A. Exemptions from the Geotechnical/Geological Engineering Report submittal requirements are:

Similar documents
PINELLAS COUNTY SURFACE WATER UTILITY ADJUSTMENTS AND MITIGATION CREDITS POLICY

August 15, 2006 (Revised) July 3, 2006 Project No A

Please include this addendum in your Bid proposal for the above referenced project. Questions are in black ink, and the answers are in red ink.

SECTION UNCLASSIFIED EXCAVATION AND GRADING

INITIAL INSPECTION REPORT ASH LANDFILL AREA SPRINGERVILLE GENERATING STATION SPRINGERVILLE, ARIZONA

B. Subsurface data is available from the Owner. Contractor is urged to carefully analyze the site conditions.

1. All underground utilities under railroad tracks shall be encased in a larger pipe or conduit called the casing pipe.

STORMWATER RUNOFF AND WATER QUALITY IMPACT REVIEW

TECHNICAL CONTENT PROPOSED STEEP SLOPE REGULATION

In preparation for constructing buildings on a property, the builder. Site Preparation CHAPTER

Building Code of New York State

SECTION 3 DRAINAGE. 3-1 General. 3-2 Drainage Ordinances and Legal Requirements

Chapter 30.63B LAND DISTURBING ACTIVITY

Stormwater Standards. Clackamas County Service District No. 1. Infiltration Testing Guide

Infiltration Guidelines

STORMWATER AND EROSION CONTROL PERMIT

File No Supplemental November Geotechnical and Environmental Consulting Engineers

SEGMENTAL BLOCK RETAINING WALLS. Comply with Division 1 - General Provisions and Covenants, as well as the following:

State of Florida Department of Community Affairs Areas of Critical State Concern Implementation Status Report Apalachicola Bay Area

OHIO ENVIRONMENTAL PROTECTION AGENCY L PE RMIT-TO4 N STALL t

STANDARDS FOR CONSTRUCTION AND USE OF PUBLIC RIGHTS-OF-WAY AND EASEMENTS

STORMWATER MANAGEMENT DESIGN REPORT

ENGINEERING SERVICES REPORT FOREST LAKES BOULEVARD PAVEMENT EVALUATION TAMPA ROAD TO COUNTY LINE FOR PINELLAS COUNTY, FL. May 21, 2010 URS CORPORATION

(1) All sanitary landfill facilities, at a minimum, shall include the following:

This report presents the findings of the subsurface exploration concerning the design of the taxiway rehabilitation. Description

Chapter 21 Stormwater Management Bylaw

HILLSBOROUGH COUNTY UTILITY ACCOMMODATION GUIDE AND RIGHTS-OF-WAY USE PROCEDURES MANUAL APPROVED

MONROE COUNTY ZONING OFFICE

SW-74 SERENOVA PRESERVE SITES 2, 3, 4, 8 MITIGATION PLAN

2. Pavement Materials: Consist of flexible or rigid pavements, typically HMA or PCC, respectively, or a composite of the two.

SECTION 17.1 STORMWATER MANAGEMENT AND EROSION CONTROL

CHAPTER 7 - INFRASTRUCTURE INSPECTION AND ACCEPTANCE... 2

Determination of Design Infiltration Rates for the Sizing of Infiltration based Green Infrastructure Facilities

N.J.A.C. 7:8 Stormwater Management Rules - Design and Performance Standards. Nonstructural Strategies Assist with Strategy #2; See Page 3

SOUTH FLORIDA WATER MANAGEMENT DISTRICT. Question 13: Wetlands

Ordinance amending the San Francisco Public Works Code by adding Article 4.2,

Closure Plan Ash Disposal Area PGE Boardman Power Plant

STANDARD SPECIFICATIONS SECTION BORING AND JACKING. A. Section includes requirements for boring and jacking casing pipe.

