PIANC UK Seminar Design Developments and Specification for Steel. Duncan Nicholson Arup Fellow 9/3/17 ICE London

Similar documents
Materials Services Infrastructure. Global expertise for infrastructure projects.

SCREW PILE APPLICATION SHEETS

Minimum Guidelines for the Design and Use of Underpins When Performing Foundation Stabilization and/or Supplementation UP-08

Temporary Structures. Cofferdams TOKYO INSTITUTE OF TECHNOLOGY ATCE-II ADVANCED TOPICS IN CIVIL ENGINEERING DEPARTMENT OF CIVIL ENGINEERING

Combined Pile Foundation System for a Residential Complex

Schnabel Foundation Company

DESIGN AND INSTALLATION OF THE SHORING AND DECKING FOR TTC YONGE STATION

SEMINAR. Introduction to Continuous Flight Auger (CFA) piling Thursday 21/8/2013. Facilitator: Martin Larisch

SCOPE OF WORK FOR PILING JOB

Temporary Shoring. Specifications, Applications, & Best Practices. Stephen M. (Matt) Revell, P.E. Assistant Geotechnical Engineer

Diaphragm wall Construction

UNDERPINNING A CRANE FOUNDATION

Topic: Site Formation

SPECIAL CONDITIONS FOR PIPE JACKING (PJ) October, 2006

Silent Vibrationless. Technology. teel Sheet Piles. Vinyl Piling. etaining Walls. Piles. tory Piling. oundations. ite Piles. n Free Piling.

TRENCHLESS CONSTRUCTION (BORING, JACKING, AND TUNNELING)

Trench Sheeting CONSTRUCTION

The Technical and Contractual Matters of Bored Piling Works. By Wallace Yeung Vibro (H.K.) Ltd.

Oweninny Wind Farm. Oweninny Environmental Impact Statement Appendix 5. Turbine Foundation Construction Method Statement

Development of the Combi-Gyro Method, a New Steel Wall Construction Method Combining Steel Sheet Piles and Pipe Piles

MGF TECHNICAL FILE SHEET PILES. Description. Product Notes.

Pipe Jacking/Microtunnelling. Dr. Mark Knight. Centre for Advancement of Trenchless Technologies (CATT) University of Waterloo.

Anchor bolts ASTM F1554, Gr. 36 Wide flange beams ASTM A992, Fy = 50 ksi Misc. structural steel ASTM A36, Fy = 36 ksi

Attachment D-1: Civil/Structural Scope of Work

1. Introduction Selection of Pile Type Soil Report / Boreholes Obstructions Design and Installation of Piling Mat 3

USE OF DIPP PILES FOR A NEW SUP BRIDGE IN WEST MELBOURNE

+ PPV FINLAND. Drilling Interlocked O-Pile Walls with DTH

1. All underground utilities under railroad tracks shall be encased in a larger pipe or conduit called the casing pipe.

STANDARD SPECIFICATIONS SECTION TUNNELING. A. Section includes requirements for constructing tunnels 48-inch and larger diameter.

Sheet Pile Retaining Walls Design and Construction in a Brown Fields Environment

Wet Speed-Mixing WSM - Soil Mixing Procedure in Twinmix Design

A DSM WALL FOR EXCAVATION SUPPORT

TRENCHLESS INSTALLATION OF ROAD DRAINAGE & SERVICE DUCTS

STANDARD SPECIFICATIONS SECTION BORING AND JACKING. A. Section includes requirements for boring and jacking casing pipe.

Marina Bay Sands Hotel Arch 631 Kayla Brittany Maria Michelle

Features. A Wide Selection of Shapes and Types. Superb Drivability and Water tightness

Construction Planning, Equipment, and Methods PILES AND PILE-DRIVING EQUIPMENT

TYPICAL INSTALLATION INSTRUCTIONS

ROTARY DRILLING TECHNIQUES LARGE DIAMETER

SPECIFICATION : BORING AND JACKING

INNOVATIVE SLOPE STABILISATION BY USING ISCHEBECK TITAN SOIL NAILS

Soil Mechanics Lateral Earth Pressures page Lateral Earth Pressures in case of inclined ground surface or friction at wall-ground interface

SECTION TRENCHLESS INSTALLATION

Piling & Contaminated Land. Dr Derek Egan Technical Director Keller Ltd

Lesson 4. Construction Techniques and Materials. Learning Outcomes. Basic Construction

Secoroc Rock Drilling Tools CASING ADVANCEMENT SYSTEMS

Steven Dapp, Ph.D., P.E. Steven Dapp, Ph.D., P.E. Dan Brown and Associates

CONSTRUCTION METHOD FOR CCSP AND REVETMENT

Hollowcore Floors. The ideal structural floor solution for all building types in all sectors.

