Electricity trading and transmission arrangements. Towards better electricity trading and transmission arrangements

Similar documents
Investing under regulatory uncertainty

Generation Capacity Mechanisms and Resource Adequacy Planning

DSR follow on final presentation

About Energy UK. Introduction

Federal Energy Regulatory Commission Working Paper on Standardized Transmission Service and Wholesale Electric Market Design

Uniform Price vs. Differentiated Payment Auctions

TODAY S ORGANIZED MARKETS A STEP TOWARD COMPETITION OR AN EXERCISE IN RE-REGULATION?

CAN YOU RELY ON A RELIABILITY OPTION?

Locational Marginal Pricing II: Unlocking the Mystery

Course notes for EE394V Restructured Electricity Markets: Locational Marginal Pricing

ISO-NE FCM Capacity Market Design Scott M. Harvey. October 9, 2007

1.818J/2.65J/3.564J/10.391J/11.371J/22.811J/ESD166J SUSTAINABLE ENERGY. Prof. Michael W. Golay Nuclear Engineering Dept.

Electricity System Operator Incentives BSUoS Seminar

GB Balancing Arrangements

Future Electricity Markets. Dr. Daniel Matuszak Clean Coal and Carbon Management Office of Fossil Energy U.S. Department of Energy May 24, 2016

Locational Marginal Pricing (LMP): Basics of Nodal Price Calculation

INDEPENDENT SYSTEM OPERATORS (VI + Access Rules vs. ISO vs. ITSO)

Demand Response as Flexibility Provider: what are the challenges to achieve its full potential?

UK Electricity Market Reform: Lessons from a policy and regulatory journey

UK Electricity Market Reform: Lessons from a policy and regulatory journey

Dispatching Variable Generation Resources

Efficient regime for the expansion of renewable energies, further development of the energy-only market and preservation of EU-ETS

Comments of Northern California Power Agency CAISO Load Granularity Refinements Issue Paper. September 20, 2010

Methodology for calculating subsidies to renewables

1st International Conference on Large-Scale Grid Integration of Renewable Energy in India Durgesh Manjure, MISO Energy September 6, 2017

Ofgem s embedded benefits reform minded to decision

Zero Net Carbon Portfolio Analysis

In sickness and in health: improving the analysis of healthcare mergers

Ireland Country Report

2014 Report to the Minister on the Effectiveness of the Electricity Generation and Retail Corporation Regulatory Scheme

Interconnection capacity and regulation

Mergers in the energy sector. Xavier Vives IESE Business School

Tackling Tariff Design. Making distribution network costs work for consumers

Problems in the Organized Markets

Renewable sources of energy, dispatching priority and balancing the system, facts and options: Part I

Lessons from UK energy policy & Energy Market Reform

Section 3 Characteristics of Credits Types of units. Economic Noneconomic Generation.

The economic welfare impacts of reserving interconnector capacity for trade in balancing products

Adam Mantzos Brockley Consulting. Review of cost attribution and cost allocation approaches. A report for Network Rail

Introduction to the PJM Markets

the Real-Time Market will be based on the system marginal costs produced by the Real-Time

Innovative business models making use of the flexibility of the industrial electricity demand for integrating wind energy

Draft Whitepaper to Platte River Board of Directors

EdF/BE: Yin and Yang why complementarity can be problematic

New PJM Rules Contribute To 37 Percent Increase In Capacity Auction Clearing Price

Flexible power generation and interconnection capacity needs of the Italian power system using PLEXOS LT plan.

Flexibility from the Demand Side

11.0 Energy. Summary Energy snapshot

Summary of 2016 MISO State of the Market Report

ANNUAL REPORT ON MARKET ISSUES & PERFORMANCE

Cambridge David Newbery Richard Green Karsten Neuhoff Paul Twomey

U.S. Energy Market Deregulation

IB Economics Competitive Markets: Demand and Supply 1.4: Price Signals and Market Efficiency

APPENDIX B: WHOLESALE AND RETAIL PRICE FORECAST

Electricity market in Germany Does the current market design provide security of supply?

2014 State of the Market

Initial Modification Report No.39. Transfer of Exit Capacity between Northern Ireland Exit Points to permit Secondary Trading of Exit Capacity

Presentation based on study for IEA RETD

COGENERATION: Opportunities in Today s Power Markets

Cost of Service and Public Policy. Ted Kury Director of Energy Studies, PURC

Are the 2020 renewables targets (for electricity and heat) achievable? If not, why not?

