SECTION SPECIFICATION FOR STONEBRIDGE RETAINING WALL SYSTEM

Similar documents
CONCRETE SEGMENTAL RETAINING WALL SYSTEM

SPECIFICATIONS FOR PRECAST MODULAR BLOCK RETAINING WALL SYSTEM (revised 5/8/7)

MODULAR CONCRETE RETAINING WALL

SEGMENTAL BLOCK RETAINING WALLS. Comply with Division 1 - General Provisions and Covenants, as well as the following:

LANDSCAPE RETAINING WALLS

VERTI-BLOCK - DESIGN MANUAL

Design Manual: Gravity Wall. Section 1

Redi Rock Specification and Installation Manual

ICC-ES Evaluation Report Issued July 1, 2011 This report is subject to renewal in one year.

SECTION PERMEABLE INTERLOCKING CONCRETE UNIT PAVEMENT

INSPECTION GUIDE FOR SEGMENTAL RETAINING WALLS TEK 18-11B

Uwall UNIVERSAL CONSTRUCTION MANUAL

02632 Segmental Concrete Retaining Wall System Page - 1

Specification Guidelines: Allan Block Modular Retaining Wall Systems

Wall Modular Block Mechanically Stabilized Earth, Item S.

STATE OF OHIO DEPARTMENT OF TRANSPORTATION SUPPLEMENTAL SPECIFICATION 863 REINFORCED SOIL SLOPES. October 19, 2012

STANDARD SPECIFICATION FOR CRIBLOCK CONCRETE CRIBWALL

Construction Procedures

SPECIFICATION FOR REINFORCED SOIL WALL

Anchorplex retaining wall construction guide. Building. Anchorplex. Retaining Wall Systems

PERMEABLE INTERLOCKING PAVERS

2011 INSTALLATION MANUAL

DESIGN CONSIDERATIONS FOR NSWS NATURAL STONE RETAINING AND FREE-STANDING WALL SYSTEMS

R-TANK SPECIFICATIONS

NOVEMBER 2016 MAGNUMSTONE. retaining walls installation manual

BIO-AQUIFER STORM SYSTEM

C. Foundation stabilization for pipe and utility structures.

cambridgewallsupport.com cambridgepavers.com

SECTION FOUNDATION DRAINAGE

SECTION UTILITY MANHOLES AND STRUCTURES

LS 2519 CONCRETE PAVER PAVEMENT RECONSTRUCTION

HYDROGRID SUBSURFACE IRRIGATED HARTRU TENNIS COURTS

ENGINEERING DIRECTIVE

StormTech Construction Guide

ITEM D-701 PIPE FOR STORM DRAINS AND CULVERTS

Design and Installation Guidelines for Retaining Walls. 1 P age. Geo Products, LLC 8615 Golden Spike Lane Houston, TX Phone:

Trusted ICC ES. Conformity! Evaluation. ICC-ES Evaluation

DIVISION: EXTERIOR IMPROVEMENTS SECTION: RETAINING WALLS SECTION: SEGMENTAL RETAINING WALLS REPORT HOLDER:

SECTION 19 - TRENCH EXCAVATION, BEDDING AND BACKFILL TABLE OF CONTENTS

A. Product Data: Submit manufacturer s product data, with complete general and specific installation instructions, recommendations, and limitations.

MANHOLES, VAULTS AND CATCH BASINS SECTION A. Section Soil and Aggregate Materials. C. Section Storm Drainage Systems

A.2.a Random Riprap... Table

PAVING SLABS ON A CONCRETE BASE

SECTION AGGREGATES

ODOT Design & Construction Requirements for MSE Walls

Master Specification SECTION 02621

BENTOMAT CL GEOSYNTHETIC CLAY LINER SPECIFICATION GUIDELINES

Retaining Wall Systems

SECTION 19 - TRENCH EXCAVATION, BEDDING AND BACKFILL TABLE OF CONTENTS

***************************************************************************************************************

DESIGNING AND CONSTRUCTION OF T-WALL RETAINING WALL SYSTEM

SECTION 19 - TRENCH EXCAVATION, BEDDING AND BACKFILL TABLE OF CONTENTS

PERMEABLE PAVERS PHYSICAL AND GEOMETRICAL CHARACTERISTICS - PAVERS DRIVEWAYS, PERMEABLE DRIVEWAYS & PATIOS CHARACTERISTICS CSA A231.

