SITE WORK II: Footings, Cisterns

Similar documents
Table of Contents. Page Title

PLATON FOUNDATION WRAP

JC Code & Construction Consultants, Inc. Advanced Training: The FBC & ASTM C 1063

LIQUID RUBBER INDUSTRIES ENGINEERING SPECIFICATIONS FOR ENGINEERS AND ARCHITECTS. Diagram 1: Standard Membrane Continuation 150 mm Overlap

Safety on Heights: Our Policy

PLATON RUGGED, DIMPLED HIGH-DENSITY POLYETHYLENE (HDPE) MEMBRANE THAT KEEPS FOUNDATIONS AND FLOORING DRY ADVANCED TECHNOLOGY EASY INSTALLATION

4 EXTREME FOUNDATION PANELS

SpaVault TM Installation Guide for Bullfrog Spas (7-10 x 7-10 x 38 )

Steps And Stairs Installation Option 1 - Steps In Wall Option 2 - Steps With Plant Space Option 3 - Steps In Front of Walls Option 4 - Steps Along

Steps And Stairs Installation Steps In Wall - Option 1 Steps In Front of Walls - Option 2 Steps In Wall; 10 (25cm) Tread - Option 3 Step Parallel to

SECTION CHAIN LINK FENCES AND GATES (GALVANIZED) A. Fence framework, fabric, gates, and accessories.

Confined masonry. Definition

Anchor bolts ASTM F1554, Gr. 36 Wide flange beams ASTM A992, Fy = 50 ksi Misc. structural steel ASTM A36, Fy = 36 ksi

BUILD A SHOWER CUBICLE

Contact Clark Public Utilities Construction Services department at (360) to initiate a request for service.

HOW TO BUILD Garden Walls Frestanding & Landscape Walls

Installation Guide. PrivacyShield Outdoor Enclosure

CONSTRUCTION PROCEDURES. AWWA D110 Type I Prestressed Concrete Tanks

Successful Home Contracting

SECTION 1043 FENCE MATERIAL

Houston Community College 3200 Main Parking Garage November 15, 2010 Houston Community College

CONSTRUCTION SURVEY. Construction survey includes personnel, equipment, and supplies required for, but not limited to, the following:

Nepal Biogas Plant -- Construction Manual. Construction Manual for GGC 2047 Model Biogas Plant

THE POTTING SHED PF-1D-1144 CONSTRUCTION DRAWINGS PROJECT PLAN INDEX FOUNDATION / FLOOR PLAN 2 ROOF PLAN 3

DARTMOUTH COLLEGE DESIGN January 3, 2012 & CONSTRUCTION GUIDELINES

CONCRETE FORMWORK CHECKLIST AT SITE

SECTION STAY-IN-PLACE INSULATED CONCRETE FORMING SYSTEM

Soil Mechanics Lateral Earth Pressures page Lateral Earth Pressures in case of inclined ground surface or friction at wall-ground interface

When I started tiling, we didn t do our own shower pans that BATHS

The better way to build TM. Installation Manual FOUNDATION SIPs & FROST WALLS SIPs


NOVEMBER 2016 MAGNUMSTONE. retaining walls installation manual

ITEM 6 CONCRETE CURBS, GUTTERS, AND SIDEWALKS

Habitat For Humanity: How to Build a House by Larry Haun

Foundation/Site Work Code Requirements

Chapter 7. Roof Framing

Steps in Building a Shed

Planning and installation instructions

CHAIN LINK FENCES AND GATES

MERCHANTS METALS. A. ASTM F552 Standard Terminology Relating to Chain Link Fencing

WIRING METHODS CHAPTER 38

Concrete weighs about 150 pounds per cubic foot

The Otji-Toilet self builder manual The Clay House Project Otjiwarongo

NORTHWESTERN UNIVERSITY PROJECT NAME JOB # ISSUED: 03/29/2017

Delivering Reliability. Electrical Vaults. Power & Energy-Underground Structures

THE WORLD LOOKS UP TO COMPOSITE ELEVATED TANK

Planning, Laying Out, and Tooling Concrete Block

Redi Rock Specification and Installation Manual

Foundation Manual. Part Number: Version: Updated: July 5, S. Meadows Pkwy. A-9, #329 Reno, NV

Smarter. Safer. Leaner.

PV Mounting System 2703 SERIES 200 UL GROUND MOUNT SYSTEM. SnapNrack Residential PV Mounting Systems Code Compliant Installation Manual

PATENTS ARE PENDING. Building Dimensions. Exterior Dimensions Roof Edge to Roof Edge

Senergy Platinum CI Stucco Typical details for an impact resistant cement plaster stucco system featuring Neopor GPS Plus Rigid Insulation Board

Haener Block General Building Tips

Attached Solar Greenhouse Plans for a solar heated greenhouse attached to your home

MACHINE-LAY Installation Manual

at home installation guide Manufactured by:

SECTION UTILITY MANHOLES AND STRUCTURES

84 Lapping & Jointing 86 Service Pipe Penetrations 87 Sealing to Cavity Wall Constructions 88 Protecting Membranes System Components.

