GRAVITY CIRCUIT Knelson Performance, Maintenance, Back to Basics. Drissa ARAMA, Plant Manager

Similar documents
Improvements in bi-metal production at the Brunswick plant, Costerfield.

COMMINUTION CIRCUIT OPTIMISATION

High pressure grinding rolls applications for the platinum industry

Integration and Optimisation of Blasting, Crushing and Grinding at the Newmont Ahafo Operation

RESOURCE GOLD PTY. LTD.

Evaluation of Grade Engineering using Enterprise Optimization. Michael Scott, Nick Redwood

CIP/CIL Modelling. Theory and Application. Tyler Crary, SGS Canada. October 20, Presented By: Chad Czerny, SGS Australia

Forward Looking Statement

For personal use only

Copyright in this document is wholly reserved to Ausenco Services Pty Ltd.

Report No. A13575 Part 5

Awak Mas DFS Optimisation - Metallurgical Breakthrough

Development and Implementation of the new 2240 kw (3000 HP) VERTIMILL Grinding Mill for Newcrest

Bertil Norén. Processing Manager, Björkdalsgruvan. Euromine Expo, Skellefteå June 15, 2016

TAKING CONTROL OF THE MILL FEED: CASE STUDY - PARTIAL SECONDARY CRUSHING MT RAWDON. Brian Putland, Bernie Siddall and Andrew Gunstone

VertiMill Performance Updates in Secondary and Regrind Duties at Cannington Mine, BHP-B

Cadia Expansion The Impact of Installing High Pressure Grinding Rolls Prior to a Semi-Autogenous Grinding Mill

Increasing Grinding Circuit Robustness with Advanced Process Control

RE: REVIEW OF THE PRAIRIE CREEK MINE SCOPING STUDY

MILLING CONTROL & OPTIMISATION

49. MASS BALANCING AND DATA RECONCILIATION EXAMPLES

THE FUTURE OF DIAMOND LIBERATION AND RECOVERY 2012 PPM

FLOTATION CONTROL & OPTIMISATION

Olympias: Highlights Q Phase 1 Retreatment. Acquired from European Goldfields in February. EIA approved. Phase 1 Retreatment began

Resource Efficient Mining Processes of Tomorrow

SUBMITTED BY. The Morrell Method Sub-Committee of the Industrial Comminution Efficiency Working Group VERSION DATE. 21 Aug 2015 APPROVED BY

STARVED ACID LEACH TECHNOLOGY (SALT) CONCEPTUAL STUDY. InCoR Holdings Plc MINING AND METALLURGY. April 2014 REPORT Rev. 00 > Internal ref.

Hycroft Oxidation Pilot Plant Overview

Mobile processing plant to reinvigorate small

System-50 Material Flow

Primary size reduction with jaw crushers

COPPER PRECIPITATION AND CYANIDE RECOVERY PILOT TESTING FOR THE NEWMONT YANACOCHA PROJECT

Metallurgical Plant Design and Operating Strategies Conference Perth, March 2006

Massawa gold project January 2016

QNI uses the OSIsoft PI System to control refinery operations and gain 41 percent IRR in 3.5 years

IsaMill Design Improvements and Operational Performance at Anglo Platinum

OCEANAGOLD PROVIDES AN UPDATE TO HAILE COMMISSIONING AND REVISED COMPANY GUIDANCE

#287 FOOD GRADE FLUSHING AGENT

The materials used herein and this presentation (collectively, the Presentation ) have been prepared by PT Agincourt Resources (the Company ) solely

An Overview of the HPGR and Fine Grinding Technologies to Characterize Ore Grindability

ABM Hits 3000 Ounce Target from Trial Mining

EINRIP. Specification and Construction Issues

Mt Morgans Australia s next 200kozpa gold producer

Outotec OreMet Optimizer

BIENVENIDOS / WELCOME

SAGDesign TM Using Open Technology for Mill Design and Performance Assessments

19 th Zinc and its Markets Seminar May 4 th 6 th, 2015 Radisson Blu Royal Hotel, Helsinki, Finland. Welcome address. Robin Lindahl

ELG Mine Ramp-Up David Alduenda & Bernie Loyer

HEAP LEACHING TECHNOLOGY Moving the frontier for treatment

KINROSS GOLD CORPORATION Tasiast analyst & investor tour: Developing a world-class mine