INTERNATIONAL EXPERIENCE A report to EDF Energy. November 2010

APRIL Serena Hesmondhalgh Dan Harris Penny Dickson

Executive summary OECD/IEA Executive Summary

Presentation based on study for IEA RETD

California Grid Operations: Current Conditions and Future Needs

ECN Policy Studies 1. INTRODUCTION. Amsterdam, October 10, Note to : Ministry of Economic Affairs. : Adrian Wals Martin Scheepers

Five Minute Settlement. Submission to AEMC Directions Paper May 2017

Energy Supply Costs Information Paper

Headline Germany - Experiences with implementing RES E auctions

ENABLING EMBEDDED GENERATION

Reform in China s Electric Power Industry. - A Case Study of East China s Wholesale Electric Power Market -

Identification of high-level options and filtering criteria

Electricity Restructuring: Looking Back and Planning Ahead

NordREG memo to EMG on the price peaks in the NPS market

Creating New Electricity Markets in Europe to Meet Energy Policy Challenges

Competitive energy landscape in Europe

EVALUATION OF MIDWEST ISO INJECTION/WITHDRAWAL TRANSMISSION COST ALLOCATION DESIGN. Prepared by Scott Harvey and Susan Pope

DS3: System Services Review TSO Recommendations

California ISO. Q Report on Market Issues and Performance. July 10, Prepared by: Department of Market Monitoring

Neas Energy A/S. Electrolysis for grid balancing - BioCat European Power-to-Gas Platform: Second meeting Square Hotel, Copenhagen, 22 June 2016

Economic and Political Constraints on the Demand-Side of Electricity Industry Restructuring

DRAFT. EU consultation on new Energy Market Design ERRA CHAIRMEN MEETING. 6 October 2016

Input to public consultation on ENERGY MARKET DESIGN

CSTF Poll Feedback. 02 June 2014

Comments of Powerex Corp. on Congestion Revenue Rights Auction Analysis Report. Submitted by Company Date Submitted

Final report. Solar feed-in tariff for regional Queensland for

PJM Interconnection Economic Analysis of the EPA Clean Power Plan Proposal

Perfectly competitive markets: Efficiency and distribution

DUTY LAND TAX RELIEF FOR NEW ZERO-CARBON HOMES

Implications of Australian Renewable Energy Mandates for the Electricity Sector

ICIS Power Index Analysis 2015 UK energy prices fall further

Modeling Transmission Outages in the CRR Network Model

Dynamic Price, Product and Messaging Specification

PJM Proposal for Incremental Auction Redesign

PJM ARR and FTR Market

Capacity Performance Training. March 16, 2015

Glossary of Terms in Sustainable Energy Regulation

Technical Bulletin Comparison of Lossy versus Lossless Shift Factors in the ISO Market Optimizations

Capacity Markets in the Northeast:

Transcription:

Agenda Advancing economics in business Electricity trading and transmission arrangements Towards better electricity trading and transmission arrangements The UK is facing the significant challenge of integrating into its electricity market up to 3% of electricity from intermittent wind generation, much of it located far from demand centres. Richard Green, Oxera Associate and Professor of Energy Economics at the University of Birmingham, argues that the current trading arrangements are not fit for purpose in terms of providing efficient outcomes in such a market environment. The market design implemented in the north-eastern United States is likely to be more suitable In Great Britain, electricity trading takes place within the framework of the British Electricity Trading and Transmission Arrangements (BETTA). The principle underlying BETTA is that electricity is traded like any other commodity, although the system does have special features to deal with its unique physical characteristics. Under BETTA, most electricity in Great Britain is traded well in advance of real-time, with prices being agreed through bilateral trades between generators and retailers. Additional arrangements have been put into place to manage the non-storability of electricity and the need to ensure that generation matches demand on a second-by-second basis. Generation and demand levels may be out of balance when the physical volumes of electricity generated or demanded differ from the volumes contracted for in advance. Imbalances also arise due to constraints on the electricity transmission system, which mean that electricity cannot be transported from regions with excess generation to those with excess demand. The system operator, National Grid, is tasked with resolving these short-term imbalances between contracted and physical positions by buying and selling electricity. The market has operated smoothly under BETTA for over eight years, with only one significant failure of generation to meet demand. However, the electricity market is now undergoing considerable changes as a result of the significant renewable energy targets faced by the UK. In order to meet these targets, it is likely that 3% of electricity consumed in the UK will have to come from renewable sources by 22. Most of this renewable electricity is likely to come from wind energy, which is characterised by its variability given its dependence on changing wind speeds. Substantial wind generation creates a number of challenges for electricity markets. First, the variability of wind output creates a requirement to ensure that output from conventional generators (eg, coal and gas) can change quickly in response to sudden changes in wind availability. Second, wind variability implies that very little wind capacity can be relied upon to meet peak demand. Conventional generators will need to be remunerated sufficiently to be available to operate for the few hours in the year when electricity demand is high and wind speed is low. Finally, with most new wind generation in Great Britain expected to be located in the north, and demand located further south, the likelihood of transmission constraints and associated constraint costs is expected to increase. 1 This article asks whether BETTA is suited to meet these challenges. It finds that BETTA is unlikely to result in efficient outcomes BETTA relies on high prices during periods of high demand to ensure that generators are remunerated sufficiently, but prices do not rise high enough to ensure that generators needed to run for short periods of time to meet peak demand are viable. Furthermore, under BETTA, generators receive the same electricity price irrespective of their location and are consequently not incentivised to reduce their impact on transmission costs. The market design used in parts of the USA, incorporating explicit capacity markets and locational marginal pricing, is likely to provide more efficient signals for investment and generators operations. This article is based on Green, R. (21), Are the British Electricity Trading and Transmission Arrangements Future-proof?, forthcoming in Utilities Policy. Oxera Agenda 1 October 21

