Geo-treatments in Constructing a Tunnel in Karst Strata: Lessons Learned from the Metro Subway Project in Guangzhou, China

Similar documents
TBM Selection and Specification

Research on Mutual Influence between Pipes of Curved Pipe-jacking Roof Project

Pipe Jacking/Microtunnelling. Dr. Mark Knight. Centre for Advancement of Trenchless Technologies (CATT) University of Waterloo.

13/05/2016. Introductions of Pipe Roof. Focuses. Application of Rectangular Shield Jacking

Prof. Eng. Daniele PEILA

SITE INVESTIGATION. Foundation Engineering

Tunnels. Introduction in Shield tunnelling Pipe jacking & tunnelling Slurry & hydroshield Slurry versus EPB Principles of support pressure

Tunnelling and Underground Space Technology

Pipe Jacking. Japan Sewage Works Association

Performance review of a pipe jacking project in Hong Kong

King County Uses Trenchless Methods to Construct a Large Siphon Under Seattle s Ship Canal

2

Study on earth pressure acting upon shield tunnel lining in clayey and sandy grounds based on field monitoring

Subsurface Investigations PDCA Professor s Driven Pile Institute. Loren R. Anderson Utah State University June 25, 2015

Rock Tunnel Engineering INTRODUCTION. Tunnel a hole in the ground to provide for desired movement or as mobility channel.

Behavior of Surrounding Soil during Construction and Its Countermeasures Using Pipe Jacking Method in Deep Strata

Wastewater Capital Projects Management Standard Construction Specification

Design Data 4M. Jacking Concrete Pipe

Analysis of the EPB-TBM Excavation Parameters Used in a Tunnel Construction in Istanbul

STANDARD SPECIFICATIONS SECTION BORING AND JACKING. A. Section includes requirements for boring and jacking casing pipe.

Solutions for tunneling and mining TBM. Expanding Horizons Underground

Awesome Aquifers Vocabulary

Diaphragm wall Construction

Soil conditioning for EPB tunnelling in choesionless soil, clay and rock masses and backfilling in shield tunnelling

Secoroc Rock Drilling Tools CASING ADVANCEMENT SYSTEMS

water-powered drilling in ground engineering

Design Data 4. Jacking Concrete Pipe

Excavation and Trenching

EMBANKMENT DAM SEEPAGE MODIFICATIONS CHOICES AND CONSIDERATIONS. John W. France, PE, D.WRE 1 ABSTRACT INTRODUCTION

Civil Engineering Practice

Hardrock Tunnel Boring Machines

IMPROVEMENT OF CONCRETE DURABILITY BY COMPLEX MINERAL SUPER-FINE POWDER

Bi-Directional Static Load Testing of Driven Piles

Determining radius of influence of the face in EPB shield tunneling by finite difference method.

Trenching & Shoring Safety Course Outline

Tunnel Lining Design and Construction

Available online at ScienceDirect. Procedia Engineering 189 (2017 ) 11 17

PIPE JACKING. An introduction to pipe jacking prepared by the Pipe Jacking Association

192GasCatalog.

Trenchless Technology

CleanReam Premium Casing-Reaming Bit Efficiently drills out casing and liner using a robust cutting structure

CE 6012 Ground Improvement Techniques Question Bank

LARGE DIAMETER PIPE ROOF BOX EXCAVATION FOR PASSENGER LINKWAY TUNNEL

ON THE BEHAVIOR OF A STUCK CURVED PIPE JACKING

INDEX FOR SPECIFICATIONS FOR JACKING CULVERTS THROUGH EMBANKMENTS SCOPE... 2

Safety Assessment of Excavation with Fault Tree Analysis

Temporary Structures. Excavations and Excavation Supports

SPECIFICATION : BORING AND JACKING

INNOVATIVE PILE EXTRACTION TECHNIQUE OF CFA PILES FOR THE NEW HARBOR BRIDGE PROJECT

SECTION GRAVEL PACKED WATER WELL

SPECIAL CONDITIONS FOR PIPE JACKING (PJ) October, 2006

Weekly Safety Talks: Excavation & Trenching Application

USE OF MICROTUNNELING TO INSTALL PIPES IN AN ENVIRONMENTALLY SENSISTIVE AREA. Miranda Roman D. *, LaFaso Edward

Foundation/Site Work Code Requirements

Wastewater Capital Projects Management Standard Construction Specification

D7: TUNNEL CONSTRUCTION AND METHODOLOGY

PAUL ZICK, PE NORTH SHORE CONSTRUCTORS JV

Pipe Jacking. Progress is built on ideas.

