INSTRUCTION: This section consists of TWO (2) structured questions. Answer ALL questions.

Similar documents
INSTRUCTION: This section consists of TEN (10) short questions. Answer ALL questions.

INSTRUCTION: This section consists of THREE (3) structure questions. Answer ALL questions.

INSTRUCTION: This section consists of SIX (6) essay questions. Answer FOUR (4) questions only.

INSTRUCTION: This section consists of SIX (6) structured questions. Answer FOUR (4) questions only.

INSTRUCTION: This section consists of TEN (10) short questions. Answer ALL questions.

PEPERIKSAAN AKHIR SEMESTER DISEMBER 2006/2007

Answer all questions Jawab semua soalan

INSTRUCTION: This section consists of SIX (6) structured questions. Answer FOUR (4) questions only.

UNIVERSITI SAINS MALAYSIA. CCS521 Advanced Distributed Systems Concepts and Design [Konsep dan Reka Bentuk Sistem Teragih Maju]

This section consists of FOUR (4) structured questions. Answer ALL questions.

UNIVERSITI SAINS MALAYSIA. EAA 455/2 Reinforced Concrete Structural Design II [Rekabentuk Struktur Konkrit Bertetulang II]

DJF5022: MANUFACTURING SYSTEM

IBK 201 Fundamentals of Bioprocess Technology [Asas Teknologi Bioproses]

*'t * o, {ffi. PEPERIKSAAN AKIIIR SEMESTER II sesr 20r2t2013 KONTRAK DAN TAKSIRAN DAC DAA/DAC MAC 2OI2 2 JANT

IBG 311 ENZYME TECHNOLOGY [TEKNOLOGI ENZIM]

PARASITIC MOMENT EFFECT FOR THE THREE SPANS CONTINUOUS PRESTRESSED CONCRETE BRIDGE SITI SARAH SALIM

UNIVERSITI SAINS MALAYSIA

UNIVERSITI MALAYSIA PERLIS. ENT 145 Material Engineering [Kejuruteraan Bahan]

EAP 412/4 Environmental Studies [Pengajian Alam Sekitar]

RMT 553 Organisation and Management (Organisasi dan Pengurusan)

UNIVERSITI SAINS MALAYSIA. EAS 181/2 Concrete Technology [Teknologi Konkrit]

EPM 342 Production Management [Pengurusan Pengeluaran]

(Kertas soalan ini mengandungi 6 soalan dalam 6 halaman yang dicetak) (This question paper consists of 6 questions on 6 printed pages)

UNIVERSITI SAINS MALAYSIA. EAA 455/2 Reinforced Concrete Structural Design II [Rekabentuk Struktur Konkrit Bertetulang II]

HUMAN VALUES IDENTIFICATION AND ASSESSMENT TOOL DEVELOPMENT FOR TQM CONTEXT MUHAMMAD NOMAN MALIK. A thesis submitted in fulfilment of the

UNIVERSITI SAINS MALAYSIA. Second Semester Examination 2010/2011 Academic Session. April/May 2011

EMM 213 Strength of Materials [Kekuatan Bahan]

QUANTITY SURVEYOR S LIABILITY DURING PRE TENDER STAGE ASMAH ALIA BT MOHAMAD BOHARI UNIVERSITI TEKNOLOGI MALAYSIA

BEST ENDEAVOURS FOR GRANTING AN EXTENSION OF TIME IN CONSTRUCTION CONTRACT NUR FARAH FARHANA BINTI RASID UNIVERSITI TEKNOLOGI MALAYSIA

UNIVERSITI SAINS MALAYSIA. First Semester Examination 2013/2014 Academic Session. December 2013 / January 2014

SCES3310 : KIMIA ALAM SEKITAR II ENVIRONMENTAL CHEMISTRY II

MULTIMEDIA COLLEGE JALAN GURNEY KIRI KUALA LUMPUR

Kertas soalan ini mengandungi ENAM (6) muka surat bercetak.