Construction Specification for Concrete Unit Pavers

SECTION INTERLOCKING CONCRETE PAVERS

SPECIFICATION FOR PREFABRICATED VERTICAL DRAINS

E. Section Polymer Modified Cement Waterproofing. K. Section Sub drainage: Foundation perimeter drainage.

TensarTech TW1 Wall System Earth Retaining Structures

BAYFILTER SPECIFICATIONS

SECTION RIPRAP, BOULDERS, AND BEDDING

ADDENDUM No. 6. ITB No. 4424: W.R. Wheeler (Swift Run) Service Center PUD Non-motorized Improvements Phase 1

CITY OF FARGO SPECIFICATIONS AGGREGATE BASES

SECTION 1 BIO-INFILTRATION BUMP OUTS (BIBO)

MACHINE-LAY Installation Manual

ITEM 6 CONCRETE CURBS, GUTTERS, AND SIDEWALKS

Cement Stabilized Soil (CSS) (Portland cement)

Bureau of Materials Materials Approval Procedures

PASSAIC COUNTY TECHNICAL INSTITUTE CCA 1422 NEW S.T.E.M. BUILDING 2017

1.0 Introduction. 2.0 Retaining Wall Principles. 3.0 Retaining Wall Installation. 4.0 Installation Details. 5.0 Installation Tables

SECTION A1 EXCAVATION AND BACKFILL GENERAL

B. Subsurface data is available from the Owner. Contractor is urged to carefully analyze the site conditions.

ITEM 458 WATERPROOFING FOR STRUCTURES

INTERLOCKING CONCRETE PAVERS SECTION 02780

Section Storm Sewers STORM SEWERS PART 1 - GENERAL 1.01 SECTION INCLUDES. A. Storm Sewers. B. Abandonment of Storm Sewers

Specifications for Concrete Embedment Liner

AEC Premier Straw Double Net Quick Mow EROSION CONTROL BLANKET SPECIFICATION

Tasman Retaining Wall System

INDEX FOR SPECIFICATIONS FOR JACKING CULVERTS THROUGH EMBANKMENTS SCOPE... 2

SECTION CAST-IN-PLACE CONCRETE

BELGARD.COM. Tandem Wall Segmental Retaining Wall System BELGARD.COM 1

MSE WALLS CASE STUDIES. by John G. Delphia, P.E. TxDOT Bridge Division Geotechnical Branch

A-2000 PVC Pipe for Storm Sewers and Drainage

DETERMINATION OF THE LONG-TERM PROPERTIES FOR MIRAGRID XT GEOGRIDS

SPECIFICATION FOR PIPE CULVERT CONSTRUCTION

SECTION ECO-CITYLOCK PERMEABLE INTERLOCKING CONCRETE UNIT PAVING

CETCO-VOLCLAY CG-50 SPECIFICATION GUIDELINES MIX IN PLACE

Curlex High Velocity EROSION CONTROL BLANKET SPECIFICATION

Innovation in Joint Restraint Systems for PVC Pressure Pipe and Fittings. Clean & Safe Drinking Water Workshop. Wednesday, March 25, 2015

PRODUCT SPECIFICATION CSI FORMAT Slope and Channel Grid Systems April 2009

Narrow Modular Pavers (NMP) for Sand-Set Installations

PERMEABLE ARTICULATING CONCRETE BLOCK (P-ACB) SPECIFICATION FOR PARKING LOTS, DRIVEWAYS, ALLEYS AND ROADWAYS

AUGUST 2017 HASTINGS. retaining walls installation guide

PRODUCT DATA SHEET SikaProof Bentonite

TensarTech TW3 Wall System Earth Retaining Structures

Curlex II EROSION CONTROL BLANKET SPECIFICATION

SECTION 20 INDEX PAVING FABRIC 1. SCOPE OF WORK MATERIAL REQUIREMENTS CONSTRUCTION AND INSTALLATION REQUIREMENTS...