Assessment of trading arrangements To assess the suitability of BETTA and alternative trading arrangements, their ability to meet the following objectives is considered: ensuring efficient operation by generators connected to the system, such that generation is carried out by lowest-cost generators. At the same time, transmission constraints need to be respected, and adequate reserve generation capacity made available to deal with unexpected changes in demand (arising, for instance, due to changes in wind speed or failures in conventional generators); allowing generators to connect to the transmission network in a timely fashion, provided that the system can safely cope with additional generation capacity; giving generators the incentives to build new generators (or keep old ones open) if capacity is needed, and to close them if it is not. Impact of renewables Penetration of up to 3 of wind generation by 22 (as compared with 5 today) is likely to have significant implications for the electricity wholesale market. First, fluctuations in wind output imply that conventional and nuclear generators will face greater hour-to-hour changes in the demand that they will have to meet as wind generation increases (Figure 1). 2 The illustrative figures suggest that the greatest hourly changes in demand net of wind output (ie, demand to be met by conventional and nuclear generators) rise to 13.7 and +17.4, compared with changes in gross demand of 6.3 and +1.1. Market rules will need to ensure that enough generators will change their outputs quickly to respond to these new demand patterns. Second, variable wind generation also affects the number of hours that conventional and nuclear generators will be required to operate. Figure 2 shows the number of hours for which demand exceeds a given level, considering separately gross demand and demand net of wind output (ie, demand that will have to be met from conventional and nuclear generators). It highlights that although peak demand will remain almost unchanged due to wind output, the amount of capacity needed for only a few hours a year will increase. The key market design issue will be in ensuring that this capacity is remunerated sufficiently (or that greater demand-side response is incentivised). Third, given that renewables resources are not evenly distributed across the UK, the majority of new wind generators are likely to be built in the North Sea, a long way from centres of electricity demand in the Midlands and the south. Figure 1 Simulated hour-to-hour changes in electricity demand in Great Britain in 22 6 5 4 3 2 1 Hours 1.9.8.7.6.5.4.3.2.1 change in gross demand change in demand net of wind -15-1 -5 5 1 15 2 Note: The starting point of the demand and load duration curves presented in this figure and Figure 2 are 13 years of hourly electricity demand data between 1993 and 25, obtained from National Grid. Each year is scaled up to a predicted level for 22, assuming future annual demand growth of 1.1%, and basing the scaling on annual weather-adjusted energy consumption. The simulated hourly wind outputs are based on wind speed data from the British Atmospheric Data Centre. Individual weather stations are used to represent 19 onshore and 11 offshore regions, with generation capacities assigned to them in proportion to the amount being planned (or built, or existing) in the British Wind Energy Association Database. The regional wind generation output is based on a standard wind turbine output curve. The simulated demand and load duration curves for gross demand are calculated by summing the scaled-up demand data for the 13 years. The demand net of wind curve is obtained by subtracting the simulated wind output for each hour from the simulated demand in that hour. Figure 2 Simulated load duration curve for Great Britain in 22 gross demand demand net of wind.2.4.6.8 1 Proportion of hours Figure 3 below highlights that wind generation is likely to exceed demand in Scotland for a number of hours in a year, resulting in an increase in transmission constraints. 3 The system operator will have to manage this transmission congestion by constraining the output of some Scottish wind generators and buying extra power from generators further south. Oxera Agenda 2 October 21

