Approach to Overseas EPC Project

Similar documents
Design and Operating Experience of Supercritical Pressure Coal Fired Plant

SOME ENERGY-EFFICIENT TECHNOLOGIES IN JAPAN

Lünen State-of-the-Art 813MW Coal-Fired USC Boiler with High Efficiency and Flexibility

Recent Technologies for Steam Turbines

Equipment Design. Detailed Plant Conceptual Design. Version 9.0

Kazushige KUROSAWA*, Zhibao ZHANG**, and Zhengbing WANG** [Delivered Products & Systems] 1. Introduction. 2. Overview of Nanjing

Worldwide Pollution Control Association. August 3-4, 2010

Samcheok Green Power 4 x 550 MW e Supercritical Circulating Fluidized-Bed Steam Generators in South Korea

COAL WATER SLURRY FUEL Alternate Fuel for Thailand

New 790-Megawatt Unit. Council Bluffs Energy Center

Oxyfuel retrofit to coal power plant (Part1) - FS of 500MW class plant

TruePeak TDLS200. NH 3 Slip Measurement. <Document Number> Copyright Yokogawa Electric Corporation <date/time>

Steam Turbines. Leading Technology for Efficient, Reliable Generation Siemens Steam Turbines from 90 MW up to 1,900 MW.

Adoption of USC CFB Technology to Achieving Lower Cost Generation and Environmental Sustainability. Gerd Heiermann & Douglas Spalding

Post Combustion CO 2 Capture Scale Up Study

FLEXI BURN CFB WP4: Boiler design and performance

Full Steam ahead for Flamanville 3 EPR turbine island construction

Downsizing a Claus Sulfur Recovery Unit

PPC specializes in maximum efficiency air pollution control equipment using a variety of different

MIT Carbon Sequestration Forum VII Pathways to Lower Capture Costs

20/06/2011 Seminar on Geothermal Exploitation Santiago de Chile

Steam Power Station (Thermal Station)

Optimal Design and Operation of SNCR System for a 150t/h CFB Boiler and Discussion on the Measurement of Flue Gas Components

Retrofit of Rodenhuize 4 power station: The Max Green and Cold Back-up-projects

Your partner for the right solution

Operating Experience of Circulating Fluidized Bed Scrubbing Technology in Utility Size Power Plants

SCR RETROFIT FOR NO X REDUCTION EXPERIENCES IN CHINA & POLAND TWO COUNTRIES WITH COAL AS DOMINATING FUEL SOURCE

WHITE PLUME REMOVAL USING FUEL ADDITIVES IN THERMAL POWER PLANTS

2,400 TONS PER DAY REFUSE DERIVED FUEL FACILITY WITH ADVANCED BOILER AND AIR POLLUTION CONTROL SYSTEMS

Circulating Fluidized Bed Technology for Large Scale Power Generation Using Coal and Petroleum Coke

Geothermal Power Plant

Welcome to. Kendal Power Station

5. Steam Turbine Performance

Towards New Milestones In CFB Boiler Technology CFB 800MWe

NTPC O&M Conference Performance and Optimization of Water Utilisation Increase of Existing Power Plants. Speaker Name; Tufani Ram 13-14/02/2013

Babcock Borsig Steinmüller GmbH. Bełchatów - Retrofitting the EU s Largest Power Plant Site

UPDATE ON THE KEMPER COUNTY IGCC PROJECT Gasification Technologies Conference

CIRCULATING FLUIDIZED BED- FLUE GAS DESULFURIZATION TECHNOLOGY EVALUATION PROJECT NUMBER

495-MW Capacity Genesee Phase 3 Project: The First Supercritical Pressure Coal-Fired Boiler in Canada

Customized Solutions for Environmental Compliance. Combining proven experience, technology and reliable performance for our customers

Fundamental oxy-fuel combustion research carried out within the ENCAP project

Circulating Fluidized Bed Technology Towards 800 MWe Scale Lagisza 460 MWe Supercritical CFB Operation Experience

Combined-Cycle Units and Block Design Data (Voluntary Reporting)

Magnetically Coupled Submerged Cryogenic Pumps and Expanders for Ammonia Applications

GEA Niro Spray Drying Absorption. The easy way to clean the flue gas from waste incinerators. engineering for a better world. GEA Process Engineering

SHRI RAMSWAROOP MEMORIAL COLLEGE OF ENGG. & MANAGEMENT B.Tech. [SEM IV (ME-41, 42,43 & 44)] QUIZ TEST-1 (Session: )

Steam Turbine Performance Improvements Through R&M

GE solutions for NOx compliance and increased availability for WtE / Biomass plants

Catalytic Activated Ceramic Dust Filter a new technology for combined removal of dust, NOx, dioxin, VOCs and acids from off gases.

