Walls generally range from 600 to 1500 mm thickness, in wide between 2000 and 3500 mm and can be excavated to depths of 60m or more.

Similar documents
Diaphragm wall Construction

TECHNOLOGY. Continuous Flight Auger

DIAPHRAGM WALLS, CUT-OFF WALLS AND SLURRY WALLS

NEW PERFORMANCE CRITERIA FOR FRESH TREMIE CONCRETE

Soil Mechanics Lateral Earth Pressures page Lateral Earth Pressures in case of inclined ground surface or friction at wall-ground interface

GeoEng2000 An International Conference on Geotechnical & Geological Engineering

Wet Speed-Mixing WSM - Soil Mixing Procedure in Twinmix Design

SCOPE OF WORK FOR PILING JOB

Pipe Jacking/Microtunnelling. Dr. Mark Knight. Centre for Advancement of Trenchless Technologies (CATT) University of Waterloo.

h Installation Manual

SECTION EXCAVATING, BACKFILLING, AND COMPACTION FOR UTILITIES

ROTARY DRILLING TECHNIQUES LARGE DIAMETER

Combined Pile Foundation System for a Residential Complex

TRENCHLESS CONSTRUCTION (BORING, JACKING, AND TUNNELING)

S.No Description Unit Quantity Rate (Rs) Amount (Rs)

CF50/100 KW TURBINE ACCESS ROAD, CRANE PLATFORM, CONCRETE, AND LIFTING SPECIFICATIONS C&F GREEN ENERGY REVISION PREPARED BY APPROVED BY DATE

SECTION A1 EXCAVATION AND BACKFILL GENERAL

1. All underground utilities under railroad tracks shall be encased in a larger pipe or conduit called the casing pipe.

HEKAPLAST. PE-HD twin wall cable ducts and cable protection pipes for underground installation. Corrugated and Twin Wall Pipes of Plastics

UNDERPINNING A CRANE FOUNDATION

Building pit District adjacent to St.Katharinenkirche Hamburg, Germany

Topic: Site Formation

PAUL ZICK, PE NORTH SHORE CONSTRUCTORS JV

Construction Planning, Equipment, and Methods PILES AND PILE-DRIVING EQUIPMENT

SITE INVESTIGATION. Foundation Engineering

The Technical and Contractual Matters of Bored Piling Works. By Wallace Yeung Vibro (H.K.) Ltd.

CHANGES IN 2006 SPECIFICATIONS SECTION 804 DRIVEN PILES SECTION 814 DRILLED SHAFTS

Hydraulic Excavators

ITEM D-701 PIPE FOR STORM DRAINS AND CULVERTS

SPECIFICATION FOR REINFORCED SOIL WALL

Oweninny Wind Farm. Oweninny Environmental Impact Statement Appendix 5. Turbine Foundation Construction Method Statement

Concrete Slab-on-Ground

SAMPLE SPECIFICATION for CROSSHOLE SONIC LOGGING (CSL) September 2015

SPECIFICATION : BORING AND JACKING

Development of Steel Diaphragm Wall with Soil Cement

C. Foundation stabilization for pipe and utility structures.

PIANC UK Seminar Design Developments and Specification for Steel. Duncan Nicholson Arup Fellow 9/3/17 ICE London

There are several types of trenchless technology applications for new installations. The following are some of the most prominent applications.

SECTION GRAVEL PACKED WATER WELL

Page 10-1 Hubbell Power Systems, Inc. All Rights Reserved Copyright 2014 LIGHTING AND SIGNS

1 Exam Prep Placing Reinforcing Bars Tabs and Highlights

1. Introduction Selection of Pile Type Soil Report / Boreholes Obstructions Design and Installation of Piling Mat 3

Installing DELTABEAM. Installation of DELTABEAM. Deliveries. Storage on-site

INSTALLATION AND OPERATING INSTRUCTIONS

Technical Bulletin No. MK3176. PREPARED: July, 2010

DIVISION 03 CONCRETE SPECIFICATION : FORMS AND FORMWORK

SITE SERVICES GUELPH TRANSIT OPERATIONS & MAINTENANCE SECTION WATSON ROAD FACILITY PAGE 1 OF 6 WATER RECLAMATION PROJECT JUNE 2013

Marina Bay Sands Hotel Arch 631 Kayla Brittany Maria Michelle

PACIFIC SHORING, LLC ALUMINUM SHORING PRODUCTS PSH HYDRAULIC STRUT. TABULATED DATA Effective December 10, 2013

Silent Vibrationless. Technology. teel Sheet Piles. Vinyl Piling. etaining Walls. Piles. tory Piling. oundations. ite Piles. n Free Piling.

