Best Practices for Building High-Performance Resource Roads. Road Drainage. Developed by: The Roads and Infrastructure Group

Similar documents
Construction Best Management Practices Handbook BEST MANAGEMENT PRACTICES

Brush layering construction

APPENDIX E. CONSTRUCTION SPECIFICATIONS FOR ACCESS ROADS (January 2005)

Nancy L. Young, Forester USAID/USDA Natural Resources Conservation Service

Temporary Watercourse Crossing: Culverts

WEST VIRGINIA DIVISION OF FORESTRY STATE FOREST STANDARDS for LOGGING ROADS AND SKID TRAILS HAUL ROADS

LOW WATER CROSSINGS, fords, or drifts, as they

Ohio Department of Transportation Division of Production Management Office of Geotechnical Engineering. Geotechnical Bulletin

Installation and Maintenance of Erosion Control BMPs

Section 3 Guidelines for Forest Roads

PART 1 GENERAL REQUIREMENTS

Departments of Agronomy C709 Conservation Farming and Biological and Agricultural Engineering. Permanent grass cover

ALABAMA S BEST MANAGEMENT PRACTICES. Protection of Water Quality During Timber Harvesting

PASER Manual Gravel Roads

Standards for Soil Erosion and Sediment Control in New Jersey May 2012 STANDARD FOR SLOPE PROTECTION STRUCTURES. Definition

TEMPORARY SEDIMENT TRAP CODE

Straw Bale Barrier. - Along the face and at grade breaks of exposed and erodible slopes to shorten slope length and spread runoff as sheet flow

10.1 INTRODUCTION 10.1 DRAINAGE

W. Goodrich Jones State Forest. Best Management Practices Virtual Demonstration Tour

Design and Installation Guidelines for Retaining Walls. 1 P age. Geo Products, LLC 8615 Golden Spike Lane Houston, TX Phone:

SECTION TRENCHING & BACKFILLING

Unit E: Basic Principles of Soil Science. Lesson 7: Understanding Soil Erosion and Management Practices

Recommended Resources: The following resources may be useful in teaching this lesson:

Straw Bale Barrier. Parallel to a roadway to keep sediment off paved areas

2. Pavement Materials: Consist of flexible or rigid pavements, typically HMA or PCC, respectively, or a composite of the two.

NEW ENGLAND COUNCIL ON FOREST ENGINEERING CASE STUDY MARCH 6, 2012

LAYING IBSTOCK CLAY PAVERS FOR PERMEABLE PAVEMENTS

CHAPTER 3 Environmental Guidelines for WATERCOURSE CROSSINGS GOVERNMENT OF NEWFOUNDLAND AND LABRADOR DEPARTMENT OF ENVIRONMENT AND LABOUR

Understanding Soil Erosion and Management Practices

The Good, The Bad, and The Ugly

Homeowners Guide for Flood, Debris, and Erosion Control after Fires

Filter Tube Barriers (Instream)

901 - TEMPORARY EROSION AND POLLUTION CONTROL SECTION 901 TEMPORARY EROSION AND POLLUTION CONTROL

Created by Simpo PDF Creator Pro (unregistered version) Asst.Prof.Dr. Jaafar S. Maatooq

Storm Drain Inlet Protection for Construction Sites (1060)

Med (3) Locator Information/GPS GPS shows 16 ft accuracy Lat: Impact Rating

SPECIFICATION FOR ENGINEERED FILLS

CHAPTER 12 BRIDGE DECK DRAINAGE SYSTEMS

The Work under this Section consists of performing all operations necessary to complete construction of the leveling course on the prepared subbase.

Understanding Stormwater Pollution Prevention Plans (SWPPPs) (SWPPPS)

Design Data 6. Loads and Supporting Strengths Elliptical and Arch Pipe. Values of B d

Earthworks, Formation and Capping Material

Block or Log forms of PAM and PAM blends are manufactured for specific use in drainage waterways to remove suspended particulates from runoff.

