APPENDIX B Construction Surface Water Management Plan PLANT CITY, FLORIDA SYDNEY ROAD RECLAIMED WATER PROJECT INVITATION TO BID ITB NO.

Similar documents
Erosion & Sedimentation Control Policy

Construction Best Management Practices Handbook BEST MANAGEMENT PRACTICES

Understanding Stormwater Pollution Prevention Plans (SWPPPs) (SWPPPS)

Town of Essex, Vermont January, 2017 Standard Specifications For Construction CHAPTER 3 EROSION AND SEDIMENT CONTROL

SITE DESIGN ENGINEER'S STATEMENT:

901 - TEMPORARY EROSION AND POLLUTION CONTROL SECTION 901 TEMPORARY EROSION AND POLLUTION CONTROL

NEW CASTLE CONSERVATION DISTRICT. through. (Name of Municipality) PLAN REVIEW APPLICATION DRAINAGE, STORMWATER MANAGEMENT, EROSION & SEDIMENT CONTROL

SECTION EROSION AND SEDIMENTATION CONTROLS

901 STORMWATER POLLUTION MANAGEMENT SECTION 901 STORMWATER POLLUTION MANAGEMENT

General Permit No.: OHR Page 53 of 146

Boise City Public Works General Drainage Plan Review Requirements Checklist

Town of Fortville Utility Street Standards

Review of State and Federal Stormwater Regulations November 2007

LOUISIANA URBAN STORMWATER COALITION. EXECUTING A SWPPP DURING CONSTRUCTION Presented by: Diane T. Baum

STORMWATER RUNOFF AND WATER QUALITY IMPACT REVIEW

C. This project shall be designed to meet LEED Silver design criteria. Construction activity pollution prevention is a mandatory requirement.

Block or Log forms of PAM and PAM blends are manufactured for specific use in drainage waterways to remove suspended particulates from runoff.

C. Foundation stabilization for pipe and utility structures.

EROSION & SEDIMENT CONTROL/STORMWATER CERTIFICATION: (Rev ) SP1 G180

SUBSURFACE INFILTRATION SYSTEM DESCRIPTION. Alternative Names: Sump, Drywell, Infiltration Trench, Infiltration Galleries, Leach Fields

STATE OF MINNESOTA MINNESOTA POLLUTION CONTROL AGENCY FINDINGS OF FACT

11 Ways to Avoid Storm Water Fines. No Exceptions!

STORMWATER MANAGEMENT PROGRAM. Table of Contents

Storm Drain Inlet Protection for Construction Sites (1060)

E. STORMWATER MANAGEMENT

SECTION UNCLASSIFIED EXCAVATION AND GRADING

PART 1 GENERAL REQUIREMENTS

UMD Storm Water Program Construction Requirements. Greg Archer, MBA Environmental Compliance Specialist

SECTION IV. PIPELINE EXCAVATION AND BACKFILL

JEFFERSON COUNTY STORM WATER MANAGEMENT


WELCOME TO THE CONSTRUCTION STORMWATER PERMIT WEBINAR

STORMWATER POLLUTION PREVENTION PLAN (SWP3)

Section SNOW DISPOSAL SITE DESIGN CRITERIA

FIRM NAME DESIGNER: CHECKER: DATE: FPID #: DESCRIPTION: COUNTY: DRAINAGE DESIGN CHECKLIST. Designers Initials. Checkers Initials.

SECTION TRENCHING & BACKFILLING

The Good, The Bad, and The Ugly

Elements of the Storm Water Management Plan. Storm Water Pollution Prevention Plan (SWPPP)

CITY STANDARD DETAILS FOR CITY OF JACKSONVILLE FLORIDA DEPARTMENT OF PUBLIC WORKS

Richland County Department of Public Works Engineering (Land Development) Division

SOUTH FLORIDA WATER MANAGEMENT DISTRICT. Question 13: Wetlands

SECTION WATER TREATMENT RESIDUAL REMOVAL, DISPOSAL, AND LAGOON CLEANING

10:00 AM, Wednesday, April 8, 2015

Erosion and Sediment Control Plan for a Timber Harvesting Operation

COON CREEK WATERSHED DISTRICT PERMIT REVIEW. Spring Lake Park Schools Westwood Middle School st Avenue NE, Spring Lake Park, MN 55432

Texas Department of Transportation Book 2 - Technical Provisions. IH 35E Managed Lanes Project. Attachment 4-3

TEMPORARY SEDIMENT TRAP CODE

Ingham County Drain Commissioner Patrick E. Lindemann 707 BUHL AVENUE P. O. BOX 220 MASON MI PH. (517) FAX (517)