MAGIC BLOCK DESIGN RESOURCES

TRENCHLESS CONSTRUCTION (BORING, JACKING, AND TUNNELING)

Ohio Department of Transportation Division of Production Management Office of Geotechnical Engineering. Geotechnical Bulletin

Transcription:

SECTION 32 32 23 SPECIFICATION FOR STONEBRIDGE RETAINING WALL SYSTEM PART 1: GENERAL 1.01 Scope Work includes furnishing all materials, labor, equipment, and supervision to install a Stonebridge segmental retaining wall system to the lines and grades designated on the construction drawings and as specified herein. 1.02 Reference Standards A. Segmental Retaining Wall Units ASTM C 140 - Sampling and Testing Concrete Masonry Units ASTM C 1372 Standard Specification for Dry-Cast Segmental Retaining Wall Units B. Geosynthetic Reinforcement C. Soils ASTM D 4595 Standard Test Method for Tensile Properties of Geotextiles by the Wide- Width Strip Method ASTM D 5262 Standard Test Method for Evaluating the Unconfined Tension Creep and Creep Rupture Behavior of Geosynthetics ASTM D 5321 Standard Test Method For Determining the Coefficient of Soil and Geosynthetic or Geosynthetic and Geosynthetic by Direct Shear Method ASTM D 5818 - Standard Practice for Exposure and Retrieval of Samples to Evaluate Installation Damage of Geosynthetics ASTM D 6637 Standard Test Method for Determining Tensile Properties of Geogrids by the Single or Multi-Rip Tensile Method ASTM D 6706 Standard Test Method for Measuring Geosynthetic Pullout Resistance in Soil ASTM D 6992 Standard Test Method for Accelerated Tensile Creep and Creep-Rupture of Geosynthetic Materials Based on Time-Temperature Superposition Using Stepped Isothermal Method ASTM D 422 Standard Test Method for Particle-Size Analysis of Soils ASTM D 698 Standard Test Method for Laboratory Compaction Characteristics of Soil Using Standard Effort ASTM D 2487 Standard Practice for Classification of Soils for Engineering Purposes ASTM D 4318 Standard Test Method for Liquid Limit, Plastic Limit and Plasticity Index of Soils ASTM D 6913 Standard Test Methods for Patricle-Size Distribution (Gradation) of Soils Using Seive Analysis

ASTM D 6938 Standard Test Method for In-Place Density and Water Content of Soil and Soil-Aggregate by Nuclear Methods (Shallow Depth) ASTM G 51 Standard Test Method for Measuring ph of Soil for Use in Corrosion Testing D. Drainage Pipe ASTM F 405 Standard Specification for Corrugated Polyethylene (PE) Pipe and Fittings ASTM F 758 Standard Specification for Smooth-Wall Polyvinyl Chloride (PVC) Plastic Underdrain Systems for Highway, Airport or Similar Drainage E. Engineering Design NCMA Design Manual for Segmental Retaining Walls, Third Edition ASTM D 6638 Standard Test Method for Determining the Connection Strength Between Geosynthetics Reinforcement and Segmental Concrete Units ASTM D 6916 Standard Test Method for Determining the Shear Strength Between Segmental Concrete Units F. Where specifications and reference documents conflict, the Wall Design Engineer shall make the final determination of applicable document. 1.03 Submittals A. The Contractor shall submit manufacturer's certifications stating that the Stonebridge units, geosynthetic reinforcement, reinforced backfill, and stone fill meet the requirements of Part 2.0 of this specification. The certifications shall be provided 30 days prior to the start of the work. B. The Wall Installer shall provide a list of successful projects with references showing that they are qualified and have a record of successful performance installing segmental block walls. C. The Professional Engineer responsible for the wall design shall submit a set of stamped construction drawings and design calculations for the Stonebridge retaining wall system. The Professional Engineer must be experienced in segmental retaining wall design and registered in the State where the wall is to be built. The design shall clearly state the material properties, design methodology, and factors of safety or load and resistance factors used. The design shall consider wall stability, including bearing capacity, global or slope stability, and settlement. The design shall address both internal and external drainage of the wall. 1.04 Delivery, Storage, and Handling A. The Contractor shall inspect the materials upon delivery to assure that proper type and grade of material and color of Stonebridge units has been received. B. The Contractor shall store and handle materials in accordance with manufacturer's recommendations and in a manner to prevent deterioration or damage due to moisture, temperature changes, contaminants, corrosion, breaking, chipping or other causes. C. The Contractor shall prevent excessive mud, wet cement and like materials from coming in contact with the Stonebridge units. D. The Contractor shall protect geosynthetic material from direct sunlight or UV exposure. Any protective covering on geosynthetic material shall remain until immediately before installation. E. The Contractor shall protect the materials from damage. Damaged material shall not be incorporated into the Stonebridge retaining wall. SECTION 323223-2