Welded Mesh Gabions and Mattresses River Protection Design Guide Anping County Zhuoda Hardware Mesh Co.,Ltd. Wire Mesh Industrial Zone, Anping

Lecture 7 BALLAST & SUBGRADE. Dr. Charisma Choudhury. April 2011

The Islamic University of Gaza- Civil Engineering Department Sanitary Engineering- ECIV 4325 L5. Storm water Management

CONTINUOUSLY REINFORCED CONCRETE AND UNPAVED ROADS CONDITION SURVEY FIELD MANUAL PUBLICATION 343 APRIL 2017 PUB 343 (4-17)

Installation and maintenance instructions for PLATIN and PLATIN XL Rainwater Underground Tank

Application for resource consent Form B Damming and diversion of water

Lyon Creek Cedar Way Stormwater Detention Dam Operation and Maintenance Manual

CITY OF TROY CONSTRUCTION SPECIFICATIONS PREPARED BY: F-7587

SPECIFICATIONS FOR PRECAST MODULAR BLOCK RETAINING WALL SYSTEM (revised 5/8/7)

GROUNDtrax GROUNDGRIDZ

Page 1. Name:

Infiltration Guidelines

PERVIOUS PAVEMENT. Alternative Names: Permeable Pavement, Porous Concrete, Porous Pavers

Section SNOW DISPOSAL SITE DESIGN CRITERIA

SECTION A1 EXCAVATION AND BACKFILL GENERAL

KDOT TEMPORARY EROSION - CONTROL MANUAL

At least 2 feet above the seasonal high water table Overflow path or structure provided

CHAPTER 7: TREE PROTECTION DURING CONSTRUCTION 7.1 TREE PROTECTION AREAS

BIG O HDPE TUBING HDPE CORRUGATED TUBING FOR AGRICULTURAL, RESIDENTIAL AND HIGHWAY DRAINAGE INCREASE CROP YIELDS LOWER PRODUCTION COSTS

SUBSURFACE INFILTRATION SYSTEM DESCRIPTION. Alternative Names: Sump, Drywell, Infiltration Trench, Infiltration Galleries, Leach Fields

Chapter 7. Street Drainage. 7.0 Introduction. 7.1 Function of Streets in the Drainage System. 7.2 Street Classification

Applications. 5 reasons why you should choose Hebden X Grid cellular paving

GRAYBACK THINNING KV PROJECT ROAD REHABILITATION AND SEDIMENT CONTROL

INSTALLATION INSTRUCTIONS

APPENDIX C INLETS. The application and types of storm drainage inlets are presented in detail in this Appendix.

Determination of Design Infiltration Rates for the Sizing of Infiltration based Green Infrastructure Facilities

Tasman Retaining Wall System

iv) Alberta fish weirs

North Umpqua Hydroelectric Project (FERC 1927) Erosion Control Plan Site Remediation/ Assessment Form

Job Reports WR 240 / WR 240 i. Performing to highest quality standards whatever the job

Water Budget IV: Soil Water Processes P = Q + ET + G + ΔS

REROUTING DRAINAGE SYSTEMS

UNDERSTANDING UNPAVED ROAD MATERIAL PERFORMANCE INTERPRETATION David Jones, PhD University of California Pavement Research Center

Topic: Site Formation

This unofficial translation of. Ministerial Decision No 421/1998. was downloaded from METS is not the copyright owner.

