Promoters. Presentation. Tunnel. Tim Smart Head of Engineering & Operations. 20 th October

Similar documents
D7: TUNNEL CONSTRUCTION AND METHODOLOGY

IMPACTS OF TUNNELS IN THE UK. Non-technical summary

CROSSRAIL INFORMATION PAPER D8 TUNNEL CONSTRUCTON METHODOLOGY

HS2 Phase One Ground Investigation: Challenges and Requirements

PIPE JACKING. An introduction to pipe jacking prepared by the Pipe Jacking Association

HUDSON TUNNEL PROJECT

Pipe Jacking/Microtunnelling. Dr. Mark Knight. Centre for Advancement of Trenchless Technologies (CATT) University of Waterloo.

HS1 Link The View from London

High Speed Rail in the Chilterns: Feasibility Study of Alternative Tunnelling Options

From Colonia Jardín to Cuatro Vientos

The Technical and Contractual Matters of Bored Piling Works. By Wallace Yeung Vibro (H.K.) Ltd.

Sound, Noise and Vibration

TBM Selection and Specification

4D grouting pressure model of a bored tunnel in 3D Tunnel

introduction Introduction to Bridge and Tunnel Engineering Characteristics of ideal bridge Ideal location Factors affecting bridge type Classification

4D grouting pressure model PLAXIS

Introduction to Tunnel Construction

Case study The construction of the West Rail Tsing Kwai Tunnel from Mei Foo to Tsuen Wan

COMPETITIVENESS OF PIPE-JACKING TUNNEL LININGS

King County Uses Trenchless Methods to Construct a Large Siphon Under Seattle s Ship Canal

Trenchless Technology

PAUL ZICK, PE NORTH SHORE CONSTRUCTORS JV

Selection of Proprietary Shoring Equipment

The Building Codes A.R.E. Building Design and Construction Exam Prep

Pipe Jacking. Japan Sewage Works Association

Tunnels. Introduction in Shield tunnelling Pipe jacking & tunnelling Slurry & hydroshield Slurry versus EPB Principles of support pressure

Western Rail Link To Heathrow

ROTARY DRILLING TECHNIQUES LARGE DIAMETER

Diaphragm wall Construction

Who are we and what do we do?

SPECIAL CONDITIONS FOR PIPE JACKING (PJ) October, 2006

Hudson River Tunnels, Mega Projects, and Risk A Designer s Perspective

Box Culverts. Easy to install, suitable for very shallow or deep fill, ideal for use in a wide variety of civil engineering applications.

Concrete Pipe Jacking

Hampton Roads Bridge-Tunnel Expansion Feasibility Study. Design Considerations

USE OF MICROTUNNELING TO INSTALL PIPES IN AN ENVIRONMENTALLY SENSISTIVE AREA. Miranda Roman D. *, LaFaso Edward

GENERAL GUIDANCE FOR Low Noise and Low Vibration Slab Track

Funding was provided by the City of New York via the Hudson Yards Infrastructure Corporation and Hudson Yards Development Corporation.

Safely designing High Speed Two

Performance review of a pipe jacking project in Hong Kong

The New Guanjiao Tunnel on Qinghai-Tibet Railway SHAOHUA CHEN

MEDIA BRIEFING NOTE: CROSSRAIL TUNNEL CONTRACTS, TUNNELLING STRATEGY AND CROSSRAIL PROGRESS

DESIGN AND CONSTRUCTION OF DERRY ROAD AND CANADIAN NATIONAL RAIL GRADE SEPARATION

Design Data 4. Jacking Concrete Pipe

Policy for the Assessment and Mitigation of Traffic Noise on County Roads

Wendover Cut & Cover Tunnel Extension

San Jacinto National Underground Science Laboratory. Site Visit February 28 March 1, 2001

NZQA registered unit standard 738 version 5 Page 1 of 7

LARGE DIAMETER PIPE ROOF BOX EXCAVATION FOR PASSENGER LINKWAY TUNNEL

Solutions for tunneling and mining TBM. Expanding Horizons Underground

INDEX FOR SPECIFICATIONS FOR JACKING CULVERTS THROUGH EMBANKMENTS SCOPE... 2

ROSTA Anti-vibration Mountings

Key developments in the Channel Tunnel safety rules and the wider EU framework

4th International Engineering and Construction Conference - July 28, 2006

Urban EPB Tunneling in Limited Space: A Case Study of the San Francisco Central Subway Project

Trenchless Pipeline Crossings

STANDARD SPECIFICATIONS SECTION TUNNELING. A. Section includes requirements for constructing tunnels 48-inch and larger diameter.

An indicative program for works to be conducted within the Sydney Park construction compound is provided in Table 6-20.