Report from visit of Dr. A.C.(Thanos) Bourtsalas and ten EEE graduate students to WTE facility in West Palm Beach, Florida, May 2016

The Locomotive. A Copper-Plated Thief: The Problem of Copper Deposits in Turbines

Economics of Lime and Limestone for Control of Sulfur Dioxide

Development status of the EAGLE Gasification Pilot Plant

Topsoe s Emission Management Solution--DeNOx

POWER PLANT AIR QUALITY CONTROL and FLY ASH QUALITY & AVAILABILITY

Secondary Systems: Steam System

State of the art CFB technology for flexible large scale utility power production

Simply Safer... Wahlco U2A Urea to Ammonia System

MODERN COKE OVEN GAS TREATMENT TECHNOLOGY AT A NEW COKE MAKING PLANT IN BRAZIL*

Environmental Control Solutions

ADECOS II. Advanced Development of the Coal-Fired Oxyfuel Process with CO 2 Separation

Hitachi Turbine Generator Technology for Nuclear Applications

BLUE OPTION White space is filled with one or more photos

Item Hydrogen Gas Plant

Application of CFB (Circulating Fluidized Bed) to Sewage Sludge Incinerator

Understand boiler performance characteristics. Use these suggestions when buying, designing or optimizing steam generators

Fossil Materials and Repair - Program 87

Energy turnaround and consequences for conventional power stations. Dr.W.A. Benesch Director Energy Technologies

metals temperature limits.

WET FLUE GAS DESULFURIZATION (FGD) SYSTEMS ADVANCED MULTI-POLLUTANT CONTROL TECHNOLOGY

Plant construction and waste heat systems for the chemical industry

OUTCOME 2 TUTORIAL 2 STEADY FLOW PLANT

Geothermal Steam Turbines for Various Purposes

Performance Tests of Water Cannon Furnace Cleaning Systems

High efficient multi-fuel CYMIC concept for biomass, rejects and coal for Hamburger Hungaria Katriina Jalkanen Valmet Technologies Oy

POST COMBUSTION CO 2 CAPTURE SCALE UP STUDY

natcom burner solutions Advanced burner technology for stringent emissions requirements

Electric Furnace Off-Gas Cleaning Systems Installation at PT Inco ABSTRACT

Consider a simple ideal Rankine cycle with fixed turbine inlet conditions. What is the effect of lowering the condenser pressure on

CFB Combustion Control System for Multiple Fuels

Controlling Ammonia-in-Ash through Direct Measurement of Ammonium Bisulfate

FACT SHEET. Whelan Energy Center 4520 East South Street Hastings, Nebraska March 26, 2004

Operational flexibility enhancements of combined cycle power plants

COMPUTER SKILLS : Windows, MS Office, Internet : EMPAC (Enterprise Maintenance Planning and Control) System

Controlling NOx and other Engine Emissions

ABSTRACT. Electrostatic precipitators (ESPs), which are particulate collectors, are now used as part

8 th SGC International Seminar on Gasificaton October 15 th -16 th, 2014 Malmö, Sweden

Meeting New Environment Norms - Challenges and Possibilities. Presented by: A.K.Sinha General Manager NTPC Limited

LIMESTONE INJECTION FOR PROTECTION OF SCR CATALYST

ALSTOM Atomenergomash LLC developing ARABELLE based Turbine Islands for newly constructed and retrofitted nuclear power plants.