Figure 3 Simulated load duration curve for Scotland in 22 7 6 5 4 3 2 1-1 -2-3 -4-5 -6 gross demand demand net of wind Proportion of hours Note: Based on four years of data from April 21 as this is the earliest date for which National Grid publishes detailed data on Scottish demand. Efficient operating decisions How does BETTA perform in incentivising generators to operate efficiently? Efficient operation requires that the costs of generation are minimised, which involves ensuring both that the lowest-marginal-cost generators produce electricity and that the marginal costs of transmission are minimised. The latter include the costs of electrical losses during transmission and the opportunity costs of transmission constraints. The market that BETTA operates in works as follows. Generators commit much of their generating capacity through bilateral trades well in advance of real-time, facing a significant degree of uncertainty over outturn levels of electricity demand and generation input costs. This would not be a concern if higher-cost generators were able to find a lower-cost generator to replace them in short-term markets. Given the low liquidity of GB short-term markets, such costminimising trades are unlikely. Generators face high penalties (imbalance prices) for being out of balance. This incentivises them to produce at less than full capacity as protection against the risk of generator failure and consequent imbalance penalties, tending to increase production costs. Under BETTA, there are inefficiencies in the management of transmission costs by National Grid. Under the existing market arrangements, National Grid avoids arbitraging between high- and low-cost generators when managing constraints, and does not take account of the costs of transmission losses when determining which generators should generate. This tends to raise the overall system costs. Such costs are expected to rise further in future with increasing transmission constraints on the interconnector from Scotland to England as the level of renewable generation in Scotland increases. While it would not be cost-effective to build so much transmission capacity that all constraints are eliminated, the target should be to use existing capacity as efficiently as possible. This may be achieved if generators are exposed to the costs they impose on the transmission system. This would require the introduction of a system of locational marginal prices, whereby the price of electricity and transmission constraint costs are calculated for every point on the system, instead of the current approach of a uniform price of electricity throughout Great Britain. With constraints on the transmission system, the locational marginal prices in exporting areas (where generation is greater than demand) will fall, and those in importing areas will rise. This will provide generators with the correct incentives to increase or reduce output during periods of transmission constraints, helping the system operator to manage those constraints. Such a system of locational marginal prices (or nodal prices) has been operating in three markets in the north-eastern United States (New England, New York, and Pennsylvania Jersey Maryland, PJM) for over ten years (see box below), and could provide a model for pricing in Great Britain. Efficient connection decisions Under the recently introduced connect and manage regime for connecting generators to the transmission system in Great Britain, 4 generators will be allowed to connect as soon as any local work required on the network has been completed, even if this worsens Locational marginal pricing in the north-eastern United States The system operators in New England, New York and PJM operate voluntary markets in which generators offers are used to calculate the marginal cost of electricity at each point (or node) in the network. The day-ahead market accepts bids to buy power and offers to generate and provide reserve capacity for the following day. The system operator calculates an operating schedule that maximises net benefits from trading (ie, the value of accepted bids less the value of accepted offers), while respecting transmission constraints. A real-time market allows for adjustments to the committed volumes at new prices calculated from revised bids and offers from companies able to adjust their positions in the short term. Although much of the electricity is traded bilaterally in advance and markets are voluntary, there is sufficient liquidity for the markets to be attractive to generators. This ensures the minimisation of generation costs. Oxera Agenda 3 October 21

