Los Angeles Westside Purple Line Extension Project Challenges and Lessons Learned

Similar documents
Purple Line Extension Section 1 Construction Community Meeting September 26, 2017

Purple Line Extension Section 2 Construction Community Meeting February 22, 2018

Westside Purple Line Extension Section 1 Project

Westside Subway Extension Project, Section 1 - Design/Build RFP No. C1045. Pre-Proposal Meeting

Risk Evolution from Planning to Construction on the LA Metro Crenshaw/LAX Light Rail Transit Project

Exposition Light Rail Transit Project

Exposition Light Rail Transit Project

COMPARISON OF PROJECT AGAINST EXISTING CONDITIONS

Santa Clara Valley Transportation Authority Board of Directors. General Manager, Nuria I. Fernandez

WESTSIDE SUBWAY EXTENSION. Hydrology and Water Quality Technical Report

Executive Summary Introduction and Background

6.2.2 Environmental Consequences and Mitigation Measures

On Time Performance. PRESENTATION TO THE BOARD OF DIRECTORS Sept 24, Presented by Kenneth Mc Donald - COO Sonali Bose - CFO

Funding was provided by the City of New York via the Hudson Yards Infrastructure Corporation and Hudson Yards Development Corporation.

Notice of Preparation For Link Union Station (Link US) Project. Joint Environmental Impact Statement and Environmental Impact Report

SAN FRANCISCO MUNICIPAL TRANSPORTATION AGENCY

Phase 2 Exposition Metro Line Project

Agenda. PRE-CONSTRUCTION PUBLIC MEETING September 18, 2014

AUTHORIZE THE CHIEF EXECUTIVE OFFICER (CEO) TO EXECUTE CONTRACT MODIFICATIONS

TECHNICAL MEMORANDUM

EMERGENCY STORAGE PROJECT San Vicente Pipeline and San Vicente Dam Raise Update Presentation Summary

Metro Blue Line Improvements & Project Update

9 Before and After Study Plan

Transbay Transit Center Program

THE PROJECT. Executive Summary. City of Industry. City of Diamond Bar. 57/60 Confluence.

GLX Project AUGUST 2 4 FMCB MEETING

Jim Alexander Director of Design and Engineering, Southwest Light Rail Transit Project

Traffic Noise Introduction to Traffic Noise Analysis and Abatement

LONE HILL TO WHITE DOUBLE TRACK STUDY Community Open Houses May 16 & 17

JCDecaux N O R T H A M E R I C A

Transportation Cost Estimation

Northern Intermodal Transit Facility WHAT IS AN INTERMODAL TRANSIT FACILITY?

Construction Project Briefing

Purpose of the Countywide Transportation Plan SAN FRANCISCO COUNTY TRANSPORTATION AUTHORITY

or (800)

I-405 Sepulveda Pass Widening Project. Community Advisory Committee Meeting June 24, 2010

Hoback 1. Sensitivity Analysis of Light Rail Transit Unit Capital Costs. Total Words: 3824 words + 3 figures + 5 tables = 5824 words.

Stockton Freight & Passenger Rail Mobility Enhancement

CASE STUDY GOVERNMENT. Metropolitan Council. Managing Project Risks through the Establishment of Effective Project Controls. e-builder.

SECTION F UPDATED PERMIT REQUIREMENTS

City of Palo Alto (ID # 7047) City Council Staff Report

SUBJECT: LEASE FOR INTEGRATED PROJECT MANAGEMENT OFFICE

Transportation and Works Department The Regional Municipality of York Yonge Street Newmarket, Ontario L3Y 6Z1

William W. Hay Railroad Engineering Seminar. #2 Capacity Allocation in Vertically Integrated Railway Systems: A Sequential Bargaining Game Approach

UCSF Mission Bay & Dogpatch Construction Community Meeting 11/7/2017

Transit Service Guidelines

Joshua Ritti. Professional Profile. Academic Credentials & Professional Honors

SUBJECT: LEASE FOR INTEGRATED PROJECT MANAGEMENT OFFICE

Hudson River Tunnels, Mega Projects, and Risk A Designer s Perspective

Michael Gillam Deputy Program Director - Southern California

TRAFFIC & TRANSPORTATION COMMISSION AGENDA REPORT

LAFAYETTE RAILROAD RELOCATION, NORFOLK SOUTHERN CORRIDOR

PUBLIC HEARING April 24, 2017

CHAPTER 21: COMMITMENT OF RESOURCES

1.1 Purpose of the Project

2040 Transportation Policy Plan Conversion to Performance Based Planning Basis. 25 th Annual CTS Transportation Research Conference May 21, 2014