LIST RETIREMENT UNITS. (Electrical Plant)

Increased efficiency and flexibility of large coal-fired power plants applied to 350-MW-class units

In The Name OF God Hampa E ner ner Ener y gy Engineering EEngineering & & Design Company Design Compan

TOSHIBA. Steam Turbine

Purification of Oxyfuel- Derived CO 2

SANY ASPHALT BATCHING PLANT

Efficiency improvement of steam power plants in Kuwait

Nuclear Service Valves

CEA Guidelines for Ash Handling Plants

PRESENTATION OF CONDENSATE TREATMENT

Transcription:

Approach to Overseas EPC Project 98 Approach to Overseas EPC Project Technical Features of MidAmerican Project in the U.S. Akitaka Tateishi Hidetoshi Fujii Tomoshige Koga Hajime Kimura OVERVIEW: Hitachi has been awarded a contract for an overseas EPC (engineering, procurement and construction) project. This opportunity has provided us with a wealth of experience. In February 2003, Hitachi was asked by MidAmerican Energy Company in Iowa U.S., through Mitsui & Co. Energy Development, Inc., to execute the EPC of the Council Bluffs Energy Center, Unit 4, an 870-MW (gross) capacity power plant. This is the first large-capacity coal-fired EPC project for Hitachi in the U.S. This paper describes the technical features of the Council Bluffs Energy Center, Unit 4 project. This plant adopts PRB (powder river basin) coal-fired super critical once-through, sliding pressure, BHK (Babcock-Hitachi K.K.)-type Benson boiler under steam condition of 25.3 MPa g, 566/593, a four-flow tandem compound turbine, with long 40-inch last stage blades, the largest-class two-pole generator, and cooling towers for circulating water. In addition, we adapted a De-NOx unit, a DFGD (dry flue gas desulfurization) unit, and highly efficient fabric-filter dust bags to satisfy the environmental regulations. Hitachi established a construction team to complete the plant within 45 months from the NTP (notice to proceed) to the S/C (substantial completion) phases. Advanced supercritical technology coal-fired power plants have not been constructed in the US. for at least 20 years. Working in close cooperation with MidAmerican Energy Company, the construction is now in progress. INTRODUCTION BASED on its accumulated expertise and practical experience, Hitachi was awarded an EPC (engineering, procurement and construction) contract to build the Council Bluffs Energy Center s Unit 4, a highly efficient 870-MW (gross) capacity coal-fired power Fig. 1Photo of Project Construction in Progress, May 2005. Boiler steel frame construction is almost completed, and condenser installation work is now in progress.

Hitachi Review Vol. 54 (2005), No. 3 99 plant (see Fig. 1). The construction of Unit 4 commenced in September 2003. Erection of the structural steel boiler started in June 2004 and the construction is progressing. This paper describes the technical features of the turbine, generator, boiler, AQCS (air quality control system), and construction plans. PROJECT OVERVIEW AND TECHNICAL FEATURES MidAmerican Energy Company is the largest utility company in Iowa. Council Bluffs Energy Center, Unit 4 is located in Council Bluffs, as shown in Fig. 2. Table Council Bluffs, Iowa Fig. 2Location of Council Bluffs City, Iowa. The plant is located on the outskirts of Council Bluffs in the state of Iowa in the U.S. 1 summarizes the main specifications. The scope of work is summarized as follows: (1) Turbine island (a) Turbine-generator (b)condensate system (condenser, extraction pumps, vacuum pumps, polisher, etc.) (c) Feedwater heating system (pumps, feedwater heater, deaerator, etc.) (d)electrical, instruments, and control (2) Boiler island (a) Boiler proper (burner, superheater, etc.) (b)ash handling system (c) Coal handling system (3) Air quality control island (a) De-NOx system (b)flue gas desulfurization unit (c) Fabric filter (4) BOP (balance of plant) (a) Well and well pumps (b)well water clarifier (c) Water treatment unit (5) Civil engineering and architecture (a) Turbine building (b)boiler building (c) Administration building (d) Warehouse (e) Maintenance building (f) Stack TABLE 1. Main Power Plant Design Specifications Basic design conditions and key specifications for the boiler, turbine, and generator are shown. Basic design conditions Item Rated output Steam conditions Unit MW MPa g Council Bluffs Energy Center, Unit 4 870 (gross) 25.3 566/593 Fuel Coal (PRB coal) Supercritical once-through boiler with sliding pressure operation Boiler Steam pressure Steam temperature MPa g 26.2 570/595 Key conditions Max. continuous rating t/h 2,530 Tandem compound 4-flow exhaust Turbine Rotational speed r/min 3,600 Condenser vacuum mmhg 722 Generator Capacity MVA Cylindrical rotor type, synchronous alternator 1,025 PRB: powder river basin