CROSSRAIL INFORMATION PAPER D8 TUNNEL CONSTRUCTON METHODOLOGY

SPECIFICATION FOR REINFORCED SOIL WALL

CW 3615 RIPRAP TABLE OF CONTENTS

DFI DEEP FOUNDATIONS. Brazil s Megaproject Shipyard Winner of the 2010 Outstanding Project of the Year

METHOD STATEMENT for INSTALLATION OF MICROPILE

Design and Construction of Drilled Full Displacement Piles using the Penetration Resistance Method

Chapter A-8 GEOTECHNICAL ANALYSIS FAIRFAX-JERSEY CREEK (JERSEY CREEK SHEET PILE WALL)

Aveng Ground Engineering Profile

SECTION FACILITY SANITARY SEWERS

STRUCTURAL MASONRY SPECIAL INSPECTOR. Study Guide

SPECIAL SPECIFICATION 4900 Sacrificial Cathodic Protection Pile Jacket

SECTION 19 - TRENCH EXCAVATION, BEDDING AND BACKFILL TABLE OF CONTENTS

PASSAIC COUNTY TECHNICAL INSTITUTE CCA 1422 NEW S.T.E.M. BUILDING 2017

Houston Community College 3200 Main Parking Garage November 15, 2010 Houston Community College

Ground Improvement Piling Piled Retaining Walls Enlarged Head Piles Innovations.

1. Decks, balconies, and sun porches 2. Walkways, ramps, and stairways 3. Patios and courtyards

Observations and Performance of a Soil Nail Shoring Wall in Seattle Silts and Clays

Case study on a deep excavation in Baku: Flame Towers project earth retaining system

Structural Tests and Special Inspections Form. Inspection of Fabricators (1704.2)

CF50/100 KW TURBINE ACCESS ROAD, CRANE PLATFORM, CONCRETE, AND LIFTING SPECIFICATIONS C&F GREEN ENERGY REVISION PREPARED BY APPROVED BY DATE

SECTION GRAVEL PACKED WATER WELL

SECTION 19 - TRENCH EXCAVATION, BEDDING AND BACKFILL TABLE OF CONTENTS

water-powered drilling in ground engineering

A. The extent of extruded aluminum walkway covers is shown on the Drawings and as specified herein.

Ground Improvement. Martin G. Taube, P.E., P.G. February 4, 2003

WORK BELOW LOWEST FLOOR FINISH 1/7 230, , , FRAME 2/6 96, , ,056.00

Learning Outcomes. Background Definitions. Lesson 2 & 3. Definitions, Background, Classification, Applications and Costs

Concrete Slab-on-Ground

Project Address: Name of Person Completing Form:

AUGUST 2017 HASTINGS. retaining walls installation guide

CM 420. Lesson 4: Cofferdams. describe cofferdams and when they are used on construction projects;

A Design Review of Waterproofing Codes

There are several types of trenchless technology applications for new installations. The following are some of the most prominent applications.

Case study of deep excavation in existing underground structure of three-story basement and diaphragm wall

Bridge Manual - Part I - June CHAPTER 5 SPECIAL PROVISIONS AND ESTIMATE

Building pit District adjacent to St.Katharinenkirche Hamburg, Germany

SECTION CAST-IN-PLACE CONCRETE

Earth Mechanics, Inc. Geotechnical & Earthquake Engineering

SPECIFICATIONS FOR PRECAST MODULAR BLOCK RETAINING WALL SYSTEM (revised 5/8/7)

REPORT STATUS: DATE: Report n :

STANDARD SPECIFICATIONS SECTION JACKED CASING

Confined masonry. Definition

CONTINUOUS FLIGHT AUGER (CFA) PILES QC/QA PROCEDURES. Preferred QC/QA Procedures

Underpinning This involves deepening an existing foundation or parts of foundation down to firmer ground to create even support for the structure.