Metro Montreal Successful operation of a state-of-the-art roadheader ATM 105-ICUTROC competing with drill & blast operation in urban tunnelling

Tubewell Shallow Tubewell (h<7.5m) Deep tubewell (h>75m) Alternative technologies. Rain water harvesting etc.

Independent Consulting Engineers NV Zaegersgut Rd #13 tel +(599) Date: 25 januari 2008 Project: Troy Hill Saba Projectnr:

PRACTICAL CONSIDERATIONS IN THE SELECTION AND USE OF CONTINUOUS FLIGHT AUGER AND DRILLED DISPLACEMENT PILES. Dan A. Brown 1, P.E., M.

ROTARY DRILLING TECHNIQUES LARGE DIAMETER

INTERNATIONAL SEMINAR LONG TUNNELS

STANDARD SPECIFICATIONS SECTION TUNNELING. A. Section includes requirements for constructing tunnels 48-inch and larger diameter.

HCC completes up-line tunnel for DMRC CC30

Identification of Tunnel Settlement Caused by Land Subsidence in Soft Deposit of Shanghai

Challenges in Design and Construction of Deep Excavation With Case Studies - KVMRT in KL Limestone

Oweninny Wind Farm. Oweninny Environmental Impact Statement Appendix 5. Turbine Foundation Construction Method Statement

Earthquake Reinforcement Using Jet Grouting for a Factory in Operation

SOURCES OF WATER SUPPLY GROUND WATER HYDRAULICS

DESIGN AND INSTALLATION OF THE SHORING AND DECKING FOR TTC YONGE STATION

North American Society for Trenchless Technology (NASTT) NASTT s 2015 No-Dig Show. Denver, Colorado March 15-19, 2015 MM-T2-03

Standard Cut vs. Keyhole

CURRICULUM VITAE RELEVANTE

Case study of deep excavation in existing underground structure of three-story basement and diaphragm wall

Low Mobility Grouting (LMG) and Compaction Grouting, "Application Review"

SIDEWALK REPAIR GUIDE

From Colonia Jardín to Cuatro Vientos

Tunnel Boring Machines used for Irrigation in Andhra Pradesh, India. D.Harding 1 1 The Robbins Company, Solon, Ohio, USA

Tunneling the Metro do Porto - Under Pressure in Porto Granite

Alto Tunnel Study. Weekly Progress Report February 10, 2017

DISPERSIVE SOILS. Dispersive soils are those in which the clay content has a high percentage of sodium.

MINING products MINING PRODUCTS

Compensation grouting for TBM tunnelling beneath shallow-cover

Current Hydro Power Plant Projects of Verbund in Austria and the use of High Strength Steel an Operators View

Membrane for tunnels and underground construction

SEMINAR ON WATER SECURITY IN BULGARIA SOFIA, SEPTEMBER 18-19, 2017 DAM SAFETY IN ROMANIA

Stabilization of Running Granular Soils in TBM Alignment with Sodium Silicate Grout

ONSITE ASSEMBLY AND HARD ROCK TUNNELING AT THE JINPING-II HYDROPOWER STATION POWER TUNNEL PROJECT

The Aizhai Suspension Bridge is

RIGID INCLUSIONS. Rigid Inclusions offer an economical approach for building on sites underlain by soft soil.