4.8. Subsurface Infiltration

CHAPTER 13 R-5 MANUFACTURED MOBILE HOME PARK RESIDENTIAL DISTRICT

UNHSC Bioretention Soil Specification February, SOIL PREPARATION (PERFORMANCE SPECIFICATION) for Bioretention Systems

PIMA COUNTY COMPREHENSIVE PLAN CO PIMA COUNTY REGIONAL COMPREHENSIVE PLAN POLICY MAJOR PLAN AMENDMENT

Section 1: Geotechnical Report Manual

PERVIOUS PAVEMENT. Alternative Names: Permeable Pavement, Porous Concrete, Porous Pavers

POST CLOSURE PLAN. CFR (d) GERS Landfill. Pirkey Plant Hallsville, Texas. October, 2016

David Miller, P.E.- Atlanta. The New Coal Ash Regulations Wednesday, May 6, 2015

Walker County Manufactured Home Rental Community Regulations Infrastructure Development Plan

BMP 6.4.4: Infiltration Trench

STORMWATER MANAGEMENT PRACTICES AND PROCEDURES MANUAL

Wastewater Capital Projects Management Standard Construction Specification

BUILDING A STRUCTURE IN THE FLOODPLAIN. IMPORTANT REQUIREMENTS Of Warren County Floodplain Management Ordinance

Report of Geotechnical Engineering Investigation OIA SOUTH CELL LOT (W340) AID Project No. GOA16001 Orange County, Florida GEC Project No.

SECTION EXCAVATION AND BACKFILL FOR UTILITIES AND STRUCTURES

CITY OF ORANGE MANUAL OF GRADING DEPARTMENT OF PUBLIC WORKS ENGINEERING DIVISION

CITY OF ASTORIA PUBLIC WORKS ENGINEERING DIVISION ENGINEERING DESIGN STANDARDS FOR IN-FILL DEVELOPMENT

4.8. Subsurface Infiltration

SECTION EXCAVATING, BACKFILLING, AND COMPACTION FOR UTILITIES

(1)(A)Inventory of the following existing natural resources on the USFSP Campus or within the context area adjacent to the University.

SPECIFICATIONS FOR STREET CONSTRUCTION WITHIN THE TOWN OF PLAINVILLE

MEMORANDUM. RAI Responses Related to East Lake Road Wellfield Drawdown Analysis, WUP No SDI Project No. PCF-180.

DIVISION 31 EARTHWORK 2006 Edition, Published January 1, 2006; Division Revision Date: January 31, 2012

Subsequent to these early efforts, the complexities associated with potable water provision have increased significantly.

B. Backfill and compact utility bedding and fill placed in the utility trenches between the top of the utility bedding and the subgrade elevation.

STANDARD SPECIFICATIONS SECTION TUNNELING. A. Section includes requirements for constructing tunnels 48-inch and larger diameter.

BIO-AQUIFER STORM SYSTEM

The following sections provide the approved standard infiltration testing specifications.

POND SITING REPORT TABLE OF CONTENTS LIST OF TABLES LIST OF FIGURES EXECUTIVE SUMMARY SECTION 1.0 INTRODUCTION SECTION 2.0 PROJECT DESCRIPTION

Permit Number: 1900B Expiration Date: July 15, 2021

Stormwater Management Technical Manual

ICC-ES Evaluation Report Issued July 1, 2011 This report is subject to renewal in one year.

CITY OF AIRWAY HEIGHTS SPOKANE COUNTY, WASHINGTON ORDINANCE C-664

SECTION TRENCHING & BACKFILLING

CHAPTER 6 ADDITIONAL STANDARDS APPLYING TO SHORELAND AREAS AND PUBLIC WATERS

S.O.P. No. HMD

COMBINED CONCRETE SIDEWALK AND RETAINING WALL. Comply with Division 1 - General Provisions and Covenants, as well as the following:

UNIVERSAL ENGINEERING SCIENCES

Boise City Public Works General Drainage Plan Review Requirements Checklist

Permit Requirements: Building Codes: The City of Clanton has adopted the following codes which are enforced by the Building Department:

FENCES. This hand out is for REFERENCE ONLY. For more details see specific code sections.

TECHNICAL PROCEDURE TABLE OF CONTENTS

Minimum Guidelines for the Design and Use of Underpins When Performing Foundation Stabilization and/or Supplementation UP-08

Article 5: Conservation Overlay Districts

Sections:

Applied GeoScience, Inc Hammond Dr., Suite 6 Schaumburg, Illinois

STATE OF FLORIDA DEPARTMENT OF ENVIRONMENTAL PROTECTION GENERIC PERMIT FOR DISCHARGE OF STORMWATER FROM PHASE II

1 Introduction. 2 Office Locations/Map. 3 General Requirements. 4 Structures and Planting. 5 Equipment Crossings. 6 Excavations. 7 Utility Crossings