BORANG PENGESAHAN STATUS TESIS

DEFLECTION MONITORING OF CAST IN-SITU BALANCED CANTILEVER PRESTRESSED CONCRETE BOX GIRDER BRIDGE MOHD KHAIRUL AZMAN BIN HAMBALI

PENYERAHAN DAN PENILAIAN TUGASAN ASSIGNMENT SUBMISSION AND ASSESSMENT BBPP1103 PRINCIPLES OF MANAGEMENT MAY 2014

BERASAS KOMPUTER. Oleh Mohamad Rodzizan b. Hj. Ahmad Tajuddin. 0 MOHAMAD RODZIZAN TAJUDDIN, Hak Cipta Terpelihara.

IEK 212 PROCESS HEAT TRANSFER [PEMINDAHAN HABA PROSES]

UNIVERSITI SAINS MALAYSIA SUKATAN PEPERIKSAAN PERKHIDMATAN BAGI PEGAWAI TADBIR GRED N41

(4 the undersigned, certib that)

EAS 562/4 - Construction Materials and Repair Techniques EAS 562/4 - Bahan Binaan dan Teknik Baikpulih

RUMAH TAMU SEMI-D TAMAN KINGFISHER, UNIVERSITI MALAYSIA SABAH (UMS)

1 rrrnnarn

SIMULATION PERFORMANCE OF LOW DAMAGE BASE CONNECTION ON ABAQUS MAHDI HATAMI

: 20 Mac Tujuan Peperiksaan : Untuk memenuhi sebahagian daripada syarat-syarat untuk pengesahan dalam jawatan Penolong Pegawai Penerbitan N29

This item is protected by original copyright

UNIVERSITI SAINS MALAYSIA ln Collaboration With TAYLOR'S COLLEGE. First Semester Examination Academic Session 2OOSl20Oo.

ENERGY EFFICIENT RESIDENTIAL BUILDINGS ASSESSMENT USING BUILDING INFORMATION MODELING AMIN FAKHKHAR ZADEH

MAINTENANCE MANAGEMENT ASSESSMENT IN A LOCAL MANUFACTURING COMPANY MOHAMMAD ANNUAR BIN MD SALLEH

IWK 103 Pulp Preparation and Paper Recycling [Penghasilan Pulpa dan Pengitaran Kertas]

EAG245 Soil Mechanics [Mekanik Tanah]

: 20 Mac Tujuan Peperiksaan : Untuk memenuhi sebahagian daripada syarat-syarat untuk pengesahan dalam jawatan Penolong Pegawai Tadbir N29.

UNIVERSITI SAINS MALAYSIA. Peperiksaan Semester Kedua Sidang Akademik 2002/2003. Februari / Mac Masa : 3 jam

PENTAKSIRAN DIAGNOSTIK AKADEMIK SBP 2012 PERCUBAAN SIJIL PELAJARAN MALAYSIA. BIOLOGI Kertas 3 Satu jam tiga puluh minit

PEPERIKSAAN PEGAWAI KESELAMATAN DAN KESIHATAN SAFETY AND HEALTH OFFICER EXAMINATION

IEK 101 Chemical Process Calculations [Penghitungan Proses Kimia]

RESEARCH UNIVERSITY FINAL EXAMINATION SEMESTER II, SESSION 2014/2015

PENGAKTIFAN PENDAFTARAN KE SISTEM E-PROCUREMENT ARIBA

INSTITUT ALAM SEKITAR DAN PEMBANGUNAN UNIVERSITI KEBANGSAAN MALAYSIA BANG1

UNIVERSITI PUTRA MALAYSIA MEASURING EFFICIENCY OF A MALAYSIAN HOTEL CHAIN USING DATA ENVELOPMENT ANALYSIS

UNIVERSITI PUTRA MALAYSIA SUMBER, PERMINTAAN DAN BEKALAN AIR DOMESTIK DI KELANTAN UTARA HAJI ZAINUDDIN BIN HAJI IBRAHIM FPAS

