INDEX FOR SPECIFICATIONS FOR REMOVING CULVERTS AND PLACING CULVERTS SCOPE... 1

Similar documents
INDEX FOR SPECIFICATIONS FOR JACKING CULVERTS THROUGH EMBANKMENTS SCOPE... 2

ITEM D-701 PIPE FOR STORM DRAINS AND CULVERTS

SPECIFICATION FOR PIPE CULVERT CONSTRUCTION

C. Foundation stabilization for pipe and utility structures.

SPECIFICATIONS FOR BRIDGE CONSTRUCTION SECTION 2 BACKFILL. 2.1 General...2-1

SECTION 19 - TRENCH EXCAVATION, BEDDING AND BACKFILL TABLE OF CONTENTS

SECTION 19 - TRENCH EXCAVATION, BEDDING AND BACKFILL TABLE OF CONTENTS

CONSTRUCTION SPECIFICATION FOR TRENCHING, BACKFILLING, AND COMPACTING

SECTION TRENCHING & BACKFILLING

SECTION A1 EXCAVATION AND BACKFILL GENERAL

CW 3615 RIPRAP TABLE OF CONTENTS

2.1 Backfill - General

SECTION 19 - TRENCH EXCAVATION, BEDDING AND BACKFILL TABLE OF CONTENTS

SECTION EXCAVATION AND BACKFILL FOR UTILITIES AND STRUCTURES

Construction Specification for Concrete Unit Pavers

TRENCH EXCAVATION AND BACKFILL

SECTION RIPRAP, BOULDERS, AND BEDDING

B. Subsurface data is available from the Owner. Contractor is urged to carefully analyze the site conditions.

SECTION GRADING AND SITE PREPARATION CITY OF LEE S SUMMIT, MISSOURI STANDARD SPECIFICATIONS

LANDSCAPE RETAINING WALLS

***************************************************************************************************************

CITY OF FARGO SPECIFICATIONS AGGREGATE BASES

PERMEABLE INTERLOCKING PAVERS

STATE OF OHIO DEPARTMENT OF TRANSPORTATION SUPPLEMENTAL SPECIFICATION 811 CONDUIT AND DRAINAGE STRUCTURES

Section Storm Sewers STORM SEWERS PART 1 - GENERAL 1.01 SECTION INCLUDES. A. Storm Sewers. B. Abandonment of Storm Sewers

BASE CONSTRUCTION MATERIALS A Aggregate

LS 2519 CONCRETE PAVER PAVEMENT RECONSTRUCTION

SECTION 820 PUMP STATION DEMOLITION AND SITE RESTORATION

SPECIFICATION FOR ENGINEERED FILLS

The Work under this Section consists of performing all operations necessary to complete construction of the leveling course on the prepared subbase.

Section 25 Aggregate Subbase

FLOWTECH WASTEWATER TRENCH SYSTEMS Manufactured with 100% Recycled Artificial Aggregate

SECTION UTILITY MANHOLES AND STRUCTURES

SECTION C1 DUCTILE IRON PIPE AND FITTINGS GENERAL

SITE SERVICES GUELPH TRANSIT OPERATIONS & MAINTENANCE SECTION WATSON ROAD FACILITY PAGE 1 OF 6 WATER RECLAMATION PROJECT JUNE 2013

SECTION AGGREGATES

DIVISION 31 EARTHWORK 2006 Edition, Published January 1, 2006; Division Revision Date: January 31, 2012

CONCRETE SEGMENTAL RETAINING WALL SYSTEM

Method of Measurement for Road Works Series MM Earthworks

B. Backfill and compact utility bedding and fill placed in the utility trenches between the top of the utility bedding and the subgrade elevation.

