Progress on Fast Reactor Development in Japan

Similar documents
Safety Implication for Gen-IV SFR based on the Lesson Learned from the Fukushima Dai-ichi NPPs Accident. Ryodai NAKAI Japan Atomic Energy Agency

Current Status and Future Challenges of Innovative Reactors Development in Japan

Regulatory Actions and Follow up Measures against Fukushima Accident in Korea

Isolation Condenser; water evaporation in the tank and steam into the air. Atmosphere (in Severe Accident Management, both P/S and M/S)

Preliminary Lessons Learned from the Fukushima Daiichi Accident for Advanced Nuclear Power Plant Technology Development

Safety enhancement of NPPs in China after Fukushima Accident

OVER VIEW OF ACCIDENT OF FUKUSHIMA DAI-ICHI NPSs AND FUTURE PLANNING TOWARD D&D

SENIOR REGULATORS MEETING Strengthening the Implementation of Defence in Depth IAEA Perspective

Present Status of Kyoto University Research Reactor, KUR

Lessons Learned from Fukushima Daiichi Nuclear Power Station Accident and Consequent Safety Improvements

Preparedness at PFBR Kalpakkam to meet the challenges due to Natural events Prabhat Kumar, Project Director, PFBR, Director construction BHAVINI

HPR1000: ADVANCED PWR WITH ACTIVE AND PASSIVE SAFETY FEATURES

Joint ICTP-IAEA Essential Knowledge Workshop on Deterministic Safety Analysis and Engineering Aspects Important to Safety. Trieste,12-23 October 2015

SUPER-SAFE, SMALL AND SIMPLE REACTOR (4S, TOSHIBA DESIGN)

XII. Lessons Learned From the Accident Thus Far

SYSTEMATIC AND DESIGN SAFETY IMPROVEMENTS OF NPPS IN CZECH REPUBLIC

Ensuring Spent Fuel Pool Safety

HTR reactors within Polish strategy of nuclear energy development Cooperation with Japan

SFR System Status and Plans

Post-Fukushima Assessment of the AP1000 Plant

Westinghouse Small Modular Reactor. Passive Safety System Response to Postulated Events

Implementation of Lessons Learned from Fukushima Accident in CANDU Technology

Concepts and Features of ATMEA1 TM as the latest 1100 MWe-class 3-Loop PWR Plant

Nuclear Power Plant Safety Basics. Construction Principles and Safety Features on the Nuclear Power Plant Level

BN-1200 Reactor Power Unit Design Development

Attachment VIII-1. July 21, 2011 Nuclear and Industrial Safety Agency

Post-Fukushima Action Plan in Korea. WNU-SI 2011, August 11 Christ Church, Oxford

Harmonized EUR revision E requirements corresponding to currently available technical solutions

Current Status of Research and Development on System Integration Technology for Connection between HTGR and Hydrogen Production System at JAEA

HTGR Brayton Cycle Technology and Operations

Enhancement of Nuclear Safety

The Westinghouse Advanced Passive Pressurized Water Reactor, AP1000 TM. Roger Schène Director,Engineering Services

Contents of summary. 1. Introduction

Chapter VI. VI.Situation regarding efforts to address lessons learned (28 items)

European level recommendations Sect. in NAcP 2 Generic recommendation for WENRA, Finland participates and follows the work.

Meetings for Sharing International Knowledge and Experience on Stress Tests

Small Modular Reactors: A Call for Action

Safety Challenges for New Nuclear Power Plants

The 2011 Tohoku Pacific Earthquake and Current Status of Nuclear Power Stations

Module 05 WWER/ VVER (Russian designed Pressurized Water Reactors)

REACTOR TECHNOLOGY DEVELOPMENT UNDER THE HTTR PROJECT TAKAKAZU TAKIZUKA

ANTICIPATED ANALYSIS OF FLAMANVILLE 3 EPR OPERATING LICENSE - STATUS AND INSIGHTS FROM LEVEL 1 PSA REVIEW

Analysis of Unprotected Transients in the Lead-Cooled ALFRED Reactor

IV. Occurrence and Development of the Accident at the Fukushima Nuclear Power Stations

Safety Issues for High Temperature Gas Reactors. Andrew C. Kadak Professor of the Practice