PARASITIC MOMENT EFFECT FOR THE THREE SPANS CONTINUOUS PRESTRESSED CONCRETE BRIDGE SITI SARAH SALIM

: 20 Mac Tujuan Peperiksaan : Untuk memenuhi sebahagian daripada syarat-syarat untuk pengesahan dalam jawatan Penerbit Rancangan B29

EPM 321 Manufacturing System [Sistem Pembuatan]

1 nrrnrrni COLUMN REPAIRED BY JACKETING METHOD. MUHAMMAD ZULIIlLMI BIN ALI

SUKATAN PEPERIKSAAN PERKHIDMATAN BAGI PELUKIS PELAN(SENI BINA)/PENOLONG PEGAWAI SENI BINA JA29. : 20 Mac 2017

KIT 356 Chemical Processes [Pemprosesan Kimia]

EEM 221 PRINSIP DAN MEKANIK BAHAN

BORANG PENGESAHAN STATUS TESIS***

EPP 331- Manufacturing Technology II [Teknologi Pembuatan II]

FINAL EXAMINATION SEMESTER II, SESSION 2016/2017 PROGRAMME : SKMM/SKMP/SKMI/SKMB/SKMT/SKMV/SKMO

(Kertas soalan ini mengandungi 4 soalan dalam 7 halaman yang dicetak) (This question paper consists of 4 questions on 7 printed pages)

STUDY ON IRON AND MANGANESE REMOVAL IN RIVER WATER FOR TEXTILES INDUSTRY USAGE ZAITON BIN SAMAD UNIVERSITI TEKNOLOGI MALAYSIA

KAEDAH-KAEDAH BURUH (PEKERJA SEPARA MASA) (SABAH) 2013 LABOUR (PART-TIME EMPLOYEES) (SABAH) RULES 2013

AN EFFICIENT MICROCONTROLLER-BASED ELECTRONIC BALLAST FOR HIGH PRESSURE SODIUM LAMPS USED IN STREET LIGHTING MOHD HAMIZAN BIN OMAR

ALTERNATIVE DESIGN OF FOUNDATIONS SUBJECTED TO UPLIFT FOR TRANSMISSION LINE TOWER

ANALYSIS OF SQUAT SHEAR WALL WITH DIFFERENT DIMENSIONS AND POSITIONS OF OPENING UNDER DIFFERENT TYPE OF STATIC LOAD ANG YIP HONG

UNIVERSITI TEKNIKAL MALAYSIA MELAKA OPTIMIZING OPERATOR CYCLE TIME IN A SEMICONDUCTOR COMPANY

TABLE OF CONTENTS TITLE ACKNOWLEDGMENT ABSTRACT ABSTRAK

Jurnal Teknologi PERFORMANCE APPRAISAL OF STEEL CONNECTION IN LOW RISE BUILDINGS. Full Paper. H. F. Siuw, M. Taib *

THE USE OF BANANA TRUNKS ASH AS CEMENT REPLACEMENT IN MORTAR MUHAMAD LUKMAN HAKIM BIN WAHAB

WAN SYARIAH BINTI WAN JAMALUDDIN

UNIVERSITI MALAYSIA PERLIS. ENT 145 Material Engineering [Kejuruteraan Bahan]

I hereby declare that I have read this capstone project report and in my opinion this capstone project report is sufficient in terms of scope and

TS2963 : Pangkalan Data. Nota Makmal. Makmal 6

FLOOD DAMAGE ASSESSMENT MODEL USING COST-BENEFIT ANALYSIS NOR AZLIZA BINTI AKBAR

A CASE STUDY ON COMPARISON BETWEEN WOOD TRUSS AND STEEL TRUSS FOR ROOF STRUCTURE. It J :i uvv u h1iisji

III fl I BETWEEN C( COMPARISON ( EG BOND STRENGTH PAIR MATERIALS NURULNIZAM BIN MOHAMED

BORANG KEBENARAN MENJALANKAN KERJA LUAR/PERUNDINGAN

UNIVERSITI SAINS MALAYSIA. EPP 201 Manufacturing Technology I [Teknologi Pembuatan I]

