Petronet LNG Ltd., India. LNG Terminal Design- Major Design Considerations

Similar documents
B.C. TOWBOAT INDUSTRY CONFERENCE

Natural Gas. and the Liquefaction Process

ELIGIBILITY CRITERIA FOR QUALIFICATION OF EPC CONTRACTORS FOR LNG TERMINAL AT GANGAVARAM, VISAKHAPATNAM, ANDHRA PRADESH (INDIA)

Improving Natural Gas Liquefaction Plant Performance with Process Analyzers

LNG Terminal on the Island of Krk OPEN SEASON PROCESS PAPER BINDING PHASE

PETRONET LNG LIMITED, INDIA Current Activities : Agenda No. 5

1) 2) 3) 4) 5) The oil and gas cycle. Life cycle of oil and gas (time) Potential requirement on ground

AKAKUS OIL OPERATIONS- LIBYA Gas Utilization& Flare Emission Reduction Project

LIQUEFACTION STORAGE DISTRIBUTION BUNKERING SMALL-SCALE LNG SOLUTIONS

Woodfibre LNG Limited Response to SIGTTO LNG Ports and Risk Reduction Options

Teknologi Pemrosesan Gas (TKK 564) Instructor: Dr. Istadi ( )

LNG Plant Overview. Seminar with Supplier Association Murmanshelf Murmansk, 15 May 2012 Jostein Pettersen

Transportation and regasification infrastructures

A World of Solutions Visit Product Storage Terminals for Bulk Liquids

Modern Small-Scale LNG Plant Solutions

OLT Offshore LNG Toscana Alessandro Fino CEO

Processing LNG Offshore: Maximizing Reliability, Performance & Safety. By Inga Bettina Waldmann at KANFA Aragon FLNG World Congress 28 th June 2016

FUGRO GROUP LNG FIELD DEVELOPMENT AND FACILITIES. TACKLING your complex challenges. UNDERSTANDING your operational objectives

STANDARD FOR THE STORAGE AND HANDLING OF LIQUEFIED NATURAL GAS (LNG) OISD STD 194

Estimation of Boil-off-Gas BOG from Refrigerated Vessels in Liquefied Natural Gas Plant

MLNG DUA DEBOTTLENECKING PROJECT

Appendix A: Project Characteristics

Introduction to the Safe Design of LNG, CNG and Hydrogen Refueling Stations

COMPLETING THE LNG VALUE CHAIN

MOLECULAR GATE TECHNOLOGY FOR (SMALLER SCALE) LNG PRETREATMENT

LCNG-LNG refuelling stations LNG AS A FUEL FOR VEHICLES.

Floating storage and regasification barges

Alaska South Central LNG (SCLNG) Project

Liquefied natural gas

Pivotal LNG Natural Gas Fuel for Heavy Duty Trucks. David Jaskolski Senior Account Manager

Gas Access To Europe

We deliver gas infrastructure

Braemar Technical Services

Marine Transportation of LNG. Intertanko Conference March 29, 2004 Bob Curt Ship Acquisition Manager, QatargasII Development

LARGE STORAGE TANK PROJECT

Enabling safe and reliable offshore LNG transfer operations By Vincent Lagarrigue, Marketing & Project Manager within Trelleborg Industrial Solutions

Optimising. the LNG process. The rapidly expanding global LNG industry continues. Projects

PART 3 TERMINAL INFORMATION

Capabilities in LNG

Ministry of Energy and Water Government of Lebanon

CoTE Presentation LNG to Power Stornoway s Renard Mine Canada LNG Export 2015 May 19, 2015

Environmental, Health, and Safety Guidelines for Liquefied Natural Gas (LNG) Facilities

Energy East Pipeline. Project Overview. Kevin Maloney Manager, New Build Pipeline AB, NB, JV Irving and Cromer September, 2014

MOLAS APPLICATION. GERG Project 1.59

Offshore Oil Exploration: Probabilistic Simulations of Plume Dispersion and Potential Impacts on Beaches

LNG Facts A Primer. Presentation before US Department of Energy, Office of Fossil Energy, LNG Forums. March 10, Kristi A. R.

