Virtual power Plant Concept in Electrical Networks

Similar documents
fenix The FENIX project: Integration of Renewables and Distributed Generation in Networks through aggregation

EU policy objectives and European research on Smart Grids

Southern Demonstration

Gas Natural Fenosa s Experiences on Renewable Energy Integration

Microgeneration and new end-use technologies in ADDRESS, INCA and SEESGEN-ICT

into Smart Grids with Virtual Power Plants

EDF and Integration of Distributed Energy Resources

SmartNet project: TSO-DSO interaction architectures to enable DER participation in ancillary services markets

WP2: Metering, DSM and DER flexibility Management

Optimal Demand Response Bidding and Pricing Mechanism: Application for a Virtual Power Plant. Authors: Ashot Mnatsakanyan Scott Kennedy

The new role of DSO. David Trebolle Trebolle Manager, Active Networks and Network Analysis Applications Gas Natural Fenosa

Virtual Power Plants general review: structure, application and optimization

Distribution System Operator (DSO) Construct as a Bridge for End-to-End Transactive Operation

Bosch Energy Storage Solutions Smart integration of storage

active demand Active Demand: main results, lessons learnt and recommendations from the ADDRESS European project Régine Belhomme, EDF SA

Simulatie van het EU-wijde elektriciteitsysteem. Modellering van de elektriciteitsmarkt en de hierin gebruikte elektriciteitsinfrastructuur

Outcomes and recommendations GREDOR

Planification du réseau, exploitation et gestion : nouvelles approches dans la recherche

A*STAR Funded IEDS Project - Microgrid Energy Management System. by H B GOOI

La regulación del incierto futuro de los sistemas eléctricos

Electricity Grid of the Future. Program Director: Dr. Sonja Glavaski

Active Distribution Networks

Demand Response as Flexibility Provider: what are the challenges to achieve its full potential?

MAUI SMART GRID PROJECT

Integration of RES: What are the local system challenges and how to organise a market for flexibility?

EMS of the Future. EMS Users Conference Chicago, Illinois. John McDaniel September 20, Proprietary 1 Experience you can trust.

SMART GRID SCENARIO. Marina Egea,

NEW R&D Status of ongoing projects and future opportunities. Labora and III China-Portugal Energy R&D Seminar 2017

Preparing the Market for Virtual Power Plants :DRAFT. Fiona Riddoch COGEN Europe, Brussels

Innovation & Grid Modernization at ComEd. Laura García García Grid Strategy & Analytics Commonwealth Edison

Die Stadt als Speicher Making Cities Smarter

Variable Renewable Energy Sources in Distribution Networks Martin Braun Fraunhofer IWES & Universität Kassel

Two Settlement PJM /06/2016

Economic assessment of distribution network planning: a practical approach

SEA - MILAN AIRPORTS DREAM PROJECT. ETIP SNET South-Eastern Regional Workshop Nicosia (Cyprus), November, 23 th 2017.

VIRTUAL POWER PLANTS RENEWABLE ENERGY PRODUCTION OF THE FUTURE

Costs and Benefits of the Smart Grid. Hans de Heer 10 October 2012

1 Workshop on Power System Testing

Medium voltage products. Technical Application Papers No. 17 Smart grids 1. Introduction

SPP at a Glance. Located in Little Rock. Approximately 600 employees

The Impact of Wind Generation on System Services in Ireland

CERTS Microgrids. Tom Jahns Professor, University of Wisconsin-Madison. LPPC Rates Roundtable May 21, 2013

Microgrid EPFL Méthodes innovantes issues de la recherche

IV Riunione IU.NET. Towards the Internet of Energy A pathway to electric revolution. Paolo Tenti, Tommaso Caldognetto

Green+ ELECTRICITY AUTHORITY OF CYPRUS. NER 300 European Program 2 nd call of proposals Zero Energy Mountains of Cyprus. Green

Estimation of Active and Reactive Flexibility Range in Primary Substations

Smart Grid Concept, Applications and Lessons Learned from Recent Deployments

I-SEM Testing Tariff High Level Options Consultation

California Grid Operations: Current Conditions and Future Needs

Controlling the Electricity Load in Future Intelligent and Integrated Energy Systems

Virtual Power Plant Simulation

EcoGrid EU. Analysis of the European Framework for Balancing Power opportunities and new trends identified within the EcoGrid EU project 20/05/2013

