A case study on the expansion of power plant from simple cycle to combined cycle

Similar documents
WORK BELOW LOWEST FLOOR FINISH 1/7 230, , , FRAME 2/6 96, , ,056.00

Selection, installation and USage of HatcHeS

11. Construction processes and materials Power House Maintenance Building Fuel Treatment Building...

Barilla Cogeneration Power Plant main tips

Estimate FOR THE SEPTIC TANK

New Eco-friendly Two-way Void Slab

Chapter 5 Hydraulic Structures

Development of an Efficient Tapered Slip-Form System Applying BIM Technology

The designer shall also submit additional information required by the University as described and underlined below.

Installing DELTABEAM. Installation of DELTABEAM. Deliveries. Storage on-site

Parametric Study for Evaluation of Design Parameters of Standing Column Well

DESIGNING AND CONSTRUCTION OF T-WALL RETAINING WALL SYSTEM

Testing of Concrete Blocks

STANDARD SPECIFICATION FOR CRIBLOCK CONCRETE CRIBWALL

See the IRC for additional information. See CPD-DS Information Bulletin 100 for Requirements for 1 & 2 Family Dwelling plan submittals.

Structural Tests and Special Inspections Form. Inspection of Fabricators (1704.2)

INTERNSHIP REPORT GOUTHAM.J

Design and Estimation of Reinforced Building: A Case Study

Foundation/Site Work Code Requirements

Introduction of a Japan Concrete Institute Guideline: Practical Guideline for Investigation, Repair and Strengthening of Cracked Concrete Structures

SAMPLE SPECIFICATION for HIGH STRAIN DYNAMIC TESTING of DRIVEN PILES

EXPO'98 PORTUGUESE NATIONAL PAVILION A LARGE USE OF LIGHT WEIGHT STRUCTURAL CONCRETE

ctbuh.org/papers Prediction and Compensation of Column Shortening for Bitexco Financial Tower Title:

SECTION CAST-IN-PLACE CONCRETE

SECTION ENTRANCE FLOOR GRILLES STAINLESS STEEL GRATING

GUIDE SPECIFICATIONS For STRUCTURAL PRECAST HOLLOW CORE SLABS SECTION 03410

NEW PERFORMANCE CRITERIA FOR FRESH TREMIE CONCRETE

PERFORMANCE OF MECHANICAL SEISMIC LOAD TRANSMISSION DEVICE BASED ON IMPACT

ctbuh.org/papers Optimal Combination between Concrete Strength and Sets of Forms in High-rise Building Title:

Possible solution to past CM exam question. Question 2 July New city centre office block. by Rajavel Inbarajan

PROPOSED STOCK PILE YARD PHASE 1 SITE: MYRA FALLS MINE

In-plane testing of precast concrete wall panels with grouted sleeve

CIVIL BREADTH Exam Specifications

1 Exam Prep Placing Reinforcing Bars Tabs and Highlights

Estimation of existing tall buildings pile foundations bearing capacity under seismic and wind loads. T.Davitashvili 1,a, I.

SECTION BASIC ELECTRICAL MATERIALS AND METHODS

SECTION A1 EXCAVATION AND BACKFILL GENERAL

REPAIR AND STRENGTHENING SPECIALISTS

DIVISION 31 EARTHWORK 2006 Edition, Published January 1, 2006; Division Revision Date: January 31, 2012

PRECAST CEMENT PRODUCTS

Structural Inspection Report

RFP/GRC/LSV/ : RENOVATION (CIVIL WORKS) AT SKALA SYKAMNIAS CHILDRENS PLAYGROUND BILL OF QUANTITIES

16. Design of Pipeline Structures.

MACHINE-LAY Installation Manual

4th International Engineering and Construction Conference - July 28, 2006

***************************************************************************************************************

The Chief Estimator Software. Item Cost Summary Bridge & Overpass Projects

SECTION FACILITY SANITARY SEWERS

Project Address: Name of Person Completing Form:

Development of Steel Diaphragm Wall with Soil Cement

Structural Evaluation and Strengthening Strategy for a Reinforced Concrete Commercial/Residential Complex in Northern Beirut

Case study of deep excavation in existing underground structure of three-story basement and diaphragm wall

T-WALL & STONE STRONG

International Journal of Advanced Structural Engineering, Vol. 3, No. 1, Pages , July 2011

DESIGN AND CONSTRUCTION OF DERRY ROAD AND CANADIAN NATIONAL RAIL GRADE SEPARATION

The Ultimate Structural Engineering Software Package!