PART 2: MATERIALS 2.01 Wall Units A. Wall units shall be Stonebridge as produced by a licensed manufacturer. B. Wall units shall meet the requirements of ASTM C1372, except that the minimum required net average compressive strength shall be 4000 psi (27.6 MPa). C. Exterior block dimensions shall be uniform and consistent. Maximum dimensional deviations shall be 1/8 inch (3 mm) excluding the architectural surface. 2.02 Geosynthetic Reinforcements Geosynthetic reinforcement shall consist of high-tenacity PET geogrids or geotextiles manufactured for soil reinforcement applications. The type, strength and placement of the geosynthetic reinforcement shall be as specified by Wall Design Engineer in the construction drawings and specifications. Only geosynthetic reinforcements which have been tested with Stonebridge units according to ASTM D6638 and ASTM D 6916 shall be considered for use. 2.03 Drainage Pipe A. The drainage collection pipe shall be a perforated or slotted PVC or corrugated HDPE pipe. The pipe may be wrapped with a geotextile that will function as a filter. B. Drainage pipe shall be manufactured in accordance with ASTM F 405 or ASTM F 758. 2.04 Leveling Pad Leveling Pad material shall consist of a compacted, open-graded or dense-graded crushed stone or non-reinforced concrete as shown on the construction drawings. 2.05 Stone Fill A. Stone fill shall be angular, clean stone meeting the gradation requirements of ASTM No. 57 Stone, as defined in ASTM C33 and determined in accordance with ASTM D422: Sieve Size 1 ½ inch 100 1 inch 95-100 ½ inch 25-60 No. 4 0-10 No. 8 0-5 Percent Passing B. Stone fill shall be used in the cores, between, and at least 12 inches (300 mm) behind Stonebridge units. 2.06 Reinforced Backfill A. Material used as backfill in the reinforced soil zone shall meet the requirements detailed in the construction drawings and specifications prepared by the Professional Engineer responsible for the wall design. B. The Plasticity Index of the backfill material shall be less than 6. Organic soils and frost susceptible soils shall not be used. C. The ph of the backfill material shall be between 3 and 9 when tested in accordance with ASTM G 51. D. The Contractor shall submit a sample of any imported backfill to the Owner s Geotechnical Engineer for pre-approval. SECTION 323223-3