Power Generation. Ronaldo Jenkins Electrical Engineering Branch Chief Office of New Reactors (NRO)

Development and use of SAMGs in the Krško NPP

Brazilian Operator s Response to Fukushima Daiichi Accident Luiz Soares Technical Director

International Atomic Energy Agency. Impact of Extreme Events on Nuclear Facilities following Fukushima. Dr C H Shepherd Nuclear Safety Consultant, UK

HTGR development in Japan and present status

Nuclear Emergency Preparedness and Response in Japan following Fukushima Accident

DESIGN AND SAFETY PRINCIPLES LEONTI CHALOYAN DEPUTY CHIEF ENGINEER ON MODERNIZATION

LFR core design. for prevention & mitigation of severe accidents

Lessons learned from the accident at the Fukushima Daiichi Nuclear Power Plant

Verification of the MELCOR Code Against SCDAP/RELAP5 for Severe Accident Analysis

COUPLING A HYDROGEN PRODUCTION PROCESS TO A NUCLEAR REACTOR

Reactor Technology: Materials, Fuel and Safety. Dr. Tony Williams

AP1000 European 19. Probabilistic Risk Assessment Design Control Document

CNE Cernavoda Response to Fukushima Event/EU Stress Test Requirements

CLASSIFICATION OF SYSTEMS, STRUCTURES AND COMPONENTS OF A NUCLEAR FACILITY

The ESBWR an advanced Passive LWR

Comprehensive Safety Assessment for Kashiwazaki Kariwa NPS

National Nuclear Safety Administration, P. R. China

Nuclear Power A Journey of Continuous Improvement

Regulation of existing and new nuclear power stations in South Africa in the light of the Fukushima Accident

French R&D program on SFR and the

Radiation Control in the Core Shroud Replacement Project of Fukushima-Daiichi NPS Unit #2

APR1400 Safe, Reliable Technology

Advanced Design of Mitsubishi PWR Plant for Nuclear Renaissance

SAFETY GUIDES. Deterministic Safety Assessment РР - 5/2010 ÀÃÅÍÖÈß ÇÀ ßÄÐÅÍÎ ÐÅÃÓËÈÐÀÍÅ BULGARIAN NUCLEAR REGULATORY AGENCY

Module 06 Boiling Water Reactors (BWR)

Improvements Needed in Nuclear Power Plant Probabilistic Risk Assessments: Lessons Learned from Fukushima

Chapter 3 Accident of Fukushima Daiichi Nuclear Power Plant: Sequences, Fission Products Released, Lessons Learned

System Analysis of Pb-Bi Cooled Fast Reactor PEACER

Design Safety Considerations for Water-cooled Small Modular Reactors As reported in IAEA-TECDOC-1785, published in March 2016

Side Event of IAEA General Conference. Severe Accident Analyses of Fukushima-Daiich Units 1 to 3. Harutaka Hoshi and Masashi Hirano

Dry storage systems and aging management

Topics on Current Nuclear Regulation in Japan

RESULTS OF THE GRADUAL UPGRADING AT BOHUNICE WWER - 440/230 NPP

Assessing and Managing Severe Accidents in Nuclear Power Plant

Measures against Earthquakes and Tsunamis in View of the Accident at Fukushima Daiichi Nuclear Power Station

Safety Enhancement of Nuclear Power Plant Post Fukushima. Kumiaki Moriya

Decommissioning Group Ketut Kamajaya

Evolution of Nuclear Energy Systems

Concept and technology status of HTR for industrial nuclear cogeneration

Study on Severe Accident Progression and Source Terms in Fukushima Dai-ichi NPPs

Westinghouse SMR & Nuclear Fuel Overview

GIF Lead-cooled Fast Reactor Development Status Alessandro Alemberti (EURATOM / Ansaldo Nucleare)