Approach to Overseas EPC Project 100 (a) (b) Fig. 340-inch (about 102-cm) Last Stage Blade (a), and 33.5-inch (about 85-cm) Last Stage Blade (b) with CCB (continuous cover blade) Construction for 60 Hz Use. The steam turbine for this project uses 40-inch last stage blades. Fig. 4High-pressure Turbine Blades with CCB. Blades are interconnected by tip covers. STEAM TURBINE Structure of Steam Turbine The electrical output of the steam turbine unit for this project is 870 MW, which is the largest Hitachi steam turbine produced for service outside of Japan. The turbine layout is TCDF-40 [tandem compound double flow with 40-inch LSBs (last stage blades)]. Fig. 3 shows the 40-inch (about 102-cm) blade. Technical Specifications of Steam Turbine High-temperature material was used in the primary parts of the steam turbine to meet the high thermal conditions (main steam pressure: 25.3 MPa g, main steam/reheat steam temperature: 566/593). For example, we used 9 Cr-forged steel for the following parts: body of main stop valve, main steam control valve, and combined reheat valve,main & reheat steam lead piping. Additionally, 12-Cr steel was used in the following parts: HP/IP rotors, HP/IP internal casings, and diaphragm for HP/IP sections. To improve efficiency and reliability, we applied a CCB in the moving blades in the HP & LP (high pressure & low pressure) sections of the turbine. Fig. 4 shows a typical HP rotor with CCB-type blades. To improve efficiency, an AVN (advanced vortex nozzle) was used in the nozzle blades in each section of the turbine. GENERATOR Features of Generator The generator for the MidAmerican Project is rated at 1,025-MVA which is among the largest Hitachi twopole generators designed for thermal power plants. The capacity of this generator is one of the largest generators that have ever been manufactured in our factory. Development of this generator is based on our advanced technology as well as a well-verified new technology. Applied Technologies In Table 2, the technologies used to obtain large capacity generators are shown. Some examples are described as follows. Rotor In general, the generator output increases in proportion to the square of the rotor diameter. The stress in the rotor part increases in a similar way. Therefore, a high strength and fracture resistant rotor shaft material is required under high-stress conditions. Recently we developed and applied the high-tensilestrength (1,000-N/mm 2 class) rotor materials. This material has high purity and high-tensile strength, without segregation and embrittlement, because it is deacidified by vacuum treatment and ladle refinement. Stator We need to improve the gas cooling ability in extremely large capacity generators because huge

Hitachi Review Vol. 54 (2005), No. 3 101 TABLE 2. Technical Issues and Applied Technologies for Large Capacity generator Technologies overcoming the challenges of increased capacity (increased current and size) were applied to the 1,025-MVA capacity generator. Increased current Technical issues Stator winding cooling Stator winding end support structure Stator core end structure Rotor winding cooling Applied technologies Mixed strand stator winding Structure with non-separated water path from current path Water cooling for connector separated from windings Large-diameter insulation hose Tetra-lock structure Shield core, copper-plate shield Direct H 2 cooling field lead H 2 gas cooler structure Top dome cooler structure Bushing Hydrogen direct cooling bushing Rotor shaft material High-strength and fracture toughness material End-ring material High-strength 18Mn-18Cr steel Increased size Rotor vibration Rotor cross-sectional shape Reduction of vibration sensitivity Stress reduction through optimum design Stator frame Compact frame Large diameter bearings Elliptic bearing with central groove Secondary superheater Steam separator Tertiary superheater Secondary reheater Primary reheater 76.4 m Primary superheater Fig. 5Cross-sectional View of Council Bluffs Energy Center, Unit 4 Boiler. The design closely follows the latest large-capacity supercritical Benson boiler technology. Furnace slagging countermeasures Adopt large furnace Water-cannon type ash removal equipment Low NO x combustion technology Hitachi-NR3 burner Two-stage combustion using over-air ports Fuel economizer DeNO x Air preheater losses occur. Therefore, we used 0.52-MPa g hydrogen for better cooling, the same as is used in four-pole type large turbine generators (1,500-MVA class). The coolers are not the vertical type that is standard in twopole generators, but the top dome type commonly used in four-pole type generators, which enabled us to obtain a compact stator frame structure. In addition, we directly cooled the rotor windings using hydrogen and the stator windings using water to achieve high reliability, as done in other large generators. BOILER AND AQCS Boiler Equipment The furnace of boiler was designed for PRB (powder river basin) coal, where the ash slagging characteristics are extremely demanding. PRB coal ash is glassy and hard, and difficult to remove from the furnace efficiently using conventional steam or air blowers. We plan to install water-cannon type ash removal equipment, considering the furnace capacity. By monitoring the heat flux in each part of the furnace water wall, the dirty parts can be effectively cleaned using water cannon type removal by changing the water flow direction. This cleaning system reduces the temperature rise of the furnace exit gases during PRB coal firing. In the combustion system, the large capacity new Hitachi-NR3 burner uses an in-flame NOx reduction system with a high temperature reducing flame. The burner combustion and two-stage AAP (after air port) combustion enables us to reduce

