THE NOVELEDGE IGCC REFERENCE PLANT: COST AND EMISSIONS REDUCTION POTENTIAL. Gasification Technologies 2004, Washington, DC, October 6, 2004

Similar documents
Cost and Performance Baseline for Fossil Energy Plants

GASIFICATION TECHNOLOGIES 2003

BLUE OPTION White space is filled with one or more photos

UPDATE ON THE KEMPER COUNTY IGCC PROJECT Gasification Technologies Conference

SOME ENERGY-EFFICIENT TECHNOLOGIES IN JAPAN

Understand boiler performance characteristics. Use these suggestions when buying, designing or optimizing steam generators

Mr. Daniel has authored a gasification patent and represents GE on the Gasification Technologies Council.

Equipment Design. Detailed Plant Conceptual Design. Version 9.0

Item Hydrogen Gas Plant

A Parametric Investigation of Integrated Gasification Combined Cycles with Carbon Capture

Comparison of a New Warm-Gas Desulfurization Process versus Traditional Scrubbers for a Commercial IGCC Power Plant

Technical and Economic Evaluation of a 70 MWe Biomass IGCC Using Emery Energy s Gasification Technology

Abstract Process Economics Program Report 180B CARBON CAPTURE FROM COAL FIRED POWER GENERATION (DECEMBER 2008 REPUBLISHED MARCH 2009)

MIT Carbon Sequestration Forum VII Pathways to Lower Capture Costs

TRONDHEIM CCS CONFERENCE

Impact of novel PCC solvents on existing and new Australian coal-fired power plants 1 st PCC Conference, Abu-Dhabi

Development status of the EAGLE Gasification Pilot Plant

Ion Transport Membrane (ITM) Technology for Lower-Cost Oxygen Production

Latest Development of Lurgi s MPG-technology Update on Hydrogen Unit for NWU Project

ISAB ENERGY IGCC NEW HYDROGEN PLANT. Authors Gianluca Rospo, ISAB Energy Rosa Domenichini, Silvio Arienti, Paolo Cotone - Foster Wheeler Italiana SpA

Geothermic Fuel Cell Applications in Coal Coal Gasification---Coal to Liquids (Summary Highlights)

Cansolv Technologies Inc. Alberta NOx and SOx Control Technologies Symposium April 9, Rick Birnbaum

Coal Gasification Study

Categorizing Units Based on Controllable Loss Parameters using PEPSE θ

High Bridge Combined Cycle Plant

Coal based IGCC technology

Post Combustion CO 2 Capture Scale Up Study

ENI REFINING & MARKETING SANNAZZARO GASIFICATION PLANT PROJECT UPDATE AND START UP EXPERIENCE

Chapter 8. Vapor Power Systems

An Update On Shell Licensed Gasification Projects and the Performance of Pernis IGCC

Efficient Technologies for Down Stream Gasification Process and Integration with IGCC Power Production

Feedwater Heaters (FWH)

Advanced Coal Technology 101

Rectisol Wash Units Acid Gas Removal for Polygeneration Concepts downstream Gasification

Steam balance optimisation strategies

Carpet Waste Gasification:

Carbon Dioxide Capture from Coal-Fired Power Plants: A Real Options Analysis

Consider a simple ideal Rankine cycle with fixed turbine inlet conditions. What is the effect of lowering the condenser pressure on

Chapter Two. The Rankine cycle. Prepared by Dr. Shatha Ammourah

Evaluation of Hydrogen Production at Refineries in China. The new UOP SeparALL TM Process. Bart Beuckels, UOP NV

Power-Cost Alternative De-NOx Solutions for Coal-Fired Power Plants

Chapter 3 Coal-Based Electricity Generation

Steam Cycle Chemistry in Air-Cooled Condensers. NV Energy ACC User s Group * November 12-13, 2009 Andrew Howell * Xcel Energy

ROYAL SOCIETY OF CHEMISTRY TECHNOLOGY IN THE USE OF COAL

NEW DESIGN OF IGCC FOR COMPETITIVE POWER GENERATION

TruePeak TDLS200. NH 3 Slip Measurement. <Document Number> Copyright Yokogawa Electric Corporation <date/time>

5. Steam Turbine Performance

Reforming Natural Gas for CO 2 pre-combustion capture in Combined Cycle power plant

Efficient and Flexible AHAT Gas Turbine System

Lurgi s MPG Gasification plus Rectisol Gas Purification Advanced Process Combination for Reliable Syngas Production

FLEXI BURN CFB WP4: Boiler design and performance

HIGH PUITY CARBON MONOXIDE FROM A FEED GAS ARNOLD KELLER AND RONALD SCHENDEL KINETICS TECHNOLOGY INTERNATIONAL CORPORATION MONROVIA, CALIFORNIA

Texas Hospital. Central Plant Redesign. Central Utility Plant SECOND PLACE HEALTH CARE FACILITIES, EXISTING 2013 ASHRAE TECHNOLOGY AWARD CASE STUDIES

Process Economics Program

Regenerative Firing vs. Oxy Fuel Firing: An Applications Approach Steven J. O Connor Senior Applications Engineer, Bloom Engineering Company

Draft Results Capital Cost and Performance of New Entrant Peaking Unit

EFFECT OF AMBIENT TEMPERATURE, GAS TURBINE INLET TEMPERATURE AND COMPRESSOR PRESSURE RATIO ON PERFORMANCE OF COMBINED CYCLE POWER PLANT

Welcome to. Kendal Power Station

The Locomotive. A Copper-Plated Thief: The Problem of Copper Deposits in Turbines

Feasibility of Partial Upgrading of Athabasca Bitumen. Jim Colyar, Technology Consultant Colyar Consultants October 2010

Biomass Gasification

RTI/Eastman Warm Syngas Clean-up Technology: Integration with Carbon Capture

RTI Warm Syngas Cleanup Technology Demonstration

Direct Hot Water Production for an Oil Sands Mining & Extraction Process

POST COMBUSTION CO 2 CAPTURE SCALE UP STUDY

Grand Composite Curve Module 04 Lecture 12

Ultra-Heavy Oil Production and Upgrading with Gasification

NTPC O&M Conference Performance and Optimization of Water Utilisation Increase of Existing Power Plants. Speaker Name; Tufani Ram 13-14/02/2013

SCR for NO x Control in Coal-fired Power Plants

GT-LPG Max SM. Maximizing LPG Recovery from Fuel Gas Using a Dividing Wall Column. Engineered to Innovate

Combined cycle with detailed calculation of Cp in the HRSG

KEPCO KEPRI Kim eui hwan

Natural Gas Partial Oxidation for Chemical Processing in Longview, Texas

The Zero Emission Power Plant Concept

metals temperature limits.