SPECIFICATIONS FOR PRECAST MODULAR BLOCK RETAINING WALL SYSTEM (revised 5/8/7)

The superior self-compacting concrete

02800 SHADE STRUCTURES

Safety Assessment of Excavation with Fault Tree Analysis

The construction of deep excavation ditch in weak soil in St. Petersburg

Read Only Copy Not For Distribution. Chapter 17. Private Potable Water Supply Systems 17.1 GENERAL REGULATIONS 17.2 QUANTITY OF WATER REQUIRED

SECTION CLIMBING WALLS

ACOTEC. Acotec panel production D /EN/E 1(14) PROCESS DESCRIPTION ACOTEC PANEL PRODUCTION

Cardok Sàrl CP37 CH-1295 Tannay Switzerland Phone:

Flygt Advanced Low Pressure Sewer System Package

Behaviour of Post-Installed GFRP Adhesive Anchors in Concrete

Numerical study of shear wall behavior coupled with HPFRCC beam and diagonal reinforcements

Masonry block construction in Haiti

ATP Oil Shale Plant in China

Topic: Site Formation

MID-STORY SEISMIC ISOLATION FOR STRENGTHENING OF A MULTI-STORY BUILDING

A. Coordinate concrete unit masonry (also termed CMU and block ) work with work before and after, especially:

Comparison of Eurocode 8 and Turkish Earthquake Code 2007 for Residential RC Buildings in Cyprus

Seismic isolation of LFR Reactor Buildings

Minimum Guidelines for the Design and Use of Underpins When Performing Foundation Stabilization and/or Supplementation UP-08

DESIGN CALCULATIONS INSTA-FOOTING LOAD BEARING CAPACITIES ON CONCRETE SLAB. January 14, 2017 Rev -

Tolerances for Concrete Construction. Tolerances for Concrete Construction. Tolerance 6/16/2015

NONDESTRUCTIVE EVALUATION (NDE) METHODS FOR QUALITY ASSURANCE OF EPOXY INJECTION CRACK REPAIRS

PRE-CAST HOUSE CONSTRUCTION

Well Road Project Accelerated Bridge Construction Using Self-Propelled Modular Transporters (SPMT s) By: Mark Bucci, P.E.

Structural Technical Report 1 Structural Concepts / Structural Existing Conditions Report

Next Generation Canada-France-Hawaii Telescope Pier Building Evaluation

1. Cast-in-place concrete is specified in Section

In order to get the maximum comfort out of a radiant system, it is paramount to go through a precise design phase (ref. UNI EN 1264).

This unofficial translation of. Ministerial Decision No 421/1998. was downloaded from METS is not the copyright owner.

1.2 DEFINITIONS, REFERENCES, AND OVERALL STANDARDS Follow 07500

DUCTILE IRON PILES ARE HIGHLY EFFECTIVE, FAST AND VERSATILE MODULAR DRIVEN MICROPILE SYSTEMS

A.2.a Random Riprap... Table

Anchorplex retaining wall construction guide. Building. Anchorplex. Retaining Wall Systems

UNIT 9 INSPECTION AND QUALITY CONTROL

Preventing Water Leakage through Construction Joints using SYNKOFLEX Preformed Compressible Waterstop

CONNECTION TO INSPECTION CHAMBERS PRAKTO

DARTMOUTH COLLEGE DESIGN January 3, 2012 & CONSTRUCTION GUIDELINES

SikaProof Bentonite Plastic DPM overlap - Compacted Backfill Scale 1:5. Detail no: SB01 - Nov 2013

Status of ITER Buildings construction and next procurement steps

ITEM D-701 PIPE FOR STORM DRAINS AND CULVERTS

SECTION HVAC GRAVITY VENTILATORS

Reinforced concrete slot channel

Transcription:

Creative Construction Conference 2015 A case study on the expansion of power plant from simple cycle to combined cycle Hoon Choi*, Hyouk Sueng Kwon, Dong Won Shin, Han Seok Kwon KEPCO E&C, 2354 Yonggudaero, Giheung-gu, Youngin-si, Gyeonggi-do, 446-713, South Korea Abstract This is a case study of expansion of a power plant from a simple cycle to a combined cycle in Cote d lvoire in West Africa. The project is called CIPREL IV Volet B Project. The original plant was composed of 2 units of Gas Turbines (GT) and related equipment. With increasing demands on the electricity in Cote d lovire, the owner of the plant came up with an expansion plan and KEPCO E&C won an EPC project. For the expansion of power plant, a Steam Turbine (ST), two units of Heat Recovery Steam Generators (HRSGs), an Air Cooled Condenser (ACC), and many of other equipment are installed. This paper focuses on civil works among many fields of engineering in the project. In this paper, efforts to overcome environmental and geographical challenges are described. Creative civil design concepts and construction methods of civil works are also described. To address the underground water, the submerged rectangular concrete casing method was applied. Vibration damping springs were installed under the ST foundation instead of pile works. To avoid interference between exist piping line and new civil structure, and to maximize the efficiency, precast concrete product and related construction method were applied. Furthermore, to save transportation costs, steel members were divided into segments and delivered using container. Keywords: Combined Power Plant, Expansion, Submerged Rectangular Concrete, Vibration Damping Spring, Precast Concrete Product, Segment 1. Introduction 1.1. Project General The Republic of Cote d'ivoire, the driving force of West Africa, has resolutely taken up the path to development in a climate of peace. This move will inevitably require investment in infrastructure and electric power, an area where demand is growing at a fast pace (+18% annually). According to this demand increase, the CIPREL IV Volet B Project had been started in the middle of 2013. The plant had been already operated in the simple cycle mode with 2 units of gas turbines and generators. To increase efficiency of power generating capacity without additional fuel, the expansion works from simple cycle to combine cycle had been begun. To this end, one (1) Steam Turbine (ST), two (2) Heat Recovery Steam Generators (HRSGs), one (1) Air Cooled Condenser (ACC), and related equipment were installed. This is ongoing project and is schedule to be finished in December 2015. This paper is focused on civil works among many fields of engineering in the project. In this paper some of creative civil design concepts and construction works are introduced to overcome obstacles for the successive project. * Corresponding author. Tel.: +82-31-289-4124 ; fax: +82-31-289-4323 E-mail address:hchoi@kepco-enc.com 93

Figure 1. Schematic View of Combined Power Plant (Expansion Concept) 2. Plan and Construction As shown on Figures 2 and 3, the master plan was composed with GTG (Gas Turbine Generator) 1 and 2 that are existing. The GTGs generate electricity using fuel gas and emit exhaust gas with heat. This exhaust gas is transferred to HRSG (Heat Recovery Steam Generator) 1 and 2, and steam is generated inside of HRSG 1 and 2. HRSG 1 and2 are new facilities. The steam is transferred to STG (Steam Turbine Generator) that is inside of STB (Steam Turbine Building) through the steel pipe line on the piperack. Steam pipe is most important pipe among the entire piping system. STG, STB, Piperack and Steam pipe line are new facilities. Using steam, STG can generate electricity and this generated electricity is transferred to transformer nearby STB through IPB (Isolate Phase Bus). Used steam is transferred to ACC (Air Cooled Condenser) for cooling and recycling. At ACC, used steam is cooled, condensed and become water. This condensate water is transferred to HRSG again for recycling. The ACC is controlled in the ACC electrical room under the ACC and those are also new facilities. The waste water from each facility is transferred to the water treatment facility. Before waste water is discharged to outside of plant, water is treated fully. The expected total amount of generated electricity is 119MV. Figure 2. Project View Figure 3. Mast Plan of Project 94

3. Obstacles to Project During the project, we have faced many kinds of obstacles. In this paper, we describe briefly four main obstacles and how we could address them. First is that the entire process of the project including design, procurement, delivery and construction shall be finished only within 2 years. Second is distance from Korea to Cote d Ivoire taking more than 20 hours by airplane. Furthermore, communication between the design team in Korea and the construction team in Cote d Ivoire is difficult due to an 8-hour time difference. Because of the short project duration, sometimes engineering decisions shall be made urgently between design and construction engineer groups with considerable thought. However, these kinds of judgments are hard to make fast due to the time difference. As a result, this may induce waste time of construction. Third is lack of quality infrastructure in Cote d'ivoire. According to the minimum functional specifications (MFS), we have to produce results with high quality within a limited project budge. We had to use domestic construction equipment (fork lift, back hoe, drilling equipment, etc) and construction materials (steel plate, anchor, etc.) to minimize unnecessary spending according to priority. The transportation costs may exceed the budget, if all equipment and materials are procured outside of Cote d Ivoire. However, we sometimes cannot use heavy equipment because of limitation on available equipment. So, we must wait until such heavy equipment is available. It is indeed difficult to speed up construction works even after necessary equipment acquired because of poor management conditions. As a result, we shall undergo the project with limited construction techniques. These obstacles are summarized on Table 1. Fourth is natural and social environment limitation. During the raining season (about 2 months), construction cannot be carried out preventing from securing enough time. The construction site is reclaimed land and there exists sea nearby the construction site. So underground water elevation (EL.) is only GL - 2.0m. In addition, the leaked oil from the underground oil pipe line is mixed with the water. So, we shall treat this oily water before draining this oily water out of the site. The spread of Ebola-virus disease in 2014 in the West Africa region also brought impacts on the procurement plan. Table 1. Obstacles toproject First Second Third Forth Short construction period Distance and time different Lack of equipment and low quality of material Natural and social condition Figure 4. Site View After Rain Fall Figure 5. Underground Water After Excavation 95