Cryobox-Bio. Biomethane upgrading and liquefaction nano station. & Virtual Pipeline

Marine Protection Rules Part 100 Port Reception Facilities Oil, Noxious Liquid Substances and Garbage

Waarom moeilijk doen als het makkelijk(er) kan

Evolution of an LNG Terminal: Senboku Terminal of Osaka Gas

TEMA LIQUEFIED NATURAL GAS PROJECT ENVIRONMENTAL AND SOCIAL IMPACT ASSESSMENT

Till date, Rotary has built more than 60% of independent storage tanks in Singapore.

Project Overview. Northwest Innovation Works LLC and the Port of Kalama propose to develop and operate

Magnetically Coupled Submerged Cryogenic Pumps and Expanders for Ammonia Applications

Floating LNG: The Challenges of production systems and well fluids management By: Frederic MOLLARD, TECHNIP France 04/19/2013

Conceptual Design of CO 2 Transportation System for CCS

Natural Gas STAR Methane Challenge Program: Supplementary Technical Information for ONE Future Commitment Option

2 COWI expertise. Spudcan analysis for jack-up Power systems and SCADA Risk analyses. COWI - quality - schedule - cost. Worldwide experience

MARINE POLLUTION DEGRADATION MITIGATION MANAGEMENT IS ESSENTIAL FOR IMPROVING MARINE ENVIRONMENT

Gorgon Project Update: Selected Images

Appendix A. Project Description

ADVANCED PROCESS CONTROL QATAR GAS ONE YEAR EXPERIENCE

LNG storage: a growth story? StocExpo Rotterdam commercial manager

ON LIQUEFIED NATURAL GAS (LNG 17) 17 th INTERNATIONAL CONFERENCE & EXHIBITION ON LIQUEFIED NATURAL GAS (LNG 17)

Saudi Aramco General Bid Slates (GBS)

SPE DISTINGUISHED LECTURER SERIES is funded principally through a grant of the SPE FOUNDATION

3 rd LNG SUPPLY, STORAGE AND TRANSPORTATION PHILLIPINES FORUM 2016 SMX AURA, MANILA

DECLARATION OF INSPECTION

Stratus Development in Joint Venture with Middle East Petroleum Services (Offshore) SAL

LNG AGEING DURING SHIP TRANSPORTATION

Thomas G. Braga Manager, Research and Development. SulfaTreat, a Business Unit of M I L.L.C. A Smith/Schlumberger Company

INCREASING THE CAPACITY OF NGL RECOVERY TRAINS. Stéphane MESPOULHES XVI CONVENCIÓN INTERNACIONAL DE GAS Caracas de Mayo de 2004

Chemistry of Petrochemical Processes

BOIL-OFF GAS MANAGEMENT LNG TERMINAL TECHNOLOGIES

SMALL LNG SOLUTIONS FOR INDONESIA

GNL Mejillones, GenCo oriented

Objectives. Emerging Risks Response Awareness Training. Liquefied Natural Gas

Alaska LNG Concept Information. Alaska LNG. Overview. October

ZEEBRUGGE LNG TERMINAL: FROM REGAS TERMINAL TO VERITABLE LNG HUB IN NORTH-WESTERN EUROPE

Natural Gas Processing

OFF-THE-SHELF MID-SMALL-MINI-SCALE LNG PLANT CASE STUDYFOR APPLICATION

UNIQUE DESIGN CHALLENGES IN THE AUX SABLE NGL RECOVERY PLANT

REFRIGERATION CYCLES

Transactions on Ecology and the Environment vol 14, 1997 WIT Press, ISSN

Conversion table working groups Name working group Old number New number Conception des barrages mobiles et de barriers anti-tempêtes PIANC WG 101

Port and Harbour Monitoring Systems

40 YEARS OF MARINE OPERATIONS & ENGINEERING IN HAWAII. Makai Research Pier, Waimanalo, Hawaii. 863 N. Nimitz Hwy, Honolulu Harbor