Gasification of Residue as a Source of Hydrogen for Refining Industry in India

Simple Dew Point Control HYSYS v8.6

Kalex Kalina Cycle Power Systems For Use as a Bottoming Cycle for Combined Cycle Applications

SCR Retrofit Improves Performance

Heat Integration of an Oxy-Combustion Process for Coal- Fired Power Plants with CO 2 Capture by Pinch Analysis

OUTCOME 2 TUTORIAL 2 STEADY FLOW PLANT

Clean Coal Technology Status: CO 2 Capture & Storage

WESTINGHOUSE PLASMA GASIFICATION

CANSOLV SO2 Scrubbing System - 10 Years of Reliable Operation Integration with SRU Tail Gas Incineration

COMBINED CYCLE OPPORTUNITIES FOR SMALL GAS TURBINES

GASIFICATION FOR COMBINED PRODUCTION OF ELECTRIC POWER AND CHEMICALS

WWT Two-Stage Sour Water Stripping

Gasification: A Key Technology Platform for Western Canada s Coal and Oil Sands Industries

The Effects of Operation Parameters on the Performance of Entrained-bed Pulverized Coal Gasifier with High Fusion Temperature Coal

GE Energy. Advancements in Gasification Technology Allan Connolly, General Manager of Gasification Technology October 12, 2005

IGCC Plants : a Practical Pathway for Combined Production of Hydrogen and Power from Fossil Fuels

Energy Penalty Analysis of Possible Cooling Water Intake Structure Requirements on Existing Coal- Fired Power Plants

Insert cover here. Valero Cover.cdr

Conception of a Pulverized Coal Fired Power Plant with Carbon Capture around a Supercritical Carbon Dioxide Brayton Cycle

Hitachi H-25 & H-80 Gas Turbine. Bucharest, Apr.23, 2013

Paper Mill Repowering with Gasification

Worldwide Pollution Control Association. August 3-4, 2010

1 st Renewable Energy Technologies, LP. Organic Rankine Cycle

Nuclear-Power Ammonia Production

COAL WATER SLURRY FUEL Alternate Fuel for Thailand

Transcription:

THE NOVELEDGE IGCC REFERENCE PLANT: COST AND EMISSIONS REDUCTION POTENTIAL Gasification Technologies 2004, Washington, DC, October 6, 2004 Dave Heaven, Fluor; William S. Rollins, NovelEdge Technologies, LLC ABSTRACT NovelEdge Technologies has developed and patented a combined cycle power block concept that utilizes duct firing in the to increase the power output from the steam turbine relative to power from the gas turbine(s). The net effect of this approach is power output and heat rates almost matching those of conventional natural gas fired combined cycle designs while achieving reduced capital investment and maintenance. The purpose of this paper is inquiry into the integration of this NovelEdge technology with a reference gasification plant. Overall performance and cost are estimated and compared with a reference IGCC plant. Results indicate this is a practical alternative to the conventional IGCC configuration. INTRODUCTION Production of electric power from gasification-derived syngas has conventionally been accomplished in Integrated Gasification Combined Cycle (IGCC) plants. This technology has been successfully deployed in 12 operating plants today. These IGCC plants have typically fired the available syngas in the gas turbines with little or no supplemental syngas duct firing in the heat recovery steam generators (), which recover heat from the gas turbine exhaust. NovelEdge Technologies has developed and patented a combined cycle power block for natural gas-fired plants, which relies upon considerable duct firing in the to substantially increase power production from the steam turbine relative to power production from the gas turbine. For this study, the duct firing is limited to temperatures that do not require water-cooled walls in the for simplicity. The benefits of this approach are reduced capital investment and reduced maintenance expense for a given net plant power output. The first purpose of this paper is inquiry into the integration of this NovelEdge technology with a reference gasification plant. The first step in the general approach was to start with a nominal 1000 MW IGCC plant based around four General Electric 7FA+e gas turbines, then reduce the gas turbine count to three and duct fire the remaining syngas in the three s. Plant feed rate and the gasification system were held fixed between the two cases. All interfaces between the gasification block and the power block were examined carefully to confirm a workable fit between the two sections. This provided a base comparison where the impact was focused only on the power island.

The second purpose of this paper was presentation of a plant design and performance based on conditions deemed more favorable to NovelEdge without forcing comparability to a reference conventional IGCC plant as was done initially. BASIC NOVELEDGE CONCEPT NovelEdge Technology is a new process for combined cycle power plants. This new process has been awarded 4 patents by the US Patent and Trademark Office, while numerous other patent applications are still pending. Essentially, NovelEdge Technology is a combined cycle process that allows for a substantial increase in power through supplemental firing in the, only without the large degradation in heat rate that is associated with duct firing. The net effect is a high power-density combined cycle plant that has a lower specific capital cost (lower $/kw), but retains an excellent heat rate. To understand how NovelEdge Technology works, it is beneficial to first examine a basic natural gas-fired combined cycle, as illustrated in Figure 1. This cycle is arbitrarily based upon an F class gas turbine (GT) with a single pressure level and a reheat steam cycle. Note that although the steam cycle may be efficient, the combined cycle is not optimally efficient as a result of the high stack temperature (400 F). This basic steam cycle simply cannot recover all of the exhaust gas energy that is available when utilizing a clean fuel such as natural gas or syngas. Figure 1 2