UNIVERSITI PUTRA MALAYSIA DEVELOPMENT OF A FUZZY LOSS-BASED PROCESS CAPABILITY INDEX

KEBERKESANAN PENGURUSAN PERUBAHAN DI AGENSI AWAM: PERSEPSI WARGAKERJA TERHADAP KEBERKESANAN PENGURUSAN

EAH 325E/3 Engineering Hydrology (Hidrologi Kejuruteraan)

USER RESISTANCE FACTORS IN POST ERP IMPLEMENTATION SAYEED HAIDER SALIH MAHMOUD

Achievement of Client's Charter Report 2017 / Laporan Pencapaian Piagam Pelanggan 2017

UNIVERSITI SAINS MALAYSIA

BEST MANAGEMENT PRACTICE IN CONSTRUCTION WASTE MANAGEMENT PRESENTED BY KHAIRUL IRWAN BIN KALID PPSPPA

BORANG AS/PUB/N-CHIMNEY FORM AS/PUB/N-CHIMNEY

MULTIMEDIA COLLEGE JALAN GURNEY KIRI KUALA LUMPUR

UNIVERSITI MALAYSIA PERLIS. ENT147 Engineering Materials [Kejuruteraan Bahan]

Transcription:

SECTION A : 50 MARKS BAHAGIAN A : 50 MARKAH INSTRUCTION: This section consists of TWO (2) structured questions. Answer ALL questions. ARAHAN: Bahagian ini mengandungi DUA (2) soalan berstruktur. Jawab semua soalan. QUESTION 1 SOALAN 1 CLO1 (a) State FIVE (5) stages related to construction. Nyatakan LIMA (5) aktiviti yang berkaitan dengan pembinaan. [5 marks] [5 markah] CLO1 C2 (b) Table Tender Document is very important during the tendering process. Identify FOUR (4) characteristics of Table Tender Document. Dokumen Meja Tender sangat penting semasa proses tawaran. Kenalpasti EMPAT (4) ciri-ciri Dokumen Meja Tender. [8 marks] [8 markah] CLO1 C2 (c) Describe SIX (6) criteria that need to be considered by the Board of Tender in the process of selecting a contractor. Terangkan ENAM (6) perkara yang perlu dipertimbangkan oleh Lembaga Tawaran dalam proses pemilihan kontraktor [12 marks] [12 markah] 2 SULIT

QUESTION 2 SOALAN 2 CLO1 (a) State FIVE (5) principles of contract according to Contract Act 1950. Nyatakan LIMA (5) prinsip kontrak berdasarkan Akta Kontrak 1950. [5 marks] [5 markah] CLO1 C2 (b) A subcontractor is an individual or company that signs a contract to perform a specific work as part of the overall project. Describe THREE (3) differences between Domestic Sub-contractor and Nominated Sub-contractor. Subkontraktor adalah individu atau syarikat yang menandatangi kontrak untuk melaksanakan tugasan yang tertentu sebahagian dari keseluruhan projek. Terangkan TIGA (3) perbezaan diantara Subkontraktor Domestik dan Subkontraktor Dinamakan. CLO1 C2 c) Turnkey Contract is one of the contracting methods used in the construction industry. Identify FIVE (5) characteristics of the contract. Kontrak Turnkey merupakan salah satu daripada kaedah kontrak yang digunakan dalam industri pembinaan. Kenalpasti LIMA (5) ciri-ciri kontrak tersebut. 3 SULIT