DEMAND SIDE WATER ELECTROLYSIS COMPROMETIDOS CON SU FUTURO

SmartNet: Aggregator role

Innovative business models making use of the flexibility of the industrial electricity demand for integrating wind energy

Regulatory Recommendations for the Deployment of Flexibility

VTT WORKING PAPERS 166. Murtaza Hashmi. Survey of smart grids concepts worldwide

Key Attributes of Possible Designs for Flexible Distribution System Operation

Master Thesis Jonathan Wood and Stefan Funk EnergyLab

Section 3 Characteristics of Credits Types of units. Economic Noneconomic Generation.

Renewable sources of energy, dispatching priority and balancing the system, facts and options: Part I

RES forecasting from a TSO perspective

SMART GRID CONCEPTUAL MODEL

Renewable Integration at ERCOT

IEA-DSM Task XVII: Country Report Austria

2750 Monroe Blvd Audubon, PA

Direktvermarktung von Strom auf dem Großhandelsmarkt: Rahmenbedingungen und Ausblick Ein deutschfranzösischer

Smart grids summit, Nice February 2015, 19th

Session 1 DER Integration and Grid control

Modeling of the Dynamic Behavior of the Island Power System of Cyprus

Schedule 2 TECHNICAL INFORMATION

Introduction to the PJM Markets

IMPROVING DISTRIBUTION SYSTEM PLANNING TO INCORPORATE DISTRIBUTED ENERGY RESOURCES

The value of local electricity storage in a smart grid: How important is intermittency?

International ejournals

New England States Committee on Electricity

MARKET MODELS FOR AGGREGATORS. Activation of flexibility

6.1.9 IFM Initial Conditions

California Independent System Operator Corporation Fifth Replacement Electronic Tariff

Flexibility services in the electrical system

TotalFlex demonstration

HANDLING OF FLUCTUATING WIND PRODUCTION ON THE EL SPOT MARKET,

Energy storage in intelligent energy networks

Where is moving the electricity sector and how are Electric. Industry Investment Decisions Influenced by Potential

Transmission and Distribution System Interaction

An Aggregator Framework for European Demand Response Programs. Rune Hylsberg Jacobsen Department of Engineering Aarhus University, Denmark

Consultation on Connecting Further Generation in Northern Ireland. Call for Evidence

the most promising locations for new renewables in the Imperial CREZ.

Communications & Situational Awareness

Energy Markets - The Basics

Case 2 Croatia - project microgrid Positioning. Ivona Štritof EU and Regulatory Affairs Department

Evaluation of Smart Grid projects for inclusion in the third Unionwide list of Projects of Common Interest

Virtual Power Plant Introduction of the project

Wind power variability and power system reserve requirements at 2020 at 2030 scenarios for offshore wind power in Northern Europe

Proof of Concept and Prototype

ANTICIPATING AND ADDRESSING SECURITY CHALLENGES IN AN EVOLVING POWER SYSTEM

Potential Barriers and Solutions for Active Demand: a Qualitative Analysis

ISO Smart Grid Use Case

The Role of TSO to integrate Renewables in Germany

Smart Buildings in Smart Grids. Vesna Mikulovic, Senior Strategy Manager

Transcription:

Virtual power Plant Concept in Electrical Networks J. Corera Iberdrola Distribution on behalf of a step towards the future of a step towards the future of electricity networks 1

Introduction to the VPP 2

VPP FENIX solution to DER integration Overall aim: Integrate DER cost effectively in the operation and development of electricity networks Integration: solving system (network) problems with DER FENIX approach : Virtual Power Plant (VPP) as key delivery mechanism for integration of DER and demand response 3

VPP analogy with conventional transmission system operation Large generation is integrated in transmission network operation and development At transmission level power plants are the main source of system control (balance between supply & demand) Operators control transmission network flows by modulating outputs of generators In the future there will be a large number of small generators connected to the distribution network DER (and demand response) to provide control of distribution and transmission networks This integration will enhance the value of DER 4

TSO network constraint (congestion) management Overload = 5

VPP concept for network control 400 kv 400 kv 400kV = 132kV VPP P, Q P, Q (&L) 33kV L 11 kv/0.4 kv 11kV L Characteristics: (1) Output (2) Reserve (3) Dynamic response (4) Cost characteristics LV area 1 LV area 2 TVPP area 1 TVPP area 2 6