Sediment Basin. Fe= (Depends on soil type)

Low Cost Design Standards for Rural Roads Projects. 4654RO/B.1./3a/3.5/010

HEAVY-DUTY HAUL ROAD APPLICATION BULLETIN

StormTech Construction Guide

RWSSHP Resource Manual # 3b. Spring Development. Construction Manual

Standards for Soil Erosion and Sediment Control in New Jersey May 2012 STANDARD FOR RIPRAP. Conditions Where Practice Applies

SECTION 3 DRAINAGE. 3-1 General. 3-2 Drainage Ordinances and Legal Requirements

Rural Roads: A Construction and Maintenance Guide for California Landowners

GRAVEL ROADS CONSTRUCTION & MAINTENANCE GUIDE

BMP #: Infiltration Basin

Installation Instructions

Stream Watch Visual Survey Instructions

Constructed Wetland Pond T-8

E. STORMWATER MANAGEMENT

Builder s enviro guide

Village Hope Technical Report 12d. Construction_Roads. Jonathan Bart 2011 Standard VHTR disclaimer

Types of Hydropower Facilities

North Carolina. Forestry Best Management Practices Manual. To Protect Water Quality

603 - ASPHALT PAVEMENT SMOOTHNESS SECTION 603 ASPHALT PAVEMENT SMOOTHNESS

SECTION EXCAVATION AND BACKFILL FOR UTILITIES AND STRUCTURES

Government of Fiji Republic of Fiji Islands. Fiji Forest Harvesting Code of Practice 2008

CHAPTER 8 EROSION AND SEDIMENT CONTROL PLAN REQUIREMENTS

Transcription:

Best Practices for Building High-Performance Resource Roads Road Drainage Developed by: The Roads and Infrastructure Group

THIS GUIDE IS INTENDED FOR EQUIPMENT OPERATORS CONSTRUCTION CONTRACTORS FIELD SUPERVISORS Developed by: The Roads and Infrastructure Group Introduction 2

The goal is to teach you the benefits of building resource roads with effective drainage which can prolong road life and reduce maintenance costs. You will learn about the available drainage options, where each one is most applicable, and the criteria for using that form of drainage succesfully. Developed by: The Roads and Infrastructure Group Introduction 3

PROBLEM STATEMENT Water is the enemy of any road structure. The accumulation of water on the road s surface or inside its structure can lead to: - pothole development; - erosion of fine-grained materials into streams; - loss of fine particles from the surface; - slippery conditions during wet weather; - reduced load-bearing capacity. Developed by: The Roads and Infrastructure Group Introduction 4

SOLUTION Effective drainage The most important element to ensure good road performance is drainage. - provides a long-lasting road - reduces road failures and surface damage; - reduces maintenance costs; - increases transportation efficiency; - reduces erosion problems and prevents the transport of sediment into streams. Developed by: The Roads and Infrastructure Group Introduction 5

We will focus on when to use and how to build: - crowns and cross-slopes - ditches; - off-takes; - cross-drainage; - other drainage systems. Developed by: The Roads and Infrastructure Group Introduction 6

CROWNS AND CROSS-SLOPES On a flat surface, water will not go anywhere. The purpose of a crown is to provide enough of a slope that water will drain off the road surface. Crowns are used in most cases, whereas crossslopes are used on steep slopes, cut-slopes and in curves. Developed by: The Roads and Infrastructure Group Crowns and Cross-Slopes 7

AMOUNT OF CROWNING Slope = Drop / Distance x 100 = % 4cm / 100cm x 100 = 4% The amount of crowning that is necessary depends on the nature of the road. We recommend a minimum crown of 4% for unpaved roads. This means a drop of 4cm for 1m of distance from the centre of the road. Developed by: The Roads and Infrastructure Group Crowns and Cross-Slopes 8

TABLE FOR CALCULATING A CROWN for a 4% crown Drop from centerline to the edge of the road (to the shoulder) (cm) Road width (m) 10 5 12 6 14 7 16 8 18 9 20 10 22 11 Developed by: The Roads and Infrastructure Group Crowns and Cross-Slopes 9

INSUFFICIENT CROWNING Slope = 3cm / 100 cm x 100 = 3% A 2% or 3% crown is not enough to drain water from the road surface, especially on wide roads. 2% is sufficient for paved roads but not for gravel roads. Developed by: The Roads and Infrastructure Group Crowns and Cross-Slopes 10