SECTION B : 50 MARKS BAHAGIAN B : 50 MARKAH INSTRUCTION: This section consists of FOUR (4) essay questions. Answer TWO (2) questions only. ARAHAN: Bahagian ini mengandungi EMPAT (4) soalan esei. Jawab DUA (2) soalan sahaja. QUESTION 1 SOALAN 1 a) i) Define Preliminary Estimating Definisikan taksiran awalan [2 marks] [2 markah] ii) List THREE (3) methods that can be used to prepare the Preliminary Estimating. Senaraikan TIGA (3) kaedah yang biasa digunakan dalam menyediakan taksiran awalan. [3 marks] [3 markah] 4 SULIT

b) Based on Table B1, calculate the cost of construction of Hospital C which can accommodate 6000 patients, taking into consideration that there will be an additional 25% cost for materials. Berdasarkan Jadual B1, kirakan kos pembinaan untuk Hospital C yang mana boleh memuatkan 6000 orang pesakit, anggaran kos mestilah mengambilkira terhadap penambahan kos sebanyak 25% bagi kos bahan. Table B1/Jadual B1 Types / Jenis Construction Cost / Kos Pembinaan (RM) Total Patients / Jumlah Pesakit Hospital A 2,800,500. 00 3,500 Hospital B 3,500,000. 00 4,200 5 SULIT

c) Based on Figure B1, calculate the cost of the building using the Cubic Content Method, assuming that the price rate is RM 550.00 / m 3. Berdasarkan Rajah B1, kirakan kos bangunan dengan menggunakan Kaedah Isipadu Bangunan, andai kadar harga adalah RM 550. 00 / m 3. 4100 3200 2000 8000 Floor Plan / Pelan Lantai 800 1500 7500 6800 Side View / Pandangan Sisi Figure B1/Rajah B1 6 SULIT

QUESTION 2 SOALAN 2 (a) List FIVE (5) elements to be considered in doing pricing for excavation work Senaraikan LIMA (5) elemen yang dipertimbangkan dalam membuat kadar harga kerja penggalian. [5 marks] [5 markah] (b) Based on Table B2(a), calculate the cost of 1m 3 for trench excavation work by hand. Type of soil is ordinary soil. Berdasarkan Jadual B2(a), hitungkan kos 1m 3 kerja pengorekan parit dengan menggunakan tangan. Jenis tanah adalah tanah biasa. Labour wage Upah buruh Labour Output:- Angkatap buruh:- Excavation soil Pengorekan tanah Table B2(a)/Jadual B2(a) RM 55.00/ day RM 55.00/sehari 2.50 hours/m 3 2.50 jam/m 3 Removal & transported soil Mengeluarkan dan mengangkut tanah Backfill & soil compacting Tambak & pemadatan tanah Profit & overhead Keuntungan & kos pengurusan 2.00 hours/m 3 2.00 jam/m 3 1.50 hours/m 3 1.50 jam/m 3 10% 10% 7 SULIT

(c) Based on Table B2(b), calculate the cost of 1m 3 concrete work (1:2:4 aggregates 19mm) using hand. Berdasarkan Jadual B2(b), hitungkan kos 1m 3 kerja konkrit (1:2:4-19- batu baur dengan menggunakan tangan. Table B2(b)/Jadual B2(b) Materials:- Bahan-bahan:- Cement./ Simen. RM 18.00/bag/RM 18.00/kampit Sand./ Pasir RM 30.00/m 3 /RM 30.00/m 3 Aggregate./ Batu baur RM 45.00/m 3 /RM 45.00/m 3 Labour output:- Angkatap buruh:- Mixing concrete./ Menggaul konkrit. 2.5 hours./ 2.5 jam Transporting concrete./ Mengangkut konkrit. 2.0 hours./ 2.0 jam Casting and Compacting concrete. 2.8 hours Menuang dan memadatkan konkrit. 2.8 jam Labour wage per day/ Upah buruh sehari RM 50.00/Rm 50.00 Profit and overhead 10% Keuntungan dan kos pengurusan 10% Others:- Lain-lain:- 1m 3 cement equal to 28 bag./ 1m 3 simen bersamaan dengan 28 kampit. Shrinkage and wastage 50%./Pengecutan dan pembaziran -50% Standard working day 8 hours./ Jam berkerja sehari 8 jam 8 SULIT