3 rd Edition of the ITA Tunnelling Awards - the winners 2017!

Design and development of a decline shaft through poorly consolidated Kalahari deposits at Ghaghoo Diamond Mine.

Design Data 4M. Jacking Concrete Pipe

STANDARD SPECIFICATIONS SECTION BORING AND JACKING. A. Section includes requirements for boring and jacking casing pipe.

URBAN TRACK Final Conference Alternative to Floating Track Slab High Attenuation Sleeper. Presented by Ian Robertson, ALSTOM 24 June 2010, Prague

Victoria Station Upgrade PAL 10. The challenges of mining an escalator barrel within an operational station

SCREW PILE APPLICATION SHEETS

Geotechnical control of a major railway project involving tunnel works in Hong Kong

SPECIFICATION FOR PIPE CULVERT CONSTRUCTION

Risk Management based Ground deformation monitoring during Queens Bored Tunnels project

water-powered drilling in ground engineering

UNDERPINNING A CRANE FOUNDATION

TECHNICAL MEMORANDUM

CTRL London Tunnels: an alternative approach to delivering a major tunnelling project

THE GROUNDBREAKING TUNNEL

Introduction. Disclaimer. Table of contents

RIGID INCLUSIONS. Rigid Inclusions offer an economical approach for building on sites underlain by soft soil.

Advert pages 24/3/03 12:25 pm Page METROSUR 2

Venice Pumping Plant Dual Force Main Project Draft EIR

Compensation grouting for TBM tunnelling beneath shallow-cover

Tagus Crossing at Carregado (Portugal): A project respectful of its sensitive environment

Tabulated Data Waler Rails

AGENDA. HS1 Overview. Construction ti & Engineering i Overview. Funding. Procurement & Delivery. Operating Railway

Fire Inspection and Code Enforcement, 7 th Edition. Chapter 6 Building Construction: Components Inspector II


BAUM INDUSTRIAL PARK DEVELOPMENT, PERFORMANCE AND MAINTENANCE STANDARDS DOCUMENT. October, 1991

BASED ON DFD MASTER SPECIFICATION DATED 2/24/2014

A case study of twin bored tunnelling under mixed-face soil - Bendemeer MRT station project (Downtown Line 3), Singapore

TUNNEL WIENERWALD ABSTRACT

HS2. Beth West Commercial Director, HS2 Ltd

Noise Assessments for Construction Noise Impacts

Lecture 7 BALLAST & SUBGRADE. Dr. Charisma Choudhury. April 2011

RHEDA MRT The ballastless track for underground and surface commuter transit

Tunnel Works. How we got here - Fort Wayne s Consent Decree. Tunnel Works Program Frequently Asked Questions

13/05/2016. Introductions of Pipe Roof. Focuses. Application of Rectangular Shield Jacking

Hardrock Tunnel Boring Machines

SEMINAR. Introduction to Continuous Flight Auger (CFA) piling Thursday 21/8/2013. Facilitator: Martin Larisch

THE SLAB TRACK SOLUTION FOR THE REQUIREMENTS OF TOMORROW LOW VIBRATION TRACK (LVT)

SPECIAL PURPOSE SIMULATION TEMPLATE FOR UTILITY TUNNEL CONSTRUCTION

Transcription:

Promoters Tunnel Presentation Tim Smart Head of Engineering & Operations 20 th October 2014 1

Tunnel Briefing Agenda 1. Why tunnel? 2. Operational aspects of tunnels 2.1 Safety requirements 2.2 Noise and vibration 2.3 Aerodynamics and porous portals 2.4 Vent shafts and smoke control 2.5 Energy requirements 3. Construction 3.1 Tunnelling techniques 3.2 Shaft construction 3.3 Settlement 3.4 Rate of tunnelling 3.5 Construction aspects 4. Costs implications 4.1 Costs of tunnelling 4.2 Land costs 4.3 Impact on programme 2

Tunnels Location 3

1. Why Tunnel? Terrain Chiltern Tunnel Long Itchington Connectivity South Heath Wendover Burton Green Greatworth Surface Disruption Cost effective Euston Northolt Bromford 4

Amersham Terrain Example: Chiltern Tunnel Chalfont St Giles Little Missenden Chalfont St Peter 5