REQUEST FOR CONSTRUCTION BIDS May 23, 2017

Tree Protection & Preservation

Streamlines V2, n2 (May 1997) A Newsletter for North Carolina Water Supply Watershed Administrators

Builder s enviro guide

CITY UTILITIES DESIGN STANDARDS MANUAL

Outline of Presentation. Inspecting Construction Site BMPs. Inspector. Back to Basics. Erosion Control. Erosion Control

SECTION 3 DRAINAGE. 3-1 General. 3-2 Drainage Ordinances and Legal Requirements

STANDARD TECHNICAL SPECIFICATIONS

CITY OF MIDDLETOWN, OHIO EROSION AND SEDIMENT CONTROL RULES & REGULATIONS

I. General Information. A. Project Team & Contacts: Role Company Name Phone City of Johnson City Jeff Owner Water & Sewer Harmon, PE Department

SACHSE EROSION CONTROL GUIDELINES

BMP 6.4.4: Infiltration Trench

The Village of Wellington NPDES Guidance/Reference Document

A. Exemptions from the Geotechnical/Geological Engineering Report submittal requirements are:

Module 4 Regulatory requirements for Land Disturbing Activities

Erosion Control for Home Builders

CITY OF ASTORIA PUBLIC WORKS ENGINEERING DIVISION ENGINEERING DESIGN STANDARDS FOR IN-FILL DEVELOPMENT

SECTION 17.1 STORMWATER MANAGEMENT AND EROSION CONTROL

EROSION AND SEDIMENT CONTROL PLAN (ESCP) FOR PROJECT TITLE

Design Specifications & Requirements Manual

SMART GYPSUM STACK MANAGEMENT FROM CONCEPT TO REALITY

1. All underground utilities under railroad tracks shall be encased in a larger pipe or conduit called the casing pipe.

SECTION 820 PUMP STATION DEMOLITION AND SITE RESTORATION

POLLUTION PREVENTION AFTER CONSTRUCTION

Standards for Soil Erosion and Sediment Control in New Jersey May 2012 STANDARD FOR GRASSED WATERWAYS. Definition. Purpose

NPDES/SDS Stormwater Permit Program for Construction Activity Inspection Report Corrective Actions. ( ) - ext. ( ) - ext. Owner Name Telephone Fax

STATE OF MINNESOTA MINNESOTA POLLUTION CONTROL AGENCY

Questions & Responses RFP No Design-Build Services, Twin Brooks Golf Course Renovations

Straw Bale Barrier. - Along the face and at grade breaks of exposed and erodible slopes to shorten slope length and spread runoff as sheet flow

CITY OF FARGO SPECIFICATIONS EROSION AND SEDIMENT CONTROL

Gainesville Technical Center 5399 Wellington Branch Drive Gainesville VA Phone (703)

HIGHLANDS COUNTY BOARD OF COUNTY COMMISSIONERS Tuesday, February 20, :30 PM 600 S. Commerce Ave. Sebring, FL AGENDA

CHAPTER 8 EROSION AND SEDIMENT CONTROL PLAN REQUIREMENTS

The Clean Water Act: Phase I

PINELLAS COUNTY SURFACE WATER UTILITY ADJUSTMENTS AND MITIGATION CREDITS POLICY

STATE OF FLORIDA EROSION AND SEDIMENT CONTROL DESIGNER AND REVIEWER MANUAL

Roscommon County Soil Erosion and Sedimentation Control (SESC) Program Guide

Stormwater Drainage Criteria Manual. City Of Clearwater Engineering Department Effective July 1, 2015

ASH MANAGEMENT PLAN. U.S. Environmental Protection Agency Region 4, Atlanta, GA. Mr. Joe Alfano, Remedial Project Manager

UTILITIES COMMISSION CITY OF NEW SMYRNA BEACH, FLORIDA 200 CANAL STREET P.O. BOX 100 NEW SMYRNA BEACH, FL

Utility and Sanitary Sewer Permitting & Design. Gibson-Thomas Engineering Co., Inc. Consulting Engineers

Environmental Guideline on Stone crushing plant set up temporarily for the purpose of a project by a public department

Section GRASSING

Storm Drain Inlet Protection

Straw Bale Barrier. Parallel to a roadway to keep sediment off paved areas

INSTRUCTIONS FOR SUBMITTING A COMMERCIAL SEWAGE DISPOSAL PERMIT APPLICATION

Installation and Maintenance of Erosion Control BMPs

UNDERSTANDING THE LAW. In Pennsylvania, both state and federal law govern water pollution caused by stormwater. We briefly examine both.