Nuclear Reactor Types. An Environment & Energy FactFile provided by the IEE. Nuclear Reactor Types

Recent Approaches related to Safety Enhancement of Operating NPPs in Korea Tae Eun JIN KEPCO E&C

Overview of the IAEA and Fast Reactor Activities

WORKING MATERIAL. Technical Meeting on Impact of Fukushima event on current and future FR designs

EXPERIMENTS ON THE PERFORMANCE SENSITIVITY OF THE PASSIVE RESIDUAL HEAT REMOVAL SYSTEM OF AN ADVANCED INTEGRAL TYPE REACTOR

Regulatory Guide Monitoring the Effectiveness of Maintenance at Nuclear Power Plants

FUKUSHIMA DAI-ICHI ACCIDENT: LESSONS LEARNED AND FUTURE ACTIONS FROM THE RISK PERSPECTIVES

NUCLEAR POWER NEW NUCLEAR POWER PLANTS IN 2012

Mid-and-Long-Term Roadmap towards the. Decommissioning of TEPCO s Fukushima Daiichi. Nuclear Power Station

PROBABILISTIC SAFETY ANALYSIS IN SAFETY MANAGEMENT OF NUCLEAR POWER PLANTS

Outline of the Fukushima Daiichi Accident. Lessons Learned and Safety Enhancements

Transcription:

Presented for Meeting of the Technical Working Group on Fast Reactors (TWG-FR) (45th Annual Meeting) Progress on Fast Reactor Development in Japan June 20-22, 2012 Hiroaki OHIRA, Nariaki UTO Japan Atomic Energy Agency (JAEA)

1 1. Experimental Fast Reactor JOYO Current Status and Future Plan of Joyo Mark-III

Experimental Fast Reactor Joyo 2 Attain Initial Criticality:1977 First Operation (MK-I; 50/75MWt; Breeder core) :1978/1980 ibid (MK-II; 100MWt; Irradiation core) :1983 ibid (MK-III; 140MWt; Upgraded irradi. core) :2004 Main Control Room Overview of Main Cooling Bldg. Rotating Plug Air Blower Role of Joyo To demonstrate the basic FBR technology To conduct irradiation of fuel and materials To validate innovative technologies for the development of future FR Apply to Monju JSFR

Safety of Joyo in case of a tsunami and blackout Joyo is located at 38 meters above sea level. The heat is released into air in the secondary loop finally. Decay heat can be removed by a natural circulation of sodium. Natural circulation 3 Location of Joyo Air 38m ~ Ocean Approx. 300m

Master Schedule of Joyo JFY 2007 2008 2009 2010 2011 2012 2013 2014 4 MK-III 6 cycle 15 th Periodical Inspection Failure of the test subassembly disconnection In-vessel Visual Inspection Planning of UCS Replacement Work Manufacturing of New UCS and device for replacement UCS Replacement MARICO-2* Transfer pot MARICO-2* Retrieval Lifting-up test of MARICO-2* Manufacturing of MARICO-2* Retrieval Device Design of MARICO-2* Retrieval Device

5 2. Current Status of Monju

Main specifications and progress of Monju 6

Overview of System Start-up Test (SST) 7

Withdrawal of In-Vessel Transfer Machine (IVTM) 8 Auxiliary Handling Machine Gripper assembly Opening rod Closing rod 2010 Aug.26 Nov.16 Dec.16 : Investigation and analyses on the IVTM drop : Outside observation on the area around guide tube connection : Planning of withdrawing IVTM with fuel throat sleeve drop IVTM Fuel throat sleeve Connecting part of the guide tube Rotating rack Control rod drive mechanism Shield plug Fuel handling machine 2011 May.24 Jun.24 Aug.29 Nov.11 : Start of withdrawal work : End of withdrawing IVTM with fuel throat sleeve : Restoration work at the upper part of the reactor : Completion of repair work of upper part of the reactor Core