transmission constraints elsewhere. The objectives of this regime include ensuring that enough generators connect to the system to enable the achievement of renewables targets. However, this increase in renewables would also raise transmission constraint costs. How would a regime enabling efficient connection decisions be characterised? Generators would make efficient connection decisions when they face the economic consequences of their location decisions, with net generation revenues being lower in transmission-constrained areas. This would arise because of higher transmission prices or lower electricity prices in such areas. A system based on locational marginal pricing could give generators the correct incentives for their location decisions, with lower revenues being received for connecting in regions with frequent transmission constraints. Locational pricing can pose potential risks to renewables generation because renewable resources are located far from demand centres and are likely to face higher costs with the pricing of transmission with locational marginal pricing. However, these risks can be mitigated as follows. Locational pricing can increase the level of financial support needed by renewable generators located in high transmission-cost areas. This would either reduce renewable investment or raise the cost of the renewables support scheme. The impact on support costs could be minimised with more targeted support schemes for example, through tenders for specific contracts, as occurred in the 199s. This would allow the amount of support to equal the amount actually needed to make specific projects viable. It would also reduce the rents received by generators in favourable locations and make it possible to target transmission costs on those generators that cause them without impeding the achievement of renewables targets. With locational pricing, generators already located in export-constrained areas will see their net revenues fall as generation capacity is added and constraints more frequently become binding. Long-term financial transmission rights may be issued to existing generators to allow them to lock in the prices they expected to receive before new entry took place. Efficient capacity decisions How does BETTA incentivise generators to make sufficient capacity available to meet peak demand? This question is of particular concern because increasing wind generation will imply that some plant will need to operate for only a few hours a year (ie, in periods of high demand and low wind). Under BETTA, generators are remunerated for selling electricity. Alternative market arrangements exist where generators are explicitly remunerated for making capacity available, even when they are not generating electricity. In theory, a market like BETTA may provide the right incentives for making generation capacity available, in particular if prices rise well above the variable costs of the most expensive generators at certain times, allowing generators to recover their fixed costs. Such high prices may be expected to arise when demand for output from conventional generators is high. However, with most trades taking place well in advance, generators will not be able to predict exactly when low wind and high demand create high demand for them. Consequently, they may not be able to adjust their price offers to maximise their revenues. Ofgem s Project Discovery highlights that under the current market arrangements there are significant risks to security of supply in the period leading to 22. 5 It has identified a range of reform options to enable investment to replace retiring power generators and to raise the level of renewables investment. These include an option to have long-term tenders for low-carbon generation and short-term tenders for conventional capacity, as is the case in certain US power markets (see box below). In addition to its proposals for market-based solutions of tendering and capacity mechanisms, Ofgem has proposed more radical reform measures such as the possibility of setting up a central energy buyer that would determine the type and quantity of capacity to be built. Given the success of market-based solutions in the USA, it would be premature to consider such a sweeping departure from the market-based policies of the past 2 years. Annual capacity markets: the US experience In some US power markets, retailers buy capacity to cover their customers demand, in annual auctions held three or four years in advance. These aim to ensure that generators have sufficient incentives to keep capacity available to meet expected demand and reserve requirements. The long-term time interval and potential for security of returns allow both incumbent and new entrant generators to bid to provide capacity. In return for payments from the capacity market, generators provide a hedge on energy prices, ensuring that they do not gain from both capacity and energy markets, giving them a strong incentive to be available to generate when they are most needed. Oxera Agenda 4 October 21

Conclusions The integration of a high proportion of intermittent renewable generation in the electricity market poses significant challenges for trading arrangements. Existing trading arrangements are inefficient in resolving transmission constraints, ensuring efficient location of new generation, and that sufficient capacity is made available to meet short-lived demand peaks. A better approach might be to learn from US markets where trading arrangements address the problems facing the UK. A system of locational marginal pricing, whereby the price of electricity varies across the country, would provide incentives to reduce generation and investment in transmission-constrained areas. In addition, capacity markets might be introduced to increase incentives for the investment in generation needed to meet peak demand. Richard Green 1 Transmission constraints arise when the amount of electricity flowing through the line is at the limit allowed by safety. In the presence of transmission constraints, a cheap but distant generator may have to be replaced with a more expensive but local generator to meet local demand. The opportunity cost of a transmission constraint may therefore be estimated as the cost of generation under a constrained system less the costs under an unconstrained system. 2 The analysis of the impact of renewables draws on Green, R.J. and Vasilakos, N. (29), Market Behaviour with Large Amounts of Intermittent Generation, Energy Policy, 38:7, pp. 3211 2. 3 The simulation results highlight that for around 1,25 hours a year, wind generation is likely to exceed demand in Scotland. This implies that some power will have to be exported across the interconnector with England. However, with the capacity of the interconnector due to rise to 3 by 22, and the existence of 2 of nuclear capacity in Scotland in 22, exports of power are likely to be constrained whenever wind output is greater than 1. In addition, constraints will be tightened further if some conventional generators need to be kept running to allow fast, local responses to changes on the system. 4 Department of Energy and Climate Change (21), Government Response to the Technical Consultation on the Model for Improving Grid Access, July 27th. 5 Ofgem (21), Project Discovery: Options for Delivering Secure and Sustainable Energy Supplies, February 3rd. If you have any questions regarding the issues raised in this article, please contact the editor, Dr Gunnar Niels: tel +44 () 1865 253 or email g_niels@oxera.com Other articles in the October issue of Agenda include: Correctly labelled? The economic benefits of retailer own-brands Taking stock: the Bristol Water inquiry To Timbuktu, and back again: why transport connectivity is important For details of how to subscribe to Agenda, please email agenda@oxera.com, or visit our website www.oxera.com Oxera, 21. All rights reserved. Except for the quotation of short passages for the purposes of criticism or review, no part may be used or reproduced without permission. Oxera Agenda 5 October 21