SECTION RIPRAP, BOULDERS, AND BEDDING

THE WORLD LOOKS UP TO COMPOSITE ELEVATED TANK

PilePro Group 2017 Product Line Overview

ANALYSIS, DESIGN AND CONSTRUCTION OF TIE-BACK ANCHOR FOR COFFER DAM

Dewatering & Foundations. Water. Low tech

Transcription:

PIANC UK Seminar Design Developments and Specification for Steel Duncan Nicholson Arup Fellow 9/3/17 ICE London

Contents 1. Design Issues 2. SPERWall Edition 3 (2016) 1. Steel Sheet Piles (Section 14) 3. Steel Piling Group 4. Pre-augering examples.

Section B14 Specification Changes B14.1 General Hot rolled piles Cat 2 structures Interlock standards Cold formed Design for buckling etc B14.2 Project Spec Construction tolerances moved to B14.4.4 Water-tightness to basement grades B14.4.4 Pile Installation Tolerances - BS EN 12063;1999 Table 2 - Agree tighter tolerances but cost and practical implications. Built up environment press-in piles B14.4.9 Methods of Assisting Pile Installation Degree of water jetting /pre-augering depends on design assumptions and local sensitive buildings B14.5 Corrosion Consider at design to BS EN 1993-5:2006

Section C14 Guidance Changes C14.1 General U-type sections Clutch slippage on NA - Use NAD to BS EN 1993-5:2006. C14.3.5 Clutch sealant and seal welding Use Accelor Mittal Piling Handbook 2016 Chapter 2. C14.4.4 Pile Installation Panel driving requirements clarified Pile rolling tolerances effect layouts Press-in methods are virtually vibration free. C14.4.9 Methods of Assisting Pile Installation Pre-augering - use in hard ground or to reduce section size. Spoil heap similar to sheet pile volume. Pre-augering should not proceed too far in advance of piling. Where large soil volume removed prove conditions by SPT. Close to structures - Use CFA monitoring equipment to control volume loss. Water jetting can lead to flooding and heave to adjacent foundations. C14.8.1 Combi-walls Essential to have a good pile driving template frame. Drive with extreme care to achieve straightness. Avoid declutching the intermediate piles. C14.8.3 Crush Piling Avoid excessive soil removal to control ground settlement In harder material including weak rocks the soil removal can effect passive response.

Wall tolerances EN12063:1999 Table 2. Limited guidance for Combi-walls

Steel Piling Group www.steelpilinggroup.org The SPG Mission:- Contact John Powell powellj@bre.co.uk for more information.

Work group B SPG - Work Groups Title Description Progress Completion Sustainability Recycling, re-use, embodied energy, environmental impact. Virtually complete Q3 2017 C Innovation Steel Innovative - alternatives to concrete piles. Web page Q3 2017 D Durability Sacrificial steel, ALWC, coatings, cathodic E F protection, new steel grades Current technology and reviews latest plant developments. Plant Development Thermal Piles Use of steel piles for thermal piles and Closed Ground Source Heat Pump (GSHP) systems. Complete Q3 2017 Ist draft Q4 2017 Draft paper Q3 2017 H Tie Rods Standard Piling Details & Tied Wall details Complete Q3 2017 I Ground Pretreatment Particularly pre-augering and water jetting techniques. J Re-use of steel Quality issues to Codes and Standards. piles Link with steel reuse and sustainability. K Case Studies Good selection on line, but need more. Ongoing L High Modulus Walls Now in new Steel Piling Handbook. 1st draft Q4 2017 website See workgroup B New studies online Q3 2017 Reference doc Q3 2017 M Sealants In Steel Piling Handbook Reference doc Q3 2017

Giken Press-in Sheet piles with the Crush pre-augering.

Typical Cofferdam section 11.4 m +5.5mOD Deflection Monitoring Point +4.55mOD +4.5mOD Dock Silt Sand Fill -4.5mOD 13m -6.8mOD -7mOD -7.3mOD Lambeth Group -14.6mOD Thanet Sand -16.0mOD

Giken Press-in piles with Crush pre-auger Auger in enclosed casing Auger in enclosed casing Giken Rig Auger head is approx. 400mm ahead of sheet pile

800mm Auger Details Auger diameter is adjustable Auger teeth set at 800m opening.