VPP source of control VPP as a source of control of T & D Networks VPP to be used by DSOs/TSOs to support system operation Frequency control (TSO) Voltage control (TSO and DSO) Flow control (TSO and DSO) Stability enhancement (TSO) Security and reliability enhancement (TSO and DSO) 7

Example: Alcora substation (20kV) Cotasa feeder 2.1 MW COTASA 10 MW INCOAZUL 1 MW 0.3 MW TILESA ATOMISA 2 MW 2 MW 2 MW 2.2 MW 0.5 MW 0.5 MW 20 MW 9.1 MW 0.5 MW 2 MW 1 MW 0.5 MW 13 MW RID SUPPLY POINT 5 MW 6 MW 15 MW 8

Cotasa feeder and generation data COTASA INCOAZUL TILESA ATOMISA REST OF THE NETWORK 2 MW 10 MW 2 MW 1 MW 2.2 MW 0.3 MW 2 MW 0.5 MW 0.5 MW 0.5 MW 2 MW 1 MW 0.5 MW Index D name Pset Pmin Pmax Qmin Qmax Offers Bids *scheduled (MW) (MW) (MVAr) (MVAr) *Inc *Dec (MW) (MW) (MW) (MVAr) (MVAr) ( /MWh) ( /MWh) 1 COTASA 10 2 15.7-12 12 60 10 2 INCOAZUL 0.96 0 1-0.5 0.5 50 10 3 TILESA 0.29 0.25 0.3 0 0 40 10 4 ATOMISA 2 1 8-4 4 30 10 Total: 13.25 3.25 25-16.5 16.5 9

PQ diagram of Cotasa VPP 15 10 Reactive Capability (MVAr) 5 0-5 -10 0 5 10 15 20 25 30-15 P VPP (MW) 10

Re-dispatch cost function of VPP 350 300 250 200 R (Cost) 150 100 50 0-50 -100-150 0 5 10 15 20 25 P VPP (MW) 11

Project FENIX 12

FENIX Project coordinates FENIX is an European collaborative project, partly funded by the European Commision within the 6th Framework Programme for Research It was launched in October 2005 and its duration is 4 years 20 partners are involved The total budget is 14,7 MEuro 13

FENIX partners 2 TSO 3 DSO 4 Manufacturers 3 ICT specialists 7 R&D centers & Universities 1 Business consultant 14

FENIX Challenges Identify potential present (and future) contribution of DER to networks that can be performed at advantageous cost (see Fenix at poster session). Identify network needs and the way to satisfy them using DER Revise regulations, incentive mechanisms and contractual relationships between the different participants (DER, aggregators, network operators and markets), to enhance DER contribution to the network with a fair economic return Investigate aggregation (VPP) so the limited size of DER and their non-deterministic behaviour limitations can be overcome Develop the ICT architecture to make it work: At DER level: FENIX box At VPP level: DEMS systems At system operators: revision of EMS and DMS tools 15

Challenges in characterising VPP VPP is a complex generating plant Diversity of technology and locations electricity led, heat led CHP, weather condition driven output Characteristics of demand (process, amount of storage, load recovery patterns) Inter-temporal dependencies Uncertainty VPP output, reserve capabilities and dynamic response characteristics (wide range of time horizons to be considered from seconds, minutes to hours) Role and value of ICT to facilitate VPP and reduce uncertainty (data management and forecasting tools) 16

Fenix players Energy Markets Transmission System Operator Distribution System Operators FENIX software Households Aggregators CHP Industrial & commercial Wind farms 17

Fenix agent functionality and architecture 18

VPP Functionality: Market and System Management participation (UK pilot context) 19

VPP Functionality & Interaction Fenix Box & VPP Optimise position of local of DER and demand, transmit data on DER position and operating parameters, costs etc. CVPP (Commercial Virtual Power Plant) Aggregates output from Fenix Box/VPP (before market closure) Facilitates access to wholesale electricity markets Reduces imbalance risk TVPP (Technical Virtual Power Plant) Aggregates output and BOAs from Fenix Box/VPP (at market closure and during system balancing) Facilitates access to transmission system balancing congestion management markets Manages local constraints on distribution system Facilitates access to scheduled ancillary services markets 20