Restoration situation of IVTM(Aug.29~Nov.11 2011) 9

10 Emergency safety countermeasures against Tsunami

Enhancement of safety countermeasures 11

Operation conditions in Station Black-Out (SBO) Reactor Building Containment Vessel» The main pumps of the primary and secondary main cooling systems are inoperable.» The blowers of AC are also inoperable and AC power supply is stopped in a big earthquake. Primary Main Circulation Pump Primary Sodium Intermediate Heat Exchanger N2 Gas Pump Shutdown Secondary Main Circulation Pump Secondary Sodium Air Cooler Air Cooler Outlet Stop Valve (Opened) Steam Generator Inlet Stop Valve (Closed) Air Cooler Blower Shutdown» The SG inlet stop valves are closed, and the AC outlet stop valves are opened just after the reactor scrum.» The pony motors are still operating by the emergency DGs. DG» However, SBO occurred by a huge Tsunami. seawater 12 Fuel Control Rod Guard Vessel Reactor Vessel

Cooling characteristics of primary and secondary heat transport system» Natural circulations of sodium in the primary and the auxiliary cooling systems were generated and removed the decay heat safely into the atmosphere. 13 Temperature (ºC) (a) Primary Heat Transport System 550 160 Natural circulation 500 450 400 RV outlet Forced circulation 度(350 )300 Pony motor 250 RV inlet restarted 200 Flow rate 150 0 1 2 3 4 5 6 7 地震発生津波来襲時間 ( 日 ) ディーゼル発電機 1 台復旧 Earthquake~SBO Time (day) 140 120 100 100 流量(80 % )温 80 60 40 20 0 0 Flow rate (%) Temperature (ºC) (b) Secondary Heat Transport System 550 500 450 400 160 Forced circulation Natural circulation 140 120 度()350 AC inlet 300 250 AC outlet Pony motor restarted 200 Flow rate 150 0 1 2 3 4 5 6 7 時間 ( 日 ) 0 1 2 3 4 5 6 7 地震発生 津波来襲 Earthquake~SBO Time (day) ディーゼル発電機 1 台復旧 100 100 流量(80 % )温 80 60 40 20 0 0 Flow rate (%)

14 Fuel handling and storage system» Spent fuels are transferred from the reactor to the Ex-Vessel Fuel Storage Tank (EVST), and then they are cleaned by water and transferred to the Spent Fuel Pool (SFP) after the decay heat reduces to lower enough level.» The evaluation of the cooling capability of EVST is much more important than that of SFP in Monju.

15 EVST and Fuel transfer pot

Temperature ( ºC ) Temperaruer (ºC) 350 300 250 200 150 Cooling characteristics of EVST» The upper part of sodium temperature in the tank reduces gradually from the maximum temperature of approximately 260ºC» The maximum temperature was approximately 320ºC in the case of three loops natural circulation without power supply. Earthquake~SBO Upper region (A) Lower region (B) Flow Rate (A) Solid line : Without power supply (3 loop NC) 10 Dashed line : Power supply at 8.hours after SBO 100 0 0 50 100 150 200 250 300 Time (h) ( hr ) Tmperature and flow in EVST [EVST] (B) 100 100 90 90 80 70 60 50 40 30 20 Flow Rate (kg/s) Flow(kg/sec) 16

Temperature and water surface change in SFP 壁 Fuel transfer 燃料移送機レール machine s rail SF キャスク cleaning 洗浄ピット system 使用済燃料 SF キャスク詰 canning ピット system Fuel 貯蔵ラック rack Wall 壁 Fuel can Air Temperature ( ) 80 70 60 50 40 70ºC Water temp. Room temp. 110 days 30 0 20 40 60 80 100 120 Time (day) 14 12 Humidity 100% 70% 40% 0% 17 Fuel SA Water» The water temperature became constant value of approximately 70ºC.» It takes more than 3 months before the top of the can appeared in the gas region. Water height (m) 10 8 6 4 Top of fuel cans 2 110 days 0 0 20 40 60 80 100 120 Time (day)

Evaluation for Severe Accident 18» Stress tests are being conducted for the following 7 issues based on the instruction by NISA dated July 22, 2011; (1) Earthquake, (2) Tsunami, (3) Combination of Earthquake and Tsunami, (4) SBO, (5) LUHS (Loss of Ultimate Heat Sink), (6) Combination of SBO and LUHS, and (7) Accident management.» These evaluations should be conducted on the damage or failure of the equipment or facilities with deterministic and realistic methods, and cliff-edges should be identified, which lead to a significant fuel damage.» Effectiveness of the countermeasures should be also investigated from the viewpoint of the defense-in-depth.