BIO-AQUIFER STORM SYSTEM

Fabrication and Installation Table of Contents

901 - PIPE SEWERS COMPLETE IN PLACE

Design Data 6. Loads and Supporting Strengths Elliptical and Arch Pipe. Values of B d

***************************************************************************************************************

SPECIFICATIONS FOR PRECAST MODULAR BLOCK RETAINING WALL SYSTEM (revised 5/8/7)

Redi Rock Specification and Installation Manual

TRENCHLESS CONSTRUCTION (BORING, JACKING, AND TUNNELING)

ITEM 6 CONCRETE CURBS, GUTTERS, AND SIDEWALKS

Table of Contents. Section Trench Excavation and Backfill Section Includes Description of Work 1. 1.

SECTION CAST-IN-PLACE CONCRETE

SPECIFICATION FOR REINFORCED SOIL WALL

SECTION PERMEABLE INTERLOCKING CONCRETE UNIT PAVEMENT

h Installation Manual

BASED ON DFD MASTER SPECIFICATION DATED 2/24/2014

SECTION 3: SUB BASE AND BASE COURSES

SPECIFICATION : BORING AND JACKING

SECTION SPECIFICATION FOR STONEBRIDGE RETAINING WALL SYSTEM

Uwall UNIVERSAL CONSTRUCTION MANUAL

TYPE "A" CATCH BASIN

CITY OF EDMOND STANDARD SPECIFICATIONS FOR CONSTRUCTION

SPECIFICATIONS FOR STREET CONSTRUCTION WITHIN THE TOWN OF PLAINVILLE

MANHOLES, VAULTS AND CATCH BASINS SECTION A. Section Soil and Aggregate Materials. C. Section Storm Drainage Systems

Corrugated Metal Pipe Design Guide

DIVISION 33 - UTILITIES SECTION UTILITY PIPE BORING AND JACKING DIVISION 33 UTILITIES SECTION UTILITY PIPE BORING AND JACKING

STANDARD SPECIFICATION FOR CRIBLOCK CONCRETE CRIBWALL

CONSTRUCTION SPECIFICATION FOR CONCRETE CROSSWALK INDEX TS SCOPE...3

Summary of the 2011 Changes

Providing proper drainage system

SECTION EXCAVATING, BACKFILLING, AND COMPACTION FOR UTILITIES

ADDENDUM No. 6. ITB No. 4424: W.R. Wheeler (Swift Run) Service Center PUD Non-motorized Improvements Phase 1

R-TANK SPECIFICATIONS

BACKFILL COMPACTION FOR VOLCLAY WATERPROOFING: An Essential Ingredient for a Successful Project

PAVING SLABS ON A CONCRETE BASE

ITEM 506 Temporary Erosion Control

Table of Contents for Guide Specifications

Standards for Soil Erosion and Sediment Control in New Jersey May 2012 STANDARD FOR SLOPE PROTECTION STRUCTURES. Definition

INDUSTRIAL PIPE FITTINGS, LLC

CW 3620 INSTALLATION OF UNDERGROUND TRAFFIC SIGNAL SERVICES TABLE OF CONTENTS

ENGINEERED SOLUTIONS. Corrugated Metal Pipe Design Guide

Item Name Description Unit of Measure Mobilization Per WSDOT Lump Sum

BID # REPAIR AREA OF PARKING LOT DAMAGED BY WATER LINE LEAK SECTION C TECHNICAL SPECIFICATIONS OWNER

Extraction and Sieve Analysis ( µm minus) Forming Marshall Specimens, Field Method

4 EXTREME FOUNDATION PANELS

City of Brandon Division 2 Standard Construction Specifications Section January 2000 Page 1 of 10 SOIL CEMENT BASE COURSE PART 1 GENERAL

BENTOMAT CL GEOSYNTHETIC CLAY LINER SPECIFICATION GUIDELINES

MATERIAL SPECIFICATION FOR CIRCULAR AND ELLIPTICAL CONCRETE PIPE

SECTION DUCTILE IRON FITTINGS. A. This section includes materials, installation, and testing of ductile iron fittings 48 inches and smaller.

SECTION MANHOLES AND STRUCTURES. A. Section Includes: 1. Manholes for water, storm drain and sanitary sewer systems.

