Review of lessons learned Standards 313, 634, 629

Similar documents
CETCO-VOLCLAY CG-50 SPECIFICATION GUIDELINES MIX IN PLACE

Ponds. Pond A water impoundment made by excavating a pit, or constructing a dam or an embankment.

Manure Storage for Environmental Management Systems

SECTION WATER TREATMENT RESIDUAL REMOVAL, DISPOSAL, AND LAGOON CLEANING

C. Foundation stabilization for pipe and utility structures.

B. Subsurface data is available from the Owner. Contractor is urged to carefully analyze the site conditions.

(1) All sanitary landfill facilities, at a minimum, shall include the following:

Design and Operation of Landfills

SITE INVESTIGATION. Foundation Engineering

LANDSCAPE RETAINING WALLS

SPECIFICATIONS FOR PRECAST MODULAR BLOCK RETAINING WALL SYSTEM (revised 5/8/7)

Avon Lake Municipal Landfill, Lorain County Ohio Administrative Code (OAC) Rule Authorization

SUBSURFACE INFILTRATION SYSTEM DESCRIPTION. Alternative Names: Sump, Drywell, Infiltration Trench, Infiltration Galleries, Leach Fields

SECTION EXCAVATING, BACKFILLING, AND COMPACTION FOR UTILITIES

MAEAP GUIDANCE DOCUMENT FOR COMPREHENSIVE NUTRIENT MANAGEMENT PLANS

Determination of Design Infiltration Rates for the Sizing of Infiltration based Green Infrastructure Facilities

PERMEABLE INTERLOCKING PAVERS

SECTION EXCAVATION AND BACKFILL FOR UTILITIES AND STRUCTURES

CONSOLIDATED EDISON COMPANY OF NEW YORK, INC. 4 IRVING PLACE NEW YORK, NY DISTRIBUTION ENGINEERING TOOLS AND STRUCTURES

CONCRETE SEGMENTAL RETAINING WALL SYSTEM

SEWER SYSTEM DESIGN GUIDELINES

Section 25 Aggregate Subbase

B. Backfill and compact utility bedding and fill placed in the utility trenches between the top of the utility bedding and the subgrade elevation.

BACKFILL COMPACTION FOR VOLCLAY WATERPROOFING: An Essential Ingredient for a Successful Project

PERMEABLE PAVERS PHYSICAL AND GEOMETRICAL CHARACTERISTICS - PAVERS DRIVEWAYS, PERMEABLE DRIVEWAYS & PATIOS CHARACTERISTICS CSA A231.

Design Considerations. Pursuing Dynamic Compaction. waste considered. Pursuing Dynamic Compaction. Page 1 of6

SECTION TRENCHING & BACKFILLING

GUIDELINES FOR INSTALLATION OF ON-SITE SEWAGE SYSTEMS

VIRGINIA POLLUTION ABATEMENT PERMIT APPLICATION

SLAB ON GRADE Insul-Joint or Expansion Joint Material as Required by A/E Specifications AquaCheck Liquid Coating 400 (Waterproofing Membrane) with Aqu

THE FUTURE OF NUTRIENT MANAGEMENT IN WISCONSIN

SUBSURFACE EXPLORATION & GEOTECHNICAL ENGINEERING EVALUATION

Standards for Soil Erosion and Sediment Control in New Jersey May 2012 STANDARD FOR SLOPE PROTECTION STRUCTURES. Definition

TURF-TEC 6 and 12 INCH INFILTRATION RINGS INSTRUCTIONS (IN7-W & IN8-W)

GEOTECHNICAL ENGINEERING REPORT

Subsurface Exploration and Foundation Analysis Proposed New Weight Room / Fieldhouse Building 429 N Highway 83 Leakey, Texas

SECTION SPECIFICATION FOR STONEBRIDGE RETAINING WALL SYSTEM

Applied GeoScience, Inc Hammond Dr., Suite 6 Schaumburg, Illinois

SEGMENTAL BLOCK RETAINING WALLS. Comply with Division 1 - General Provisions and Covenants, as well as the following:

SPECIFICATIONS FOR BRIDGE CONSTRUCTION SECTION 2 BACKFILL. 2.1 General...2-1

GEOTEK ENGINEERING & TESTING SERVICES, INC. 909 East 50 th Street North Sioux Falls, South Dakota Phone Fax

BIG O HDPE TUBING HDPE CORRUGATED TUBING FOR AGRICULTURAL, RESIDENTIAL AND HIGHWAY DRAINAGE INCREASE CROP YIELDS LOWER PRODUCTION COSTS

Redi Rock Specification and Installation Manual

PROPOSED STOCK PILE YARD PHASE 1 SITE: MYRA FALLS MINE

Erosion & Sedimentation Control Policy

Ohio Department of Transportation Division of Production Management Office of Geotechnical Engineering. Geotechnical Bulletin

COMBINED CONCRETE SIDEWALK AND RETAINING WALL. Comply with Division 1 - General Provisions and Covenants, as well as the following:

DIVISION 31 EARTHWORK 2006 Edition, Published January 1, 2006; Division Revision Date: January 31, 2012