19 3. Fast Reactor Cycle Technology Development (FaCT Project) JSFR (Japan Sodium-cooled Fast Reactor) Design Study and R&D Progress

1977 *2 Joyo Experimental Steps to Commercialization of Fast Reactor in Japan *1: study performed *2: initial criticality attained -->Monju resumed in May, 2010 1994 *2 Monju Prototype 1990s *1 DFBR Design for Demonstration FaCT Project Confirmation of FR Basic Technologies Verification of Safe and Stable Operation Power :50MWt 100MWt 140MWt (Mk-III Core) Temperature :435ºC 500ºC 500ºC JSFR Original plan (under review) - 2025-2050 Demonstration / Commercialization Innovative Technology for Economics and Reliability Design Study of Demonstration Reactor Development of Element Technologies Power : 1,600MWt / 660MWe Temperature : 550ºC Demonstration of Reliable Operation Establishment of Sodium Handling Power :714MWt / 280MWe Temperature : 529ºC System Development as Electricity Generation 20

Framework of Promoting the FaCT Project 21 Atomic Energy Commission (AEC) Ministry of Economy, Trade and Industry (METI) Ministry of Education, Culture, Sports, Science and Technology (MEXT) JAEA Core Engineering Company (MFBR/MHI) Electric Utilities Manufacturers Universities, Research Organizations, etc.

Secondary pump Japan Sodium-cooled Fast Reactor (JSFR) SG Integrated pump-ihx Reactor Vessel Reactor Core Items Electricity output Thermal output Configuration Specifications 1,500 MWe 3,730 MWt Loop Number of loops 2 Primary sodium outlet temperature 550 degree C Reactor vessel material 316 FR stainless steel Piping material Mod. 9Cr-1Mo steel Plant efficiency Approx. 42% Fuel type Burn-up (ave.) for core fuel TRU-MOX Approx. 150GWd/t Breeding ratio Break even (1.03) ~ 1.2 Cycle length 22 26 months or less, 4 batches

Output of FaCT Phase-I (JFY2006-2010) R&D results on innovative technologies and design studies for commercial FR cycle plants Evaluation results of each innovative technology applicability to the commercial FR cycle plants Evaluation results of the degree of achievement toward the development targets for the commercial plants to confirm the direction of R&D plans toward the next stage 23

Evaluation Results of Innovative Technologies for Reactor System 9 of 10 technologies are suitable for installation to the demo./commercial reactors. ODS steel will be further evaluated on manufacturing with stable quality. Plant constituent parts Key technologies Safety SASS, re-criticality free core Core and Fuel High burn-up fuel with ODS cladding material Reactor System Compact reactor system Two-loop cooling system of large diameter piping made of Mod. 9Cr-1Mo steel Cooling System Integrated IHX/Pump component Highly Reliable SG with double-walled straight tube DHRS Natural convection DHRS BOP Simplified fuel handling system CV made of steel-plate-reinforced concrete (SCCV) Reactor Building Advanced seismic isolation system for SFR : adoptable, : further R&D needed for judgment, No: not adoptable 24 24

New Framework for Nuclear Energy Policy Status of Energy Policy Making Innovative Strategy for Energy and the Environment New Basic Energy Plan 25 Nation-wide discussion on desirable energy mix Interim Compilation (Nuclear fuel cycle options, FRs) Interim Compilation (Nuclear fuel cycle costs) Alternatives for innovative strategy for energy and the environment Cost review committee report Alternatives for the bestmix of energy sources Basic principle on the best-mix of energy sources AEC New nuclear policyplanning council National Policy Council (Direct to the Prime Minister) Energy and Environment Council METI Advisory Committee for Natural Resources and Energy

