DSLNG Project Update Andy Karamoy PT Donggi Senoro LNG 4 th LNG Supply, Transport and Storage Indonesia 19-21 May 2014 Bali, Indonesia
Table of Contents 1. Introduction of Donggi Senoro LNG Project 2. Keys to successful project execution 3. DSLNG s effort for project integration 2 Strictly Confidential
1. Introduction of Donggi Senoro LNG Project Project Location Central Sulawesi 4 th LNG Project in Indonesia Arun NGL Badak NGL DSLNG Tangguh LNG 1862 km from Jakarta to Luwuk ( 3 hours flight B-737) 3 Strictly Confidential
Aerial Photo at LNG Plant Site Current Material Offloading Facility LNG Jetty Air Fin Coolers Firewater Tank Main Control Room Refrigerant Storage LNG Tank Flare MCHE Main Substation Gas Turbine Generators 4 Strictly Confidential
EPC Construction Progress Admin Building
EPC Construction Progress Camp Area
1. Introduction of Donggi Senoro LNG Project Business Structure Indonesia s first down stream LNG Business model to produce LNG MGDP/ Matindok Gas Sales Agreement 85 mmscfd TCA DES LNG SPA 1 mtpa Chubu Electric Kyushu Electric JOB PMTS/ Senoro LNG SPA 0.3 mtpa Gas Sales Agreement 250 mmscfd 2 mtpa LNG SPA 0.7 mtpa FOB KOGAS Upstream DSLNG LNG Buyers 5 Strictly Confidential
1. Introduction of Donggi Senoro LNG Project Highlights of Donggi Senoro LNG 1. A good example of Development of Stranded Natural Resources Best-mix development provides an opportunity for development of natural resources which left undeveloped for more than decades. 2. Front Runner project in Eastern Indonesia (Sulawesi EC) One of the biggest projects in Sulawesi Economic corridor of which development is one of the objectives under ACCELERATION AND EXPANSION OF INDONESIAN ECONOMIC DEVELOPMENT 2011-2015 MASTERPLAN. 3. First downstream LNG project in Indonesia All investment and operating risk will be borne by PT DSLNG No cost recovery burden of considerable LNG Plant Development to GOI 4. Collaboration amongst Indonesia, Korea, Japan The first LNG project which stakeholders from upstream, midstream (LNG Plant Operator) up to LNG buyers are all Asian companies. 6 Strictly Confidential
2. Key to successful project execution Key Challenges of Donggi Senoro LNG DSLNG is a joint venture with cross-culture and various backgrounds First Business Model (Downstream LNG Project) in Indonesia Corporate Vision, Mission and Values Schedule Management and Cost Control Coordination between upstream parties and DSLNG Code of Conduct Stakeholders Management QHSE policy Operation readiness Enterprise Risk Management Strong Organization 7 Strictly Confidential
2. Key to successful project execution Land Acquisition experience 1. Legal Basis Law Number 5 of 1960 concerning the Basis Agrarian Law Law Number 2 of 2012 concerning Land Procurement for Development of Public Interests; etc 2. The Principle of Indonesian Land Law Indonesian land law recognize horizontal separation Principle (separated ownership of the land and buildings/plants) 3. Type of Rights of Land: Land with individual rights and Tanah Negara (Indonesia still recognize Adat Land and Ulayat Right) Land with individual rights, consists of: Hak Milik (Right of Ownership), Hak Guna Usaha (Rights of Cultivation), Hak Guna Bangunan (Rights of Use of Building), Hak Pakai (Right to Use) 7 Strictly Confidential
2. Key to successful project execution Procedure to Obtain Land PT X Obtaining Location Permit Land Acquisition, by: -Kepala Desa -Camat/Lurah -Notaris Issued by Local Government after recommended by BPN Land Deed Offiicer (PPAT) Transferring (the Land title is same) Registration to Change the ownership name Releasing (the Land title is different) HGB in the name of PT X Page 11 BPN Application for the HGB Free State Land