SCG INTERNATIONAL TRINIDAD AND TOBAGO LIMITED COUVA CHILDREN S HOSPITAL

SECTION 19 - TRENCH EXCAVATION, BEDDING AND BACKFILL TABLE OF CONTENTS

SECTION PERMEABLE INTERLOCKING CONCRETE UNIT PAVEMENT

PROPOSED STOCK PILE YARD PHASE 1 SITE: MYRA FALLS MINE

SECTION 19 - TRENCH EXCAVATION, BEDDING AND BACKFILL TABLE OF CONTENTS

Stormwater Local Design Manual For Houston County, Georgia

Habitat Management Workshop Report

SOUTHWEST FLORIDA WATER MANAGEMENT DISTRICT ENVIRONMENTAL RESOURCE PERMIT APPLICANT S HANDBOOK VOLUME II

CF50/100 KW TURBINE ACCESS ROAD, CRANE PLATFORM, CONCRETE, AND LIFTING SPECIFICATIONS C&F GREEN ENERGY REVISION PREPARED BY APPROVED BY DATE

901 STORMWATER POLLUTION MANAGEMENT SECTION 901 STORMWATER POLLUTION MANAGEMENT

Subsurface Exploration and Foundation Analysis Proposed New Weight Room / Fieldhouse Building 429 N Highway 83 Leakey, Texas

HAROLD L. MOSELEY SUBDIVISION, RESUBDIVISION OF LOT 2

APPLICATION FOR PUBLIC INFRASTRUCTURE PERMIT

Erosion & Sedimentation Control Policy

Transcription:

CHAPTER 800. SECTION 807. NATURAL AND CULTURAL RESOURCES PROTECTION SOILS AND GEOTECHNICAL HAZARDS 807.1. Intent and Purpose The intent and purpose of this section is to evaluate the suitability of soils for the proposed development and identify any subsurface conditions or geological hazards that may need mitigation or avoidance. 807.2. Applicability A. All applications where structures are proposed and construction is authorized shall include a Soils and Geotechnical/Geological Engineering Report containing the information meeting the requirements of this section. Areas proposed for development shall be evaluated for soil suitability and investigated for existing geologic hazards and the presence of poor soil conditions or other factors that may affect the improvements proposed for the site. At the developer s option and where the proposed development of single-family homes are on lots of one (1) acre or more of uplands, the Geotechnical/Geological Engineering Report may be completed for each lot at the time of Building Permit submittal. Where the developer chooses this option, it shall be noted on each deed. B. All development or structures in unincorporated Pasco County for which applications are submitted after March 1, 2008, and not otherwise exempt by this section, shall be subject to this section. 807.3. Exemptions A. Exemptions from the Geotechnical/Geological Engineering Report submittal requirements are: 1. Structures on lands which do not require preliminary site plan, preliminary development plan, subdivision, or construction plan approval or for which the land is subject to a valid approval issued prior to March 11, 2008. However, this exemption expires with the expiration of the said development approval. Included in this exemption are the alterations of the same to include detached structures such as garages, barns, and swimming pools. 2. Limited Family Lot Divisions 3. Developments for which a completed development application has been submitted prior to March 11, 2008. However, this exemption expires with the expiration of the said development application or the expiration of the subsequent approval of the application. Page 807-1

B. Exemption from land development compaction requirements: Developments where a hard copy Site Development Permit for a Class I, II or III development approval has been issued prior to March 11, 2008. However, this exemption expires with the expiration of the approval. 807.4. Geotechnical/Geological Engineering Report The report shall be prepared by a qualified professional geologist in accordance with Chapter 492, Florida Statutes, and a qualified professional engineer in accordance with Chapter 471, Florida Statutes, or a professional engineer with experience in the geotechnical field in accordance with Chapter 471, Florida Statutes. All development permit applications required to submit a geotechnical/geological engineering report must also contain certification of an appropriate design professional that the proposed project complies with the geotechnical /geological engineering report recommendations. The report shall be project specific and shall identify, within the scope of the investigation and with reasonable probability, subsurface conditions encountered, and recommendations in each of the topic areas. Reports shall be prepared in accordance with the accepted industry standard for evaluation of a site and shall include, at a minimum: A. Project description and general site information. B. Map or map series of the area(s) proposed for development depicting site specific test location performed as part of the geologic evaluation, including soils composition and locations of features related to known or found geologic hazards. C. Evaluation of the site including, but not limited to, the following: 1. Evaluation of subsurface, soils, and groundwater conditions. 2. Conclusions as to the presence of known or found geologic hazards. 3. Subsurface conditions, including boring logs along with a map(s) of location of borings overlaid with the proposed development plan. At a minimum, borings appropriate for the proposed development shall be required under areas where roadways, structures, and retention/detention areas are proposed to be located. 4. The County soil survey information, which, at a minimum, includes a map of generalized soils, description of the soils likely to be present on the site, or laboratory data substantiating soil characteristics relied upon in the engineering/geological analysis of the site. The Soil Survey of Pasco County - Natural Resources Conservation Service maps may be used for general reference. Page 807-2