W. W. HAY SEMINAR SERIES. Tower 55 Multimodal Improvements NATIONAL UNIVERSITY RAIL CENTER UNIVERSITY OF ILLINOIS AT URBANA-CHAMPAIGN

The Policies section will also provide guidance and short range policies in order to accomplish the goals and objectives.

Airborne Noise and The New NY Bridge Project

FINDINGS CALIFORNIA DEPARTMENT OF TRANSPORTATION FINDINGS FOR THE INTERSTATE 10 CORRIDOR PROJECT SAN BERNARDINO AND LOS ANGELES COUNTIES, CALIFORNIA

S-09: Auburn Station Access Improvements

Project Team. D6 South Miami-Dade Resident Engineer Erik Padron, P.E. D6 Construction Project Manager Dari Vorce

REGIONAL LIGHT RAIL CONNECTOR DOWNTOWN

SIXTH STREET VIADUCT REPLACEMENT PROJECT MONTHLY EXECUTIVE MEETING REPORT JULY 2013

KIEWIT FOUNDATIONS GROUP

Project Steering Committee April 14, 2015

Route 670 Connector Road

Funding Intelligent Transportation Systems in the Los Angeles Region

Washington Metropolitan Area Transit Authority INVITES YOUR INTEREST IN THE POSITION OF CHIEF ENGINEER

Brewster Transfer Station Traffic Flow Alternatives

VRE AT WORK PREPARING VIRGINIA RAILROADING FOR ITS NEXT QUARTER CENTURY

Western Rail Link To Heathrow

Montgomery County, MD

A. INTRODUCTION B. EXISTING CONDITIONS

Phase 2 Exposition Metro Line Project

Route 7 Corridor Improvements Project Reston Avenue to Jarrett Valley Drive Public Hearing

PROJECT SHOWING MINUTES

HS1 Link The View from London

APPENDIX B. Public Works and Development Engineering Services Division Guidelines for Traffic Impact Studies

Durham-Orange Light Rail Transit Project

Anaheim Regional Transportation Intermodal Center (ARTIC) 2014 AIA TAP / BIM Awards

ARLINGTON COUNTY TRANSIT DEVELOPMENT PLAN

MONITORING IMPLEMENTATION AND PERFORMANCE

TRANSPORTATION IMPACT ANALYSIS GUIDELINES FOR ENVIRONMENTAL REVIEW

MEMORANDUM EXAMPLES FOR ILLUSTRATIVE PURPOSES NEXT STEPS. Item 3 Long-Range Plan Task Force May 17, 2017

1. Name of the Project 2. Necessity and Relevance of JBIC s Assistance 3. Project Objectives 4. Project Description

MAINE MEDICAL CENTER

To provide an update on the progress of the Peel Goods Movement Task Force and Peel Goods Movement Strategic Plan.

Caltrain Rapid Rail Plan

407 TRANSITWAY. Planning & Preliminary Design

COEXISTING: FREIGHT FACILITIES & COMMUNITIES. The Capital District Intermodal and Automotive Terminal Rick Crawford, Norfolk Southern April 24, 2013

Transportation Workshop. FORA Staff 9/8/17

Downtown Estes Loop Project Frequently Asked Questions

Metro REVISED CONSTRUCTION COMMITTEE JULY 19, 2012 SUBJECT: METRO SUBWAY STATION ENTRANCE CANOPY PROJECT

KIEWIT FOUNDATIONS GROUP

Fairfax County Countywide Transit Network Study

Introduction to Health Impact Assessment

I-66 Corridor Improvements Outside the Capital Beltway in Northern Virginia, USA

Quarterly Capital Progress Update

Members of the Board of Directors. Laurena Weinert, Clerk of the Board

Transcription:

Los Angeles Westside Purple Line Extension Project Challenges and Lessons Learned Ashok Kothari, P.E. WSP USA, Sr. Vice President Los Angeles, California Michael McKenna, P.E. LACMTA Executive Officer, Program Management Los Angeles, California

Currently WSP Project Director, $8.2 billion Westside Purple Line Ext. Project, Los Angeles, CA since November 2010. Head of Programme Management, London Overground Infrastructure, for the 1 billion design-build East London Line Project and 350 million North London Railway (2005 2010). Ashok Kothari, PE Ashok has worked on several major rail development and extension projects on the $3.2 Billon Bay Area Rapid Transit (BART) Extensions Program, in San Francisco, CA where he led the GEC team and supported BART s transition to a Design-Build Project Delivery System (1989 2005). Ashok worked on the Metropolitan Atlanta Rapid Transit Authority (MARTA) project in Atlanta, GA for over 15 years as Manager of the Project Management Office for a $1.5 billion project (1974 1989). As Global Projects Director, Ashok has been actively involved in peer reviews of transit mega-projects worldwide, program management conferences and seminars and has presented many papers.

Westside Purple Line Extension Wilshire/ Rodeo Westwood/ UCLA Wilshire/ La Cienega Wilshire/ Fairfax Wilshire/ La Brea Existing Purple Line Westwood/ VA Hospital Century City/ Constellation (Existing)Wilshire/ Western Wilshire/Western to Westwood/VA Hospital Stations

Westside Purple Line Extension - View East Towards Century City and Downtown Los Angeles from Westwood Subway Under Wilshire Blvd.

Westside Purple Line Extension Project The FTA Record Of Decision for the 9-Mile Alignment was issued on August 9, 2012 9 Mile Extension

Westside Purple Line Extension Project Features 9.1 mile extension of Metro Purple Line 7 new cut and cover stations Maintenance of way building 80,000 sq. ft. Twin tunnel boring from three locations using 6 pressure-face TBMs $8.2 billion Project 78,700 new daily project trips Travel time downtown to VA Hospital Station 26 minutes Crosses seismic faults in two locations Unique ground conditions at La Brea tar pits Use of Building Information Modelling (BIM): Revit software for 3D computer aided design from PE through Final Design

Westside Purple Line Extension Section 1 Wilshire/La Brea Station

Westside Purple Line Extension Section 2 Wilshire/Rodeo Station

Westside Purple Line Extension Section 3 Westwood/UCLA Station

Westside Purple Line Extension Standard Circulation Units End-Loaded (Typical), Double- End Loaded (UCLA Only) 450-ft long, 28-ft wide center platforms as system standard Standard Crossover Units Critical ancillary rooms are within the Station box Variations of same module are used at all stations Modular Station Design

Westside Purple Line Extension Project Status of Major Construction Contracts Section 1 (3 stations, 3.92 miles) Section 2 (2 Stations, 2.59 miles) Section 3 (2 stations, 2.59 miles) Budget $2.82 Billion (FFGA) $2.50 Billion (FFGA) Capital Cost Est. :$3.48 Billion No. of Construction Contracts Advanced Utilities Relocation Major Construction Contract (s): 5 1 3 3 D/B/B Contracts Complete C1045 Stations, Line &, Tunnels: $1.64 billion D/B Contract NTP Date: 01/12/2015 Contractor - Skanska, Traylor, Shea JV Design Status: Complete Construction Status: 21.8 % (as of 7/31/17) 3 rd. Party Utilities Relocation In Progress C1120 Stations, Line & Tunnels: $1.38 billion D/B Contract NTP Date: 04/26/2017 Contractor -Tutor Perini/O&G JV Design Started 05/2017-14% Complete 1 D/B/B Contract (Bids Received 7/17/17, Anticipated Award in October 2017) D/B Tunnel Contract RFQ/RFP Issued 04/19/2017 D/B Stations Contract RFQ/RFP issued in September 2017 CURRENTLY IN PROCUREMENT BLACKOUT PERIOD Forecast Revenue Service Date 11/08/2023 08/29/2025 03/04/2026