PERVIOUS PAVEMENT. Alternative Names: Permeable Pavement, Porous Concrete, Porous Pavers

Extended Detention Basin Maintenance Plan for [[== Insert Project Name ==]]

U.S. ARMY CORPS OF ENGINEERS. Little Rock District

Item Name Description Unit of Measure Mobilization Per WSDOT Lump Sum

Transcription:

APPENDIX B Construction Surface Water Management Plan PLANT CITY, FLORIDA SYDNEY ROAD RECLAIMED WATER PROJECT INVITATION TO BID ITB NO. 11-91360-001 ADVERTISED: November 5, 2010 MANDATORY PRE-BID MEETING: November 29, 2010 at 2:00 P.M. BID DUE DATE: December 10, 2010 at 2:00 P.M. PREPARED BY: Jones Edmunds & Associates, Inc. 324 South Hyde Park Avenue, Suite 250 Tampa, FL 33606 For the City of Plant City, Florida 4-0

CITY OF PLANT CITY, FLORIDA CITY OFFICIALS 2010 Daniel D. Raulerson, Mayor William D. Dodson, Vice Mayor/City Commissioner Rick A. Lott, City Commissioner Michael S. Sparkman, City Commissioner Mary Yvette Thomas Mathis, City Commissioner Gregory S. Horwedel...City Manager Kerri J. Miller..City Clerk Kenneth W. Buchman City Attorney 4-1

CONSTRUCTION SURFACE WATER MANAGEMENT PLAN SYDNEY ROAD RECLAIMED WATER PROJECT CITY OF PLANT CITY Note: The information provided is descriptive of the project and provides necessary and required information as outlined in the Stormwater Pollution Prevention Plan as described in SWFWMD and FDEP NPDES documents. All specific details for controlling surface water discharge including meeting specific time schedules are included in the accompanying technical specifications and will be the responsibility of the selected contractor for the City of Plant City. All required Generic Permits will be applied for and obtained by the contractor prior to any construction. Prepared By: Tak Kai Pang, P.E. # 66736 Jones, Edmunds & Associates, Inc. Date: Approved By: G.D. Willie Nabong, P.E., Public Works Director City of Plant City Date: 1.0 SITE DESCRIPTION a. Nature of Construction Activity: The project involves the construction of approximately 19,000 feet of 2-inch to 24-inch diameter reclaimed water transmission main, connection of reclaimed water service to 4 private customers, several crossings by jack and bore methods under culverts and roadways, and area restoration, all within Plant City Rights-of-Way and utility easements. The work will include furnishing and installing the new pipes, valves, fittings, connections, crossings, excavation, backfilling, compacting, testing, re-paving, disposal, restoration and maintenance of traffic in accordance with the project plans, City of Plant City specifications, complete and ready to use. The project is partially funded by the Florida Department of Environmental Protection (FDEP) and the Southwest Florida Water Management Department.(SWFWMD). 1

b. Major Soil Disturbing Activities. Excavation for trenching for utility work. c. Area Estimates: TOTAL PROJECT AREA: TOTAL DISTURBED IMPERVIOUS AREA: 23.0 +/- acres 11.0 +/- acres d. Runoff Data: Pre-construction: C = 0.30 through 0.95 During construction: C = 0.30 through 0.95 Post construction: C = 0.30 through 0.95 The soil in this project area is mainly Myakka fine sand with other soil varieties such as Pomello, Zolfo and Basinger sands. A geotechnical report was prepared for this project. e. Site Map: A USGS map is included for reference at the end of this document. More detailed views can be made with the construction plans. Drainage Patterns: Existing drainage characteristics within the project involve surface water sheet flow, ditch flow & pipe flow. The proposed design will not alter existing drainage patterns. Approximate Slopes: Slopes of drainage areas vary. Typical street slopes vary from flat to 1% and the grassy area slopes vary from 1% to 10%. Areas of Soil Disturbance: Areas of soil disturbance are within the Rights-of-Way of the existing streets. Easements have been obtained within the Walden Lake golf course and connection of the reclaimed water distribution mains to existing golf course ponds will be performed. Soil disturbance will be within the easements. Areas that may not be disturbed: No areas outside of the limits of construction shall be disturbed. Location of Controls: See Section 2.0 Controls 2