2. Key to successful project execution Intensify the socialization of future local benefits CRUDE (NET GOVERNMENT SHARE) 100% 85% Government 15% Contractor 100% 85% Central 15% Local 3% Province 12% Regent/ City FINANCIAL SPLIT GOVERNMENT REVENUEA AFTER COST RECOVERY AND TAX 6% Producing Regent 6% Other Regents in the Province GAS ( NET GOVERNMENT SHARE) 100% Less: 70% Government 30% Contractor - Province tax - Local Retribution 100% 70% Central 30% Local 6% Province 24% Regent/City 12% Producing Regent 12% Other Regents in the Province
3. DSLNG s effort for the project integration - spent and schedule Schedule Management and Cost Control Good management of schedule and cost by progress measurement agreed by DSLNG and EPC contractor Overall EPC progress Weight Planned Actual Engineering 11.05% 100% 100% Procurement 44.93 98.56% 100% Construction 44.02% 95.11% 96.50% Overall Progress 100% 97.20% 98.46% Physical Construction Progress Overall EPC progress Last Month (Cummulative) This Month This Month (Cummulative) Plan 90.5% 2.6% 93.1% Actual 93.6% 1.5% 95.1% As of 25 April 2014 8 Strictly Confidential
3. DSLNG s effort for the project integration Coordination between upstream parties and DSLNG Steering Committee is established amongst Ultimate Shareholders to monitor overall progress PERTAMINA MEDCO MITSUBISHI KOGAS Upstream Downstream Coordination Forum Coordination & Collaboration for interface matters by management level PHE Tomori 50% Medco Tomori 30%i SENORO Pertamina EP 100% MATINDOK Tomori EP UK 20% Pertamina Hulu Energi 29.0% Medco LNG 11.1% Donggi Senoro LNG Sulawesi LNG Development 59.9% Upstream Downstream Working Groups Technical Working Group/Commercial Working Group CSR Working Group/QHSE Working Group Tomori EP UK: MITSUBISHI 51%/ KOGAS 49%, Sulawesi LNG Development: MITSUBISHI 75%/KOGAS 25% 9 Strictly Confidential
3. DSLNG s effort for the project integration Preparation for start-up and Operation Readiness Preparation for hand-over from EPC contractor and readiness for DSLNG s independent operation EPC Phase Start-Up 2011~2013 2014 2015 O&M Phase Mechanical completion Commissioning Feed Gas First LNG Commercial Operation Operation Readiness Operation Organization Process Safety Management Production and Marine Maintenance and Inspection Technical Services Operations Support Gas & LNG Delivery Procedure QHSE ICT Security Assurance Business Continuity 11 Strictly Confidential
Thank you
2. Key to successful project execution Key Challenges of Donggi Senoro LNG DSLNG is a joint venture with cross-culture, various backgrounds VISION To be a safe and reliable provider of LNG MISSION Build and operate a reliable LNG project Ensure all stakeholders benefit from the LNG value chain Be a socially and environmentally responsible LNG company Strictly Confidential
LNG Plant Specifications Feed Gas Supply LNG Sales Process Technology LNG Tank Capacity Refrigeration Compressor Driver 335 million standard cubic feet per day 2 million tonnes per year APCI propane pre-cooled mixed refrigerant 170,000 cubic meters x 1 tank Gas Turbine (Frame 5) Generating Capacity 3 x 22.6 Mega Watts Cooling Media Loading Arms LNG Loading Pumps Jetties Air 2 LNG Loading, 1 Vapor Return 2 x 2,000 cubic meters per hour LNG Loading (Max. 155,000 m3) and MOF Strictly Confidential
LNG Specifications Gross Heating Value 1,060 1,170 BTUs /scf Methane 85 mol % minimum Butane 2 mol % maximum Pentane 0.1 mol % maximum Nitrogen 1 mol % maximum Hydrogen Sulphide 0.25 grain /100scf Total Sulphur 1.3 grain/100scf Strictly Confidential
Additional Informations Feed Gas LNG Condensate Own Utilities Flare Plant Thermal Efficiency 88.95% 371,374 MMBTUD 335 MMSCFD 1,108.579 BTU/SCF 319,634 MMBTUD 1,100.48 BTU/SCF 4,144 tons/day 2,313 bbl/day 40,850 MMTUD 41.9 MMSCFD 176 MMBTUD 0.15 MMSCFD Hyundai Utopia Northwest Swallow Cargo Per Voyage 56,865 tons 126,086 m3 2,949,588 MMBTU 56,660 tons 125,632 m3 2,938,954 MMBTU Strictly Confidential