VIA U.S. MAIL AND . Re: C & H Hog Farms, Inc. Regulation 5 Draft Permit - Number 5264

Characterizing Engineering Properties of Foundry Sands

GRAY WATER RECYCLING SYSTEMS

A Design Review of Waterproofing Codes

SECTION PERMEABLE INTERLOCKING CONCRETE UNIT PAVEMENT

NGWA s Water Well Construction Standard: ANSI/NGWA 01-14

EINRIP. Specification and Construction Issues

BENTOMAT CL GEOSYNTHETIC CLAY LINER SPECIFICATION GUIDELINES

4 EXTREME FOUNDATION PANELS

Manure Management Manual Revisions

SECTION MONITORING WELL ABANDONMENT

Section Storm Sewers STORM SEWERS PART 1 - GENERAL 1.01 SECTION INCLUDES. A. Storm Sewers. B. Abandonment of Storm Sewers

SEPTIC TANK CONSTRUCTION GUIDELINES

R-TANK SPECIFICATIONS

Sanitary Sewer Extensions, Lift Stations, and Force Mains Engineering Report Form. I. General Information. 1. Name of Facility:

Applications of Waste Tire Products in Civil Engineering

Excavation for Natural Gas Mains and Services

Stormwater Standards. Clackamas County Service District No. 1. Infiltration Testing Guide

ONSITE SEWAGE SYSTEMS*

TYPICAL INSTALLATION INSTRUCTIONS

TRENCH EXCAVATION AND BACKFILL

Instructions for 12 IGT system

ROLES AND RESPONSIBILITIES Small Pond Approval. SWM MD-378 Pond Checklist Training 10/17/07. Exemptions EMBANKMENT HEIGHT. Height of Dam Weir Wall

Building Code of New York State

GUIDE SPECIFICATION FOR CONSTRUCTION

SECTION RIPRAP, BOULDERS, AND BEDDING

1. ADD the attached test hole reports for Well Nos. 19 & 20 to the specifications.

Please include this addendum in your Bid proposal for the above referenced project. Questions are in black ink, and the answers are in red ink.

SECTION FOUNDATION DRAINAGE

Design Guideline for Gravity Systems in Soil Type 1. January 2009

HANDHOLES, PULLING VAULTS AND JUNCTION BOXES

GRAY WATER SYSTEMS FOR RESIDENTIAL BUILDINGS

POST CLOSURE PLAN. CFR (d) GERS Landfill. Pirkey Plant Hallsville, Texas. October, 2016

File No Supplemental November Geotechnical and Environmental Consulting Engineers

Geotechnical Engineering Report South Shore Carter Lake Campground Expansion Northwest of CR 31 and Cougar Run Lane Larimer County, Colorado

4 EXTREME FOUNDATION PANELS

Infiltration Guidelines

Sealing Leaking Ponds

SACRAMENTO COUNTY ASPHALT RUBBER HOT MIX-GAP GRADED (ARHM-GG):

Pennsylvania Stormwater Best Management Practices Manual. Chapter 3. Stormwater Management Principles and Recommended Control Guidelines

SECTION 19 - TRENCH EXCAVATION, BEDDING AND BACKFILL TABLE OF CONTENTS

Economics of Controlled Drainage and Subirrigation Systems

Design Data 6. Loads and Supporting Strengths Elliptical and Arch Pipe. Values of B d

MODULAR CONCRETE RETAINING WALL

BMP #: Infiltration Basin

ORDINANCE NO. 1. A large concentrated animal feeding operation as described in Table 1 in Section 3.07.

Completing an NPDES or SDS Feedlot Permit Application

REPORT OF SUBSURFACE EXPLORATION AND GEOTECHNICAL ENGINEERING SERVICES

CHAPTER 10 PAVEMENT DESIGN AND REPORT TABLE OF CONTENTS

ITEM D-701 PIPE FOR STORM DRAINS AND CULVERTS

GEOTECHNICAL INVESTIGATION I-15 SIGN BRIDGES LAS VEGAS EA JANUARY

SPECIFICATION FOR PIPE CULVERT CONSTRUCTION

Transcription:

Review of lessons learned Standards 313, 634, 629 Dean Sylla, NRCS Appleton Ralph Hemling, DATCP Richland Center WLWCA Conference March 11, 2014 Appleton, WI

Standard 313 Table 1 Site evaluation, construction, waivers Spec 300 review, borrow source evaluations 313 concrete construction

Site Evaluations for Table 1 Need to show separation distances Need to get soil samples from soils that will be left in place for liner Sample all the significant soil layers; don t know which will be needed to construct dikes and 1 recompacted layer Look for tile

Constructing the 1 Liner Basically over excavate the pit and recompact using the appropriate construction spec. Depth of over excavation required depends on the length of the teeth of the footed compactor to be used

For example: Need to end up with a 1 liner, so if the compactor feet are 4, then over excavate 8, compact the in-place soil that is there, and replace the 8 in two lifts to get 1. The reason for this is that the compactor teeth should fully penetrate the lift to get good clay compaction. If the teeth are 6, then over excavate 6, etc.