As a result of the lower efficiency of the basic combined cycle, the industry has gravitated to the multi-pressure level combined cycle arrangement as illustrated in Figure 2. By taking advantage of the latent heat required to boil water, and the fact that lower pressure steam boils at lower temperatures, the multi-pressure system can attain higher combined cycle efficiencies by recovering more exhaust gas energy than the basic combined cycle of Figure 1. This multipressure process reduces the stack temperature to a nominal 200 F. Figure 2 With NovelEdge Technology a different approach is taken to recover exhaust gas energy (see Figure 3). Rather than utilize a multi-pressure level, a single pressure level is employed in conjunction with a large economizer section and duct firing. As duct firing increases, steam production in the increases. Higher steam flows equate to higher feedwater flows into the low temperature end of the. Essentially, when the correct amount of duct firing is used, the cold feedwater flow into the back end of the cools the stack gases down to a nominal 200 F. Thus the NovelEdge design retains the higher steam cycle efficiency yet still recovers all of the exhaust gas energy that is available. 3

Figure 3 Let s examine mathematically how NovelEdge Technology works. An F class gas turbine (GT) has a simple cycle efficiency of approximately 36%. After losses, approximately 58% of the energy consumed by the GT is available in the. A conventional combined cycle, with a 3-pressure level and its mix of HP, IP, and LP steam, has a steam cycle efficiency of about 35.3%. Therefore, the combined cycle efficiency, η, is expressed as follows: η = 0.36 + (0.58)(0.353) η =.565 or 6040 Btu/kwh This heat rate is similar to published numbers from the OEM s for their 2-on-1 F class power plants. For the NovelEdge combined cycle, the GT efficiency is unchanged at 36%. Also, there is 58% of the GT input energy available to the. However, to achieve a low stack temperature similar to the conventional plant (nominally 200 F), duct firing must be employed, and 30% more energy must be input to the. However, by now utilizing all high-pressure (HP) steam and increasing the main steam pressure, the steam cycle efficiency is increased to 42%. The efficiency for the NovelEdge cycle is calculated as follows: η = [0.36 + (0.58 + 0.30)(0.42)] / (1.0 + 0.30) η =.561 or 6085 Btu/kwh As can be seen by these calculations, the NovelEdge combined cycle efficiency is within 1% of the conventional multi-pressure level arrangement for natural gas fired plants. 4

Another interesting facet of the NovelEdge combined cycle is its power production split between the gas turbines and the steam turbine. In a conventional unfired combined cycle, the GTs produce a nominal 65% of the plant load, while the ST produces the remaining 35%. For the NovelEdge cycle, however, the steam turbine typically produces the majority of the plant s power output. Therefore, in essence the NovelEdge combined cycle shifts the power production emphasis in the combined cycle from a gas turbine based cycle to a one that is predominantly a steam cycle. Bearing this concept in mind, it can be understood that a conventional natural gas-fired plant at 750 MW might utilize a 3-on-1 arrangement, or 3 GTs and 1 ST, where the NovelEdge facility would utilize a 2-on-1 arrangement for the same power output. With this reduction in GTs and thus a reduction in the number of stacks, and utilizing an SCR to achieve equal NO x concentrations from all stacks, it is seen that the NovelEdge facility can have lower emissions than the conventional plant as well. By replacing more expensive gas turbine capacity with lower cost steam turbine capacity, producing a larger percentage of the plant s power with the lower maintenance steam turbine, and utilizing fewer stacks for the same power production, the net result of utilizing NovelEdge Technology is a combined cycle plant with lower capital costs, lower maintenance costs, and in many instances, lower emissions. COMPARISON OF CONVENTIONAL AND NOVELEDGE IGCC APPLICATIONS Since NovelEdge Technology can save significant capital and maintenance expenses on natural gas-fired combined cycle power plants, it is of interest to examine what effect it may have on an IGCC application. For comparison purposes, it was decided to examine two plants of the same nominal output, a conventional IGCC and a NovelEdge IGCC. Both these plants have identical gasification equipment, with some minor changes in the syngas clean-up/heat recovery systems. Conventional Plant The conventional plant has an ISO rating of 1086 MW. It will consist of two (2) blocks of a 2- on-1 arrangement. Therefore, the major pieces of equipment include: 4 Gasifiers 2 Syngas clean-up trains 4 - ASU s, nominal 2000 stpd of pure O 2 and 3045 stpd N 2 diluent each 4 - GE Frame 7FA+e gas turbines 4 s, with 3 pressure level design 2 Steam turbines, nominal 275 MW each 2 Condensers 5

The conventional plant is based upon a single stage, slurry-fed gasification system with highpressure steam production from the hot syngas. The plant utilizes a selective MDEA acid gas removal process for sulfur removal down to 40 ppm, and a zero liquid discharge system. Gas turbine NOx is controlled to 15 ppm primarily with nitrogen diluent that is moisturized with a small amount of steam. The Block Flow Diagram for this case is included as Figure 4, while the Steam, Condensate, and Diagram for this facility is shown in Figure 5. This conventional 1086 MW plant consumes 8844 stpd of Pittsburgh #8 coal on an as-received basis. The higher heating value for this fuel input is 9654 MMBtu per hour HHV, for a heat rate of 8890 Btu/kwh or 38.4% efficient. NovelEdge Plant The NovelEdge plant has an ISO rating of 1073 MW. It will consist of one 3-on-1 arrangement. Therefore, the major pieces of equipment include: 4 Gasifiers 2 Syngas clean-up trains 4 - ASU s, nominal 2000 stpd of pure O 2 and 2285 stpd N 2 diluent each 3 - GE Frame 7FA+e gas turbines 3 s, with single pressure level design 1 Steam turbine, nominal 700 MW 1 Condenser The NovelEdge plant is based upon the same gasification system as the preceding conventional IGCC Case, including the selective MDEA module for sulfur removal down to 40 ppm and a zero liquid discharge system. Gas turbine NOx is controlled to 15 ppm primarily with nitrogen diluent that is moisturized with a small amount of steam.. The Block Flow Diagram for this case is Figure 6 and the Steam, Condensate, and Diagram for this facility is shown in Figure 7. 6

