Decommissioning Planning

Similar documents
Decommissioning of Nuclear Facilities. The Decommissioning Process. Lesson Objectives. Decommissioning. Decontamination. Decommissioning Objective

Decommissioning and Site Release Problems for Georgian Nuclear Research Reactor IRT-M

ADVANCED DECOMMISSIONING COSTING CALCULATION TOOLS FOR PILOT VIENNA TRIGA MARK-II RESEARCH REACTOR

Applicability of EPRI Decommissioning Pre-Planning Manual to International Decommissioning Projects

IAEA SAFETY STANDARDS for protecting people and the environment. Predisposal Management of Radioactive Waste from Nuclear Fuel Cycle Facilities

Joint ICTP-IAEA School on Nuclear Energy Management. 15 July - 3 August, Lecture Notes. I. Mele IAEA, Vienna, Austria

IAEA SAFETY STANDARDS for protecting people and the environment. Predisposal Management of Radioactive Waste from Nuclear Fuel Cycle Facilities

NUCLEAR SAFETY REQUIREMENTS BSR

DECOMMISSIONING OF NUCLEAR FACILITIES IN UKRAINE

Pham Hoai Phuong and Pham Van Lam NUCLEAR RESEARCH INSTITUTE, VAEC

TOPICAL SESSION MANAGEMENT OF DECOMMISSIONING WASTES

C. Kennes - C. Mommaert - M. Van haesendonck (Bel V) H. Libon - A. De Backer (Belgonucleaire) Decommissioning of Belgonucleaire MOX plant

Module X. Operational safety including operational feedback

IAEA SUPPORT OF GLOBAL DECOMMISSIONING ACTIVITIES

Decommissioning Group Ketut Kamajaya

2007 ANS Topical Meeting on Decommissioning, Decontamination and Reutilization September 2007, Chattanooga, TN, United States of America

ANSTO s POLICY for MOATA & HIFAR. Prepared by John Rowling November 2007

Decommissioning of Nuclear Facilities: The Work Ahead and How to Succeed

New Swedish Regulations for Clearance of Materials, Rooms, Buildings and Land Efraimsson, Henrik Swedish Radiation Safety Authority, SWEDEN

Best practices for preparing vessel internals segmentation projects

IAEA-TECDOC-1478 Selection of decommissioning strategies: Issues and factors

0 SUMMARY 4. 1 INTRODUCTION AND METHOD Purpose Method Scope and Assumptions Scope Assumptions 12

Regulation of existing and new nuclear power stations in South Africa in the light of the Fukushima Accident

WM2013 Conference, February 24 28, 2013, Phoenix, Arizona USA. Factors Impacting Decommissioning Costs 13576

Decommissioning Worldwide and NEA Activities

P. Brennecke, S. Steyer Bundesamt für Strahlenschutz Willy-Brandt-Strasse 5, D Salzgitter, Germany

Use of PSA to Support the Safety Management of Nuclear Power Plants

Regulatory Issues and Challenges in Preparing for the Regulation of New Reactor Siting: Malaysia s Experience

WM2012 Conference, February 26 March 1, 2012, Phoenix, Arizona, USA

RESEARCH REACTOR DECOMMISSIONING PLAN

Status of Decommissioning Preparation for Kori #1

Radioactive Waste Management Agency. and. Nuclear Safety Authority. in Belgium

Safety principles of radioactive waste management activities and supportive IAEA documents

Low-Level Waste and Radiation Management

The Evolution of System Safety in the Canadian Nuclear Industry

ENVIRONET Network on Environmental Management and Remediation. Terms of Reference

WM2014 Conference, March 2 6, 2014, Phoenix, Arizona, USA

S z5a MPC&D July 31, U. S. Nuclear Regulatory Commission Attn: Document Control Desk Washington, D. C

European Commission. and the environment. Decommissioning of nuclear installations in the European Union

DECOMMISSIONING LESSONS LEARNED AT YANKEE ROWE. M. S. Terrell, D. McGee, Duke Engineering and Services (USA)

THE ROLE OF THE WORLD'S LARGEST INTERIM STORAGE FOR WASTE AND FUEL WITHIN THE DECOM PROJECT OF 6 WWER REACTORS IN GREIFSWALD AND RHEINSBERG (GERMANY)

Development of technologies for the processing and disposal of radioactive waste

International Atomic Energy Agency. Impact of Extreme Events on Nuclear Facilities following Fukushima. Dr C H Shepherd Nuclear Safety Consultant, UK