Detached Garages and Building Permits. 1 and 2 Family Dwellings

STANDARD SPECIFICATION FOR CRIBLOCK CONCRETE CRIBWALL

Preventing Water Leakage through Construction Joints using SYNKOFLEX Preformed Compressible Waterstop

CHAPTER 4. Construction Manual of Bio-gas Reactor

CATCH BASIN ST-1 ENGINEERING DEPARTMENT PLATE NUMBER 3.33' 3.0' 2.0' 4.33' 3.0' 4.0' 1.00' TO BACK OF CURB LINE

SECTION CHAIN-LINK FENCES AND GATES 02821/1

Design Data 6. Loads and Supporting Strengths Elliptical and Arch Pipe. Values of B d

One and Two Family Additions

GUIDELINES FOR INSTALLATION OF ON-SITE SEWAGE SYSTEMS

AUGUST 2017 HASTINGS. retaining walls installation guide

Tasman Retaining Wall System

Installation Information 2016

Product Data Sheet SikaFuko Swell-1 Positioning Description Uses Advantages Approval / Standards Construction Product Data Packaging

Construction. Hydrophilic, swellable hose for sealing construction joints in watertight structures. (formerly Sika Injectoflex HPM)

Design and Installation Guidelines for Retaining Walls. 1 P age. Geo Products, LLC 8615 Golden Spike Lane Houston, TX Phone:

A. Product Data: Submit manufacturer s product data, with complete general and specific installation instructions, recommendations, and limitations.

KIM Best Practices Guide for Shotcrete Nov 2013

HOW TO INSTALL PATIOS AND WALKWAYS STEP 2 STEP 1. For all Patios and Walkways. The base is the most important step in your patio and walkway projects.

SECTION MANHOLES AND STRUCTURES. A. Section Includes: 1. Manholes for water, storm drain and sanitary sewer systems.

ITEM 458 WATERPROOFING FOR STRUCTURES

A. BILL OF QUANTITIES FOR SANITARY SEWER

PROPOSED YONTOY PREFAB OFFICES PROPOSED PREFAB INSTALLATION -YONTOY- JUBBALAND STATE OF SOMALIA PROJECT: IMPLMENTED BY: GOVERNMENT.

Inlets & Catch Basins

See the IRC for additional information. See CPD-DS Information Bulletin 100 for Requirements for 1 & 2 Family Dwelling plan submittals.

Encapsulated, Sealed & Closed Crawlspace Installation Manual

FLUID APPLIED WATERPROOFING

SECTION FOUNTAINS

Design & Construction Standards, Revised January

CITY OF FARGO SPECIFICATIONS CONCRETE SIDEWALKS AND DRIVEWAYS

SPECIFICATIONS FOR PRECAST MODULAR BLOCK RETAINING WALL SYSTEM (revised 5/8/7)

GENERAL SHALE NATURAL THIN ROCK VENEER Installation Guide. GeneralShale.com

Attachment A-Flagpole(s) Specifications

FORMING THE RETAINING WALL FOUNDATION OUTER WALL

PART A: JOB PROCDRE FOR PLASTERING

2003 International Residential Building Code

City of Hughson Building Safety Division 7018 Pine Street Hughson, CA (209)

Foundation Systems 1, spread foundations. What s the point? What types? The foundation s primary purpose is:

hurricane resilient wooden houses safer building and retrofitting guidelines

Affordable Buildings, Exceptional Quality!

Transcription:

SITE WORK II: Footings, Cisterns RUBBLE FOOTINGS FOR EARTHBAG BUILDINGS Materials: Rubble, stone, gravel Tranchée/ Trench: The bottom of the trench must be level and at least 20 cm (8 ) deep on the downhill side of the building. It must be dug down to firm, undisturbed subsoil. The trench must be 45-50 cm (18-20 ) wide, as wide as the bags and the plaster layers both inside and outside. Gravier/ Gravel: Use finely crushed rubble or gravel to fill 3 courses of doubled poly bags for a footing. Sol/ Floor: Fill the interior of the building with rubble or clean fill and earth. Décombres/ Rubble: Use a 12-15 cm thick layer of rocks and pieces of rubble mixed with gravel for the trench footing.

Ouverture/ Opening: Make sure that two courses of bags fit beneath the floor level at the door. Décombres/ Rubble: Set the floor level 10 cm (4 ) below the top of the third course of footing bags. If a concrete floor is added later it will still be below the earthbag walls. Note: In areas that are subject to frost, the rubble foundation should extend below the frost level. WALL BASE REINFORCEMENTS FOR RUBBLE FOOTINGS Materials: Tubular bag, cement, rebar, metal for fasteners. If reinforced cement footings cannot be used in earthquake prone areas, metal can help to reinforce the wall base. Sac/ Bag: Earth-filled bags are laid on top of the three footing courses of gravel-filled bags.