GROWTH OF LNG GAS MARKET AS ALTERNATIVE FUEL IN TRANSPORT

OUR CONVERSATION TODAY

DR. CHARLES ELLINAS Executive President. Frederick University, 19 September 2013

Baseload LNG Production in Stavanger

LNG IMPORT TERMINALS RECENT DEVELOPMENTS

Summary Report - Terminal 2 (T2) Trade-Off Process and Outputs Container Capacity Improvement Program

Floating LNG Business A breakthrough in offshore gas monetization

LNG bunkering Why, How and When. Nigel Draffin Technical Manager LQM Petroleum Services Inc.

DESIGN ANALYSIS OF A REFRIGERATED WAREHOUSE USING LNG COLD ENERGY

New York State Offshore Wind Master Plan. October 20, 2017

CALL FOR MARKET INTEREST NOTICE

Transcription:

Petronet LNG Ltd., India LNG Terminal Design- Major Design Considerations

OVERVIEW 1. What is LNG and LNG Chain 2. Project Development & Site Selection 3. Studies Required 4. Marine Facilities 5. Storage Tanks 6. Regasification & Sendout 7. Terminal Layout 8. New Development

What is LNG?

Liquefied Natural Gas (LNG) LNG is a natural gas that has been cooled to the point that it condenses to a liquid, which occurs at a temperature of approximately -162 C at atmospheric pressure. Liquefaction reduces the volume of gas by approximately 600 times thus making it more economical to store natural gas, and transport gas over long distances for which pipelines are either too expensive or not feasible. Thus, LNG technology makes natural gas available throughout the world. LNG is a cold, transparent, odorless, non-corrosive, non-toxic and has low viscosity. LNG is safer than other liquid fuels. Typical LNG composition are as below: Methane [CH4] 82.0% - 94.0% Inert Nitrogen Gas [N2] Trace Ethane [C2H6] 3.0% 6.0% Carbon Dioxide [CO2] NIL Propane [C3H8] 0.1% - 2.0% Oxygen [O2] Trace Butane [C4H10] 0.1% 0.7% Hydrocarbon Liquids & Water NIL Pentane [C5H12] Trace Sulphur [S] 10 ppm of H2S and not more than 15 ppm of total sulphur Hexane-plus [C6H14+] Trace Gross Heating Value: Not less than (35.39 MJ/scm)

PROJECT DEVELOPMENT AND SITE SELECTION

Typical Design Steps & Studies Required Pre-feasibility Feasibility study BEP : Basic Engineering Package FEED : Front End Engineering Design RFP : Request for Proposal and Bids Evaluation EPC (Engineering Purchase and Construction) award Detailed Engineering, Purchase and Construction Commissioning and delivery

Typical project schedule : 60 months (5 years) S No. Description Time (Months) 1 Pre feasibility (Market Data) & Detailed feasibility Studies 6 to 9 2 Front End Engineering Design 6 to 8 3 4 5 Request for proposal and bid evaluation 4 to 6 Engineering, procurement, and construction (Storage Tanks) 36 to 42 Commissioning and delivery performance tests) 2 to 6

8 Schedule

PROJECT DEVELOPMENT AND SITE SELECTION Need of LNG terminal Project identification and formulation Feasibility studies to analyse the technical, environmental, commercial and marketing factors Site - Permitting conditions

ECONOMICS OF LNG IMPORT FACILITIES FOR NEW GAS MARKETS Sufficient demand for gas for next 15-20 years Pipelines alternatives impractical High load factor LNG imports Government policy Suitable import site Avail infrastructure for gas distribution

SITE SELECTION Suitable Port Land Availability & Soil Condition Consumer Infrastructure Gas Pippeline Water Power Present and future availability of gas Nearby center of population