STRUCTURAL RADIATION SAFETY AT A NUCLEAR FACILITY

The EnBW Strategyfor Decommissioningand DismantlingofNuclearPower Plants»

ENTERPRISE OF STATE CORPORATION "ROSATOM

SAFETY GUIDES. Deterministic Safety Assessment РР - 5/2010 ÀÃÅÍÖÈß ÇÀ ßÄÐÅÍÎ ÐÅÃÓËÈÐÀÍÅ BULGARIAN NUCLEAR REGULATORY AGENCY

The Status ofdecom m issioning in Indonesia

CLASSIFICATION OF SYSTEMS, STRUCTURES AND COMPONENTS OF A NUCLEAR FACILITY

Background. Introduction. Overview of vendor design review process

The decommissioning of nuclear plants and facilities is

Decommissioning of the Fukushima Daiichi Site: Status and Continuing Work

Safety Documents for Research Reactors

WM2012 Conference, February 26 March 1, 2012, Phoenix, Arizona, USA. Treatability Variance for Containerized Liquids in Mixed Debris Waste 12101

German contribution on the safety assessment of research reactors

Licensing Nuclear Power Plants in Canada. Ensuring Safe and Environmentally Acceptable Operations

Interim Guidance on the Regulation of In-situ Disposals of Radioactive Waste and Residual Radioactive Contamination on Nuclear Authorised Premises

Decommissioning plans for TVO's new reactors

Zion Project Overview S. Chris Baker VP EH&S

Decommissioning the North Korean Nuclear Facilities: Approaches and Costs 1

during Normal Operations

Mark Ramsay BEng MSc MSRP, CRadP

ACCESS CONTROL AND WORK AREA SETUP RCT STUDY GUIDE State responsibilities in using or initiating a RWP.

SNRIU Nuclear installation modifications

Occupational Radiation Protection in Radioactive Waste Management

Guidance on the Use of Deterministic and Probabilistic Criteria in Decision-making for Class I Nuclear Facilities

Benefits from R&D for D&D Projects Preparation

Power Generation. Ronaldo Jenkins Electrical Engineering Branch Chief Office of New Reactors (NRO)

2009:14. Review of Legislation and Regulatory Framework in Ukraine with Regard to Environmental Radiation Monitoring

Radiation Protection of the Public and Protection of the Environment

Spanish Management Issues in Radioactive and Nuclear Waste Materials Dr. Amparo González Espartero

GUIDELINES FOR REGULATORY REVIEW OF EOPs AND SAMGs

TECHNICAL MEETING ON TECHNICAL SUPPORT ORGANIZATION (TSO) ROLE AND RESPONSIBILITIES May 2013

Date: December 19 th From: Kerrie Blaise (Canadian Environmental Law Association)

IAEA Technical Cooperation Projects on Management of Non-standard and Historical Radioactive Waste from the A1 NPP Decommissioning

WGFCS Workshop Periodic safety review of French fuel cycle facilities Martine BAUDOIN and Jean-Pierre CARRETON

Joint ICTP-IAEA School of Nuclear Energy Management November Workforce Planning for Nuclear Power Programmes

Safety Implication for Gen-IV SFR based on the Lesson Learned from the Fukushima Dai-ichi NPPs Accident. Ryodai NAKAI Japan Atomic Energy Agency

Key Performance Indicators for the. European Sustainable Nuclear Industrial Initiative

Dismantling of nuclear facilities in France: what is at stake?

Optimization of Reactor Pressure Vessel Internals Segmentation in Korea

The Chernobyl shelter industrial site, where the New Safe Confinement will be constructed (Photos: PMU)

IAEA-TECDOC Managing the First Nuclear Power Plant Project

Readiness for Regulating Small Modular Reactors

RESEARCH REACTOR FRJ-1 (MERLIN) THE CORE STRUCTURES OF THE REACTOR BLOCK ARE DISMANTLED

Standardised Reporting of Radioactive Discharges from Nuclear Sites

BAE SYSTEMS Marine Ltd s strategy for the decommissioning of the Barrow nuclear licensed site

Olli Vilkamo; Kirsi Alm-Lytz Radiation and Nuclear Safety Authority, STUK. Radiation Safety in New Build

Swedish action plan. for nuclear power plants

PROBABILISTIC SAFETY ANALYSIS IN SAFETY MANAGEMENT OF NUCLEAR POWER PLANTS

- 1 - Ingenieurgesellschaft für wissenschaftlich technischen Umweltschutz

Preparation for Future Defuelling and Decommissioning Works on EDF Energy s UK Fleet of Advanced Gas Cooled Reactors