FIGURE 4: CONVENTIONAL IGCC 1100 MW NOMINAL PITTSBURGH #8 COAL 8,340 STPD, DRY BASIS UNIT 0200 GRINDING & SLURRY PREPARATION COAL SLURRY GREY SEPARATION UNIT HP O2 7,970 STPD, PURE BASIS SLAG UNIT 0100 GASIFICATION (RADIANT ONLY) UNIT 0400 COARSE SLAG HANDLING VENT UNIT 0300 LOCKHOPPER RECIRC. HP RAW SYNGAS QUENCH FINES SLAG GREY IP N2 TO CTGs GAS SCRUBBING BLACK UNIT 0300 GREY UNITS 0500/0600 BLACK FLASH & FINE SLAG HANDLING HEATED VACUUM SCRUBBED SYNGAS PROCESS STRIPPED SOUR GAS BLOWDOWN UNIT 0900 PROCESS WASTE TREATMENT LP UNIT 0800 LOW TEMP GAS COOLING & COS HYDROLYSIS PROCESS COND. VAC. (HOT) UNIT 0700 LOW PRESSURE (AMMONIA STRIPPER) EXTRACTION IP LP AMMONIA/ ACID GAS NAT GAS (START-UP) FLASH GAS AMMONIA OFFGAS EXHAUST TO ATM UNIT 1000 MERCURY REMOVAL ACID GAS UNIT 1200 IP SULFURIC ACID PLANT 1 x 100% TRAIN 756 STPD 93 WT% SULFURIC ACID TO FLARE CRUDE SYNGAS DEMIN. CWR TO LAKE CWS FROM LAKE TO NEUTRALIZATION SUMP CLEAN FUEL GAS UNIT 1100 ACID GAS REMOVAL (MDEA) UNIT 1350 VACUUM & BOILER FEED SYSTEMS PREHEATED FUEL GAS IP FROM SRU SH IP SH HP TURBINE EXHAUST RETURN UNIT 1300 COMBUSTION TURBINE GENERATOR (GE 7FA+e) CTG EXHAUST GAS UNIT 1310 HEAT RECOVERY GENERATOR () CRH HRH FLUE GAS TO ATM SH LP UNIT 1320 TURBINE GENERATOR IP N2 FROM ASU INTERNAL USERS LP FROM LTGC MP FROM LTGC SH MP No. 2 FUEL OIL (START-UP) 2 X 83.8 MW 66.6 MW 4 x 197.0 MW 2 X 266.0 MW NET POWER OUTPUT 1085.8 MW 1,280 STPD COARSE SLAG 50 WT% SOLIDS 320 STPD FINE SLAG 50 WT% SOLIDS 1 X 100% TRAIN 46 STPD 50 WT% SOLIDS FILTER CAKE TO DISPOSAL WASTE TO FACILITY ZLD SYSTEM

FIGURE 5: DIAGRAM, CONVENTIONAL IGCC 640 PSIG, SATURATED HP SUPERHEATERS 1387 psig 1000 F 385 psig 996 F GASIFICATION RADIANT SYNGAS BOILER BD 544 F 590 F 600 F HP EVAPORATOR HP ECONOMIZER #3 12-B-401 SULF. ACID PLANT IP GENERATOR BD 462 F IP KO DRUM IP EVAPORATOR 08-E-202 COS HYDROLYSIS HEATER 484 F 460 PSIG, SATURATED TO MP FLASH DRUM IP SUPERHEATERS 457 psig 566 F 13-TG-101/201 CTG INJECTION REHEATERS 439 psig 699 F HP IP LP LP 60 F 72 F CWS CWR 79 F DEMIN 55 PSIG, SATURATED HP ECONOMIZER #2 452 F IP TO SYNGAS HEATER 452 F E-203 LP BOILER 11-E-101 MDEA REBOILER 07-F-204 AMMONIA STRIPPER 09-E-904 AMMONIA STRIPPER ASU PRETREATMENT REGENERATION ZERO LIQUID DISCHARGE (ZLD) FACILITY LP 52 psig SUPERHEATER 579 F HP ECONOMIZER #1 IP ECONOMIZER BD VENT IP 303 F DA MP 303 F 65 psig IP FLASH 312 F DRUM 225 F 175 F 314 F 165 F 195 F MISC GASIFICATION USERS 303 F BD FROM DRUMS BD FLASH DRUM DEAERATOR (INTEGRAL) LP DRUM 313 F 316 F LP EVAPORATOR