NEWMONT USA AND DERRICK CORPORATION COLLABORATE ON TECHNOLOGICAL ADVANCEMENTS OF SCREEN SURFACE TECHNOLOGY IN GOLD PROCESSING PLANTS

The Latest Developments in Iron Ore Processing

Energy Conservation Preventive Maintenance

Mining. Simulation of the Mineração Serra Grande Industrial Grinding Circuit. Mineração. Abstract. 1. Introduction. Thiago Oliveira Nunan

A CASE STUDY ON THE OPERATION OF A FLOTTWEG TRICANTER CENTRIFUGE FOR SOLVENT-EXTRACTION CRUD TREATMENT AT BWANA MKUBWA, NDOLA, ZAMBIA

23 July Half-Year Trading Update Petropavlovsk PLC ( Petropavlovsk, the Company or, together with its subsidiaries excluding IRC Limited

Introduction to Cyanide Gold Mining. ORCR USEPA July 2012

HEAP LEACHING OF LOW GRADE URANIUM ORES AT SOMAIR

Banfora (Wahgnion) Project Feasibility Study Optimization and De-risking

PRELIMINARY OXIDE HEAP LEACH TESTWORK DELIVERS EXCELLENT RESULTS AT THE SOUTH HOUNDÉ PROJECT

Laboratory Investigations of the Electrical Resistivity of Cokes and Smelting Charge for Optimizing Operation in Large Ferrochrome Furnaces

NEW LIFE OF MINE PLAN AT MRC BOOSTS GOLD PRODUCTION ABOVE 200,000 OZS. Canadian dollars unless otherwise noted

SAG MILL GRINDING DESIGN VERSUS GEOMETALLURGY GETTING IT RIGHT FOR COMPETENT ORES

OSISKO REPORTS INCREASED GOLD RECOVERY RESULTS AT MARBAN

ArcelorMittal, Canada

SCREENBOX RANGE SYSTEMS WASHING TECHNICAL SPECIFICATION FEATURES

TONGON GOLD MINE TONGON TOTAL MINERAL RESOURCES AND ORE RESERVES1 TONGON PRODUCTION AND FIVE YEAR FORECAST. Moz. Resources.

Yanfolila DFS Significantly Increases NPV & IRR

Indonesia s Next World Class Mining Company

2013 PROJECT REPORT FOR METALLURGICAL TESTING ON THE SAN ALBINO PROJECT

OPTIMISATION AND CONTINUOUS IMPROVEMENT OF ANTAMINA COMMINUTION CIRCUIT

Quebrada Blanca Phase 2. April 2012

PI Alchemy Turning data into Gold

Industrial IT : Optimization for the Cement Industry

Flotation cplant: an Optimum Modular Approach

HELLENIC COPPER MINES LTD. History of the Company

CMS, FDA and AAMI Requirements for Bicarbonate Systems Made Simple. Compiled January 2012 by AmeriWater Incorporated

Comparative Evaluation of Thickened versus Slurry Tailings Surface Disposal D. Johnson Golder Associates Ltd., Canada R. Moghaddam Golder Associates

Drilling, metallurgical test work and a new resource model add 21% to oxide gold reserves

F L I P F L O W W S C R E E N S

New mill grinds down costs and boosts efficiency at Savage River

Alternative Models for the Calculation of CAPEX and OPEX for a Hydrometallurgical Plant

Minerals. WARMAN Centrifugal Slurry Pumps WBV Vertical Cantilever Slurry Sump Pump Series

White Dam Gold Project Dump Leach

PDAC 2015 MDM METALLURGICAL INNOVATION UNLOCKS CLIENT PROJECT VALUE. Listening with Care. Designing with Purpose. Delivering beyond Expectation.