SYNTHETIC GRASS INDOOR SURFACE SPECIFICATIONS: K9GRASS LITE

NOTES ON CORRUGATED PLASTIC PIPE SUBSOIL DRAIN CONSTRUCTION SPECIFICATION

VERTI-BLOCK - DESIGN MANUAL

4 EXTREME FOUNDATION PANELS

Sample Bid Specification Revision 2 PVC Expanded-in-Place Pipeline Reconstruction

Asphalt Rubber Chip Sealing DRAFT MAINTENANCE SPECIFICATION. March 22, 2007

BILL OF QUANTITIES. Construction and Rehabilitation of wadi Gaza Bridges PAL Funded by Government of Brazil

SECTION INTERLOCKING CONCRETE PAVERS

Steps And Stairs Installation Steps In Wall - Option 1 Steps In Front of Walls - Option 2 Steps In Wall; 10 (25cm) Tread - Option 3 Step Parallel to

SOLID WALL PVC SEWER PIPE

SECTION FACILITY SANITARY SEWERS

Transcription:

March 2002 No. 400 INDEX FOR SPECIFICATIONS FOR REMOVING CULVERTS AND PLACING CULVERTS 400. 1 SCOPE... 1 400. 2 REMOVING CULVERTS AND TIMBER STRUCTURES 2.1 Concrete and Metal Pipe Culverts... 1 2.2 Structural Plate Culverts... 1 2.3 Concrete Box Culverts...1 2.4 Timber Structures... 1 2.5 Excavation... 1 2.6 Filling Depressions... 1 400. 3 SUPPLYING CULVERTS 3.1 Corrugated Metal Culverts... 1 3.2 Concrete Culverts... 2 400. 4 CONSTRUCTION METHOD... 2 4.1 Culvert Foundation and Bedding... 2 4.2 Culvert Gravel for Bedding...2 4.3 Backfilling Haunch Area...3 4.3.1 Mechanical Method... 3 4.3.2 Water Jetting Method... 3 4.3.3 Compaction to Springline... 3 4.5 Backfill... 3 4.6 Trenches... 4 400. 5 CLASSIFICATION OF CULVERTS TO BE PLACED... 4 400. 6 PLACING CULVERTS... 4 6.1 Corrugated Metal Culverts... 4 6.2 Concrete Culverts... 4 6.3 Tie Straps on Concrete Pipe... 5 6.4 Extending Existing Culverts... 5 6.5 Through Existing Embankments... 5 400. 9 METHOD OF MEASUREMENT... 5 9.2 Culvert Length 6 9.3 Culvert Gravel...... 6 9.4 Shoo-Fly Detours... 6 400. 11 BASIS OF PAYMENT... 6 11.2 Placing Culverts... 6 11.3 Culvert Gravel... 6 11.4 Unsuitable Material... 6 Page

March 2002 No. 400 SPECIFICATIONS FOR REMOVING CULVERTS AND PLACING CULVERTS 400. 1 SCOPE These specifications govern all operations necessary for and pertaining to the removal and disposal of existing culverts and other drainage structures, and the placement of culverts as classified herein. 400. 2 REMOVING CULVERTS AND TIMBER STRUCTURES 2.1 Concrete and Metal Pipe Culverts All culverts removed shall become the property of the Contractor. 2.2 Structural Plate Culverts Prior to dismantling structural plate culverts, the Contractor shall match mark each plate and prepare a plan for the Engineer showing the relative position of each plate. Similar plates shall be securely banded together in convenient quantities and stored neatly at a designated location on the right-of-way. The Contractor shall repair or replace any portion of the culvert damaged during removal. 2.3 Concrete Box Culverts Reinforced concrete box culverts to be removed shall be demolished. Explosives shall not be used for demolition purposes unless permission has been granted by the Engineer. When permission has been granted it will not relieve the Contractor of liability for damage to persons or property resulting from the use of explosives. Broken concrete shall be disposed of in accordance with the requirements for Loose Rock disposal in the Specifications for Grading. 2.4 Timber Structures Material obtained from removing designated timber structures shall become the property of the Contractor. Material salvaged by the Contractor shall be removed from the right-of-way. Debris and unsalvable material shall be collected and disposed of by burning or burying. Timber or metal piles shall be cut off at ground level unless otherwise specified by the Engineer. 2.5 Excavation Excavation required for the removal of culverts and structures will not be paid for directly but will be considered incidental to the applicable unit price for removing culverts or timber structures. 2.6 Filling Depressions Construction methods for ground preparation and backfilling of depressions resulting from the removal of culverts and timber structures shall be in accordance with the Specifications for Grading. The material used for backfilling depressions will be paid for at the applicable unit price for the type of material used. 400. 3 SUPPLYING CULVERTS 3.1 Corrugated Metal Culverts The Department will supply the culverts and the supplier shall deliver and unload the culverts at one or more locations on or near the project. The Department will accept and be

