Case Study Casing Path Well An Effective Method to Deal with Cascading Water

Similar documents
INVESTIGATION RESULTS

Handbook of Ground Water Development

SECTION GRAVEL PACKED WATER WELL

Montana Ground-Water Assessment Statewide Monitoring Well Network

Montana Ground-Water Assessment Statewide Monitoring Well Network

NGWA s Water Well Construction Standard: ANSI/NGWA 01-14

SPECIFICATIONS - DETAILED PROVISIONS Section Water Well Drilling, Casing & Testing TABLE OF CONTENTS

SPECIFICATIONS - DETAILED PROVISIONS Section Water Well Drilling, Casting and Gravel Installation, Development, and Testing C O N T E N T S

2016 ANNUAL ICR AND TRR WELL FIELD REPORT ICR WATER USERS ASSOCIATION

Cost of Municipal and Industrial Wells in Illinois,

REQUEST FOR BIDS WELL DRILLING & TESTING SERVICES I-77 EXIT 1 WATER SYSTEM PROJECT DESCRIPTION

(this page left intentionally blank)

P Temporary piezometer. MW Piezometer to remain in place. P Temporary piezometer

Monitoring Well Installation Report

Read Only Copy Not For Distribution. Chapter 17. Private Potable Water Supply Systems 17.1 GENERAL REGULATIONS 17.2 QUANTITY OF WATER REQUIRED

Environmental Management Chapter ALABAMA DEPARTMENT OF ENVIRONMENTAL MANAGEMENT WATER DIVISION - WATER SUPPLY PROGRAM ADMINISTRATIVE CODE

screens TM A Weatherford Company MUNI-PAK DESIGN TECHNOLOGY

SHEET METAL ROOF TEST REPORT

Mr. Michael Malone CPS Energy 145 Navarro Street San Antonio, Texas Project No

Water Well Decommissioning Guidelines

Tennessee Underground Injection Control Program Overview

Daytona Beach Pier Building Renovation Jun 2010

STANDARD SPECIFICATIONS SECTION JACKED CASING

SECTION2 Drainage Control for Surface Mines. Some Technical Aspects of Open Pit Mine Dewatering

INIZIATIVE INDUSTRIALI

Virginia Walsh, PhD, P.G. Ed Rectenwald, P.G. February 25, 2016

Desalination Concentrate Disposal Using Injection Wells: Technical Challenges

3.0 DESIGN CRITERIA FOR SANITARY SEWER FACILITIES

Wellhead Protection General Guidelines for New Private Domestic Wells

Rehabilitation of the Coral Gables Wastewater Collection System

PipeLife Jet Stream, Inc. Post Office Box 190 Siloam Springs, AR O F

SPECIAL CONDITIONS FOR PIPE JACKING (PJ) October, 2006

MEMORANDUM. The general findings of the assessment are as follows:

Determination of Design Infiltration Rates for the Sizing of Infiltration based Green Infrastructure Facilities

Monitoring Well Construction

Effect of the Underlying Groundwater System on the Rate of Infiltration of Stormwater Infiltration Structures.

NORTHWESTERN UNIVERSITY PROJECT NAME JOB # ISSUED: 03/29/2017

TRENCHLESS CONSTRUCTION (BORING, JACKING, AND TUNNELING)

Design Guideline for Gravity Systems in Soil Type 1. January 2009

MASTERSPEC TECHNICAL SPECIFICATIONS DIVISION 22 PLUMBING

NOTE ON WELL SITING AT CORNER OF CASTLE VALLEY DRIVE AND SHAFER LANE FOR TOWN OF CASTLE VALLEY, GRAND COUNTY, UTAH

STORMWATER MANAGEMENT. 158 Attachment 2. Borough of Perkasie

CHAPTER 6 COLLECTION SYSTEM HYDRAULIC MODEL

Contact the Jurisdictional Engineer for materials allowed by each jurisdiction.

Hilmar Cheese Company, Hilmar, Merced County, California. On behalf of Hilmar Cheese Company (HCC), Jacobson James & Associates, Inc.