4. Efforts 4.1. Vibration damping spring We applied vibration damping spring between STG and STG foundation. STG is one of the most important and expensive equipment for a power plant. As STG is rotary equipment, stability check under each step of vibration shall be conducted. In consideration of the sensitive characteristic of STG against vibration, STG foundation is usually constructed directly on the bed rock or pile foundation is applied. In this project, after detail structural analysis by civil engineers, we noticed a huge STG foundation will be needed with a deep foundation (pile or casing) due to the bad status of geological condition where soil lay is too thick. It is the reason that we cannot apply point bearing piles even though the soil status (sand) itself is relatively good. Instead of soil improvement and huge foundation, we selected to install vibration spring. By adopting this design concept, cost increase in civil material, construction fee and duration outweighs additional costs increase in the equipment price itself. Figure 6. Vibration Damping Spring Figure 7. STG Foundation (sub part) Before Vibration Damping Spring Installation 4.2. Segments delivery We divided structural steel members to segements and transported them to the site using container boxes. Usually, one boby member (not segement) is better considering convenience of installation and detail steel design since connection details are not needed. In this sense structural steel member is ususally fabricated as one body member if fabrication is available and there is no problem on lifting, installation, transportation technique. However, we devided one structural steel member into segements for better transportability from the fabrication factory in Dubai to the construction site, even though no issues on fabrication, transporation technique, lifting and installation were forseen. In case that some long members cannot be transported using container, they had to be shipped as bulk cargo despite small amount, charging more than the costs of connection detail fabrication works because of long transporation distance.. 4.3. Submerged rectangular casing method Inside of STB, there needs a deep concrete pit (bottm elevation is about GL -7.0m) in order to guarantee the performance of ACC. However, there exists eletrical building in the near distance and ground water elevation is GL - 2.0m. For water prevention, sheet-pile method is not available with no available sheet pile and related equipment at that time, which in turn we have to select submerged concrete casing method instead of any other water prevention methods. Figure 8 shows the section view of a concrete pit. The Submerged rectangular casing method is applied according to the following procedures; 1 st : Construct the 1 st wall of a concrete pit on soil 2 nd : Bituminous coating for concrete protection and decrease friction between soil and concrete pit 3 rd : Submerge 4 th : Construct the 1 st, 2 nd slab and 2 nd wall 96

(a) Section (b) Concrete Work for the 1 st Wall on Ground (c) Submerge Figure 8. Construction of Submerge a Concrete Pit 4.4. Precast concrete product We applied precast concrete product to the site boundary wall (Length: 420mm, Height: 5.0m) to save costs and to accelerate construction works together since no form work was needed with placing the precast concrete shop in the corner of the site. All precast walls and columns for the site boundary wall were made at site. (a) Precast Shop Plate (b) Construction Figure 9. Construction of Precast Site Boundary Wall 97

5. Conclusion For expansion works for a combined power plant, new equipment shall be installed while obstacles potentially interrupting constructions works exist. In an effort to tackle such obstacles, creative methods as shown below were introduced and applied to the civil works. As a result the total costs could be saved and construction could be preceded as planned while achieving cost cuts. (1) Vibration damping spring (2) Segments delivery for steel member (3) Submerged concrete casing work (4) Precast concrete For the success of project, most important thing is to make a close investigation about site condition, usable infrastructure and culture. Sometimes old technique can be better than latest technique when we consider all things at the same time. So, technical decisions through brainstorming among engineers like described above are very important and essential. Acknowledgements This research was supported by the CIPREL IV VOLET B EPC Project of KEPCO E&C (code 41A15). The financial support provided by the above Project of KEPCO E&C is acknowledged. References [1] American Concrete Institute (2005), Building Code Requirements for Structural Concrete (ACI 318-05) and Commentary (ACI 318R-05), ACI Committee 318, Farmington Hills, Michigan. [2] Salmon, C. G. and Johnson, J. E. (1996), Steel Structures Design and Behavior, Harper Collins College Publishers, New York. [3] Park, R. and Paulay, T. (1975), Reinforced Concrete Structures, John Wiley & Sons, New York. 98