FIGURE 6: NOVELEDGE IGCC 1100 MW NOMINAL PITTSBURGH #8 COAL 8,340 STPD, DRY BASIS UNIT 0200 GRINDING & SLURRY PREPARATION COAL SLURRY GREY SEPARATION UNIT HP O2 7,970 STPD, PURE BASIS SLAG UNIT 0100 GASIFICATION (RADIANT ONLY) UNIT 0400 COARSE SLAG HANDLING VENT UNIT 0300 LOCKHOPPER RECIRC. HP RAW SYNGAS QUENCH FINES SLAG GREY IP N2 TO CTGs GAS SCRUBBING BLACK UNIT 0300 GREY UNITS 0500/0600 BLACK FLASH & FINE SLAG HANDLING HEATED VACUUM SCRUBBED SYNGAS PROCESS STRIPPED SOUR GAS BLOWDOWN UNIT 0900 PROCESS WASTE TREATMENT LP UNIT 0800 LOW TEMP GAS COOLING & COS HYDROLYSIS PROCESS COND. VAC. (HOT) UNIT 0700 LOW PRESSURE (AMMONIA STRIPPER) EXTRACTION IP LP AMMONIA/ ACID GAS NAT GAS (START-UP) FLASH GAS AMMONIA OFFGAS EXHAUST TO ATM UNIT 1000 MERCURY REMOVAL ACID GAS UNIT 1200 IP SULFURIC ACID PLANT 1 x 100% TRAIN 756 STPD 93 WT% SULFURIC ACID TO FLARE CRUDE SYNGAS DEMIN. CWR TO LAKE CWS FROM LAKE TO NEUTRALIZATION SUMP CLEAN FUEL GAS UNIT 1100 ACID GAS REMOVAL (MDEA) UNIT 1350 VACUUM & BOILER FEED SYSTEMS PREHEATED FUEL GAS IP FROM SRU SH IP SH HP TURBINE EXHAUST RETURN FUEL GAS UNIT 1300 COMBUSTION TURBINE GENERATOR (GE 7FA+e) NE: 3 X 33% TRAINS CTG EXHAUST GAS UNIT 1310 HEAT RECOVERY GENERATOR () CRH HRH FLUE GAS TO ATM NE: 3 X 33% TRAINS SH LP UNIT 1320 TURBINE GENERATOR NE: 1 X 100% TRAIN IP N2 FROM ASU INTERNAL USERS LP FROM LTGC MP FROM LTGC SH MP No. 2 FUEL OIL (START-UP) NE: 2 X 77.3 MW NE: 70.6 MW NE: 3 x 197.0 MW NE: 1 X 707.2 MW NET POWER OUTPUT NE: 1073.0 MW 1,280 STPD COARSE SLAG 50 WT% SOLIDS 320 STPD FINE SLAG 50 WT% SOLIDS 1 X 100% TRAIN 46 STPD 50 WT% SOLIDS FILTER CAKE TO DISPOSAL WASTE TO FACILITY ZLD SYSTEM 9

FIGURE 7: DIAGRAM, NOVELEDGE IGCC HP SUPERHEATERS IP KO DRUM 08-E-202 COS HYDROLYSIS HEATER REHEATERS HP IP LP LP HP EVAPORATOR GASIFICATION RADIANT SYNGAS BOILER 12-B-401 SULF. ACID PLANT IP GENERATOR TO MP FLASH DRUM CWS CWR DEMIN 13-TG-101/201 CTG INJECTION BD BD TO LP BOILER LINE HP ECONOMIZER #2 IP TO SYNGAS HEATER E-203 LP BOILER 11-E-101 MDEA REBOILER 07-F-204 AMMONIA STRIPPER 09-E-904 AMMONIA STRIPPER ASU PRETREATMENT REGENERATION ZERO LIQUID DISCHARGE (ZLD) FACILITY HP ECONOMIZER #1 BD IP MP FLASH DRUM TO CONDENSER MISC GASIFICATION USERS BD FROM DRUMS BD FLASH DRUM FROM ECONOMIZER #2 LT GAS COOLING 10

Just like the conventional plant, the NovelEdge plant at 1073 MW consumes 8844 stpd of Pittsburgh #8 coal on an as-received basis. With a higher heating value for this fuel input of 9654 MMBtu per hour HHV, the NovelEdge heat rate is 8997 Btu/kwh or 37.9% efficient. Process Comparison An examination of the Block Flow Diagrams for both the conventional and NovelEdge IGCC facilities (Figure 4 and Figure 6 respectively) indicates the major differences in these two cycles. For services such as the MDEA reboiler, ammonia condensate stripper, ASU air pretreatment regeneration, zero liquid discharge, and COS hydrolysis heater, all steam flows to these operations should be identical between either plant. Also, steam production from the sulfuric acid plant and the LP steam boiler should be identical. Therefore, the gasification process is essentially unchanged. From another perspective, however, such as the power island integration, a great deal has changed. For the NovelEdge process, all IP and LP sections of the have been eliminated. In addition, the LP steam line to the steam turbine is no longer required. The 4 deaerators that are integral with the LP section of each conventional are no longer necessary and are replaced with a vacuum-deaerating condenser. IP steam from the sulfuric acid plant is no longer tied to the IP steam system, but is simply used to provide moisturizing steam to be added to the nitrogen diluent. Additions to the NovelEdge process include a duct burner system for each, a low temperature gas-cooling module to preheat feedwater, and a heat exchanger to preheat low-pressure feedwater for the LP steam boiler and other miscellaneous gasification users. A vacuum-deaerating condenser is utilized in lieu of a pressurized system. For the ASU, the power requirements are reduced. Although the oxygen required is the same for either plant, conventional or NovelEdge, the conventional plant has 4 GTs, and thus requires a nominal 550,000 lb/hr of nitrogen diluent for each GT. The NovelEdge facility utilizes only 3 GTs; therefore its total diluent requirements are 550,000 lb/hr less than the conventional facility. This reduces the power requirements of the ASU, as less nitrogen must be compressed for GT injection. PERFORMANCE COMPARISON The two major performance comparisons that will be made are efficiency and emissions. Note that from the gasification perspective, these two facilities are identical, so fuel flow, slag flow, mercury removal, fine ash collection, and other such services associated with syngas treatment are the same for either option.