Potholes Ruts caused by water infiltration that weakens the surface. Wet conditions that reduce traction during heavy rain. Insufficient crowning allows water to accumulate on the surface, causing surface damage. Each of these kinds of damage can reduce driver safety. Developed by: The Roads and Infrastructure Group Crowns and Cross-Slopes 11

TOO MUCH CROWNING A crown more than 6% is too high If crown is too high (e.g., more than 6%): 1. Increase erosion of fine particles into ditches. This reduces cohesion of the surface material, loosening surface materials, and increasing rutting. 2. Force drivers to travel at the center of the road. Developed by: The Roads and Infrastructure Group Crowns and Cross-Slopes 12

Gradually eliminate the crown as you approach road intersections and railway crossings, where the meeting of the crowns would create a bump and a safety concern. Developed by: The Roads and Infrastructure Group Crowns and Cross-Slopes 13

CUT-BANK IN-SLOPED ROADS An in-sloped road drains water from the entire road toward the cut-bank. This technique can be used on steep slopes to avoid road erosion on the downslope side. Provides a safer surface that reduces the risk of sliding off the road under wet or icy driving conditions. Developed by: The Roads and Infrastructure Group Crowns and Cross-Slopes 14

FILL SLOPE OUT-SLOPED ROADS Drains water from the entire road towards the fill slope. This technique can be used to avoid the accumulation of water in a ditch. Outward slopes are also useful where side slopes are gentle and building a ditch on the cut-slope side would be difficult or expensive. Developed by: The Roads and Infrastructure Group Crowns and Cross-Slopes 15

A SINGLE CROSS-SLOPE This design is easier for graders to maintain. On narrow single-lane roads of 5 to 6m wide, a single 4% cross-slope can be used instead of a crown. Developed by: The Roads and Infrastructure Group Crowns and Cross-Slopes 16

SUPER ELEVATIONS Recommended slope is 6% but may vary depending on design speed and curve radii. When you approach a curve, you should gradually transform the crown into a superelevation, in which the curve s outside edge is higher than the inside edge. Developed by: The Roads and Infrastructure Group Crowns and Cross-Slopes 17

NORMAL CROWN TRANSITIONS SUPER ELEVATIONS SUPER ELEVATIONS Curves should be banked to help moving vehicles remain on the road. The super-elevation increases vehicle stability and safety while also providing efficient drainage. Developed by: The Roads and Infrastructure Group Crowns and Cross-Slopes 18

SUBGRADE BASE LAYERS SURFACE Start building the crown early. CONSTRUCTION TIPS This ensures ongoing drainage even if the subgrade is not graveled immediately after construction. This is recommended for secondary and tertiary roads to allow drying of the subgrade (clays and silts). It reduces the volume of aggregate required at the center of the road during graveling, which reduces gravel transportation costs. Developed by: The Roads and Infrastructure Group Crowns and Cross-Slopes 19

An inexpensive slope meter can be installed in a grader or bulldozer to help achieve the desired slope. Alternatively using a straight board with a level and measuring tape can also work. Developed by: The Roads and Infrastructure Group Crowns and Cross-Slopes 20

DITCHES The purpose of a ditch is to collect water and move it away from the road. Developed by: The Roads and Infrastructure Group Ditches 21

An effective ditch should direct water into the forest around the road at frequent intervals rather than transporting the water over long distances. Developed by: The Roads and Infrastructure Group Ditches 22

Poor ditching Good ditching Once water drains from the surface of the road, it must be moved away from the road so that it does not enter the road structure. Developed by: The Roads and Infrastructure Group Ditches 23

BACK SLOPE SIDE SLOPE DITCH PARTS OF A DITCH Ditches have 3 key components. The slope of the ditch (bottom of the ditch) should follow the same slope as the road and natural terrain and drainage patterns. Developed by: The Roads and Infrastructure Group Ditches 24