INDEX FOR SPECIFICATIONS FOR JACKING CULVERTS THROUGH EMBANKMENTS SCOPE... 2

GROUNDWATER General Facts and Concepts

Air Lift Pumps (Grit Pump) ST-027

FIBER REINFORCED COMPOSITES FOR ADVANCED SEISMIC PERFORMANCE OF WATER SUPPLIES

Module 2. The Science of Surface and Ground Water. Version 2 CE IIT, Kharagpur

MWH STANDARD OPERATING PROCEDURES SOP-1 DRILLING METHODS

Purpose. Utilize groundwater modeling software to forecast the pumping drawdown in a regional aquifer for public drinking water supply

Executive Summary. ES.1 Background

William E. Ackland and Herman Schymiczek, HerSchy Environmental, Inc.

A Design Review of Waterproofing Codes

DESIGNING COMMERCIAL SUB-SLAB DEPRESSURIZATION SYSTEMS

W ater T alk. Field Corrosion Testing using Coupons

Wastewater Capital Projects Management Standard Construction Specification

CONCRETE PIPE JOINTS, YOUR BEST CHOICE

PVC Fittings & Laterals for Solid-Wall PVC Sewer Pipe

Numerical Groundwater Model for the Kaweah Delta Water Conservation District

EES 1001 Lab 9 Groundwater

SUBCHAPTER 2C - WELL CONSTRUCTION STANDARDS SECTION CRITERIA AND STANDARDS APPLICABLE TO WATER-SUPPLY AND CERTAIN OTHER TYPE WELLS

1. All underground utilities under railroad tracks shall be encased in a larger pipe or conduit called the casing pipe.

Installation Practice InnerSeal

Analysis of Vertical Flow During Ambient and Pumped Conditions in Four Monitoring Wells at the Pantex Plant, Carson County, Texas, July September 2008

Aggregate Optimization. Quality Assurance Workshop February Justin Bryan. Frank Bryan Inc. Bryan Materials Group

7. Completing the Well s Structure

Houston Community College 3200 Main Parking Garage November 15, 2010 Houston Community College

Minimum Guidelines for the Design and Use of Underpins When Performing Foundation Stabilization and/or Supplementation UP-08

PHASE I ERNEST MINE COMPLEX. The objective of the project was to develop an economically feasible, safe

WELL RECORD INSTRUCTIONS (Unconventional Operators only)

Florida Method of Test for NONREPETITIVE STATIC PLATE LOAD TEST OF SOILS AND FLEXIBLE PAVEMENT COMPONENTS

SECTION C1 DUCTILE IRON PIPE AND FITTINGS GENERAL

CONSTRUCTION RULES TABLE OF CONTENTS

INSTRUCTIONS AND GUIDELINES

***************************************************************************************************************

Enviro Voraxial Technology

The Effects of Debris on the Flow Rates of Roof Drains and Scuppers

SOURCES OF WATER SUPPLY GROUND WATER HYDRAULICS

HYDRO GEO CHEM, INC. PNEUMATIC TESTING AND RECOMMENDED CHANGES AT THE SUNSHINE CANYON LANDFILL SYLMAR, CALIFORNIA. Environmental Science & Technology

TAMDID PIPES GRP MANHOLE BROCHURE

13.Well Records, Documentation, Reporting & Tagging

Hydrology. Jürg M. Matter Lamont-Doherty Earth Observatory, The Earth Institute at Columbia University. May 9, 2008

GEOTECHNICAL INVESTIGATION MDACC GUHN ROAD FLOOD MITIGATION PROJECT 5610 GUHN ROAD HOUSTON, TEXAS REPORT NO

In-Situ Containment and Treatment of a Free Phase Hydrocarbon Plume beneath Plant Infrastructure

Attachment D-1: Civil/Structural Scope of Work

DRAINS AND CLEANOUTS. 1. Division 7 - Thermal and Moisture Protection Piping (Plumbing).