Approach to Overseas EPC Project 102 From boiler Flue gas DeNOx Air Air preheater SDA Atomizer Bag house Smokestack Induced draft fan Disposal Water Lime bin Water Recycled ash silo SDA: spray dry absorber Slaker Lime slurry tank Recycled ash slurry tank Mixing tank Fig. 6Schematic of Environmental Equipment. Schematic of the NOx removal and desulfurization systems is shown. TABLE 3. Main NO x Removal System Planned Specifications Rather than conventional ammonia, urea for obtaining hydrolyzed ammonia gas is employed as a reducing agent. Item NOx removal system Ammonia system Designed inlet NOx concentration Designed operation temperature Inlet SOx concentration Dust concentration Outlet NOx concentration Outlet leakage NH 3 concentration SO 2 oxidation rate SCR: selective catalytic reduction ppmvd: parts per million volume distribution Specification Dry SCR method Urea hydrolysis method 128 ppmvd (6% O 2 base) 380 752 ppmvd (6% O 2 base) 11.6 g/nm 3 42 ppmvd (6% O 2 base) 2 ppmvd (3% O 2 base) Less than 3% TABLE 4. Main DFGD system planned specifications Dust collector employs a pulse jet bag filter. Item SDA No. of units Diameter Fuel gas residence time Atomizer motor output Outlet temperature Approach temperature difference Slurry concentration Bag filter Gas to close ratio Slaker No. of units Capacity Lime Unit m s kw % m/min t/h Specification 3 17.2 10 745.7 72 17 30 Pulse jet 1.0 2 5.4 Pebble lime NOx in exhaust gases. A side view of this boiler is shown in Fig. 5. The boiler design is based on the latest technology for large capacity supercritical pressure Benson boilers, established in domestic plants in Japan. AQCS To satisfy the environmental regulations, the AQCS consists of a De-NOx and DFGD (dry flue gas desulfurization) system, as shown in Fig. 6. Table 3 shows the specifications of the SCR (selective catalytic NOx reduction) system. The PRB coal contains high calcium and high catalyst poisons, and the dust easily sticks to the catalyst. This SCR system uses a Hitachi plate-type catalyst that has a higher resistance to dust plugging and has been modified to achieve higher durability in PRB-fired gas. The catalyst reactor is designed to be compact, with special flue-gas mixers upstream of the reactors. This mixer accelerates NH 3 mixing with the flue gases for a short residence time. This SCR system operates using a harmless urea instead of the toxic NH 3 normally used. This urea process has been applied in SCR systems in the U.S. since 2000, due to the safety requirements of toxic substance handling. In this process, the urea is diluted to a 40% urea/water solution, which is hydrolyzed into NH 3. We adopted U2A* system of Wahlco, Inc., which is used in dozens of commercial plants. Its performance and reliability are proven in the U.S. * U2A is a trademark or a registered trademark of Wahlco, Inc.