Soil STUDIES REQUIREMENT-SITE SELECTION Type of soil Extent of soil filling required Availability of soil Type of storage tanks Marine facilities Requirement of breakwater Type of breakwater (island type, shore based) Length & No. of breakwater Length of Jetty Trestle Local Environment Weather Condition Heavy Monsoon High Wind speed

FEASIBILITY & RANKING OF SITES Eliminate obviously unsuitable sites Compare suitability of met-oceanic and land parameters Define typical feature and estimate costs Evaluate Opex Rank sites in cost-risk terms Revisit best site: plan plant layout & berth

KEY FACTORS GOVERNED BY SITE DATA Navigation of LNG tankers & turn around times Construction schedule Safety and security of operation Expandability of design Regas methodology Method of power generation Air Emissions & water quality Pipeline route feasibiltiy Perception of safety (to Population)

ENGINEERING STUDIES DURING THE CONCEPTUALIZATION STAGE

LIST OF INVESTIGATIONS & STUDIES REQUIRED Investigations Physical features Influence on Design Bathymetry & Tidal Survey Side Scan Sonar Sea bed levels/ Water depth, tidal variation, Low, Mean & High tidal levels Profile, obstacles, wrecks. Approach of ship Location & Level of jetty head Wreck Removal Requirement Meteorological Investigations Marine Geotechnical Investigations Wind, Currents & Waves - frequency distribution of wind/ current speed/ wave height/, direction & wave period Storm surge, Past storm track, storm surge Geology & Subsoil properties Seismic sounding of subsoil strata Orientation of facilities Need for Breakwater Structural design Mooring Requirements Input to model studies Design of port structures and Assess need of geotextile

LIST OF INVESTIGATIONS & STUDIES REQUIRED Investigations Analysis of water Properties Environmental impact Study Physical features Physical chemistry of the water Salinity Pollution Turbidity Marine fauna and flora Coastline Influence on Design Assessment of suitability of Open Rack Vaporizers Assessment of Sedimentation in port area Design of ship Ballast Management System Design of Cathodic Protection System Effect of port construction & operation activities on aquatic species, mangroves etc. Interference with fishing Impact of works on beach, historic sites and Monuments

HYDRAULIC MODEL STUDIES Prediction of changes Movement of water & its effect on ships. Movement of soil & its effect on navigation areas. Effect of Marine environment on stability and safety of structures. Design Optimization Maintenance cost.

HYDRAULIC MODEL STUDIES Mathematical Model Studies Investigate the flow pattern and the resulting morphological changes. Wave propagation and wave penetration in the harbour. Estimation of shore line drift and evolution. Navigation aspects of approach channel. Forces acting on moored tanker. Physical Model Studies Examine the change in flow pattern. Orientation of proposed berth. Stability & Tranquility at berth

LNG Import Terminal

Project Execution Tie-up of LNG long term contract Shipping arrangement Preparation of DFR / Design of facilities Preparation of Front End Engineering Design (FEED) Selection of EPC Contractor Lump sum Cost plus basis Split into no. of packages, each package on turnkey basis. Selection of Project Management Consultant.

Project Execution Base line data requirement Approval requirement of State / Central Government such as Exemption for Coastal Regulatory Zone Clearance from State Environment Department NOC from Ministry of Environment & Forest (MOEF), Government of India NOC from State Pollution Control Board Clearance from Chief Controller of Explosives Clearance from Civil Aviation Authority Clearance from Naval Authorities Clearance from State Department of Forest & Wildlife NOC from Fisheries Department

Project Execution Define Design parameter Capacity of Terminal Send out rate LNG Storage Volume Gas delivery profile Battery Limit Conditions Size of LNG Carrier Location of LNG loading port Design of Jetty

COST OPTIMISATION Highly capital intensive projects Optimization of costs to increase returns Identify and analyze alternatives Design is the driver that influences project life cycle cost Project costs and revenues are largely fixed during DFR stage

Marine Facilites

Marine Facilities Mooring Dolphins Breasting Dolphins Jetty Head Trestles Unloading Arms LNG Unloading Lines