Terrain Example: Chiltern Tunnel 6

Surface Disruption Example: Northolt Tunnel Northolt OOC Station 7

Surface Disruption Example: Northolt Tunnel 8

Connectivity Example: Burton Green Plan View 9

Connectivity Example: Burton Green Plan View 10

Tunnels Phase One Twin Bored Tunnel Cut & Cover Euston 7.4km London Clay South Heath 1.1km Chalk Northolt Chilterns Long Itchington Wood Bromford 14km London Clay/Lambeth/Chalk 13.4km Chalk 1.5km Penarth Group/Mercia Mudstone 2.8km Penarth Group/Mercia Mudstone Wendover Greatworth Chipping Warden Long Itchington Wood Burton Green 1.3km Chalk 2.1km Glacial Till/Oolite/Whitby Mudstone 2.5km Low Jurassic Marlstone/Mudstone 0.4km Penarth Group/Mercia Mudstone 0.5km Lower Carboniferous Mudstone 11

2. Operational Aspects of Tunnelling 2.1 Safety Arrangements 2.2 Noise and Vibration 2.3 Aerodynamics and Porous Portals 2.4 Vent Shafts and Smoke Control 2.5 Energy Requirements 12

2.1 Minimum Safety Requirements (TSI) Safe Area to the surface every 1 km or adjacent to independent tunnel tube every 500m Fire Fighting Points - Applies to all tunnels over 1 km and rolling stock dependent Tunnel Length 1 to 5 km - portals with minimum standing area 550 sq m Tunnels Length over 5km - every 5km depending on rolling stock characteristics Fire Fighting Point defined as Location inside or outside tunnel where fire fighting equipment can be used and passengers can evacuate Water supply capacity requires a minimum of 800 l/min for 2 hrs. 13

Tunnel Cross Passage 14

Emergency Train Evacuation 15

Evacuation Walkway 16

Tunnel Cross Passage Opening HS1 17

Typical Cross passage Door 18

2.2 Vibration INDICATIVE 1. Noise/ vibration of rail caused by train 2. Attenuation through trackform 3. Attenuation through tunnel and ground 4. Attenuation through building foundations 5. Attenuation through structure building 6. Possible amplification from resonance of building structure 19

Vibration mitigation via booted sleeper track 20

Tunnel Operational Noise HS2 vent shafts are designed, constructed, operated and maintained along with associated stationary equipment so that noise in the worst affected residential receptors, conforms to British Standard Guidance and achieves the aims of the Noise Policy Statement for England. Mechanical equipment within the vent shaft is only operated under the following circumstances: During an emergency; During maintenance when required to maintain an acceptable air quality environment; and During tunnel congestion when required to maintain an acceptable air quality environment. 21

2.3 Tunnel Aerodynamics Tunnel aerodynamics are a function of the interaction of key infrastructure and rolling stock parameters such as: Diameter and roughness of tunnel Length of tunnel Provision of tunnel draught relief Portal design Train speed and length Train aerodynamic profile The primary controlling factors are the train speed and the blockage ratio (i.e. train area/tunnel area). 22

Tunnel Aerodynamics Propagation of pressure wave 23

Porous Portal Slide 24

Porous Portal 25

Porous Portal 26

2.4 Vent Shafts Primary Purpose Smoke extract and control Pressure relief Access for emergency services Passenger comfort to keep air quality and temperature within acceptable limits Secondary Uses Tunnel boring machine maintenance intervention Access for railway maintenance 27

Vent Shafts along Bored Tunnels 28

Shaft Fans FANS FANS ARE FIXED PITCH, VARIABLE SPEED, REVERSIBLE DAMPERS ARE NORMALLY CLOSED DAMPERS DAMPERS UP TUNNEL DOWN TUNNEL 29

Shaft Fans FANS DAMPERS DAMPERS UP TUNNEL DOWN TUNNEL 30

Shaft Fans FANS DAMPERS DAMPERS UP TUNNEL DOWN TUNNEL 31

In Line Tunnel Fan 32

Fans for portal arrangement via Saccardo Nozzle 33

Saccardo Nozzle viewed from the tunnel 34

2.5 Increased energy use in Tunnels Traction power Energy required for the traction power of the trains increases in tunnels. In the open air 80% of the energy used by the train goes into overcoming air resistance. This increases to 90% in a tunnel. Increased power for Mechanical and Electrical plant and equipment Increase in energy costs for the railway due to the plant necessary for safety arrangements, for example: fans lifts fire mains emergency lighting plus tunnel integrity plant (e.g pumps, cooling arrangements) 35

3. Construction 3.1 Types of Tunnelling Techniques Applicable to HS2 Bored Tunnels Shield type machines with precast segmental tunnel lining. Used when surface access is very limited at depths typically below one tunnel diameter. Longer tunnel lengths where economical to use machine. Cut & Cover Tunnels ( Green Tunnels ) Typically concrete box structures constructed in excavated ground. Used at shallower depths where there is good surface access. Mined/Sprayed Concrete Lining Tunnels Mechanically excavated with sprayed concrete lining. Used in shorter drives or more complicated shapes, also in soft rock ground conditions. 36