Ivins City Standard Specifications for Design and Construction Part 2 Engineering and Design Standards

Sampling of Aggregates

PAUL ZICK, PE NORTH SHORE CONSTRUCTORS JV

APPENDIX E SOIL VAPOR PROBE AND PIEZOMETER INSTALLATION AND MONITORING PROCEDURES Central Los Angeles High School#11 and Vista Hermosa Park

GUIDANCE MEMO NO : GUIDANCE CRITERIA FOR THE SEPARATION OF WATER MAINS AND NON-POTABLE PIPELINES

Pumps, Turbines, and Pipe Networks. Ch 11 Young

CONCRETE SEGMENTAL RETAINING WALL SYSTEM

Chapter 2: Foundation

SPECIFICATION : BORING AND JACKING

READ ONLY. Adopting Agency BSC SFM. Adopt Entire Chapter Adopt Entire Chapter as amended (amended sections listed below)

Estimating the Seasonal High Water Table: A Mix of Art & Science

Transcription:

Roscoe Moss Company Technical Memorandum 004-5 Case Study Casing Path Well An Effective Method to Deal with Cascading Water Executive Summary Air entrainment can be a serious problem with the potential to seriously affect a well s production capacity and the efficiency of its pumping equipment. In a typical air entrainment scenario, water enters the well from an aquifer and cascades downward when the pumping water level is below the top of the well screen. The cascading water entrains air during its freefall and causes the pump to cavitate as the mixture of air and water passes the pump impeller. Cascading water and entrained air can be controlled by using the casing path well design. This unique approach has been shown to be very effective in many areas within the Southwest. Background In the 1980 s well owners and operators in California s San Joaquin Valley began to notice that many water wells were losing production and also pumping water with entrained air. At that time (as now), it was not uncommon to pump water from shallow, unconfined aquifers and deep, confined aquifers in the same well. During that period, as demand increased for agricultural water in the Valley there was a marked decline in ground water recharge caused by reduced rainfall. These man-made and hydrologic conditions directly resulted in the lowering of ground water levels in many areas of the Valley. As static water levels declined in the Valley, pumping water levels in many wells were lowered below the top of the well screens. Consequently, as water entered the wells it would cascade downward and in doing so, air became entrained. Entrained Air Entrained air occurs in a well when the pumping level is lowered such that it produces a significant difference between the water level in the well and the water level in the adjacent aquifer. When this occurs, a seepage face is created between the saturated aquifer(s) exposed to the air space between the screened section(s) of the well. As the water enters the well it cascades, i.e., falls, downward to the pumping level. As it does so, air is entrained in the water. Then, when the well is pumped, the entrained air can cause the pump to cavitate and the discharge water with air. Casing Path Well Design A casing path well is designed to allow for concurrent production from a shallow aquifer and depth aquifer. Figure 1 is a typical casing path well design showing its key components, which consist of: 1. An upper exterior casing/screen segment that is installed within the upper aquifer zone; 2. A short reducer connected to the upper segment; 3. A lower casing/screen segment that is installed within the lower aquifer zone; 4. An interior casing sized to accommodate the pump bowls; and

5. Upper and lower seals between inner and outer casings. Figure 1 Typical Casing Path Well Design In the example shown above, the 22-inch diameter upper casing/screen is attached to a reducer that provides the transition piece between the 22-inch casing and 16-inch casing below it. The reducer is installed below the upper aquifer and also below the deepest anticipated setting for the pump. Both are vitally important considerations in the final design. The diameter of the inner casing should be from 4 to 6 inches smaller than the inside diameter of the outer casing to avoid stacking water in the chamber and to maximize the 2

efficiency of the well. If water is unable to flow freely from the chamber into the well, it will begin to accumulate and stack in the chamber; if this occurs, there will be a noticeable loss of production capacity. Figure 1 shows that the bottom 20 feet of the inner casing has a number of 5 x10 portals which allow water to flow from the chamber to the inner casing. The base of the inner liner is fitted with a hard rubber perimeter band that seats in the reducer and seals the lower end of the annular chamber. A similar upper seal is installed at ground level to complete the closure of the annular chamber. The annular space between the borehole wall and casing/screen is completed in a conventional manner. That is, it is filled with select gravel that is appropriately graded for the aquifers. The slot size of the well screens is then selected to retain the desired fraction of the gravel pack. A cement fill to ground level is recommended to provide sanitary protection and to preclude air from entering the upper casing through the screen. Theory of the Casing Path Well Figure 2 shows a laboratory setup that helps to explain how water flows from the upper aquifer into the well. Figure 2 Simulated Flow Path of the Casing Path Well 3