5. Groundwater information, which, at a minimum, includes depth to groundwater, seasonal high water table, and any other pertinent information. 6. Appendices containing maps, boring logs, and other subsurface data collected during the geological analysis of the site. D. Development and construction recommendations based upon the engineering/geotechnical analysis of the site including, but not limited to, the following: 1. Site preparation, including demucking and deleterious material removal. 2. Fill placement and subgrade preparation. 3. Pavement designs consideration. 4. Foundation construction requirements. 5. Maximum allowable soil bearing pressure. 6. Discussion of potential land settlement issues. 7. Soil and groundwater conditions. 8. Drainage and groundwater concerns. 9. Minimum requirements for construction inspection and testing. 10. Recommendations for mitigation of known or found geological hazardous areas, as necessary, for the development proposed. In the alternative, recommendations for additional or more detailed analysis, as may be necessary, to understand or quantify geological hazard(s), whether remediation measures are recommended, and to evaluate remediation options. 807.5. Land Development Construction Requirements A. Remediation as required by the Geotechnical/Geological Engineering Report. B. Infiltration-based green infrastructure techniques are encouraged to be considered. Page 807-3

C. Should any noticeable soil slumping or sinkhole formation become evident, the applicant/developer shall immediately notify the County, Tampa Bay Water, and the Southwest Florida Water Management District (SWFWMD) and adopt one (1) or more of the following procedures as determined to be appropriate by the County and SWFWMD: 1. If the slumping or sinkhole formation becomes evident before or during construction activities, stop all work (except for mitigation activities) in the affected area and remain stopped until the County and SWFWMD approve resuming construction activities. 2. Take immediate measures to ensure no surface water drains into the affected areas. 3. Visually inspect the affected area. 4. Excavate and backfill or grout, as required, to fill the affected area and prevent further subsidence. 5. Use soil reinforcement materials in the backfilling operation when appropriate. 6. If the affected area is in the vicinity of a water-retention area, maintain a minimum distance of two (2) feet from the bottom of the retention pond to the surface of the limerock or karst connection. 7. If the affected area is in the vicinity of a water-retention area and the above methods do not stabilize the collapse, relocate the retention area. D. Discharge of stormwater into depressions with direct or demonstrated hydrologic connection to the Floridan Aquifer shall be prohibited. E. The site shall be graded to within twelve (12) inches of the final grade. Where fill is proposed, it shall be placed in compliance with the Geotechnical/Geological Engineering Report recommendations (including any lift depths recommended) and compacted to a minimum density of ninety-five (95) percent of the modified Proctor maximum dry density. Density tests to confirm compaction shall be required within the building pad area before the next lift is placed. Upon completion of the land development construction, a professional engineer shall provide a certification to the County that the project, including each pad area, complies with the recommendations of the Geotechnical/Geological Engineering Report. 807.6. Building Permit Application Requirements The Building Permit application shall be accompanied by a statement of an appropriate design professional that they have reviewed the Geotechnical/Geological Engineering Report and that either remedial action is required or that remedial action Page 807-4 wpdata/ldcrw/ldc807soilsgeologicalhazards January 1, 2012

is not required or that the proper foundations have been designed for the structures proposed to be built thereon. The type and size of all foundations for structures in the area of the project development shall be designed in accordance with the design recommendations of the project geotechnical engineer to minimize the potential for ground settlement impacts. 807.7. Building Permit Inspection Requirements Prior to conducting the first inspection, evidence shall be provided that compressible/ collapsible material has been excavated and removed or recompacted; the site is free from the presence of organic materials, construction debris, and/or clay soils to prevent ground settlement in all areas of project development; or, in the alternative, that proper foundations have been designed for use with the compressible/ collapsible materials. All Building Permit inspection requirements shall be in accordance with the technical standards adopted in Chapter 18, Building Regulation, Pasco County Code of Ordinances, and per density testing/certification as required by the Building Official. Page 807-5 wpdata/ldcrw/ldc807soilsgeologicalhazards January 1, 2012