on which rod to use multiple types of rods were available to be used Thought pipe service was same as past weld jobs. Same rod choice in the past met weld specs Did not have weld spec available in field shortage of trucks in industry Page 7 \ 10 Cory Boisoneau Direct Statement 4 Engineering analysis 10-345 engineering assessment showed pipeline was fit for purpose determined that welds were adequate for purpose of pipeline shared server G:\engineering docs\ Brandon Prudent Document 5 site construction manager confident welds and xrays were adequate inspectors not present on job no quality inspectors on site Experienced personnel assigned to other jobs Installation specs' requred welds to meet standards Client agreed to base decision on engineering assesment Company did not audit for existing knowledge or skills Company thought he was sufficiently ready for job dug up 10 random welds to check for quality All 10 welds passed the quality tests client agreed to terms of not replacing pipeline save time to get job done under required time getting close to end of project to recieve bonus

Page 8 \ 10 Brandon Prudent Direct Statement 6 new to job muliple types of film existed in darkroom inexperience with this type radiography was unsure of what film to use 2 types of film existed Radiographer completed technician program used wrong developing procedures New radiography had 2 weeks experience film type existed in truck previous radiographer resigned Radiographer had not received much training developing procedures existed new radiography stocked truck with film used stock was low went to job with better pay recently certified No mentors assigned Short staffed radiographer was inexperienced Chris Eckert Direct Statement

Actions & Chart Page 9 \ 10 Completed ID Custom Actions - 0-0 Termination Points - 0 Cause s - 0 Unconnected Causes - 0 Empty Cause Boxes - 0 Label 351 Action Check existing projects to verify that welding and inspection requirements were clearly spelled out Cause site construction manager confident welds and xrays were adequate Assigned Completed Description Chris Eckert Due Date 9/2/2012 yes

Notes Page 10 \ 10 ID Label Description 1 Note Engineering assesment criteria were agreed to by both parties Cause Client agreed to base decision on engineering assesment

Chart Legend Transitory Non-transitory Omission - Transitory Report and chart generated by Sologic s Causelink software. Site construction manager confident welds and xrays were adequate? Omission - Non-transitory Focal Point Solution Implemented www.sologic.com Deficiencies were not addressed inspectors not present on job e Inspectors not told to be at inspection Save time To get job done under required time To recieve bonus Pre-schedule weld inspections at the begining of pipe installation Status Selected Getting close to end of project Specific use truck not available Multiple types of rods were available to be used Available on welding truck Truck was used for multiple types of welding pipeline weld standards exist Shortage of trucks in industry Welding engineer statement Welder chose to use them Same rod choice in the past met weld specs Welder thought rod choice would meet specs Thought pipe service was same as past weld jobs.? Wrong welding rods used Welding engineer statement Have welding inspector sign off on weld rod containers before use Did not have weld spec available in field? Status Identified 5 welds were out of spec Unclear direction on which rod to use Conduct pre-job review between welders and inspectors prior to the start of work. Assure welders have specs in the field and have reviewed them prior to starting. Status Selected Pipe welds did not meet standards Welding engineer statement Connects to: f No quality inspectors on site Radiographer was inexperienced New to job g Welds not inspected f No quality inspectors on site Connects to: e Inspectors not told to be at inspection Require certified X-ray technicians in the bid specs and follow up to verify certification before technicians commence work Radiographer completed technician program Inexperience with this type radiography Status Selected Company thought he was sufficiently ready for job Company did not audit for existing knowledge or skills? Was unsure of what film to use Radiographer had not received much training Implement pre-job testing/checks to verify technician competancy Status Identified When specific exposure, film and testing procedures exist, clearly include in bid specs. Status Selected Experienced personnel assigned to other jobs Muliple types of film existed in darkroom? No mentors assigned Wrong film used Short staffed Near miss -- Almost had to replace 5 miles of 6" underground oil pipe 2 types of film existed Stock was low Film type existed in truck New radiographer stocked truck with film used New radiographer had 2 weeks experience Recently certified Improper radiography Previous radiographer resigned Went to job with better pay Installation specs requred welds to meet standards Developing procedures existed Previous weld xrays were over-exposed Used wrong developing procedures Connects to: g Radiographer was inexperienced Client agreed to base decision on engineering assessment Client agreed to terms of not replacing pipeline Dug up 10 random welds to check for quality Engineering assessment showed pipeline was fit for purpose Determined that welds were adequate for purpose of pipeline Engineering analysis 10-345 Engineering analysis 10-345 All 10 welds passed the quality tests