Efficiency From the power island perspective, both the conventional and NovelEdge plants will receive the same amount of treated syngas fuel. Each plant will use identical GTs with identical performance, including fuel flow and diluent flow. The conventional plant, however, will consume all of its fuel equally in 4 separate GTs, while the NovelEdge plant, will consume ¾ of the fuel in the 3 GTs, and the remaining ¼ will be consumed equally in each of the 3 duct burners. The conventional plant utilizes main steam conditions of 1400 psia/1000 F inlet and 996 F reheat. The NovelEdge facility has main steam conditions of 1815 psia/1050 F inlet and 1050 F reheat Also, with no IP or LP steam, it becomes obvious that the NovelEdge steam cycle is a more energetic and efficient cycle. There are also some parasitic load savings with the NovelEdge cycle. Since the steam cycle will use higher pressure and more steam flow, additional pumping power is required. This equates to a nominal 4 MW. However, since the ASU must only provide diluent for 3 GTs in lieu of 4, there is an approximate 13 MW reduction in ASU power requirements. Therefore, the net effect is a nominal 9 MW reduction in parasitic loads for the NovelEdge facility. Ultimately, for the same fuel flow, the conventional plant produces 1086 MW while the NovelEdge facility produces 1073 MW. This equates to an efficiency reduction for the NovelEdge plant of nominally 1.2 %. Emissions Both the conventional and NovelEdge facilities utilize the same gasification systems, the same fuel quantity, and the same MDEA sulfur removal systems. Sulfur emissions from either plant are anticipated to be the same in tons per year. With 40 ppm of sulfur in the fuel, the anticipated sulfur emission rate is a nominal 175 lb/hr for the facility at base load. All the GTs in this comparison are designed for 15 ppm of NOx. Therefore, for the conventional cycle, each stack shall have a stack emission rate of 15 ppm NOx @ 15% O 2. However, for the NovelEdge cycle, there are duct burners that will contribute to the NOx. The rate of NOx formation for the duct burners is 0.08 lb/mmbtu HHV. Therefore, the stack outlet NOx for the NovelEdge design is 16.5 ppm NOx @ 15% O 2. Although at first glance this may seem like a sizeable increase, further examination reveals that this increase is actually quite small. At 15 ppm NOx @ 15% O 2, each GT in the conventional plant emits 139.9 lb/hr of NOx. For the entire plant with 4 GTs, this calculates to 559.6 lb/hr. For the NovelEdge facility, each stack emits 16.5 ppm NOx @ 15% O 2. This equals 189.4 lb/hr of NOx per stack or 568.2 lb/hr of total NOx for the plant. Therefore, the NOx emissions for the NovelEdge facility are only 1.5% greater than those in the conventional arrangement. 12

Further, had we elected to install SCR in these s and controlled NO x to a consistent reference level such as 3 ppm (uncorrected for O 2 ), then the overall NO x emissions would have been reduced by 33%. Summary The following data in Table 1 summarizes the performance comparison for the 1086 MW conventional and 1073 MW NovelEdge IGCC plants: Table 1 Conventional IGCC NovelEdge IGCC Plant Output - MW 1086 1073 Plant Heat Rate Btu/kwh 8890 8997 NOx ppm @ 15% O 2 15 16.5 NOx Potential Tons/year 2451 2489 SOx Potential Tons/year 768 768 Heat Rates shown are HHV COST COMPARISON Cost estimates were developed for the two plants on the basis defined above. Both plants were located at a generic Gulf Coast location and were fully self sufficient in all supplies other than the Pittsburg #8 coal feedstock. The plant included air separation facilities but no sparing of the gasifiers. These are AACE Class 5 estimates with costs stated on instantaneous 3 rd quarter 2004 basis. Initial fill of catalysts and chemicals is included but no other startup costs. Contingency is included at 8% and accuracy is deemed to be 15/+40%. Estimate assumes clear and level site, no site remediation or piling requirements. Exclusions from the estimate include owner s costs, sales/use taxes, forward escalation, working capital, inventory, scope changes, interest during construction and any premium steel prices reflecting the current market. Table 2 Conventional IGCC NovelEdge IGCC Plant Capital, MM$ 1225 1150 Plant Capital, $/kw 1128 1072 13

Operating costs of the two plants are similar in many categories. The table below focuses on the differences. Capital charges are based on 10 years depreciation and 80% availability factor. This is a simplified approach and does not correspond to the EPRI COE methodology. Option Plant Rating MW Heat Rate Btu/kwh Table 3 Electrical Fuel Cost $/kwh Capital Cost $/kw Electrical Capital Cost $/kwh Electrical O&M Cost $/kwh Total Cost for Electricity $/kwh Conventional 1086 8890.0116 1128.0161.0105.0382 NovelEdge 1073 8997.0117 1072.0153.0102.0372 Note: Capital costs charged at 10 years recovery before taxes and 80% plant availability. NOVELEDGE REFERENCE PLANT IN DEVELOPMENT In the previous comparison, two nominal 1100 MW plants were compared, a conventional IGCC plant and a NovelEdge facility. With the exception of the power island, in this comparison the gasification island, the ASU, and the balance of plant equipment were all nearly identical. This was done for purposes of consistency in the comparison. Having now verified that the NovelEdge approach does indeed provide similar performance to the conventional plant, only at a lower cost, it is logical to proceed to the next step, which is to search for potential improvements to an entire IGCC plant that is based around the NovelEdge process. Cost Effective Design It has been shown that the use of NovelEdge can reduce the cost of the power island in an IGCC application, but since the power island represents only about 40% of the overall IGCC plant cost, it is desirable to find cost savings in other portions of the plant as well. One such place where savings may be realized is in the gasification island. In some instances, the same gasifiers can be operated at higher pressure to yield more throughput. This results in an economy of scale cost savings, as the incremental power output is greater than the incremental cost adder. This may also be the case when a larger gasifier is substituted for a smaller one. In either instance, the cost of the gasification plant can be reduced on a $/kw basis by extending gasifier output to its rated capacity. The NovelEdge Reference Plant, which is still in development, will utilize the same gasifier count as in the 543 MW conventional plant (one block of the 2-on-1 as described in the aforementioned comparison), only we will increase its throughput by 25% by utilizing a larger gasifier. In addition, this will require a nominal 25% larger ASU, 14