March 2002-2 - No. 400 responsible for the culverts until the Contractor arrives on the site and receives the culverts into his custody. The Contractor shall store, transport and install metal culverts. 400. 3.2 Concrete Culverts The Department will supply the culverts and the Supplier shall deliver and unload the culverts at specified locations. The Contractor shall contact the Supplier to arrange for the time of delivery, and shall receive, store and install the concrete culverts. 400. 4 CONSTRUCTION METHOD The Contractor shall have at least two plate type mechanical compactors on the job site before commencing any culvert installations. 4.1 Culvert Foundation and Bedding The culvert foundation means the natural soil, underlying the excavation, upon which the culvert bedding or the culvert is to be placed. The culvert foundation shall be prepared and compacted to the staked gradeline and for a width sufficient to permit compaction of the bedding under the culvert haunches. Unsuitable material from below the staked gradeline shall be removed to an approved depth and replaced with suitable bedding and suitable geotextile if required, to provide uniform continuous support. Supply and installation of the geotextile will be paid for as Extra Work. The culvert bedding means a layer of selected material, generally culvert gravel, constructed on the culvert foundation so as to uniformly support the culvert. In general, culvert gravel shall be used at through grade installations and under concrete culverts installed at any location. 4.2 Culvert Gravel for Bedding Culvert gravel shall be well graded and shall consist of sound, durable particles of gravel, stone, sand and fines, free from sod, roots and organic material and shall meet the following gradation requirements: Passing 37.5 mm 100% Passing 4.75 mm 25-80% Passing 425 um (a) 15-40% when mechanically compacted (b) 5-40% when water jetted Passing 75 um (a) 6-18% when mechanically compacted (b) 0-8% when water jetted The shale content shall not exceed 25% by weight of the particles retained on a 4.75 mm sieve. Culvert gravel for bedding shall be spread uniformly along the full length of the culvert foundation. For metal culverts the bedding shall be constructed so that after compacting, a depth of at least 150 mm of gravel remains under the full length of the culvert. For concrete culverts, the bedding shall be constructed so that after compacting, a depth of at least 100 mm of gravel remains under the full length of the culvert. For concrete culverts, an additional layer of culvert gravel shall then be spread loosely and uncompacted at a uniform depth of 100 mm along the full length of the culvert foundation. After the culvert has been installed and assembled on the loose bedding, the bedding on both sides of the culvert shall be compacted. Culvert bedding shall be compacted at optimum moisture content to a minimum of 95% AASHTO Standard Dry Density. The supply of water for compaction will be considered as an incidental operation to Culvert Gravel.