Capacity Enhancement and Energy Conservation in Cement Plant

INVESTIGATION OF SORTING TECHNOLOGY TO REMOVE HARD PEBBLES AND RECOVER COPPER BEARING ROCKS FROM AN AUTOGENOUS MILLING CIRCUIT

TA SIAST. A responsible mining operator in Mauritania

BARRICK GOLD CORPORATION Denver Gold Forum Alto Chicama Update September Denver Gold Forum September 24, 2003

Pelletizing technologies for iron ore

STACK SIZER TM. Patented Technology. The highest capacity, most efficient, fine wet screening machine in the world

At Home in North America

Comparison of grinding media Cylpebs versus balls

Effect of Water Composition on Flotation of Lead and Zinc Sulphide Ore

PROCESS AND ASSET MONITORING AT A PGM CONCENTRATOR FOR UG2 CONCENTRATE

Dry Stacking Operation at Pogo Mine, Alaska June 12, Sumitomo Metal Mining Pogo LLC

Macraes Operation Analyst Site Visit Presentation. 16 March 2015

Recent Developments in Copper Hydrometallurgy

TOTAL WATER MANAGEMENT IN THE STEEL INDUSTRY. By N. Ramachandran, Ion Exchange (India) Ltd

Fine grinding, a refresher. *A.G. Doll 1

Transcription:

GRAVITY CIRCUIT Knelson Performance, Maintenance, Back to Basics Drissa ARAMA, Plant Manager

Morila Mine locality

Data for the record Commissioning Oct 2000 Official opening Feb 2001 First bullion bar poured was gravity gold Highest production record 1,052 koz in 2002 of which 337.4 koz was from gravity Average feed grade in 2002 14.14 g/t Plant upgrade 2004 Randgold took over Morila operation Management in Feb 2008

Metallurgical process Oxide Crusher SAG Mill Ball Mill Classification Thickening Sulphide Crusher Primary & Secondary Recycle Crusher Gravity Recovery BWI 16 kwh/t Throughput 520 tph Avail. 91.8 % Recovery Oxide 96 % Sulphide 92 % CIL Tailings 40% Elution Electrowinning 60% Gravity Gold CIL Gold

Metallurgy - process flow Oxide Gravity Gold 25.4% Oxide CIL Gold 95% Oxide overall Gold 96.6% Oxide Ore 10 g/t Sulphide Ore 4.3 g/t Crushing SAG & Ball Milling & Gravity Carbon in Leach & Elution Tailings Storage Facility Sulphide Gravity Gold 40% Sulphide CIL Gold 87.0% Sulphide overall Gold 92%

Metallurgy - Knelson concentration 3xKnelson Concentrator KC XD48 G5 cone 450 t/hr Crushed Slag NaCN Lime Table Feed Tank By-pass concentrate to ILR Reactor Feed Tank H 2 O 2 Reagent Pot Gemini Table Gold for direct smelting Sump Table middlings & tails Reactor Drum 250 kg/h

Key production statistics Parameters Design data After upgrade Throughput rate 400 tph 520 tph Monthly capacity 250,000 t 350,000 t Head grade - oxide ore 10 g/t Head grade - sulphide ore 4.3 g/t 3.1 g/t Gravity recovery 40% 40% Leach circuit recovery 87% 87% Overall recovery 92% 92%

Production overview Head Grade (Au, g/t) Total Gold Produced (kg) Total Gold Produced (ounce) Gravity Gold (%) Gravity Gold (kg) 2000 * 10.71 4,446 142,942 57.9 2,389 2001 7.44 19,647 631,650 39.05 7,643 2002 14.14 32,746 1,052,816 32.05 10,495 2003 7.98 24,750 795,716 34.16 8,453 2004 5.16 15,896 511,077 24.61 3,912 2005 5.75 20,252 651,117 25.61 5,187 2006 4.18 16,070 516,666 28.45 4,571 2007 3.88 13,991 449,817 21.27 2,975 2008 3.51 8,750 281,319 31.40 2,759

Recovery - Gravity vs Overall 60 95 50 40 30 20 93 91 89 10 2000 2001 2002 2003 2004 2005 2006 2007 Jan-08 Feb-08 Gravity recovery (%) Overall plant recovery (%) 87

BACK TO BASICS MAINTENANCE

Finding and remedial actions KNELSON OPERATION

Operation Knelson feed PARAMETRES PREVIOUS CURRENT Panel screen size Combination of 2.0 and 4.0 mm Panel 2.0 mm N o of cyclone U/F to gravity 03 02 (Targeting 03) N o of KC- on line 03 03 Screen Feed Channeling Spray bars (Water pressure) 20% short-cut in oversize due to eccentric feed 02 x separate bars; 10 % short-cut in oversize 10 % short-cut in oversize due to central feed Equalized pressure: 5 % short-cut in oversize Screen Capacity 3 cyclones to KC 2 cyclones (Planned to Install Double Deck Screen for more cyclone)