Since sideslopes are to be 2.5:1 or flatter, should be able to construct using bathtub method.

What to do with Table 1 pits built under previous standards??

Depends on: Permit requirements County, or both County and DNR? Cost sharing requirements; TRM, EQIP, Land and Water, or none? Whether or not the pit is causing a problem

Gather available info: Test pit logs, soil test results, etc As-built plans Private well logs Waste composition (% solids)

Maybe get more info: Test pit with soil samples to check PI, depth to saturation, get deep perm sample, etc. May be able to document pit meets specific discharge requirements and consequently the current standard.

Then evaluate the information

For example, if: Well logs in the area show water supplies are deep, and there are deep clays The P200 tests and PI tests from when the pit was built all exceeded the standard The original borings are deep and show good separation distances

Then there could be good reason to keep the existing pit as-is; and the information gathered could be used to justify a waiver request.

Or if the pit barely met the old standard(s) chances are that it will need to be upgraded.

Take home message: Answer the question Is the existing pit causing a problem, or not first, and The answer will guide you in navigating the permitting and design questions

Wisconsin Construction Specification 300 Clay Liners

Goals of the 300 Spec Ensure good materials are used in construction Ensure that these good materials are installed properly Document both of the above with tests

Good Materials. P200 must be as specified in the construction plans, so it now needs to be called out on the plans. This is because Table 1 requires 40% minimum P200 and Table 2 is 50% minimum P200.so in order to use spec 300 for both Table 1 and Table 2 projects, the P200 needs to be on the plans. Plasticity Index must be more than 12

Good Construction. Clay must be compacted to at least 95% of Standard Proctor dry density, or at least 90% of Modified Proctor dry density.at above optimum moisture. Clay liner permeability must be less than 1 x 10-7 cm/sec

Proctor Tests

Field Density Tests

Documentation. Material quality tests Construction quality tests

Documentation. Field Test Lab Tests

Documentation. Tests are generally done in the order listed One of these is done first, because the results Are used in the field to do this testing A shelby tube sample is taken out of the compacted liner and submitted to the lab to do these tests

Proctor Sample

Field Density Testing

Field Density Testing

Field Density Testing

Undisturbed sampling

Permeability Test

Perm Testing Equipment

Sequence Borrow source evaluation during design phase (designer) Proctor test sample to the lab when borrow pit opened up (contractor) Field density tests during construction

Shelby tube samples ( undisturbed samples ) obtained from the liner and taken to the lab Properly fill holes in liner with clay and bentonite

Assemble all the information into an as-built report Don t forget to document the liner thickness!! Best way is to survey subgrade beforehand and survey finished grade after

Borrow source evaluation From the 313 Standard:

Further insurance: Test samples from each pit for PI and P200 Consider testing a shallow and deep sample from each pit for questionable sources Also test samples for moisture content, this can be important during construction

Still more insurance: Do a Proctor test on a sample, and Run a permeability test at a proctor point that is wet of optimum

A job well done..

Standard 313 Liquid Tight Concrete

Standard 634 Pressure and Velocity Pressures usually low Velocities can be high, but OK if pipe/joints/etc can take it Use pump sizing spreadsheet to figure it out; need pump curve from Mfr

Pressure Testing Standard 634 Limited to severe service pipe Must use water, not air Be careful No agency experience Read more about it.references in 634 companion document

Standard 634 ASTM D2648 Drain pipe listed as pipe that DOES NOT MEET 634, in the 634 construction spec because recylced resins are used in making the pipe ASTM F 667, ASTM F2306, AASHTO M252, and AASHTO M294 meet the standard

Standard 634 Cleanout requirements recently changed NOT required now for pipes carrying wastewater, contaminated runoff, other low solids waste, or transfer pipes to cropland

Standard 634 Requirement for boring every 100 has been questioned, since Pipes may be installed in any location within the soil profile regardless of subsurface saturation or bedrock Maybe a change to the standard is warranted?...stay tuned

Standard 629 Focus on milking center wastewater and silage leachate criteria Constructed wetland criteria and vegetated treatment area criteria moved to their own standards Standard 635 has the criteria for milking center buffers and silage pad runoff treatment

Standard 629 - Silage Few agency people doing designs Not usually specifically addressed in county ordinances Need for systems driven by CAFO permits or EQIP resource concern

Standard 629 - Silage 629 requires all leachate to be collected and stored Feed pad liner criteria are in 629 Choices are soil, membrane, and concrete Most all are concrete

Standard 629 - Silage 635 has the criteria to size VTA based on how much first flush is collected and whether or not the flow in the VTA is less than 1 deep for 25% of the 25yr peak Spreadsheet was recently posted to help with these designs

Standard 629 - Silage Experience is that if a significant amount of first flush is collected, or if 25% of the 25 yr peak is collected nearly all of the annual runoff is collected So it might make sense to just collect all the runoff and not deal with a VTA

Standard 629 Milking Center Waste Criteria hasn t changed, it was just moved around. Constructed Wetland method moved to it s own standard (656) Vegetation part of the Buffer method went to the VTA standard (635) So for milking center waste, business as usual!

Thanks!