Unloading system : Sizing Parameters Number of berth : Number of carriers per year Port of call and unloading duration Number and diameter of arms Duration and flow rate of unloading LNG flow speed and pressure drop Arms reliability Number and diameter of unloading line(s) Geometrical height between carrier flanges and tank top LNG flow speed, line length and pressure drop Carrier pump rated head Gas pressure difference between carrier and storage tank

SHIP

MOSS TYPE SHIP

MEMBRANE TYPE SHIP

Turning and berthing at Dahej LNG Terminal

Loading Arm/Manifold Manifold Loading Arm Loading Arm Reach Envelope

Gangway Position Elevation High tide Low tide Ballast Laden Gangway Landing area Manifold

STORAGE TANKS

Storage capacity : General Needs LNG storage : buffer role between cargo unloading and continuous send out Total storage requirement depends on: Capacity of the largest LNG carrier Maximum ship arrival delay Corresponding send out flow rate

Storage system : sizing parameters Buffer storage capacity = C + (Tr - Td) Q + B + S C : largest carrier capacity Tr : maximal delay Td : unloading duration Q : reliable flow rate B : unpumpable S : strategic stock Number of tanks and capacity Technological limits Seismic, Available surface Environmental Impact Specific requirements of the owner

TYPES OF STORAGE TANKS

REGASIFICATION & SEND OUT FACILITIES

REGASIFICATION

Send out system : Sizing parameters (1) Send out flow rate Annual average flow rate (LNG receiving annual quantity, operating duration, equipment reliability) Maximum flow rate (m3/h) Minimum flow rate (m3/h) Send out pressure Flow rate modulation

Send out system : Sizing Parameters (1) Number and characteristics of LP pumps Recondenser pressure Storage tank height Pressure drop in LP lines Trunk loading Cool down system HP, LP and unloading lines

Lp Submerged Pump In Tank

Send out system : Sizing Parameters (2) Number and characteristics of HP pumps NPSH and geometrical height between recondenser and HP pump inlet, pressure drop safety margin to send out point Shut off head Technological limits

Send out system : Sizing Parameters (2) Vaporization General Gas Grid and pressure Send out modulation Reliability and operating costs Cogeneration Sea water T Cooling down and annual temperature range

Pot Mounted HP Pump

Send out system : Sizing Parameters (3) LNG and NG HP piping Shut off head Pressure and pressure drop at maximum flow rate «Dead» end and depressurising system Pressure control and metering, Pressure reducer Type of metering (diaphragm, turbines, ultrasonic) Gas composition and odorization Gross Calorific Value and Wobbe index (chromatography) Odorant storage (THT, mercaptan) Odorant injection (flow ratio control) Measurement of odorant ratio (chromatography)

Boil off gas recovery system : Sizing Parameters (4) Flare and Boil Off Gas (BOG) lines Operating pressure Gas return to tanker flow rate Tanker cooling down Roll-over Flare implementation Relief valve collection (storage tanks, vaporizers) Boil off gas compressors Recondenser pressure range Normal evaporation flow rate (storage tank, cooling down, ) Unloading LNG flash Pressure control of storage tanks Number of compressor, flow rate and range control

EQUIPMENT LAYOUT

REGASIFICATION TERMINAL EQUIPMENT LAYOUT EN 1473, NFPA 59 A, OISD-194, OISD-156 provides guideline Layout to ensure LNG piping is minimized Layout to ensure risk does not extend beyond the plot Main Control room to be in non-hazardous area. Hazardous area classification may be decided based on dispersion calculation from possible spills.

New Developments

LNG Satellite Terminal NG Power Plant NG Industrial users LNG Satellite terminal NG Residential users Small LNG vessels LNG Terminal

Further Opportunities PNG Supply to Domestic Consumer

L-CNG HUBS LNG/CNG HUB LNG Storage Vessel Vapouriser PNG Supply to Domestic Consumer Isolated Industrial consumer LNG Truck CNG Dispenser Pump A small LCNG station of 10 t/day can meet the domestic requirement of 25,000 households. LNG Dispenser