Building Code of New York State

Dewatering & Foundations. Water. Low tech

GUIDELINES FOR INSTALLATION OF ON-SITE SEWAGE SYSTEMS

Conventional Field Testing Methods and Issues

A.2.a Random Riprap... Table

GBR Fundamentals. Past Practices and Lessons Learned. Seminar on Geotechnical Baseline Reports. October 5, 2013

Transcription:

Geo-treatments in Constructing a Tunnel in Karst Strata: Lessons Learned from the Metro Subway Project in Guangzhou, China Qing-Long Cui, Ph.D. student Co-authors: Ye-Shuang Xu, Shui-Long Shen*, Huai-Na Wu, Zhen-Yu Yin Shanghai Jiao Tong University August 5, 2015

Outline Metro Tunnel in Guangzhou Georisks and Construction Problems Recommended Solutions Summary 2

Metro Tunnel in China 6100 1011 1471 1699 2058 2518 2886 2009 2010 2011 2012 2013 2014 2020 20 21 5 In Operation Under Construction In Planning 3

Metro Tunnel in Guangzhou 9 lines 164 stations 260.5 km (before 2015) 17 lines 677 km (2020) 4

Metro Tunnel in Guangzhou Guangzhou Geological museum : Sand Clay Rock Solitary stones Ground Water Karst Fault N 0 50km 100km Guangzhou Guangdong Province Karst caves 5

Metro Tunnel in Guangzhou Geological section: from Maanshan station to Liantangnan station Maanshan Station Sand 155m rock 53m Karst 711m upper-soft-lower-hard strata 666 m Liantangnan Station sand 299m 98 karst caves were found along the tunnel. 6

Georisks and Construction Problems Shanghai Metro line 4 Collapsed ground Pumping station constructed in 2002 Ground collapse Building destruction 7

Georisks and Construction Problems Cutter wear Foam slurry spout out 6m Photted during the tunneling of Ma-Lian section 8

Georisks and Construction Problems Surface Collapse Tunneling in Mixed Ground Cutter Wear Upper-soft (clay or sand)-lower-hard (limestone) strata and karst 9

Recommended Solutions Karst treatment Tunneling in upper-soft-lowerhard strata Tunneling in karst Cutter treatment 10

Recommended Solutions Karst cave treatment: Survey Determination Treatment Effect inspection Geological Drilling Number Sleeve-valve-pipe grouting Other grouting methods Unconfined compressive strength (> 0.2 MPa) Rayleigh wave CT Location Filling Determine the location Drilling OR Standard penetration test blow count (>18) Geological radar Treatment or not Install the grouting pipe Grouting Preparing slurry Hole sealing 11

Recommended Solutions Grouting steps 12

Recommended Solutions Tunneling in Upper-soft-lower-hard Strata Volume of excavated soil Penetration rate Excavated soil sample Tail grouting pressure Immediate analysis and cutter inspection 13

Recommended Solutions Tunneling in Caved Karst Strata: 1 2 3 The head of TBM remained raised to increase the lower jacking force and decrease the upper jacking force. The screw was shut up to slowly drain the water. Control the earth pressure to drain water and reduce excavated soil. 14

Recommended Solutions Cutter Replacement (Ma-Lian Section): Technique Ground improvement Chamber filling Preparation time (day) 2-3 7-10 Ground condition Thin sand within the excavation face; cutter can go back Cavity in the excavation face; cutter cannot be rolled; confined water pressure Advantage Time-efficiency Stable excavation face after filling; Less disturbance on ground without disk rolling Disadvantage Unavailable when the cutter is heavily damaged Re-filling is needs once there is water leakage; disk cannot be rolled 15

Recommended Solutions Cutter Replacement: Save pressure 阴影部分的面积为刀 具接触岩面的面积 S Photoed during the tunnelling of Ma-Lian section 16

Summary 1) Problems were encountered during tunneling excavation, such as karst treatment, tunneling in upper-soft-lower-hard strata, tunneling in caved karst strata, and cutter replacement. Recommended solutions are presented. 2) To make sure that the TBM could successfully pass through the caved karst strata, karst caves were explored and judged. Slurry grouting method was utilized to deal with karst caves. 3) The volume of excavated soil sample, penetration rate, tail grouting pressure, immediate analysis and cutter inspection should be controlled during tunneling in upper-soft-lower-hard strata. 4) The jacking force, screw and earth pressure should be controlled during tunneling in caved karst strata. 5) Ground improvement of grouting and chamber filling method were presented for the cutter replacement.. 17

18