Rock Sand Gravel Clay and silts Side slope 1:1 Back slope 1:4 to 1:1 Side slope 3:1 Back slope 3:1 Side slope 1.5:1 Back slope 2:1 Side slope 2:1 to 3:1 Back slope 2:1 to 5:1 DITCH DESIGN Design the ditch s side slope and back slope to minimize the soil s susceptibility to erosion. Developed by: The Roads and Infrastructure Group Ditches 25

ABOUT 0.5M WIDE Where prolonged, heavy rain is rare, a v-shaped ditch is effective. Flat-bottom ditches offer a lower flow velocity and can handle larger volumes of water Developed by: The Roads and Infrastructure Group Ditches 26

U-SHAPED DITCHES Avoid U-shaped ditches Their steep sides make them difficult to maintain, and the sides are likely to cave in, leading to blockage of the flowing water, erosion, and sediment transport. Instead, a V-shaped ditch with a rounded bottom will help to slow and disperse water. Developed by: The Roads and Infrastructure Group Ditches 27

Ditches can get obstructed by debris and vegetation. Ditches can be mechanically cleared with a grader or excavator. Maintain the ditch whenever necessary to ensure that water continues to flow smoothly. Developed by: The Roads and Infrastructure Group Ditches 28

CHECK STRUCTURES See FPInnovations Advantage report Vol. 9 no. 5 for more design information Ditch check structures are used to slow the flow within a ditch, promote deposition of suspended soil particles, and reduce erosion within the ditch. - they can be built from aggregate (or rocks), geotextile, logging debris or commercial products. - spacing is determined by the gradient of the ditch and the height of the structure. Developed by: The Roads and Infrastructure Group Ditches 29

DITCH ARMORING Reinforced matting, aggregate, and mulch or straw can be used as armor. Armoring ditches protects the soil against erosion and deepening of the ditch ("downcutting"). Developed by: The Roads and Infrastructure Group Ditches 30

Excavator preparing brushmat from branches, stumps and tree tops left on right-of-way after harvesting F ill Brushmat No defined ditch Bulldozer spreading imported fill and shaping the road NO DITCHES REQUIRED This technique is often used on soft soils where the organic layer must be kept undisturbed. Roads built on a brushmat or corduroy road covered with gravel may not require ditches because the road is elevated and drains more easily. Developed by: The Roads and Infrastructure Group Ditches 31

STREAM OFF-TAKE OFF-TAKES: DITCH TURNOUTS An off-take is an extension of a ditch that channels water away from the road and disperses it onto the forest floor, where it is absorbed by the soil. DITCH Developed by: The Roads and Infrastructure Group Off-Takes 32

Build off-take ditches, also known as ditch turnouts, outside the streamside buffer zone to carry suspended sediment away from the stream. Locate off-takes in places where the outlet will empty into a catchment area. If you can t direct an off-take into the forest, use other techniques such as the construction of a sediment pond (settling basin) or create cross-drainage using culverts. Developed by: The Roads and Infrastructure Group Off-Takes 33

Off-take Stream Off-take INSTALLATION The terrain characteristics often determine the location of off-takes. Off-takes must be frequent enough to ensure that water has no chance to accumulate and overflow the ditches. On steep slopes, you may require more than one off-take every 100m. Developed by: The Roads and Infrastructure Group Off-Takes 34

lead off-takes away from the road The ditch turnout depth should be equivalent to or slightly deeper than the ditch, to eliminate barriers to the water s flow Build off-takes at an angle of 45" to 70 to the road Extend off-takes 20 to 50m, far enough to fully dissipate the water Developed by: The Roads and Infrastructure Group Off-Takes 35

CROSS-DRAINAGE: CULVERTS Cross-drainage controls water volume and speed. Where water cannot be easily dispersed on one side of the road, cross-drainage can transfer water to the opposite side of a road and reduce the accumulation of standing water. Install cross-drainage to transfer water from the high side of the road to the low side, so that water will be able to follow its natural flow path. Developed by: The Roads and Infrastructure Group Cross-Drainage 36