Operation steel balls scats in concentrate Chinese Ball! Impact Gold Recovery

Finding and remedial actions MAINTENANCE UNIT STATUS

Maintenance leaking water around holding bolts

Maintenance silt holes

Finding and remedial actions OPERATING PARAMETERS

Machine setpoints flow Parameter Concentration flow Intermediate flow - Low flow Purge flow Setpoint 160 120 USGPM 40 USGPM 200 USGPM Positive pressure 2 psia Incorrect fluidising water pressure = Poor recovery

Machine setpoints timers Parameter Feed off delay Drain time Purge time Positive pressure delay Setpoint 5 seconds 40 seconds 30 seconds 300 seconds Knelson total purge time reduced from 360 sec to 250 sec = increased Knelson running time

Machine setpoints pressure Parameter Operating pressure - Hi alarm Operating pressure - Hi shutdown Operating pressure - Lo alarm Operating pressure - Lo shutdown Setpoint 38 psia 44 psia 14.5 psia 13.8 psia*

Utilisation Utilisation takes motor-off flush time into account, but: Feed off delay = 5 sec Ramp down = 135 sec Drain #1 = 40 sec Purge = 30 sec Drain #2 = 40 sec Total = 250 seconds Then ideally, UTILISATION = ((3600-250)/3600)X100 = 93.05% Daily running time = 22.3hours

Other soft issues TURNED OVER New Engineering staff Alarmed override POOR SUPERVISION & SKILLS LEVEL Inspection/Cleaning Motivation COST SAVING Cone (Heart of the machines) leave for longer period TRAINING ON UNIT MAINTENANCE Back to Basics Reset all Set Points Re-effect passwords TRAINING ON UNIT OPERATION Back to Basics New Supervisor IMMEDIATE REPLACEMENT OF WEAR CONE Interlock between the mills and the Knelson

Performance GRG vs grade % 70 60 50 40 30 20 10 0 GRG (%) Theoritical GRG (%) Plant Head (Au, g/t) High Grade 16 14 12 10 8 6 4 2 0 Au, g/t

Performance GRG vs recovery 70 60 93 50 40 91 30 20 89 10 0 87 Gravity recovery (%) Overall recovery (%)

Basic maintenance LUBRICATION : Correctly and on schedule as per planned maintenance schedule Bearing caps need greasing every 2 days Rotary Union needs greasing every week Bearings need greasing every 6 months Do NOT grease these items randomly and all at once. Only grease them when the rotor is turning and bearings are warm SILT EJECTION HOLES : Check (daily) and clean WATER STRAINER : Check (weekly) and clean CONCENTRATING CONES : Remove and clean as required (regular) REPLACE CONE : as required

Best practice cones cleaning Concentrating cones Monthly concentrating cone schedule by the operation Engineering staff to check and confirm if the cone is cleaned before to reinstall it Regular measurement of the cone wear Cone cleaning process Cleaned concentrating cone

Constraints KNELSON UNITS LOCATED IN CONFINED PLACE WITHIN THE GOLD ROOM Arrange simpler access CONTROL PANEL IS A STAND ALONE UNIT Integrate to SCADA or SEPARATE PC

Conclusion In summary apart from having good Gravity recovery (2000-2003) the Morila Gravity Circuit performance dipped (2004-2008) as a result of: Poor Supervision and Control on the units Poor engineering and operation practice Maintenance not as per KNELSON recommendation New Engineering staff not familiar with the UNITS Lack of training Lack of regular communication between Morila mine and Knelson Gravity Solutions

Continuous improvement BACK TO BASICS Operation & Maintenance TRAINING MODULES for new personnel including refresher training Re-enforce supervision, Zero Tolerance to deviations Technical staff to conduct PTO s on KC units Initiate Auto Flush

Continuous improvement Ensure all SETTINGS are correct Investigate additional FEED to GRAVITY CIRCUIT Overall utilization > 82%, if not investigate Target more >35% GRAVITY RECOVERY

Merci Beaucoup