From the aquifer (A), water flows through gravel pack and passes through the exterior casing via the wells screen and finally into the annular space (represented above by the chamber). Note that the chamber is sealed, as would be the annular space. The sealed chamber is under a partial vacuum. When water flows from the aquifer (A) into the inner chamber, the water level (B) in the chamber appears at an elevation higher than it should be by elevation differences alone. This is shown as apparent head loss. If one were to insert a tube (open to the atmosphere) into the chamber, the water level would be measured at the pumping level in the well (C). A unique feature of the casing path well design is the flow of water from the upper aquifer into the inner chamber. The partial vacuum created in the annular chamber provides suction that draws water from the aquifer into the well. If the partial vacuum is disrupted by opening the chamber to atmospheric pressure, the water level in the chamber will stabilize at the pumping level in the well. Design Approach The design approach for a casing path well differs little from that of a conventional well. In general, the basic steps are: 1. Identify the depth intervals of the upper and lower aquifers, and the depth of the confining zone above the lower aquifer. These parameters are used to define the settings of the upper screen, lower screen and reducer, respectively. 2. Estimate the anticipated well yield and maximum pump setting. 3. Select the appropriate diameter of the inner casing to accommodate the pump bowls. 4. Determine the wall thickness, strength requirements, and steel type for the casing and screen to meet the proposed design and site conditions. 5. Select the gravel pack gradation for the aquifer materials. 6. Select the slot opening for the well screen to retain the gravel. Construction Phase The drilling and construction methods a casing path well are essential those that apply to a conventional well. Similarly, final design decisions are generally made in the field with information obtained during the drilling of the borehole. A carefully prepared lithologic log and a suite of geophysical logs are needed to determine the thickness and depth of the upper and lower aquifers and confining zone(s). Samples collected during drilling should be analyzed to determine the gradation of the aquifer materials. The sieve results are used to finalize the gravel pack design and to select the slot size for the well screen. Well casing and screen are installed in a conventional manner. That is, the exterior casing and screen (with reducer seating seal) are lowered into the borehole and set into place. After this is completed, the gravel pack and cement seal are placed via a construction tremie pipe. With those tasks completed, the next step is development of the well. It is important to note that the inner liner would still not have been installed. Initial development of the well is conducted by mechanical methods, e.g., swabbing, bailing, and airlifting. This phase of development is followed by development pumping and backwashing with the test pump. When development pumping is completed, the well can be test pumped. However, some owners prefer to conduct the pumping test with the liner in 4

place. If that is to be done, then the test pump has to be removed after development pumping. The contractor would then install the liner, seal the chamber, and conduct the pumping test. The second option makes it possible to measure the vacuum pressure and pumping rate throughout the test. These data would be useful to have for future reference. Case Study The City of Fresno has installed several casing path wells. Well No. 133 was pump tested in 1997 and provided some interesting results from the short-duration pumping test that was performed. Figure 3 shows the changes in vacuum pressure, production rate and water levels that were measured. The test results show the correlative relationship between these three parameters. The City reported that the wells have a history of good performance and have been shown to be effective at controlling entrained air in its wells. Summary City of Fresno Well No. 133 Pump Test 7/18/97 The results of the pumping tests for the casing path well showed that 155 160 References 165 Brown and Caldwell, personal communication, 2004. Water level (ft bgs) 170 175 180 185 pump on 1500 gpm with vacuum (14 in. Hg) vacuum open (11.5 in. Hg) 2nd vacuum tube opened vacuum open (4 in. Hg) vacuum closed vacuum closed (13 in. Hg) 190 195 0 0:07 0:10 0:14 0:17 0:25 0:35 0:37 0:52 Time since test began (mins) water level vac. comp w.l. Summary Casing path wells have been successfully designed and constructed in various hydrogeologic environments throughout the Southwestern United States. This design has been shown to provide a viable approach to control entrained air in municipal, agricultural and industrial high-capacity water wells. The construction methods used for casing path wells present no unique or major challenges. Furthermore, the wells are installed using presently available technology and equipment that are standard to the water development industry. Water purveyors that currently operate casing path wells have reported that these wells have been shown to be effective, efficient and highly productive facilities. 5

References Handbook of Ground Water Development, 1990. Roscoe Moss Company. A Report on Casing Path Wells, 1985. Dennis E. Williams, Ph.D. City of Fresno, 2004. Personal communication. 6