Situation of National Policy Making and FaCT Project On July 19, 2011, JAEC decided to continue the FR cycle technology development program in the limited range of activities to contribute to international standardization (ex. safety criteria) and to maintain the technology base level until the determination of new nuclear energy policy. On Sept. 27, 2011, JAEC restarted the deliberation process for newframework for Nuclear Energy Policy. - The process was suspended after the Fukushima NPS accidents. -Major issues: Safety, Cost, Nuclear Power and Fuel Cycle Options, Waste Management, International Perspectives, R&D planning, etc. -The process has been carried out to determine the new Framework with the relationship to new governmental energy/environmental policy making. On Dec. 21, 2011, Energy and Environment Council complied Basic guideline toward Presentation of Alternatives regarding the Strategy for Energy and the Environment. In the FaCT project, focus has been on further improvement on safety of next generation SFRs based on lessons learned from the Fukushima NPS accidents. 26

Safety Goals for the Gen-IV Systems and Defence-in-Depth Levels GIF Goals Levels of DiD Plant state SR-1: Operational Safety and Reliability SR-2: Low likelihood and degree of CDA SR-3: Elimination of need for offsite emergency response (in Design) Level-1: Prevention of abnormal operation and failures Level-2: Control of abnormal operation and detection of failures Level-3: Control of accidents within the design basis Level-4: Control of severe plant conditions, including prevention of accident progression and mitigation of severe accidents IAEA SSR 2/1(Revised NS-R-1) Normal operation Anticipated operational occurrence(aoo) Design basis accidents (DBA) Design extension conditions(dec) -including significant core degradation - Level-5: Mitigation of radiological consequences of significant releases of radioactive materials corresponds to offsite emergency response - 27

Reflection of Lessons Learned from Fukushima NPS Accidents (1/2) Because of the wide area earthquake as the design basis level and the following Tsunami over the design basis level, multi-units in Fukushima area lost all AC power supplies in long-term and resulted in the SA. Based on the DiD concept, it is necessary to prevent the significant radioactive material release, even under the extreme external events exceeding the DBA. The condition corresponds to the DEC in DiD level-4. For the SFR, the bleed and feed type accident management (AM) is not easy due to the sodium chemical reactivity. ==> Enhancements of appropriate provisions for prevention and mitigation of the SA in DiD level-4 are keys to achieve the high level safety in next generation SFR. 28

Reflection of Lessons Learned from Fukushima NPS Accidents (2/2) In the Japan government report to the IAEA, there are 28 key points in 5 categories as lessons learned from the accident. 10 out of 28 key points are able to be picked up as related issues for the reflection to the SFR safety design. Category 1: Strengthen preventive measures against a severe accident Strengthen measures against earthquakes and tsunamis Ensuring the water tightness of essential equipment facilities Ensure power supplies Ensure robust cooling functions of reactors and PCVs Ensure robust cooling functions of spent fuel pools Consideration of NPS arrangement in basic designs Category 2: Enhancement of response measures against severe accidents Enhancement of measures to prevent hydrogen explosions Enhancement of the radiation exposure management system at the time of the accident Enhancement of instrumentation to identify the status of the reactors and PCVs Category 3: Enhancement of nuclear emergency responses Category 4: Reinforcement of safety infrastructure Ensuring the independence and diversity of safety systems Category 5: Thoroughly instill a safety culture 29

30 Safety Measures in DEC For the next generation SFR, built-in measures against CDA is necessary to shutdown system, coolant system and/or containment system by effectively utilization of passive mechanisms.