QUESTION 3 SOALAN 3 (a) Describe cut and fill in earthwork. Terangkan kerja pemotongan dan tambakan dalam kerja-kerja tanah. [5 marks] [5 markah] (b) Refer to the grid layout in Figure B3(a), calculate the quantity of soil using Square Method. Merujuk kepada susunatur grid pada Rajah B3(a), hitungkan kuantiti tanah dengan menggunakan Kaedah Segi Empat Sama. i. Total area / Jumlah keluasan ii. Average height of soil / Purata ketinggian tanah iii. Total volume cut/ fill/ Jumlah isipadu tanah yang dipotong/ di tambak Given / Diberi: i. Interval / Selang = 10 meter ii. Formation level / Aras formasi = 97.5 meter A1 A2 A3 B1 B2 B3 Point A1 Origin Level (m) 99.50 A2 96.20 C2 A3 94.30 B1 98.20 B2 101.80 B3 98.00 102.20 C2 97.20 Figure B3(a)/Rajah B3(a) 100.20 9 SULIT

(c) By referring to Figure B3(b) and Table B3(b), calculate the quantity of: Merujuk kepada Rajah B3(b) dan Jadual B3(b), kirakan kuantiti bagi: i. Initial pile/cerucuk awalan ii. Depth of pile penetration /kedalaman penusukan 1 2 3 4 5 6 7 A 3P B C 3P 3P D E F Figure B3(b)/ Rajah B3(b) 10 SULIT

Table B3(b)/ Jadual B3(b) ITEMS/ ITEM Type of piles /jenis cerucuk Driven Depth /kedalaman DESCRIPTION / KETERANGAN Reinforced concrete piles, size 200mm x 200mm 26 m Starter Piles /cerucuk permulaan Extension Piles /cerucuk sambungan Legend /petunjuk 12m long 6m, 3m long refers to pile with 2 pile point 3P refers to pile with 3 pile point QUESTION 4 SOALAN 4 (a) Identify the taking off list of beam and its units. Kenalpasti senarai ukur kuantiti dan unit bagi rasuk [5 marks] [5 markah] (b) By referring to Figure B4(a): Reinforced concrete beam. Carry out taking off the quantity for the following: i. Unsawn timber as formwork for beam 1/A-B ii. Reinforced concrete (1:2:4 mm aggregate) for beam 1/A-B iii. High yield steel as main reinforcement bar in beam A/1-2 iv. Mild steel as stirrup in beam A/1-2 Dengan merujuk pelan susun atur rasuk konkrit bertetulang dalam Rajah B4(a). Sediakan ukur kuantiti bagi item-item seperti berikut: i. Kayu tidak berketam sebagai kotak bentuk rasuk 1/A-B ii. Konkrit bertetulang (1:2:4-19 mm aggregate) for beam 1/A-B iii. Keluli tegasan sebagai tetulang utama untuk rasuk A/1-2 iv. Keluli lembut sebagai tetulang perangkai pada rasuk A/1-2 11 SULIT

Figure B4(a): Reinforced concrete beam Rajah B4(a):Rasuk konkrit bertetulang 12 SULIT

(c) By referring to Figure B4(b) and Table B4(b), carry out taking off the quantity of external walls finishes. Dengan merujuk kepada Rajah B4(b) dan Jadual B4(b), sediakan ukur kuantiti bagi kemasan dinding luar. W1 W2 D1 Figure B4(b): Floor Plan of external wall finishes Rajah B4(b):Pelan lantai kemasan dinding luar 13 SULIT

Table B4(b): Door/Window/Column (for deduction) Jadual B4(b): Pintu/Tingkap/Tiang (untuk kerja-kerja penolakan) Type Jenis Size Saiz Quantity Kuantiti W1 1200mm x 800mm 1no. W2 1600mm x 1800mm 1no. D1 2800mm x 2100mm 1no. Column 150mm x 150mm 4no. Building height Wall finishes 2800m English bond with brick reinforcement at every 4 th course SOALAN TAMAT 14 SULIT