Select the culvert size based on the size of the road and the anticipated maximum flow. The diameter should be at least 30cm. The culvert must be long enough to reach natural ground at the outlet. Culverts with outlets positioned on the fill slope require armoring beneath the outlet to prevent erosion (scouring) of the fill material. Developed by: The Roads and Infrastructure Group Cross-Drainage 37

INSTALLATION Cross-drainage controls water volume and speed. Install culverts at an angle of 30" to 45" to the road, with the entry point farther uphill than the exit point to improve the flow of water into the culvert. Developed by: The Roads and Infrastructure Group Cross-Drainage 38

Firmly compact the fill around the culvert, particularly under the haunches. Minimum thickness of 30cm. Install the culvert on a well-compacted surface to prevent future settling. Cover the culvert with fill at least 1/3 the pipe s diameter in thickness, to prevent vehicles from damaging the culvert. Developed by: The Roads and Infrastructure Group Cross-Drainage 39

SPACING BETWEEN CULVERTS Define the spacing between culverts based on the road s slope and the soil type. Maximum distance between culverts (m) Slope (%) Low erosion risk* Significant erosion risk** 0-3 120 75 4-6 90 50 7-10 75 40 10-12 60 35 12+ 50 30 *Coarse rocky soils, gravels, and some clays **Fine, friable soils, silts and some clays, fine sands Developed by: The Roads and Infrastructure Group Cross-Drainage 40

OTHER DRAINAGE ALTERNATIVES: - Broad-based dips - Open-top surface designs - Above-ground deflectors Developed by: The Roads and Infrastructure Group Other Drainage Alternatives 41

BROAD-BASED DIPS This low point must lie outside the stream s buffer zone. Broad-based dips (also called «rolling dips») are designed to remove water from the road surface. Construct the dip deep enough to provide adequate drainage. Design the dip so that it is sufficiently long and gradual that it will not affect vehicle traffic. Developed by: The Roads and Infrastructure Group Other Drainage Alternatives 42

Open-top surface drains are drainage structures that are placed to collect and direct surface flows off the road. These drains can be built from metal, lumber, small logs or any other material that can be laid side by side to support traffic while allowing drainage. Developed by: The Roads and Infrastructure Group Other Drainage Alternatives 43

ABOVE-GROUND DEFLECTORS Place above-ground deflectors across the road to direct the surface flow to the side. On long slopes, where water may flow downhill along the surface of the road, it is important to direct the flowing water to the sides of the road. Deflectors can be made from any durable material that does not create a large bump in the road. Recycled rubber conveyor belts are often used. Developed by: The Roads and Infrastructure Group Other Drainage Alternatives 44

SUMMARY The optimal combination depends on the location of the road, the soil material, and the amount of water that must be managed. An effective drainage system lets water follow its natural course. Accomplishing this requires a combination of the following techniques: - proper design of crowning, cross-slopes, and super-elevations; - efficient ditches with adequate capacity; - effective cross-drainage and off-take systems; - the use of drainage options such as broad-based dips, open-top surface drains, and deflectors. Developed by: The Roads and Infrastructure Group Conclusion 45

CONCLUSION Proper construction and design techniques will provide effective drainage, offering the following advantages: - increased road performance; - reduced erosion and sediment transport into streams; - increased safety; - increased transportation efficiency; - reduced maintenance costs. Developed by: The Roads and Infrastructure Group Conclusion 46

SUGGESTED READINGS Gillies, C. 2007. Erosion and sediment control practices for forest roads and stream crossings. FPInnovations, Advantage Vol.9, no.5. 87 p. Keller, G.; Sherar, J. 2003. Low-volume roads engineering Best Management Practices Guide. U.S. Agency for International Development (USAID) 158 p. Skorseth, K.; Selim, A. A. 2000. Gravel roads maintenance and design manual. U.S. Department of Transportation, Federal Highway Administration. 64 p. Developed by: The Roads and Infrastructure Group 47

www.fpinnovations.ca Follow us