however, the economy of scale factor should provide an ASU facility that is again less costly on a $/kw basis. Cycle Design As discussed earlier, the NovelEdge cycle is predominantly a steam cycle. With steam used for heat recovery from the hot syngas, the need for process steam requirements, and the presence of a great deal of low temperature energy, there are more opportunities for the NovelEdge cycle to be efficient. Some of the factors for increased efficiency are as follows: 1) It has an efficient steam cycle 2) Duct firing provides high end energy for superheat/reheat of excess steam, such as that from a convective boiler 3) Process steam can be extracted rather than just produced at user pressure 4) An additional expander can be used for the duct burner fuel 5) More plant MWs per GT equate to relatively less parasitic load for compressing nitrogen In the conventional cycle, most of the 55 psig process steam is produced in the LP steam boiler and used for various plant services. Although this steam meets the requirements for which it is intended, it produces no power. With the NovelEdge design, more 55 psig steam can be extracted from the ST, thus producing power before it is utilized for the plant services. With a steam-based cycle such as NovelEdge, more steam is generated and as a result, more cold feedwater is available for heat recovery. This allows for heat recovery of low temperature energy from returning condensate or from the syngas itself that might otherwise just be cooled by a trim cooler. Reference Plant Arrangement For this NovelEdge reference plant, we focused on a 2-on-1 arrangement based upon the GE Frame 7FA+e gas turbine. The emphasis was to utilize equipment to its maximum capacity. Therefore, utilizing gasifiers near their maximum operating pressure was deemed less costly than the use of an additional gasifier. The complement of major equipment is as follows: 2 Gasifiers (50% capacity each), with radiant and convective coolers 1 Selexol sulfur removal system 2 ASUs (50% capacity each), nominal 4700 total tpd pure O 2 2 GE Frame 7FA+e GTs 2 s, Nooter/Eriksen single pressure level 1 Steam turbine, nominal 440 MW 1 - Condenser 15

Since the concept of NovelEdge is to utilize a single pressure cycle, and recover heat with the feedwater, in lieu of producing IP and LP steam as in the conventional cycle, one of the first changes to the conventional cycle is the elimination of IP and LP steam evaporators to the greatest extent feasible. However, due to gasification practice, the LP steam boiler was utilized, only with a diminished output. In addition, to maximize efficiency, a convective heat recovery boiler was added to the outlet of the gasifier. The remaining energy contained in the syngas after exiting the convective boiler is utilized to preheat feedwater. See Figure 8 for the Block Flow Diagram of the NovelEdge Reference Plant process. 16

FIGURE 8: NOVELEDGE REFERENCE PLANT PITTSBURGH #8 COAL 10,425 STPD, DRY BASIS UNIT 0200 GRINDING & SLURRY PREPARATION COAL SLURRY GREY SEPARATION UNIT HP O2 9,962 STPD, PURE BASIS SLAG UNIT 0100 GASIFICATION (RADIANT AND CONVECTIVE) UNIT 0400 COARSE SLAG HANDLING VENT UNIT 0300 LOCKHOPPER RECIRC. HP RAW SYNGAS QUENCH FINES SLAG GREY IP N2 TO CTGs GAS SCRUBBING BLACK UNIT 0300 GREY UNITS 0500/0600 BLACK FLASH & FINE SLAG HANDLING HEATED VACUUM SCRUBBED SYNGAS PROCESS STRIPPED SOUR GAS BLOWDOWN UNIT 0900 PROCESS WASTE TREATMENT LP UNIT 0800 LOW TEMP GAS COOLING & COS HYDROLYSIS 1 X 100% TRAIN PROCESS COND. VAC. (HOT) UNIT 0700 LOW PRESSURE (AMMONIA STRIPPER) 1 X 100% TRAIN EXTRACTION IP LP AMMONIA/ ACID GAS NAT GAS (START-UP) FLASH GAS AMMONIA OFFGAS EXHAUST TO ATM UNIT 1000 MERCURY REMOVAL 1 X 100% TRAIN ACID GAS UNIT 1200 IP SULFURIC ACID PLANT 1 x 100% TRAIN 945 STPD 93 WT% SULFURIC ACID TO FLARE CRUDE SYNGAS DEMIN. CWR TO LAKE CWS FROM LAKE TO NEUTRALIZATION SUMP CLEAN FUEL GAS UNIT 1100 ACID GAS REMOVAL (MDEA) 1 X 100% TRAIN UNIT 1350 VACUUM & BOILER FEED SYSTEMS 1 X 100% TRAIN PREHEATED FUEL GAS EXP. 2 EXP. 1 IP FROM SRU SH IP SH HP TURBINE EXHAUST RETURN UNIT 1300 COMBUSTION TURBINE GENERATOR FUEL GAS (GE 7FA+e) CTG EXHAUST GAS UNIT 1310 HEAT RECOVERY GENERATOR () CRH HRH FLUE GAS TO ATM UNIT 1320 SH LP TURBINE GENERATOR 1 X 100% TRAIN IP N2 FROM ASU INTERNAL USERS LP FROM LTGC MP FROM LTGC SH MP No. 2 FUEL OIL (START-UP) 1 X 105.5 MW 31.9 MW 2 x 197.0 MW 6.5 MW EXP. 1 12.6 MW EXP. 2 1 X 433.4 MW NET POWER OUTPUT 709.1 MW 1,600 STPD COARSE SLAG 50 WT% SOLIDS 400 STPD FINE SLAG 50 WT% SOLIDS 1 X 100% TRAIN 57.5 STPD 50 WT% SOLIDS FILTER CAKE TO DISPOSAL WASTE TO FACILITY ZLD SYSTEM

Feedwater preheating is now provided by several means. First, low temperature water from the black water treatment facility provides low temperature heat. In addition, returning water from the fuel gas heaters provides some feedwater heating. And also, condensate from both the 55 psig header and the 640 psig header is utilized as well. Final preheating of the feedwater before entering the is accomplished through the use of a steam extraction feedwater heater, which utilizes low-pressure steam from the steam turbine. The majority of the process steam required by the 55 psig header is now extracted from the steam turbine, as the LP steam boiler produces only about 20% of the required flow. To minimize overall system changes, the Sulfuric Acid Plant (SAP) is unchanged, and excess steam generated in the SAP is sent to the cold reheat line. Also, to enhance efficiency and environmental performance, the standard MDEA sulfur removal system was replaced with a Selexol system to reduce sulfur to a nominal 8 ppm. With these low levels of sulfur, an SCR system in the can be effective. The for this application is built by Nooter/Eriksen. It includes the duct burner, SCR catalyst, and an ammonia oxidation catalyst. The SCR is designed to reduce the NOx to 3ppm @ 15% O 2. Due to the sulfur content of the syngas fuel, the ammonia oxidation catalyst is designed to reduce the ammonia slip after the SCR to 0.5 ppm, its purpose being to negate the effects of ammonia salt formation in the downstream sections of the. As is typical of a NovelEdge, this unit includes only one evaporator for HP steam, and a large economizer section. Superheat and reheat sections are included downstream of the duct burners. Firing temperature at maximum output is less than 1400 F. Figure 9 is a general arrangement drawing for the for this application.