Barre/ Rebar: Hammer 35 cm (14 ) lengths of rebar into each bag at the second course of earth-filled bags to hold the corrugated strip below in place. Bend the tip of the rebar over. Bande/ Strip: Place 15-20 cm (6-8 ) wide strips of corrugated metal on the center of the entire first course of earth-filled bags. Overlap strips 30 cm (12 ) minimum at ends. Use 7.5 cm nails to pin at overlaps and at corners to the bags below. Gravier/ Gravel: Three courses of gravel-filled bags will prevent dampness from damaging unstabilized earthbags. If soil is to be backfilled higher against the walls, use enough courses of gravel bags to keep earth-filled bags 15 cm (6 ) above finish grade. BUILDING A CISTERN (1) Materials: Bags and/ or tubes, gravel, cement, #4 (1/2 ) minimum rebar, galvanized metal mesh, poly or nylon fishnet, latex waterproofing, pipes, strong poly or nylon cord, and lid. Locate any cistern 1 m (3') or more from any proposed building walls. Be careful to not disturb the soil where the building will be placed. These designs are only intended for frost-free climates. Left: Cross-sectional view Bags filled with only earth are not recommended for underground use. They can be damaged by high water levels or by leaking from the cistern itself. This can cause the walls to fail. The first 3/4 meter (30 ) can be built with bags filled with angular gravel if it interlocks well enough to be stable. Bag and test your gravel to be sure. The upper courses must be filled with rubble or gravel mixed with a slurry of cement, or earth mixed with enough cement to fully stabilize it.

The curving top is built of ferrocement tied to a thick interior cement plaster reinforced with mesh. Left: Use a pole compass to build round walls Pound a 60-90 cm (24-36 ) pipe into the ground at the center of the cistern location. Put a 1.6 m (5'-3 ) height round stake or smaller pipe inside. This must be perfectly plumb. Slide a pipe clamp or clip onto the stake. This will be adjusted to the height of the bag course you are measuring. Then add a ring or a short piece of pipe above it. Tie a sturdy rope or fasten a metal arm to this moveable ring or piece of pipe. BUILDING A CISTERN (2) Note: Provide bracing if necessary until the cement plaster interior is completed.

Sac/ Bag: Doubled poly bags filled with gravel. Angle bag ends to center of dome to accommodate curve. Fasten interior layer of metal mesh to exterior layer of fishnet every 2 courses and 60 cm (24 ) horizontal. Fil de Fer/ Wire: Use 2 rows of barbed wire between each layer. Tube/ Tube: Tubes or bags filled with stabilized earth or with gravel or rubble in a cement slurry. Test to find the best ratio of cement and/ or lime needed for your fill material. Terre/ Soil: Place bag walls on undisturbed subsoil. Barre/ Rebar: Hammer rebar for ferro-cement framework through upper courses of bags or tubes before cement sets. Ciment/ Cement: Bend vertical rebar and wire horizontal rebar to it to form top. Attach mesh for top following best practices for ferro-cement. Place reinforcement of mesh or rebar for tank floor. When ferro-cement framework is complete add a thick cement finish plaster layer inside of tank and tank top, and pour reinforced concrete floor. Complete as much as possible in one day to avoid cold joints between separate cement areas, which will be more likely to leak. A latex cement additive will also improve waterproof quality. Trowel interior cement smooth for ease of cleaning. Add rough cement plaster to exterior. BUILDING A CISTERN (3): PLAN FOR A ROUND 3700 LITER (1000 GALLON) CISTERN

Bâtiment/ Building: A cistern should be located at least 1m (3 feet) from an earthbag building wall. Pipe/ Pipe: Build a ferro-cement pipe with an overflow spout, sloping up from the tank to 30 cm (12 ) above grade. This pipe must be larger than the gutter downspout, and be screened. Add a second pipe for a water supply line. Citerne/ Cistern: The cistern walls and roof must be backfilled and covered. Trappe/ Hatch: Provide a hatch of 2.5 cm (1 ) thick cast concrete or heavy metal that overhangs the scuttle beneath it. The hatch should be at least 30 cm (12 ) above grade to prevent contamination of the stored water. Do not backfill until ferro-cement structure has completely cured. Use scrap cardboard or straw to protect bags from damage if backfill material contains rocks. Note: Locate overflow spout above stone water spreader in swale.

BUILDING A CISTERN (4): PLAN FOR AN OBLONG 6000 LITER (1600 GALLON) CISTERN Bâtiment/ Building: A cistern should be located at least 1m (3 feet) from an earthbag building wall. Pipe/ Pipe: Build a ferro-cement pipe with an overflow spout, sloping up from the tank to 30 cm (12 ) above grade. This pipe must be larger than the gutter downspout, and be screened. Add a second pipe for a water supply line. Citerne/ Cistern: The cistern walls and roof must be backfilled and covered. This oval cistern will be stronger if the straight wall section includes a pier on each side. Trappe/ Hatch: Provide a hatch of 2.5 cm (1 ) thick cast concrete or heavy metal that overhangs the scuttle beneath it. The hatch should be at least 30 cm (12 ) above grade to prevent contamination of the stored water.

Do not backfill until ferro-cement structure has completely cured. Use scrap cardboard or straw to protect bags from damage if backfill material contains rocks. Locate overflow spout above stone water spreader in swale.