Westside Purple Line Extension Methane Risk Zone La Brea Tar Pits and Gassy Soil

Westside Purple Line Extension Project Challenge: Maintaining traffic and pedestrian access during construction of stations and tunnels about 60 feet below one of Los Angeles s busiest streets, Wilshire Blvd. Lesson Learned: Include detailed construction planning during PE to: Develop suggested construction sequencing. Identify potential impacts/mitigations and facilitate early third party coordination. Identify staging areas Obtain peak hour and holiday moratorium exemptions. Challenge Construction Planning

Westside Purple Line Extension Section 1 - Slope Diagram

Westside Purple Line Extension Section 1 Tunnel Launch Shaft - Former Metro Customer Care Location Wilshire/La Brea Station Staging Area

Peak Hour and Holiday Moratorium Exemptions City normally requires all lanes on Wilshire Blvd. to be open for traffic during morning and evening commute time. Metro worked closely with the City of Los Angeles and prepared Traffic Control Plans and Temporary Signal Plans needed to obtain permits for peak hour exemptions for soldier pile installation Metro obtained holiday moratorium permits from the City of Los Angeles for work on streets between Thanksgiving and Christmas. City of Los Angeles

Typical Lane Closures During Pile Installation Peak Hour (M F, 6:00 AM 9: AM and 3:30 PM - 7:00 PM) & Holiday Moratorium Exemptions (Nov. 20 Jan. 2) Work Zone Preliminary Traffic Control Plan at Fairfax Station

Challenge: Ensure Section 1 Utility Relocation Work Does Not Delay the Design Build Contractor Perform utility relocation work at three stations in advance of main design build contract work to clear the way

Challenge: Mitigate Potential Delays Caused by Changed/Unforeseen Conditions On the Advanced Utility Relocation (AUR) Contracts, the Contractor found changed conditions and unforeseen obstacles when trenches were opened, threatening the construction schedule. Lessons Learned: To provide a timely resolution of conflicts & issues: A field engineer assigned to observe night shift work and facilitate resolution quickly of conflicts discovered during construction. Completed potholing prior to all AUR contracts. Ensure up to date engineering CAD models are available at the site office. Keep Project As-Builts up to date for timely preparation of record drawings. Field Engineering

Night Shift Issue arises in field Night Shift Field Engineer reviews issue, prepares draft response Day Shift Solution reviewed by Engineering team in office and finalized Same Day Solution sent to Contractor Westside Purple Line Extension Field Engineering Support

Challenge: Do Not Underestimate the Impact of Construction on the Community The team procured Night Time Noise Variance Permits ahead of appointing construction contractors. However strict compliance (no complaints) with these permits is vital as they must be renewed every six months. Westside Approach: All staging sites have 20 ft. high noise barriers on perimeters Specified that all Westside contractors are to use noise blankets around construction site and equipment at night to meet City noise standards (ambient + 5 dba). Required contractors to install low impact back up alarms (Brigade White Noise) on construction vehicles owned by subcontractors. Developed a detailed noise control plan and performed noise compliance oversight. Noise Monitoring/Compliance

Noise Barrier Wall S. Fairfax Yard Sound Mitigation, Section 1

Challenge: Do Not Underestimate the Impact of Construction on the Community Metro has instituted programs to minimize the impact of construction on small businesses near construction alignment: Business Interruption Fund (BIF) for mom and pop businesses along Metro rail construction projects authorizes maximum $50,000 grant based on demonstrated business revenue loss. Metro marketing and community engagement campaign Eat Shop Play as of April 2017 Business Interruption Fund

Eat Shop Play Metro marketing and community engagement campaign to bring focused attention to businesses impacted by construction. Goal: make it easy for consumers to eat at local restaurants, shop at local stores and play at local destination. Online tools, traditional media and promotional materials available. Participation is free for businesses along the alignment.

Westside Purple Line Extension Construction of Wilshire/Fairfax Station through paleo zone Construction of Wilshire/Rodeo Station at Beverly Hills golden triangle Construction of Wilshire/UCLA Station under 8 lanes of traffic on Wilshire Blvd. (800 cars/hour/lane peak periods) Tunneling through gassy ground and tar sands Systems integration at existing termination station, Wilshire/Western Sequential opening (Revenue Service) for three sections: Section 1 2024 Section 2 2025 Section 3-2026 Future Challenges 26