Enhancement of Nuclear Safety

BIOMEDICAL WASTE FACILITY INSPECTION REPORT* Facility name: Permit #: Date of Inspection:

Working Party on Decommissioning and Dismantling (WPDD)

The Role of a UK Post Irradiation Examination Facility in the Treatment & Disposal of Problematic and Poorly Characterised Nuclear Fuels

OELG Event Categories

REGULATORY CONTROL OF SAFETY AT NUCLEAR FACILITIES

ICFD Session 2, Cost Estimation Stockholm, Sweden - 21 September 2016 Michael Lackey P.E. Vice President - Nuclear Operations

Transcription:

Decommissioning Planning Ingemar Lund - Swedish Radiation Protection Authority, SSI, Sweden IAEA Regional Workshop: Legal and Regulatory Aspects of Decommissioning of Research Reactors Manila, Philippines, 26-30 June 2006 Objective Discuss the decommissioning planning process, the key points of the planning process, and the importance of early planning Work breakdown structures 1

Decommissioning Planning The operator should prepare a comprehensive Decommissioning Plan, DP, with purpose to document & display how decommissioning activities can be safely performed Successful decommissioning depends on careful and organized planning, consistent with regulatory requirements Ideally decommissioning planning should start already at the facility design stage and not after shutdown one plan for each facility! General Planning The extent, content and detail of the DP depends on the complexity and hazard potential of the installation Adequate financial resources should be available to ensure decommissioning of any nuclear facility Relevant facility records are critical in the development of the decommissioning plan 2

Decommissioning Planning - Key Elements Review of decommissioning strategies Specific studies to support selected strategy Feasibility/ Cost-Benefit analyses Cost estimate for the work at the actual site Schedule for performing the work at the site Technical scope of the decommissioning effort Proper staffing and training Technical / Management Technical issues are often less critical than good management and planning Safety and Radiation Protection are prime! Decommissioning Planning Three stages of planning are usually recognized: Initial Planning On-going Planning Final Planning Degree of detail will vary from facility to facility and increases from initial to final decommissioning plan (DP) Access to relevant facility records is a critical issue when planning for decommissioning Planning is an evolutionary process. The DP is a living document The planning successively becomes more detailed, refined and definitive 3

STRATEGY IMPLEMENTATION The overall decommissioning strategy to be adopted should be identified as early as possible in the planning process Initial Planning An initial Decommissioning Plan should be prepared and submitted for each construction application for a new facility This plan would contain a lower level of detail than that which would be contained in a final DP Operating facilities without an initial decommissioning plan should have one prepared without undue delay 4

Ongoing Planning During facility operations, the decommissioning plan should be regularly reviewed, updated and made more substantial with respect to: Facility changes, incidents/abnormal operating events Regulations and government policy Technological advances Cost estimates and financial provisions Also to be included into the DP are safety considerations and experience from refurbishment activities Final Planning At final shutdown of the facility, the operating organization should initiate detailed studies and finalise planning for decommissioning The operating organization should submit an application for decommissioning including a final DP for review and approval by the regulatory body The DP may be amended or refined as the decommissioning proceeds 5

Final Planning If phased decommissioning - the operator should supply the regulatory body with a description of: The proposed surveillance and maintenance program The existing or new systems or programs necessary for facility maintenance The systems to be installed to perform deferred dismantling The proposed frequency for review of the above items The number of staff required and their qualifications during the deferral period Decommissioning Planning The final DP should be formulated as the first step in the decommissioning process by a dedicated and complete project team Adequate financial resources should be available to ensure decommissioning of any nuclear facility For deferred decommissioning, special attention should be given to periodic adjustments for inflation, technological advances, waste costs and regulatory changes 6

Decommissioning Planning Typical contents of DP - I Facility description and operational history Legal and regulatory requirements Radioactive and toxic material inventory Assessment and selection of decommissioning strategy (safety, wastes, doses, costs, funding, justification) Project management (including organization, monitoring, review, training, reporting, records) Decommissioning activities (phases, work packages, decontamination, dismantling, waste management, surveillance & maintenance) Decommissioning Planning Typical contents of DP - II Safety assessment (doses, ALARA; monitoring, protection and emergency systems; physical security & material control; risk analysis safety management & functions, justification) Radiation protection and Safety programme Waste Management (important!) Release criteria measurement/verification methods Environmental impact assessment Quality assurance programme 7