March 2002-3 - No. 400 400. 4.3 Backfilling Haunch Area Placement and compaction of fill material in the haunch area may be carried out by mechanical methods or by water jetting. 4.3.1 Mechanical Method Fill material under haunches shall be placed alternately in 150 mm layers on both sides of the pipe to permit thorough compaction. The material under the haunches must be in firm contact with the entire bottom surface of the structure. (Backfill and compaction under haunches is a manual job, consisting of shovel placement, timber rammer or hand held packers). 4.3.2 Water Jetting Method Water jetting, when approved by the Engineer, may be used as an alternative method for backfilling haunches. Free draining backfill material shall be water jetted. The water jet pipe shall be 25 mm in diameter, pinched at the outlet end, have a shut off valve and in general be at least one metre long. The operational pressure shall be sufficient so as to produce a horizontal throw of six metres. Gravel shall be placed uniformly on each side of the culvert at the same time so as to construct and compact at least two uniform lifts of gravel between the bedding and the springline of the culvert. Each lift shall be water jetted at not more than one-half metre intervals to consolidate the aggregate under the haunches and parallel to the pipe. Water shall be forced into the aggregate until the voids are filled and water is rejected. No direct payment will be made for water jetting backfill, as this work will be considered incidental to the unit price for placing culverts. 4.3.3 Compaction to Springline 400. 4.5 Backfill After the haunch area has been backfilled and compacted, additional bedding material shall be placed adjacent to the pipe haunches in lifts not exceeding 150 mm. Each lift shall be compacted with a plate type mechanical compactor. Bedding material shall be placed in this manner up to the level of the springline. Material placed above the springline shall be placed as described in Backfill. Backfill will mean culvert gravel or selected material used for fill adjacent to and over an assembled culvert. The level of backfill on both sides of the culvert shall be maintained approximately equal at all times to prevent disturbing the culvert. Excavated material or material similar to the roadway embankment should be encouraged as backfill in frost susceptible soils. Backfill used above the springline of the culvert to the subgrade elevation, shall be culvert gravel or other suitable material. Backfill material other than material excavated from the culvert trench will be paid for at the applicable unit price. When culvert gravel is not used, material placed under the haunches shall be carefully selected to ensure that it is free of rocks and lumps. Culverts placed through private access roads shall be backfilled in uniform layers not exceeding 200 mm and compacted.

March 2002-4 - No. 400 400. 4.5 Backfill (Cont'd) Culverts placed at other than through private access roads shall be backfilled in uniform layers not exceeding 150 mm and shall be compacted to a minimum of 95% AASHTO Standard Dry Density. Heavy clay material shall not be used as backfill immediately adjacent to a culvert at these locations. A select material or culvert gravel shall be used. Backfill shall be placed and compacted in uniform layers until the embankment has been constructed to a sufficient height above the top of the culvert so that normal grading equipment can operate without distorting the culvert. Further filling and compacting shall be performed in accordance with the Specification for Grading. 4.6 Trenches Trenches, when required, shall be excavated wide enough to allow for compaction on both sides of the culvert. If conditions and safety requirements permit, trench walls shall be vertical to at least the top of the culvert. Excavated material shall be stockpiled not closer than one metre from the edge of the trench. No direct payment will be made for excavating material from trenches and replacing it as backfill, as the work will be considered incidental to the unit price for Placing Culverts. 400. 5 CLASSIFICATION OF CULVERTS TO BE PLACED Culverts to be placed will be classified as follows, based on the nominal diameter or span: Diameter or Span Metal Concrete Less than 800 mm Group A Group D 800 1300 mm Group B Group E Exceeding 1300 mm Group C Group F All culverts not falling into these categories will be classed as Group "G". 400. 6 PLACING CULVERTS Culverts shall be placed at the location, grade and alignment as directed by the Engineer. 6.1 Corrugated Metal Culverts Riveted culverts shall be placed so that horizontal seams are located in the upper half of the culvert with inside circumferential laps pointing in the direction of the flow. Culvert sections shall be placed so that the coupler corrugations shall properly engage pipe corrugations with the minimum gap between section ends. Coupler bolts shall be fully tightened. 6.2 Concrete Culverts Concrete culverts shall be placed with the bell or groove on the upstream end of the culvert; the foundation or bed shall be contoured to receive the bells. Rubber gaskets shall be lubricated and installed on cleaned and lubricated joints in accordance with the specifications of the Manufacturer. Culvert sections shall be joined to form a watertight joint, with an opening not to exceed 20 mm. Culvert sections shall be secured tightly together until sufficient fill material is tamped in place to prevent the joints from opening. Culvert sections with lift holes shall be laid so that the lift holes are at the top. The lift holes shall be filled with non-shrink mortar before the culvert is covered.