Redi Rock Specification and Installation Manual

BUILDER S CONSTRUCTION SUPPLIES (Temporary in permanent position) REQUIREMENTS. March 2014

SEMINAR. Introduction to Continuous Flight Auger (CFA) piling Thursday 21/8/2013. Facilitator: Martin Larisch

Section 2: Underground

Design and construction of an immersed concrete tunnel using an integrated dock facility

NPTEL Course GROUND IMPROVEMENT USING MICROPILES

4th International Engineering and Construction Conference - July 28, 2006

SPECIFICATIONS FOR PRECAST MODULAR BLOCK RETAINING WALL SYSTEM (revised 5/8/7)

WORK BELOW LOWEST FLOOR FINISH 1/7 230, , , FRAME 2/6 96, , ,056.00

SCREW PILE APPLICATION SHEETS

INDEX FOR SPECIFICATIONS FOR JACKING CULVERTS THROUGH EMBANKMENTS SCOPE... 2

Contact Clark Public Utilities Construction Services department at (360) to initiate a request for service.

METHOD STATEMENT for INSTALLATION OF MICROPILE

TRENCH SAFETY TRAINING

water-powered drilling in ground engineering

Excavator Attachments. Product Range

Artists rendering of the Federation Tower, an aqua park, hotel and recreational facility.

E. Section Polymer Modified Cement Waterproofing. K. Section Sub drainage: Foundation perimeter drainage.

LARGE DIAMETER PIPE ROOF BOX EXCAVATION FOR PASSENGER LINKWAY TUNNEL

ASSEMBLY AND OPERATING MANUAL LTW SHORING BOXES VB 100

COMPETITIVENESS OF PIPE-JACKING TUNNEL LININGS

Behavior of Surrounding Soil during Construction and Its Countermeasures Using Pipe Jacking Method in Deep Strata

RFP/GRC/LSV/ : RENOVATION (CIVIL WORKS) AT SKALA SYKAMNIAS CHILDRENS PLAYGROUND BILL OF QUANTITIES

TABLE OF CONTENT. Equipment kit Description of the technology Installation of equipment Start of construction...

Design Data 4. Jacking Concrete Pipe

SPECIAL CONDITIONS FOR PIPE JACKING (PJ) October, 2006

The superior self-compacting concrete

Design Data 4M. Jacking Concrete Pipe

Non-Destructive Testing of Drilled Shafts Current Practice and New Method

VESDURA VINYL PLANKS 7.5MM WPC CLICK LOCK - AMERICANA COLLECTION

AUGUST 2017 HASTINGS. retaining walls installation guide

SPECIFICATION FOR PIPE CULVERT CONSTRUCTION

Tagus Crossing at Carregado (Portugal): A project respectful of its sensitive environment

SpaVault TM Installation Guide for Bullfrog Spas (7-10 x 7-10 x 38 )

Materials Services Infrastructure. Global expertise for infrastructure projects.

Bonner Bridge Replacement Update:

Box Culverts. Easy to install, suitable for very shallow or deep fill, ideal for use in a wide variety of civil engineering applications.

Steps And Stairs Installation Option 1 - Steps In Wall Option 2 - Steps With Plant Space Option 3 - Steps In Front of Walls Option 4 - Steps Along

Structural and Geotechnical Issues Impacting The Dalles Spillwall Construction and Bay 1 Erosion Repair

SECTION EXCAVATION AND BACKFILL FOR UTILITIES AND STRUCTURES

Contents. Soilmec Company Profile

Example of the Unified Design procedure for use in the September 8, 2014, short course on in Brazil

DOUBLE SLIDE RAIL INSTALLATION METHOD. Double Slide Rail August

DISCUSSION ON UNDERPINNING (28/3/12)

Development of the Combi-Gyro Method, a New Steel Wall Construction Method Combining Steel Sheet Piles and Pipe Piles

METHOD OF MAKING AND CURING CONCRETE TEST SPECIMENS IN THE FIELD FOP FOR AASHTO T 23

MKT VIBRATORY HAMMER SELECTION AND SOILS TRAINING

Transcription:

TECHNOLOGY Diaphragm walls

Diaphragm walls are one of the most important technologies of special foundation engineering. A diaphragm wall is constructed using a trench excavated in ground and supported by a mud fluids (typically bentonite or polimer mud) until the mud is replaced by concrete, after the steel cage installation. Walls generally range from 600 to 1500 mm thickness, in wide between 2000 and 3500 mm and can be excavated to depths of 60m or more.

Can be installed in all soil conditions and through rock Used in high water table conditions without excessive dewatering Low costs and speed of construction for temporary and permanent soil support

Technology Diaphragm walls are rectangular-section excavations with a complete ground asportation that is made in situ. The result is an underground concrete wall. They are essentially retention walls, which are constructed for instance at wharfs. A rectangular-section tool is generally used to remove the soil, thus creating a rectangular excavation. Furthermore the rectangles making up the wall must be interlocked to ensure structural endurance and water tightness. The diaphragm wall panel construction entails three steps: the construction of guide wall, the panel excavation (demolition removal - stabilization), and the construction phase (reinforcing cage casting curing). To build a continuous diaphragm wall the primary panels are firstly constructed and spaced at a distance slightly larger than the panel width. The secondary panels are built in the empty spaces between the primary ones.