Bored Tunnels Earth Pressure Balance Tunnel Boring Machine (EPBM) 37

Bored Tunnels HS1 EPBM in factory showing back up arrangements 38

Bored Tunnels Cutter Head 39

Bored Tunnels Slurry or Hydroshield Tunnel Boring Machine 40

Precast Tunnel Lining Manufacture Size Length - 300m Width - 100m Scale Length - 3 football pitches Width - 2 foot ball pitches 280m 50m 100m 100m INDICATIVE 41

Bored Tunnels Tunnel Ring Segments 42

Segment Yard & Drive Site Locations Washwood Heath M25 Northolt tunnel Harvil Road Old Oak Common 43

Mined tunnel Excavator 44

Sprayed Concrete Lining 45

Cut & Cover Green Tunnel 46

Cut and Cover Cross Section Construction of tunnels where all the ground above is cleared 47

Cut and Cover Construction Methodology 1 48

Cut and Cover Construction Methodology 2 49

HS1 Cut and Cover Under Construction 50

HS1 Cut and Cover Completed 51

Diaphragm Wall Construction 52

Diaphragm Wall Construction 53

Typical Plant for Cut & Cover Tunnel 54

3.2 Shaft Construction 55

Completed Shaft 56

Shaft Construction 57

Completed Shaft 58

Shaft Construction 59

Adit Construction 60

3.3 Settlement INDICATIVE 61

Settlement Protective Measures The primary form of settlement mitigation will be by good tunnelling practice, including continuous working. Where required additional measures (e.g. grouting and structural solutions) will be carried out based on a three stage assessment as set out in Information Paper C3: Ground Settlement. Phase 1 Assessment: A preliminary assessment based on green field conditions will be undertaken. Where the predicted settlement is less than 10 mm or less than 1/500 slope, no further assessment is required. Phase 2 Assessment: In the case of predicted settlement of more than 10mm or 1/500 slope, an individual building assessment will be carried out. If the potential damage classification is Category 2 (slight) or below - no further assessment is required. 62

Settlement Protective Measures Phase 3 Assessment: Where predicted settlement indicates potential damage classification of 3 (moderate) or higher, a detailed evaluation will be carried out with the aim to reduce the effects to acceptable levels. Where this is not possible further protective measures will be implemented. Settlement Deed. Properties within 30 metres of tunnels may apply for a Deed (as set out in information paper C3) to ensure that protective measures are implemented in accordance with the assessment criteria. 63

3.4 Rate of Tunnelling The rate of tunnelling is important in minimising settlement. This is achieved by operating tunnel boring machines appropriately (such as using Earth Pressure Balance machines in closed mode). In order to keep settlement to acceptable limits, HS2 has specified a maximum of 1% volume loss for bored tunnels. Continuous 24 hour tunnelling also minimises settlement as it does not allow time for the ground to fully relax. Other methods of controlling settlement include grouting techniques, particularly compensation grouting. 64

3.5 Construction Aspects (1) Construction Sites (2) 24 hours/ 7 days working (3) Supporting logistics including excavated material (4) Noise and Vibration 65

Construction Noise - Tunnel Drive Sites Tunnel drive sites generate similar noise levels to other large construction sites. Tunnelling activities and the associated local site material handling will be operated 24 hours a day. Noise mitigation is provided by the standard means such as hoarding, muffling, baffles and noise suppression on plant and equipment. Tunnel sites will be subject to the same HS2 procedures set out under the Code of Construction Practice and will be subject to Local Authority Approval under Section 61 of Code of Pollution Act 1974. 66

Construction Noise - Tunnel Boring Sound and vibration from the tunnel boring machine will be perceptible inside properties for a few days either side of the TBM as it passes beneath them. The effects of ground borne sound and vibration from the TBM on building occupants will be short term and hence they are not considered to be significant. 67

4. Costs of Tunnelling Factors Tunnel Size Ground Conditions (rate of progress) Groundwater/aquifers Material disposal methodology Number of shafts Cross Passages Ground treatment Settlement monitoring. 68

Costs of Tunnelling Fixed Costs TBM typically 15 to 20m Back up material handling similar costs order. Linear Costs Labour Lining materials Excavated material disposal Incremental Cost dependent on Surface arrangements for drive sites, reception sites, portal arrangements. Increase in shafts, cross passages, shaft M&E systems. Number of logistics vehicles 69

COST Cost vs. Length Additional Shafts + M&E plant for vent & smoke control Shaft + M&E plant for vent & smoke control Increase in cost per metre due to distance travelled by tunnel logistics requiring more spoil transport. INDICATIVE 0 0 0 LENGTH km 70

Tim Smart 71