March 2002-5 - No. 400 400. 6.3 Tie Straps on Concrete Pipe The Contractor shall use galvanized steel tie straps to secure the outer two joints at each end of the culvert installation. The straps shall be anchored at the ten and two o'clock positions on culverts up to 1 050 mm in diameter, and ten, twelve and two o'clock positions on larger culverts. Holes for wedge anchors shall be drilled to appropriate depth and diameter. Wedge anchor fasteners will be supplied as followed; Culvert Diameter DIAM Length WEDGE ANSHOR FASTENERS Minimum Drill Hole Depth Size of Drill Hole No. Required Per Installation 300 600 9.5 69 38 9.5 16 750 1050 13 95 57 13 16 1200 1800 13 95 57 13 24 Tie straps and wedge anchors will be supplied by the Department. No direct payment will be made for the additional securing of culverts as it will be considered as an incidental operation to Placing Culverts. 6.4 Extending Existing Culverts Damaged ends of existing metal culverts to be extended shall be straightened or cut off. Damaged sections of existing concrete culverts shall be removed. At least 600 mm existing culvert shall be exposed prior to installation of the extension. Removing and disposing of damaged ends will be paid for at the unit price for "Removing Metal Pipe Culverts" or "Removing Concrete Pipe Culverts". Extending existing culverts, including the necessary excavation, preparation and coupling will be paid for at unit price for "Placing Culverts", based on the length of the extension and the applicable Group. 6.5 Through Existing Embankments When placing culverts through an existing embankment, and the roadway is open to traffic, the Contractor shall construct a shoo-fly detour at each location. At the completion of the installation, the detour shall be removed and the material used in the construction of the embankment. When the Contract requires a shoo-fly detour it shall be constructed at applicable unit prices. The Contractor shall maintain it. Traffic control devices shall be supplied, installed and maintained by the Contractor. The removal of the detour, if required, will be paid for as "Extra Work". 400. 9 METHOD OF MEASUREMENT 9.1 The length of pipe culvert removed will be determined by linear measurement along its invert. The number of concrete box culverts, timber structures and structural plate pipe removed will be determined by counting.

March 2002-6 - No. 400 400. 9.2 Culvert Length The length of culvert placed will be determined by linear measurement along its invert excluding any gaps that occur between sections of pipe. 9.3 Culvert Gravel Depending on the unit shown on the tender bid page, culvert gravel will be measured in tonnes or in cubic metres. When the aggregate is measured by volume, the rated capacity of the hauling vehicles will be established by the Engineer to the nearest 0.1 m 3 using the Department's Vehicle Measurement form. The rated capacity of a vehicle shall not be changed without the consent of the Engineer. Loads will be checked at the point of delivery and, when requested by the Engineer, shall be levelled by the Contractor. No payment will be made for any portion of a load greater than the rated capacity. Deductions will be made in 0.1 m 3 units for loads less than the rated capacity. 9.4 Shoo-Fly Detours Traffic control shoo-fly detours will be measured by counting each installation constructed. 400. 11 BASIS OF PAYMENT 11.1 The unit bid price set forth for: a) Removing Metal Pipe Culverts b) Removing Structural Plate Culverts c) Removing Concrete Pipe Culverts d) Removing Concrete Box Culverts e) Removing Timber Structures will be payment in full for performing all work necessary or incidental thereto, as herein described. 11.2 Placing Culverts The unit price set forth for "Placing Culverts, Group "A", "B "C", "D", "E", "F", or "G" will be payment in full for preparing the foundation and placing the culvert and for performing all work necessary or incidental thereto, as herein described. 11.3 Culvert Gravel The unit price set forth for "Culvert Gravel", will be payment in full for supplying, loading, hauling, depositing, watering and compacting the gravel and doing all work necessary and incidental thereto, as herein described. 11.4 Unsuitable Material Unsuitable material removed from below the foundation gradeline will be measured and paid for on the basis of "Extra Work".