CPT tests at crush location Very loose Debris in auger hole. Most of soil flighted to surface. Passive earth pressure support reduced.

Auger void filled with concrete CFA Air lift Option 1 CFA rig used to concrete Crush auger void. Option 2 Debris air-lifted from auger void Tremie concrete placed in void

Deflection (mm) Cofferdam Dewatering Performance Survey targets predicted displacement 230mm Inclinometer

Giken Press-in Tubes with Crush Pre-augering

Tie Back System Marine deck Anchor tie Interlocking Giken tube Silt Terrace gravel Harwich Formation - sand Anchor Piles (3m centres) Contiguous pile (1.05m) drilled through tubes. Thanet Sand Lambeth Beds - clay Lambeth Beds - sand Steel casing

Giken Tubes -1200mm with Crush Pre-augering Crush pre-auger to penetrate harder ground Two Giken rigs - pitching tubes. 95% achieving verticality tolerance of 1 in 150

Dock draining minor seepage Occasional slight seepage Grout sock protruding out of the clutch P-P connection grouted cells

Conclusions on Crossrail Giken interlocking tubes - 1.2m diameter Equipment available to all tenderers Tolerance - Better than +/- 25mm and 1 in 125 verticality Installed through cemented layers Auger worked Good programme Clutches - good water tightness Boring piles used for Crossrail durability Could have been steel?

Conclusions Long History of Steel Piling at Canary Wharf:- Phase 1 Steel Deck Piles (1980 s). Phase 2 to 4 S Pile Cofferdams - Hammers (1990 s). Blackwell Pl. BP1 S Pile Cofferdam Vibrators (2002). Blackwell Pl. BP3/4 S Pile cantilever Vibrators (2005). Riverside Giken Crush S Piles - next to JLE (2008). Crossrail Giken Tubes (2010). Noise and Vibration - now very important:- Wood Wharf Cantilever - Vibration / boring. Bank Street Cofferdam - Giken.

Conclusions on Crossrail Giken interlocking tubes - 1.2m diameter Equipment available to all tenderers Tolerance - Better than +/- 25mm and 1 in 125 verticality Installed through cemented layers Auger worked Good programme Clutches - good water tightness Boring piles used for Crossrail durability Could have been steel?

Conclusions Long History of Steel Piling at Canary Wharf:- Phase 1 Steel Deck Piles (1980 s). Phase 2 to 4 S Pile Cofferdams - Hammers (1990 s). Blackwell Pl. BP1 S Pile Cofferdam Vibrators (2002). Blackwell Pl. BP3/4 S Pile cantilever Vibrators (2005). Riverside Giken Crush S Piles - next to JLE (2008). Crossrail Giken Tubes (2010). Noise and Vibration - now very important:- Wood Wharf Cantilever - Vibration / boring. Bank Street Cofferdam - Giken.

Conclusions Long History of Steel Piling at Canary Wharf:- Phase 1 Steel Deck Piles (1980 s). Phase 2 to 4 S Pile Cofferdams - Hammers (1990 s). Blackwell Pl. BP1 S Pile Cofferdam Vibrators (2002). Blackwell Pl. BP3/4 S Pile cantilever Vibrators (2005). Riverside Giken Crush S Piles - next to JLE (2008). Crossrail Giken Tubes (2010). Noise and Vibration - now very important:- Wood Wharf Cantilever - Vibration / boring. Bank Street Cofferdam - Giken.

Combi-wall within temporary casing Permanent works - ARUP Alternative Combi-wall Desing ByrneLooby Combi-wall Contractor Commercal Marine & Piling Ltd Concrete core piles - BBGE

Combi-wall with temporary casing Spec required push system for adjacent buildings. Dewater to 8m. Calculated Defl. = 0.45m Casings 1.219m dia, 13 to 19mm thick with connectors 1400mm Sheet piles Z Hoesch H1807

Temporary casings Piling gate for temp. casings. Excavate through temp. casing (Hard Calcrete layer) Install permanent casing and fill gap with gravel. Gap allows for tolerance.

Sheetpiles and Permanent Piles Alternative piles extended with permanent RC piles Dewatering. Waling beams added.

Conclusions Permanent works - ARUP Alternative Combi-wall Desing ByrneLooby Combi-wall Contractor Commercal Marine & Piling Ltd Concrete core piles - BBGE

Thank you for your attention Any Questions