Scalability: from few to million units Level 4 DEMS EMS - DMS Internet Level 3 Aggregation (100 to 5000 units) Service to Market Stakeholders VPP Concentrator Level 2 Aggregation (10 to 100 units per level 1 aggregator) Fenix Box Type 1 (Few MW) Fenix Box Type 2 Fenix Box Type 3 Level 1 Metering L (100kW) (10 to 500 units per level 2 aggregator) Meter L (100kW) Smart Meter Local Plant Control Smart Meter (100kW) D Controller 21

Fenix deployments: pilot in Spain 22

Alava DSO 30/13,2kV simplified network JUNDIZ 14,4 x 2 Mvar BADAIA 50 MW DER (Wind farms) MW DER (CHP) MW ALI PUENTELARRA Capacitors MVAR Transformation 30/13,2 kv UASCOR 12 MW Transformer 220/30 kv - TSO-DSO Boundary 23 AMARRA TXAORRITXU 14,4 x 2 Mvar 0,5 MW 14,4 Mvar OJAIN MICHELIN 2,7 MW ENVIROIL 47 MW 2,0 MW HOSPITAL HOLZLAN 2,0 MW 1,0 MW SEARSA 2,7 MW Small Hydro units MW 5,4 x 4 Mvar 13,2 kv Several DER 5 MW Capacitors 96,6 Mvar ALSASUA DER 168 MVA Installed capacity ELUEA URKILLA 32 MW ELUEA 30 MW

Southern Scenario Interconnections Interconnections TSO Conventional Conventionalgenerators DSO loads loads Market Fenix Active Active power power Tertiary Tertiary reserve reserve Reactive Reactive power power Ancillary Ancillary services services DER DER going going to to the the market market The goal is to manage DER to provide as much services as the conventional generators do 24

What will be demonstrated? Providing global services (TSO level) 1- Selling large amount of active power in the day ahead market 2- Tertiary reserve, balancing market Providing local services (DSO level) 3- Selling reactive power capacity (PO7.4) (4.3.6.) 4- Help maintaining voltages in lines Providing local services in emergency situations (to be simulated) 5- Use active power generation to avoid load shedding (PO 6.1), help keeping supply in local constrains,. In every use case DSO and TSO should validate feasibility in the proposed solutions: n-1, quality of service (±7% voltage) and overloads 25

Fenix deployments: pilot in UK 26

Woking Network Woking Primary 33/11kV 24MVA Civic Offices 0.11MW CHP (gas) Town Centre CHP 1.8MW CHP (gas) Horsell Primary 33/11kV Brockhill Sheltered Housing 16MVA 30kW PV export Old Woking Primary 33/11kV 12MVA BT, Telephone Exchange 0.8MW diesel gen. Priors Croft Nos 1-32 22kW CHP (gas) Woking Pool in the Park 20kW PV panel 0.2MW fuel cell 0.95MW CHP (gas) 27

Woking Horsell Old Woking 28

lass Moor Wind Farm Peterborough rid 132/33kV 8 x 2MW wind turbines Metering at the interface and at Peterborough rid 132/33kV The operator has little awareness of his operation Fenix Concentrator FB 29

Deployment over the Northern Scenario Web Access DEMS SCADA DEMS Application Server VPP Concentrator Box 4 Internet Wind generation Woking Council & EDF Energie Nouvelle Woking Swimming Pool & Imperial College Labs VPP Concentrator 1 & 2 EDF Energy 1 1 1 1 Fenland lass Moor Windpark (8 Re-Power MM2 2MW each total 16MW) Load under Demand Response Fenix Box VPP Concentrator 3 (Existing CHP SCADA) 33KV L1 3 PV Cell L2 Load under Demand Side Management 1 Woking SS Horsell SS 11KV Old Woking SS 2 Woking CHP Portfolio (total 4MW) 30

Conclusions 31

Conclusions If we want DER to effectively replace central, conventional generation, they have to contribute to system needs Fenix is a first step, however a lot of changes have to take place: Regulatory frameworks have to promote DER contribution DER Technology was not developed with this aim, however, and provided the limitations imposed by the nature of DER, efficient support to the system is possible (example Voltage control) International awareness is required Aggregation will be required to handle large DER penetration 32