2.07 Geotextile Filter Fabric Geotextile filter fabric shall nonwoven, needle-punched, polypropylene material with a minimum normal weight of 4 oz/sq. yd. PART 3: CONSTRUCTION OF WALL SYSTEM 3.01 Construction Observation A. The Owner or Owner's Engineer should verify the materials supplied by the Contractor meet all the requirements of the specification. This includes all submittals and proper installation of the system. B. The Contractor's field construction supervisor shall have demonstrated experience and be qualified to direct all work at the site. 3.02 Excavation A. The Contractor shall verify location of existing structures and utilities prior to excavation, and shall take appropriate measures to insure they are adequately protected before starting any wall excavation. B. The Contractor shall excavate to the lines and grades shown on the construction documents. The Contractor shall take precautions to minimize over-excavation. Excavation support, if required, shall be designed by the Contractor. 3.03 Foundation Soil Preparation A. Native foundation soil shall be compacted to 95% of Standard Proctor as determined by ASTM D-698 prior to placement of the Leveling Pad material. B. In-situ foundation soil shall be examined by the Owner s Geotechnical Engineer to ensure that the actual foundation soil strength meets or exceeds assumed design strength. Soil not meeting the required strength shall be removed and replaced with acceptable, compacted material. C. Over-excavation and replacement of unsuitable foundation soils shall be at the direction of the Owner s Geotechnical Engineer. Any additional compensation for over-excavation, which falls outside of the contract limits, must be pre-approved in a written change order signed by the Contractor, Engineer, and Owner or Owner s Representative. 3.04 Leveling Pad Preparation A. Leveling pad shall be placed as shown on the construction drawings. The leveling pad shall be constructed to the proper elevation shown on the plans. The leveling pad shall have minimum depth of at least 6 inches (150 mm), and should extend laterally at least 6 inches (150 mm) in front and 12 inches (300 mm) behind the bottom Stonebridge unit. B. If the construction drawings require a crushed stone leveling pad, the stone shall be placed in uniform loose lifts a maximum of 6 inches (150 mm) thick and consolidated with a minimum of three passes with a 24 inch (600 mm) wide, walk-behind, vibrating plate compactor. The compactor shall be capable of delivering a minimum of 2000 lb (9 kn) centrifugal force. C. If the construction drawings require a concrete leveling pad, the pad shall be allowed to cure to the minimum strength specified in the construction documents prior to placement of the bottom course of Stonebridge units. D. Leveling pad shall provide a firm, smooth, and level surface on which to place the Stonebridge units. There shall be full contact of the Stonebridge units on the leveling pad. SECTION 323223-4

3.05 Stonebridge Unit Placement A. Properly mark the location of the retaining wall. Use a string line or offset stakes to establish horizontal and vertical alignment. B. For the bottom course of Stonebridge units, remove the bottom lip from the back edge of the blocks with a hammer and chisel so the blocks will lie flat on the leveling pad. C. Place a complete row of blocks on the prepared leveling pad. Blocks should be placed tight together. Check all blocks for level from front to back and side to side as they are placed. D. Place and compact stone fill in the cores of the units, between the units, and at least 12 (300 mm) behind the wall. E. Place reinforced or retained soil between the stone and the back of the excavation. F. Following backfill, re-check all units for level and alignment and sweep the top of each course of blocks clean before starting construction of the next course. G. Place the next course of Stonebridge units on top of the previous course. Stonebridge units should be placed to establish a running bond, where the block straddles and is centered on the two blocks below it. Cut blocks as needed to maintain a running bond. Partial units shall be at least 6" (150 mm) long and shall not be placed directly on top of each other. Partial units shall be adhered in place with a concrete adhesive specifically formulated for segmental concrete block wall construction. H. Push the Stonebridge blocks forward until the lip on the back of the block comes in full contact with the blocks below. I. Broken, chipped, stained or otherwise damaged units shall not be placed in the wall. 3.06 Geosynthetic Reinforcement Placement A. All materials shall be installed at the proper elevation and orientation as shown in the wall details on the construction drawings. The geosynthetic reinforcement shall be installed in general accordance with the manufacturer's recommendations. B. Install geosynthetic material with the strong direction (roll direction) into the reinforced soil zone. The geosynthetic must be placed in a continuous sheet throughout its length from the connection at the Stonebridge units to the back of the reinforced zone. Overlap or splice connections of the geosynthetic material are not permitted. Adjacent sections of geosynthetic material shall be placed in a manner to assure that the horizontal coverage shown on the plans is provided. C. Place geosynthetic material on top of a course of Stonebridge units at the elevations shown on the construction drawings. Secure the front end of the geosynthetic material with the next course of blocks. Make sure the geosynthetic material is as close as possible to the front face of the wall without being visible. Pull the geosynthetic material taut to eliminate any folds. Use pins, staples, or other methods recommended by the manufacturer to maintain tension on the geosynthetic while placing the reinforced fill. 3.07 Backfill Placement A. The reinforced backfill shall be placed as shown in construction plans. The maximum loose lift thickness shall not exceed 8 inches (200 mm). Wet or dry the backfill material as needed to place the material within 2% of the optimum moisture content. Compact the backfill material to a minimum 95% of Standard Proctor as determined by ASTM D-698. Backfill shall be placed, spread and compacted in such a manner that minimizes the development of wrinkles or movement of the geosynthetic reinforcement and the wall facing units. SECTION 323223-5