NovelEdge Reference Plant Design Figure 9

The net result of optimizing the IGCC plant for the NovelEdge-based IGCC is a facility that can achieve efficiency levels of 40% HHV or greater. In this 2-on-1 arrangement with the GE Frame 7FA+e, the nominal ISO output is 709 MW. The emissions for the plant are reduced to less than 2 ppm for SO 2 and less than 3 ppm for NOx. Capital costs are also low, with an estimated Gulf Coast installation cost of less than $1000 per kw. Now let s compare the cost of electricity for the 543 and 1086 MW conventional plants from the initial comparison (one block of 2-on-1 and two blocks of 2-on-1) to the 709 MW NovelEdge Reference Plant. The three economic factors considered were fuel cost, capital cost, and maintenance cost. Plant capacity factor was assumed to be 80% in either case. Fuel costs were taken to be $1.30 per MMBtu. The annual capital and maintenance costs considered being 10% and a nominal 6.5% of the capital costs respectively. With this data, Table 4 compares the cost of electricity from the two plants. Table 4 Option Plant Rating MW Heat Rate Btu/kwh Electrical Fuel Cost $/kwh Capital Cost $/kw Electrical Capital Cost $/kwh Electrical O&M Cost $/kwh Total Cost for Electricity $/kwh Conventional 543 8890.0116 1190.0170.0110.0396 Conventional 1086 8890.0116 1128.0161.0105.0381 NovelEdge 709 8510.0111 980.0140.0091.0341 As can be seen from this data, even with its larger economy of scale, the conventional 1086 MW plant still has a higher cost of electricity than the smaller NovelEdge facility. Thus the NovelEdge Reference Plant is an efficient, yet low cost and low emissions IGCC facility. Flexibility is Key The one key issue that makes the NovelEdge IGCC approach so attractive is its flexibility. The plant rating can be tailored to meet a variety of parameters including output or cost. If transmission is a limiting factor, the NovelEdge plant can be designed to meet a specified output. To reduce cost, the necessary amount of duct firing can be designed into the facility to get the most from a particular portion of the plant, such as maximizing the output of a given gasification island, staying within the design limits for a single ASU, or maybe maximizing the output of a manufacturer s steam turbine model. The latter has significant importance in the repowering of existing facilities.

REPOWERING Many natural gas-fired combined cycle plants are currently stranded, due to the high cost of fuel. This leaves the door open for repowering opportunities. If a natural gas fired combined cycle (NGCC) plant can be reasonably converted to IGCC, this might restore a plant s profitability. From a historical perspective, approximately 75% of the NGCC plants built in the last several years included some amount of duct firing. This means a 2-on-1 NGCC plant with F class GTs will include a nominal 200 to 300 MW steam turbine. From the NovelEdge Reference Plant, it is noticed that the steam turbine utilized in this design is rated at a nominal 440 MW. Therefore, an integrated repowering could use a 1-on-1 arrangement (half size of Reference Plant presented herein with a nominal 220 MW steam turbine) and achieve a nominal 360 MW output. Therefore, all that would be needed would be the GT rework to utilize syngas, and a new. Some minor ST rework may be required, but typically these steam turbines were designed for 1800 psia/1050/1050 F steam conditions. For higher output, such as 720 MW, a second new and a new ST could be installed. This might provide an economical repowering that is mentioned here for reader interest, but is beyond the scope of this current paper. And of course, the repowering of main steam plants, be they coal, oil, or natural gas fired can be readily achieved with NovelEdge Technology, as it is a steam based combined cycle, utilizes a single pressure steam, and will be a better match to the existing steam turbine. And obviously the key element, flexibility, provides for matching the steam flow to the existing steam turbine. This can be easily accomplished by providing the correct amount of duct firing to the IGCC process. Repowering will provide many opportunities in the future, and the fact that NovelEdge is a steam based combined cycle, in conjunction with its flexibility, make it an ideal technology to accomplish this task. 21

CONCLUSIONS This paper has presented a consistent comparison of conventional IGCC with a NovelEdge IGCC. This comparison required a larger plant than would usually be built but was necessary to remain within the bounds of an integer number of gas turbines and the design range of duct firing for the NovelEdge process. The more usual size of 500 MW+ was discussed under the NovelEdge reference plant. The conclusions reached in the comparison of conventional IGCC with NovelEdge IGCC were: Power production from the power block is less for NovelEdge. Although the incremental duct-fired steam cycle is very efficient, it does not quite compete with combined cycle efficiency. Power production from NovelEdge improves because elimination of one gas turbine eliminates the need to compress NOx control nitrogen to that gas turbine. On an overall basis, power production is 1073 vs. 1086 MW or about 1.2 percent less than the conventional IGCC. Plant availability will be the same for both cases. The same basic components are included in both cases and the level of duct firing in the NovelEdge case falls well within commercial experience. Plant risk is comparable for both cases for the same reasons. Capital investment for NovelEdge IGCC is 1150 MM$ or about 93.9% of the conventional IGCC. Note that the investment costs are dropping faster than the power output. Maintenance costs are lower for the NovelEdge case. While long term gas turbine maintenance costs are roughly $.0025/kW-hr, steam turbine maintenance costs are about 20% of this figure. Non-maintenance operating costs are expected to be equivalent between the two cases. Overall costs of electricity are significantly less. The benefits of this technology should be applicable to other gasification processes. The plant components of the NovelEdge process are commonly used in power plants and are well proven. The economics of this process are attractive and the process is worth consideration in future IGCC plants. 22