Construction stages Diaphragm wall construction requires that a proper sequence of works is followed. A rectangular-section tool is generally used to remove the soil, thus creating a rectangular excavation. The main digging tool for panels is the grab, which shall have the same size of the component it shall dig. Holes are stabilized with bentonite slurry. Concreting is performed using the tremie technique as for castin-place piles. Guide wall installation Prior to diaphragm wall excavation is necessary to construct two temporary parallel concrete beams to guide the excavation tool and to stabilize the upper. Guide walls are cast-in-place or pre-cast lightly reinforced concrete elements. Guide walls maintain the horizontal alignment and wall continuity of a diaphragm wall while are adopted to avoid superficial soil collapse, to mark the panels position and to support the steel cages during the concrete aging. This temporary support is important as the slurry levels vary during construction and the wall tends to be unstable. Equally important, guide walls help guide the diaphragm wall grabs vertically and aid in the positioning of the final structure. The dimensions and shape of the guide walls may change depending on the nature of the surface soil. As it happens in bored piles, the bentonite slurry inside the excavation hole shall always be kept some meters above the height of the water table. In some special cases where the water table is very close to the surface and the soil has poor mechanical properties, the guide walls may be built on a higher height compared to the ground plane to preserve the above mentioned height difference.

Construction stages Panel excavation The single panel is excavated downward using grab until reaching the required level. The trench is prevented from collapsing during excavation, reinforcing and casting by the use of supporting bentonite slurry. The slurry forms a thick deposit (the cake) on the walls of the trench which balances the inward hydraulic forces and prevents water flow into the trench. A slurry made of polymers can also be used. Grabs are diaphragm wall digging tool consisting of two jaws which can open and close to collect cuttings and take them out of the excavated trench. Jaw outer profiles are fitted with teeth to cut the soil. The excavation work cycle starts with the open grab rested on the ground: thanks to the tool weight and speed, the teeth penetrate the soil. By activating the closing system, the grab excavates the soil and keeps part of it inside the jaws. Teeth arrangement on the jaws is usually an odd number of teeth on one jaw, and an even number of teeth on the other, to ensure perfect closing. The jaws asymmetrical configuration tends to deviate from straightness and for this reason the grab is not always used in the same direction, but alternately in both directions: every time the grab is lowered into the excavation, it is rotated by 180. The grab is lifted with the jaws closed and the soil is discharged in a designated area. The work cycle is repeated a number of times until excavation has been completed. The primary panels are excavated first and Secondary panels are constructed between primary diaphragm wall panels. Once the panel is excavated, prior to concreting, the supporting slurry fluid must be cleaned and refreshed so its density, sand content, viscosity and PH are within specified levels.

Construction stages Panel construction One of the most delicate issues in the diaphragm wall construction is represented by the waterproof joints between panels. One of the main functions of the diaphragm wall, in addition to supporting the soil up to the final excavation inside it, is preventing settlement of buildings and superstructures beside the excavation and also guaranteeing the wall s waterproofness. The Joints are available in various type and their choose depends on the excavating equipment as much as contractor preference. Once the bottom of the panel is reached and cleaned, the reinforcement cage can be lowered into position. The reinforcement cages have a significant size and weight, as a general rule, the cage is built by laying the components (of adequate length) on the ground then connecting them together. If there is the need for building the cage in separate sections, said sections shall be properly connected using a method approved by the engineer. The concrete is placed through a vertical steel pipe with an open, funnel-shaped upper end named tremie. With the tremies, concreting of a diaphragm wall starts from the bottom and the tremies are lifted progressively as the concrete level rises. Simultaneously with placing concrete, slurry is pumped from the panel to be refreshed and re-used in the next panel excavation. STAGE 1 Excavation STAGE 2 Bentonite mud desanding STAGE 3 Placing of reinforcement STAGE 4 Pouring of concrete

Technology There are three main types of joint design used for diaphragm walls: stop and pipes Stop end pipes The steel pipes are installed at both panel fronts before concreting. The pipes rest on the excavation bottom and match the circular shape of the panel fronts. The concrete injected takes the shape of the stop end pipes, the latter are filled with bentonite slurry and the panel has concave fronts. Once primary panels have been constructed and the stop end pipes removed, secondary panels are executed. Once secondary panels have been fully excavated, concreting can start. Concrete fills the semicircular joints and provides a very good interlock. Disposable pipes Pipes are in PVC; they are fixed to the cage and lowered to rest on the bottom. During concreting, the whole section is filled by concrete, except for the pipes which remain full of bentonite slurry. The result is a panel with two holes. After excavating the secondary panels, by using a dedicated tool the concrete seam separating the pipe from the secondary panel and the pipes are demolished. As a result, a round indentation is created in the primary panel. When concrete is cast in the secondary panel, it fills the recess and creates a joint with the primary panel. primary secondary primary secondary pipes primary secondary primary