B. Only hand-operated compaction equipment shall be allowed within 3 feet (1 meter) of the front of the wall face. All compaction equipment should be large enough to achieve desired compaction, but not so large as to move the wall blocks. Monitor the wall blocks for movement during compaction and reset them if required prior to proceeding. C. Construction equipment shall not be operated directly on the geosynthetic reinforcement. A minimum backfill thickness of 6 inches (150 mm) is required prior to operation of tracked vehicles over the geosynthetic reinforcement. Turning of tracked vehicles should be kept to a minimum to prevent displacing the fill and damaging or moving the geosynthetic reinforcement. D. Place retained soil immediately between the reinforced soil zone and the back of the excavation. Material should be placed in loose lifts of 8 inches (200 mm) maximum and compacted to 95% of Standard Proctor as determined by ASTM D-698. Bring the reinforced and retained soil up to grade at the same time. At no time should the elevation of the reinforced soil be more than 1 Stonebridge unit higher than the retained soil. E. At the end of each day's operation, the wall contractor shall slope the last level of backfill away from the wall facing to direct runoff of rainwater away from the wall face. The general contractor is responsible for ensuring surface runoff from adjacent areas is not allowed to enter the wall construction area. 3.08 Stone fill and Drain Placement A. Stone fill shall be placed to the minimum finished thickness and widths shown on the construction drawings. B. Place the stone in uniform loose lifts a maximum of 8 inches (200 mm) thick. Consolidate the stone with a minimum of three passes with a 24 inch (600 mm) wide, walk-behind, vibrating plate compactor capable of delivering a minimum of 2000 lb (9 kn) centrifugal force. C. Drainage collection pipes shall be installed to maintain gravity flow of water outside of the reinforced soil zone. The pipe should daylight at the ends and/or through the face of the wall to allow for drainage. Connection to a catch basin or active storm sewer should only be made under the direction of the Professional Engineer responsible for the wall design. D. All drain pipes shall be placed as shown in the construction drawings. E. Secondary collection drain pipes should be sloped a minimum of two percent to provide gravity flow into the main collection drain pipe. Drainage laterals shall be spaced at a maximum of 50 feet (15 meters) along the wall face. 3.09 Cap Block Placement The cap block and/or top Stonebridge unit shall be bonded to the Stonebridge units below using concrete adhesive specifically formulated for segmental block wall construction. The block shall be dry and swept clean prior to adhesive placement. 3.10 Construction Tolerances A. Vertical alignment shall be within ± 1.25 inches (32 mm) over any 10 feet (3 m). B. Horizontal alignment shall be within ± 1.25 inches (32 mm) over any 10 feet (3 m). C. Rotation alignment shall be within ± 2 degrees of design batter. PART 4: MEASUREMENT AND PAYMENT 4.01 Measurement SECTION 323223-6

The unit of measurement for furnishing the Stonebridge retaining wall system shall be the vertical square foot of wall surface from the top of the leveling pad to the top of the wall, including coping. The quantity to be paid shall include all costs to supply and install the Stonebridge retaining wall system as shown in the construction drawings and specificaitons. Excavation of unsuitable materials and replacement with select fill must be pre-approved in a written change order and shall be paid for under separate pay item(s). 4.02 Payment A. Payment shall be made under: Pay Item Stonebridge Reinforced SRW Pay Unit Sq. Ft (Square Meter) PART 5: AVAILABILITY Rosetta Hardscapes, LLC 05481 South US-31, Charlevoix, MI 49720 1-877-777-6558 www.discoverrosetta.com Updated 06/06/11 SECTION 323223-7