Experiments for Severe Accident Measures Concept of the Experiments; Safety design policy for severe accident measures Measures for In-Vessel-Retention (IVR) have priority. For IVR, measures against LOHRS and ATWS should be reinforced. More attention to LOHRS (LOHS, LORL) should be paid after the Fukushima NPS accidents. Candidates of measures against LOHRS Alternative cooling system must be installed. External vessel cooling and internal vessel cooling systems are important candidates. Phenomena to be investigated for the measures Heat transfer and thermo-hydraulics in reactor vessel, from external vessel, and from steam generator Local heat removal characteristics from the damaged core 31

Material Test Reactor JMTR High Temperature Gas Reactor HTTR AtheNa Facility for SA experiments FBR Safety Facilities Sodium Thermal- Hydraulics Facility Experimental Fast Reactor JOYO AtheNa Oarai R&D Center Sodium Tech. Facility Thermal-Hydraulics Facility View of AtheNa facility 32 Construction period: 2009.11-2012.1 Dimension: 130 m x 62 m x 55 m Total floor area: 11,000m 2 Electric supply : 7,000kVA Emergency generator: 1,250kVA Cranes : 120 & 100ton Sodium inventory : 260 ton 46m 66m 18m 55m 100t crane 120t crane ( ) ( ) S o d iu m L a b o ra to ry A b o u t 3,4 4 0 0 m 2 Sodium Tank Electric supply S o d iu m L a b o ra to ry Steam systems Sodium heater room Sodium Heater Sodium Tanks Cross section Steam systems Emergency generator 62m Electric supply room (with emergency generator : 1,250kVA) Electric supply Entrance Control Room[2F] Layout of AtheNa facility Control room

33 Appendix

Reflection of Lessons Learned from Fukushima NPS Accidents Lessons in Category 1: Strengthen preventive measures against a severe accident (1) Strengthen measures against earthquakes and tsunamis (8) Ensuring the water tightness of essential equipment facilities -For the External hazards -Due consideration of loss of all AC power supplies following the extreme external hazards -Seismic events may be accompanied by subsequent events -Provision of safety functions due to common cause failure by the external hazards (2) Ensure power supplies -For the Emergency power supply -Diversity to the extent practicable and redundancy for suppressing common cause failure including external events (3) Ensure robust cooling functions of reactors and PCVs -For the Decay heat removal -Decay heat removal systems for reactor cooling even under loss of all AC power supply -Utilization of passive heat removal capability for DEC -Diversity of ultimate heat sinks for decay heat removal (4) Ensure robust cooling functions of spent fuel pools (7) Consideration of NPS arrangement in basic designs -For the Fuel storage systems -Heat removal & status monitoring even under loss of all AC power supplies -Effect of flooding water contained in storage pool during severe accident 34

Reflection of Lessons Learned from Fukushima NPS Accidents Lessons in Category 2: Enhancement of response measures against severe accidents (9) Enhancement of measures to prevent hydrogen explosions -For the Control of containment conditions -Prevention/Mitigation of the sodium fire and sodium-concrete reaction, and Due consideration of the challenges on the integrity of containment (12) Enhancement of the radiation exposure management system at the time of the accident (14) Enhancement of instrumentation to identify the status of the reactors and PCVs -For the Means of monitoring -Adequate monitoring for radiation, coolant level, pressure etc. in DEC 35 Lessons in Category 4: Reinforcement of safety infrastructure (26) Ensuring the independence and diversity of safety systems -For the Decay heat removal -Diversity to the extent practicable and redundancy for suppressing common cause failure including external events -For the Ultimate heat sink -Diversity of the ultimate heat sinks for the decay heat transfer

General safety research works for enhancement of SA measures 36 DHX Cooling DHX DHR System (Dipped/Penetrated Heat Exchanger in Upper Plenum) Flow path in inter-wrapper region by Dipped DHX Flow path in subassemblies and inter-wrapper regions via Penetration-type DHX Ex-RV Cooling Ex-RV DHR System GV Cooling System CV Cooling System Flow path in inter-wrapper region by Ex-RV cooling Flow path in RV-GV Gap region by Ex-RV cooling Flow path in lower plenum by Ex-RV cooling Convection heat transfer in vessel DHX heat transfer Convection heat transfer in vessel and gap Heat transfer in cooling tube Radiation Thermal conduction Points for heat removal experiments for SA evaluation