Technology sheet pipes primary excavation digging sheet piling removal installation of sheet piling with water stop digging and secondary panel primary panel and concreting secondary panel concreting Sheet piling With this method, a steel sheet pile is driven into the primary panel, before concrete is cast. After concreting has been completed, the concrete on the fronts of the panel takes on the shape of the sheet pile and a recess is created. When concrete has hardened enough to keep its shape, sheet piles are extracted. Afterward the secondary panel is excavated using a suitable tool to copy the recess of the primary panel and remove soil from this area. When concreting, concrete fills the recess and provides a good interlock between the panels. This technique allows for the insertion of plastic elements called water stops between the panels, in order to guarantee increased water tightness. The Milan joint Trevi Group has developed a special system during the works for the Milan Underground line 3 project in 1985, a system which has been called Milan joint because of its origin. The joint is built using a PVC pipe, connected to the primary panel cage. The bottom end of the pipe is closed by a holed cap so as to allow the bentonite slurry to flow in the tube thus preventing the walls of the tube from collapsing due to the pressure the concrete, rising up during the excavation, will exercise on the tube walls. After excavation of the secondary panels has been completed, a cleaner is mounted on the grab; the grab is then lowered and the cleaner breaks the wall of the PVC pipe. This way the concrete penetrates into the pipe s cross-section thus creating a waterproof joint.

Job site logistics A typical jobsite constructing Diaphragm walls through slurries will use the following equipment: A crane equipped with grab A plant to produce the slurry A plant to desand the slurry A service crane to position steel reinforcement cage in the borehole and to handle the tremie pipes to cast the concrete Desander Bentonite preparation plant Auxiliary crane Crane with grab

Technology advantages The main advantage of Diaphragm wall technology are listed below: Can be constructed in a very wide range of soil types and rocks. Diaphragm walls can be constructed to depths of 60 meters (and above) and to widths of 600 to 1500 mm. Diaphragm walls tend to be used for retaining very deep excavations as they can be designed to take very high structural loads. The water tight walls formed can be used as permanent structural walls. Reduced number of joints in the wall which ultimately improves the walls water tightness. Work may be carried out right against existing structures and the line of wall may be adjusted to any shape in plan. Diaphragm wall construction is relatively quiet, and minimum noise and vibration levels make it suitable for construction in urban areas. Can be used as top-down method in order to optimize the sequence of operations to be performed in densely-populated inner city areas.

Soilmec Equipment 1 2 Since 1974, with the first BHP hydraulic grab, Soilmec is a benchmark point in the field of the diaphragm wall technology executed by grabs. Today Soilmec produces and distributes the GC line, mechanical cable operated grab and the hydraulic lines BH and GH that allow excavation of a wide range of panel dimensions. Both BH and GH grabs can be equipped with the innovative Rotograb Kelly System developed by Soilmec to meet the demand of the front of wall application. 3 8 4 5 6 1 2 3 4 5 6 7 8 SPECIAL CATHEAD HYDRAULIC REVOLVING GEAR MOTORS +/- 180 (360 USING ROTOGRAB) TELESCOPIC EXTERNAL GUIDE GRAB BODY SIDE GUIDES GRAB OPERATION CYLINDER JAWS HYDRAULIC COILERS 7

Soilmec Equipment Grabs Range Mechanical cable operated and hydraulic grabs for diaphragm wall technology. Model BH-8 GH-12/ GH-12R GH-15/ GH-15R GC-11 GC-16 Max depth 75 m 75 m 75 m depending on crane depending on crane Weight (approx.) 8 t 12.5 t 15.2 t 11 t 16 t Panel thickness 350/800 mm 500/1200 mm 600/1500 mm 500/1200 mm 800/1500 mm Panel width 2000/3000 mm 2500/4200 mm 2800/4200 mm 2500/3000 mm 2800/3500 mm Type hydraulic hydraulic hydraulic mechanical mechanical Jaws clousure cylinder cylinder cylinder rope rope

Diaphragm Walls 001 02/2016 All technical data are purely indicative and subject to change without notice This brochure has been edited and distributed by SOILMEC Spa. The present document cancels and override any previous ones. This brochure shall not be distributed, reproduced or exhibited without SOILMEC Spa. authorization in accordance with to SOILMEC web site disclaimer condition. SOILMEC Spa distributes machinery and structures all over the world, supported by SOILMEC Spa subsidiary companies and dealers. The complete Soilmec network list is available on the web site www.soilmec.it www.soilmec.it