Hitachi Review Vol. 54 (2005), No. 3 103 Year 2003 2004 2005 2006 2007 Key milestones INTP NTP Boiler column setup TG on base Initial firing S/C Fig. 7Key Project Processes. Construction period is specified: 45 months from NTP until S/C. INTP: initial notice to proceed NTP: notice to proceed TG: turbine generator S/C: substantial completion The major design features of the DFGD system are shown in Table 4. Flue gas is fed from the boiler air heaters to the SDAs (spray dryer absorbers) to remove SO 2. Three SDAs are supplied to treat all the flue gases from the Unit 4 boiler. One rotary atomizer with a 1,000 HP motor is used as an integral part of the SDA vessel. The atomizer slurry feed, which is a mixture of lime slurry and recycled ash slurry, is fed to the atomizers and atomized in the SDA to form a cloud of extremely fine mist. Heat from the flue gas evaporates the moisture in the slurry cloud and lowers the flue gas temperature, while the alkaline slurry simultaneously absorbs SO 2 from the flue gas. The SDA outlet gas temperature is controlled at about 17 above the adiabatic saturation (dew point) temperature. Treated flue gas exiting the SDA vessels is directed to the bag filter trains, which are equipped with the fabric bags to separate the solids (fly ash and calcium/ sulfur compounds) entrained in the flue gas. The bag filter train, a pulse-jet cleaning type, consists of 16 compartments. The cleaning operation is controlled by either a pressure drop or a preset time interval. Compartment isolation is accomplished by closing the outlet damper to a compartment when broken bags are detected. The reagent preparation system consists of two independent slurry systems, the lime and recycled slurry preparation. Pebble lime from the storage silo is fed to the lime slakers, where the lime is slaked or hydrated. The solids are collected on the filter bags, which contain unreacted calcium hydroxide, and can be utilized as recycle slurry to react and absorb SO 2 from the flue gas. PROJECT SCHEDULE AND CONSTRUCTION PLAN Project Schedule Fig. 7 shows the project timelines and key milestones. The period between NTP (notice to proceed) and S/C (substantial completion) is 45 months. Boiler structural steel erection was started in June 2004, boiler top girders were set in February 2005, and the construction is now in progress. Construction Plan In order to maintain the construction schedule, we adopted both technical and contractual provisions. Some examples of the technical provisions are: (1) Construction has been synchronized with the erection of the steel structure, which involves delivering and installing boiler pressure parts, ductwork, the coal silo, piping, support, valve station, and other ancillary equipment and systems simultaneously. (2) The HP (high pressure) turbine and IP (intermediate pressure) turbine installation period was reduced by installing the HP and IP turbines in one assembled body, which was assembled at the factory before being transported by ships and barges. (3) A barge-unloading facility was constructed on site in order to transport large blocks of equipment by barges on the Mississippi and Missouri rivers. Some examples of contractual provisions are: (1) Civil construction work and equipment installation work were purchased from one construction company. This makes the transition from civil construction work to equipment installation work easy. (2) All the installation contracts for the structural steel, equipment, piping, cabling, and other ancillary

Approach to Overseas EPC Project 104 equipment were purchased from one construction company. This makes it easy to coordinate the installation work schedule. CONCLUSIONS This paper gives a summary of the technical features of the turbine, generator, boiler, AQCS, and construction plans for the Council Bluffs Energy Center s Unit 4. Working in close cooperation with MidAmerican Energy Company, the construction phase is now in progress, and the plant will be substantially completed by June 2007. ACKNOWLEDGMENTS We would like to express deep appreciation to all the persons from MidAmerican Energy Company who provided advice and cooperation. ABOUT THE AUTHORS Akitaka Tateishi Joined Hitachi, Ltd. in 1974, and now works at the CBEC #4 Project Engineering Department, the MidAmerican Project Operation Division, the Power Systems. He is currently engaged in the project management of thermal power plants. Mr. Tateishi is a member of Thermal and Nuclear Power Engineering Society, and can be reached by e-mail at akitaka_tateishi@pis.hitachi.co.jp. Hidetoshi Fujii Joined Hitachi, Ltd. in 1997, and now works at the Steam Turbine Design Section, the Turbine Plant Design Department, Hitachi Division, the Power Systems. He is currently engaged in the design and development of steam turbines. Mr. Fujii can be reached by e-mail at hidetoshi_fujii@pis.hitachi.co.jp Tomoshige Koga Joined Hitachi, Ltd. in 1995, and now works at the Generator Design Engineering Section, the Power Electric Machine Design Department, Hitachi Division, the Power Systems. He is currently engaged in the basic design of the large turbine generator. Mr. Koga can be reached by e-mail at tomoshige_koga@pis.hitachi.co.jp. Hajime Kimura Joined Babcock-Hitachi K.K. in 1982, and now works at the System & Engineering Section, the Boiler Engineering Department, the Thermal Power Division, Kure Division. He is currently engaged in the boiler basic engineering and development of utility boiler. Mr. Kimura is a member of Thermal and Nuclear Power Engineering Society, and can be reached by e-mail at kimura-h@kure.bhk.co.jp.