Decommissioning Planning Typical contents of DP - III Details of the estimated costs and source of funding Continued surveillance and maintenance (deferral) Future decommissioning activities (deferral) Final radiation survey proposal Outline of final decommissioning report Waste Treatment is important Waste Treatment is important The waste management plan is an integral part (or an associated document) of the overall decommissioning plan. Various treatment systems may be required Solidification, Removal of water Immobilization of the contaminants Preparation for subsequent treatment Reduction of waste volume Purification of water for reuse/discharge Separation of a contaminant from a bulk matrix 8

Other supporting Documents Characterization Plan Characterization Report Public Relations Plan Final Survey Plan Final Survey Report Final Report for the Decommissioning Project Records The Planning Basis I Records guide the decommissioning process from the start of planning, through decommissioning and then serve as a record of the decommissioning Records are also critical for Accidents and liability issues Institutional records Provide lessons learned Facilitate information exchange Various equipment and systems for records management and control are available 9

Records The Planning Basis II Never too early for compiling key decommissioning records Loss or lack of records (institutional knowledge) is precarious to the decommissioning process Inability to access records due to changes in records storage technology (long term issue) Keep duplicate records in two separate secure locations Some Common Problems Different fabrication technique & materials of construction radiological conditions and/or other hazards Inaccurate drawings Accessibility Procedure deficiencies Operator workarounds Temporary modifications 10

Unexpected occurrences or accidents Removal of fuel (loss of cooling, dropped elements, criticality) Survey of Radiation (high radiation field, malfunctioning of equipment & monitoring instruments) Decontamination (fire in solvent, rupture of vacuum filter bag, spillages, loss of essential services) Dismantling & removal of concrete (loss of containment, cutting accidents, inadequate mechanical supports, equipment failure, dropped loads, combustible waste fire, explosions of oxyacetylene) Prepare for the unexpected! Error reduction IAEA Safety Guide WS-G-2.2 DECOMMISSIONING OF MEDICAL, INDUSTRIAL AND RESEARCH FACILITIES 11

IAEA Safety Guide WS-G-2.2 DECOMMISSIONING OF MEDICAL, INDUSTRIAL AND RESEARCH FACILITIES Example Work Breakdown Structure Reactor Decommissioning Plan Safety documentation Preparatory Activities Care and surveillance Dismantling Activities Decommissioning Plans Building modifications Monitoring regime Decommissioning start up activities Regulatory documentation Maintenance site prepared Building maintenance regime Set up waste management systems Safety Case Baseline site survey Set up dismantling systems Preparation for care and surveillance Dismantle facility Waste treatment, packaging and storage End point Activities M T Cross, RWE NUKEM 12

ATSR - Argonne Thermal Source Reactor TFTR Decommissioning WBS Example TFTR Decommissioning Project PPPL Site, NJ Engineering (1.0) Field Operations (2.0) Project Management (3.0) Health Physics & Safety (4.0) Radioactive Waste Operations (5.0) Oversight & Planning (1.1) Oversight & Support (2.1) Project Office (3.1) Health Physics Oversight (4.1) Radwaste Management (5.1) Area Preparations (1.2) Area Preparations (2.2) Work Control Center (3.2) Safety Oversight (4.2) Containers and Supplies (5.2) Non-Tokamak Removals (1.3) Non-Tokamak Removals (2.3) Configuration and Document Control (3.3) Transportation and Disposal (5.3) Tokamak Removal Engineering (1.4) Tokamak Removals (2.4) Mixed Waste Management (5.4) Source: Lawrence E. Boing, ANL 13

from JAPCO/Tokai-1 NPP Decom. Web site Cost Elements Standardised List of Cost Elements (NEA / EC / IAEA) 01 Pre-decommissioning actions 02 Facility shutdown activities 03 Procurement of general equipment and material 04 Dismantling activities 05 Waste processing, storage and disposal 06 Site security, surveillance and maintenance 07 Site restoration, cleanup and landscaping 08 Project management, engineering and site support 09 Research and development 10 Fuel and nuclear material 11 Other costs also Labour, Capital Equipment and Material, Expenses, and Contingency. http://www.nea.fr/html/rwm/reports/1999/costlist.pdf 14

References IAEA Safety Guide WS-G-2.1 IAEA Safety Guide WS-G-2.2 IAEA Safety Guide WS-G-2.4 IAEA Technical Reports Series #351 IAEA Technical Reports Series #375 IAEA Technical Reports Series #399 IAEA Technical Reports Series #411 Summary Planning for decommissioning should be an ongoing process, not a feared process The entire decommissioning process should be well planned and the roles of various parties should be clearly defined Numerous useful IAEA reference documents are available use them! Early and good planning makes dividend later! 15