Areas to be Stabilized: All disturbed areas are to be re-paved, sodded or seeded to match existing conditions. Surface Waters (including wetlands): Erosion control measures to protect upland ditches and apparent wetlands and receiving waters are shown in Section 2.0 Controls. Discharge Points to Surface Water: No new stormwater discharge points are being developed in this project. All existing discharge points such as inlets and canals are being protected by erosion and sediment controls as described in Section 2.0 controls. Discharge of reclaimed water into two golf course ponds will be monitored and controlled by level-control discharge monitoring stations. A set amount of reclaimed water per day will be discharged as described in a permit application to the Florida Department of Environmental Regulation. Control will be by SCADA, a meter and totalizer and electrically-actuated valve, plus level control from a transducer measuring the pond level. Discharge to other waters of the state at the pond control weir structures will be measured also by the level control and discharge flow calculated using standard weir formulas. 2.0 CONTROLS a. Erosion and Sediment Controls Stabilization Practices: All disturbed grass or open areas are to be sodded or seeded and mulched. All stabilization practices shall be performed as soon as practical at locations where construction activities have temporarily or permanently ceased. Structural Practices: All structural practices shall be placed and/or constructed prior to construction activities that either directly or indirectly disturb stabilized areas. Locations of Baled Hay Ditch Blocks: See typical detail in the plans for placement of hay bales in accordance with current FDOT and City of Plant City practices. Locations of Baled Hay around Inlets: All proposed inlets and existing inlets within the construction limits shall be protected with baled hay. Location of Staked Silt Fence: Staked Silt Fence shall be placed along the R/W lines or at the toe of all ditch slopes. Floating turbidity barriers will be installed on open surface waters 3

b. Storm Water Management Surface water will be collected in existing swales and inlets and directed accordingly to existing outfalls. c. Other Controls Waste Disposal: The Contractor will provide litter control and collection within the project boundaries during construction activities. All fertilizer, or other chemical containers shall be disposed of by the Contractor according to EPA's standard practices as detailed by the manufacturer. No solid construction materials shall be discharged to wetlands. Off-site Vehicle Tracking: Loaded haul trucks shall be covered with tarpaulin. Excess dirt on the road shall be removed daily. Areas within the limits of construction shall be dampened with water as required for dust control. State or Local Regulations; The Contractor will adhere to all state and local regulations. Application of Fertilizers and Pesticides: Fertilizer and soil sterilizers will be used on this project in accordance with FDOT Specifications for Road and Bridge Construction, Section 982, in accordance with project specifications and with coordination with the Project Engineer. Toxic Substances: Toxic substances shall be disposed of by the Contractor according to the EPA's standard practices. Hazardous Materials: The Contractor shall not bring any hazardous materials onto the project. Should the Contractor require such for performing the contracted work, the Contractor shall request, in writing, written permission from the Project Engineer. The Contractor shall provide a copy to Plant City Utilities Operations Division at FAX (813) 757-9192. The Contractor shall provide Plant City with a copy of the Material Safety Data Sheet (MSDS) for each hazardous material proposed for use on the project. The Project Engineer shall coordinate with Plant City prior to issuing written approval to the Contractor. Because State law does not treat petroleum products that are properly containerized and intended for equipment use on the project as a hazardous material, such products do not need a MSDS submittal. Any known or suspected hazardous material found on the project by the Contractor shall be immediately reported to the Project Engineer, who shall direct the Contractor to protect the area of known or suspected contamination from further access. The Project Engineer is to notify Plant City (SEE ABOVE) of the discovery. 4

The City will arrange for investigation, identification, and remediation (removal) of the hazardous material. The Contractor shall not return to the area of contamination until approval is provided by the Project Engineer; Plant City will advise the Project Engineer. 3.0 MAINTENANCE The Contractor will be responsible for maintenance and repairs of erosion and sediment control devices, and removal of erosion and sediment control devices after the Notice of Termination. Maintenance and repair required for the control and abatement of erosion and water pollution shall be included in the Lump Sum bid for Sitework. The following practices will be used to maintain erosion and sediment controls: All measures will be maintained in good working order. If a repair is necessary, it will be initiated within 24 hours of report. All pollution controls shall be maintained at all times. Built up sediment will be removed from staked silt fence and staked turbidity barriers when it has reached one-third the height of the fence or barrier. Hay bales shall be replaced when they have served their usefulness so as not to block or impede storm flow or drainage. 4.0 INSPECTION Pollution control measures shall be inspected daily. Written documentation of inspections shall be written within 24 hours of a rain event of 0.50 inches or greater, or at a minimum of every seven calendar days. 5.0 NON-STORMWATER DISCHARGES Dewatering, if necessary, will be discharged into temporary settling areas, areas of stabilized swales on site, prior to discharge into United States waters. The Contractor will provide Plant City with an erosion control plan that will include spill reporting and response. If contaminated soil or groundwater is encountered, contact the Project Engineer. See Technical Specification 02240, Dewatering, for additional information. 5