DRAFT FOR PUBLIC REVIEW

Similar documents
2. TECHNICAL DESCRIPTION OF THE PROJECT

ENVIRONMENTAL IMPACT ASSESSMENT PROCESS AND WASTE MANAGEMENT LICENSE APPLICATION PROPOSED EXTENSION OF ASH DAMS AT HENDRINA POWER STATION, MPUMALANGA

8. ASSESSMENT OF THE BIOPHYSICAL ENVIRONMENT

Environmental Impact Report for the proposed establishment of a New Coal-Fired Power Station in the Lephalale Area, Limpopo Province

ENVIRONMENTAL IMPACT ASSESSMENT PROCESS PROPOSED CONCENTRATING SOLAR POWER (CSP) PLANT AND ASSOCIATED INFRASTRUCTURE IN THE NORTHERN CAPE AREA

DESCRIPTION OF THE GOURIKWA POWER STATION & TRANSMISSION INTEGRATION PROJECT CHAPTER 3

STRATEGIC CONTEXT FOR ENERGY PLANNING CHAPTER 2

ENVIRONMENTAL IMPACT ASSESSMENT EIA PHASE

APPENDIX 5 ENVIRONMENTAL IMPACT ASSESSMENT METHODOLOGY

TABLE OF CONTENTS. Title page Table of contents List of tables List of figures Non- technical summary

A proposed new gas-fired power station on the Wilton International site

Annesley Andalusite Mine: Section 24G Rectification Process. Consultation with community members 15 June 2017

Struma Lot 3.2 EIA Development, Working Document

AMDAL Procedure. Flowchart of Indonesian Environmental Clearance 1

RE: STAKEHOLDER INFORMATION DOCUMENT 1: RIETKOL MINING OPERATIONS

ANNEXE 2: THE TERMS OF REFERENCE FOR ESIA AND RAP. 1. Objectives. The aim of the study is to achieve the following objectives:

Majuba Underground Coal Gasification

PROPOSED VOLSPRUIT MINE, MOKOPANE DISTRICT, LIMPOPO PROVINCE. Background Information Document (BID) ESCIENCE ASSOCIATES (PTY) LTD.

Executive Summary 1. 1 Project Background 6

A Report for Solafrica. 14/12/16/3/3/3/203 Parabolic Trough

CMPDI. 4.6 Mine Closure Plan

CONTENTS 2. PROJECT DESCRIPTION NEED FOR THE PROJECT ABOUT THE PROPONENT SITE SELECTION OVERVIEW OF THE PROJECT 2 5

Advances in Dry Cooling Deployed at South African Power Stations

ENVIRONMENT ACT TERMS OF REFERENCE NOVA SCOTIA DEPARTMENT OF TRANSPORTATION AND PUBLIC WORKS. Beaver Bank Bypass

ESKOM S UNDERGROUND COAL GASIFICATION PROJECT. Eskom s Clean Coal Programme

Implementing the Mitigation Hierarchy

Introduction. They can help ensure that all key issues and elements have been considered; They help ensure that the review process is systematic; and

ENVIRONMENTAL IMPACT ASSESSMENT STATION AND ASSOCIATED INFRASTRUCTURE IN THE WITBANK AREA

Outline for. Protected Areas Management Planning

TECHNICAL INFORMATION ABOUT UNDERGROUND STORAGE RESERVOIRS FOR NATURAL GAS

Ukraine Sustainable Energy Lending Facility (USELF) Strategic Environmental Review (SER) Ecoline EA Centre

ENVIRONMENTAL AND SOCIAL IMPACT ASSESSMENT GUIDELINES FOR HYDROPOWER PROJECTS IN MYANMAR

Annex F Scoping Checklist

6 Risk assessment methodology

Appendix General Environmental Risk Analysis

18 Cumulative Impacts and Interaction of Effects

Coire Glas Pumped Storage Scheme

Draft Environmental Assessment Terminal B/C Redevelopment, Secure National Hall, and Related Improvements

GUIDE TO THE DEVELOPMENT OF A MINING AND RECLAMATION PLAN IN NEW BRUNSWICK

Information on the focal point for the Convention. Information on the point of contact for the Convention

Alinta Cogeneration (Wagerup) Pty Ltd Alinta Wagerup Units 1 2

Case Study : Underground Coal Gasification (UCG) Majuba Update. Mark van der Riet Corporate Consultant Eskom Holdings Ltd South Africa

Assessing Values in Natural Resource Decision-making

Cottonmount Landfill Stable Non Reactive (SNR) Asbestos Cell. Volume 2 NON TECHNICAL SUMMARY. December 2012 SLR Ref:

PUBLIC DISCLOSURE OF PHASE II ENVIRONMENTAL AND SOCIAL MANAGEMENT PROGRAMME. 2 Objective of the Phase II Environmental and Social Programme

Gold Standard Passport CONTENTS

Template for ToR for Transaction Advisory Services

STATE UNIVERSITY CONSTRUCTION FUND

Provincial Policy Statement 2014 Training Aid

2. Project Justification and Feasible Alternatives

A. OWENS 1 and J. BURKE 2

NOVEMBER 2016 REVISION 0. Prepared by: JG AFRIKA (PTY) LTD

Chartered Professional Engineer (Geotechnical) Body of Knowledge and Skills

SUSTAINABLE DEVELOPMENT, DISASTER-RISK REDUCTION AND GOVERNANACE: ASSESSING CLIMATE CHANGE ADAPTATION CHALLENGES FACING SOUTH AFRICA

OPERATION PHASE: ENVIRONMENTAL MANAGEMENT PROGRAMME

Annex 1: Project Tropicalia Sustainable Tourism, Dominican Republic

DEPARTMENT OF ENVIRONMENTAL PROTECTION Bureau of Water Quality Protection. Design Criteria - Wetlands Replacement/Monitoring

SABI Code of Practice for On-farm Irrigation Design

ABOUT US. Earth Link & Advanced Resources Development (ELARD)

Provincial Policy Statement 2014

A1 Australian and South Australian Government Guidelines 813. A2 South Australian Government Guidelines 871

CONSERVATION OF ENVIRONMENT ENACTMENT 1996 CONSERVATION OF ENVIRONMENT (PRESCRIBED ACTIVITIES) ORDER 1999

Environmental Impact Statement for the Slave Falls Tramway Conversion Project

Shell Quest Carbon Capture and Storage Project. Shell Canada Limited

GUIDELINE. environmental management of mining. GUIDELINE 11 - Terms of Reference and Preparation of an Environmental Impact. Statement.

TERMS OF REFERENCE FOR THE STELLENBOSCH PLANNING ADVISORY COMMITTEE

Nxuba Wind Farm NERSA PUBLIC HEARINGS. 10 September 2015

For PROPOSED IT PARK. By M/s.Balewadi Tech Park Pvt.Ltd. Submitted to State Environment Expert Appraisal Committee III, Maharashtra

THE EGGBOROUGH CCGT PROJECT STAGE 1 CONSULTATION: PROJECT INFORMATION DOCUMENT

The following potential environmental receptors and impacts form the basis of TRCA s review under Ontario Regulation 166/06 and the Fisheries Act:

Background Information Document and Invitation to Comment

Chapter 17 Cumulative Impacts

Hatch Wi-Fi Username: guest Password: qskm3123 Guest Name: NBBN Conference National Biodiversity & Business Indaba

DEPARTMENT OF WATER AFFAIRS. Submitted to: Department of Water and Sanitation Chamber of Mines of South Africa

No October 2012

FINAL ENVIRONMENTAL SCOPING REPORT (DEAT APPLICATION NO. 12/12/20/806)

Chapter 1 Introduction

INTEGRATED SAFEGUARDS DATA SHEET CONCEPT STAGE Report No.: AC3946. Date ISDS Prepared/Updated: 01/26/2009 I. BASIC INFORMATION. A. Basic Project Data

Recruitment and Appointment Policy Responsible Officer. Executive Director, Human Resources Approved by

GP 30/5/1/3/2/10242 MP

Environmental Management Plan (EMP)

Performance Standard 6 V2

Ottawa-Trussler Area Sewage Facility Class Environmental Assessment

Hydropower Sustainability Assessment Protocol Section IV Trail ESKOM. Palmiet/Drakensberg Pumped Storage Schemes. November 2009

Electricity Slide Index Slide 2: Generating Electricity Slide 3: SA Power Grid

Information Delivery Manual (IDM)

South African Mainstream Renewable Jeffreys Bay Pty Ltd

Stakeholder Engagement Plan Code Of Practice

SUNDANCE 7 January 2014

National Occupational Standards. for. Project Management

PROPOSED DEVELOPMENT OF A HOTEL AT THE CONFLUENCE OF THE TIMFENHENI AND CROCODILE RIVERS WITHIN THE KRUGER NATIONAL PARK

Electricity Safety (Electric Line Clearance) Regulations 2010

ENVIRONMENTAL IMPACT ASSESSMENT: FINAL SCOPING REPORT

KANMANTOO PUMPED HYDRO STEVE McCLARE IIIII CEO & MANAGING DIRECTOR PUMPED HYDRO ENERGY STORAGE CONFERENCE SYDNEY MARCH 2018

Summary of LAKE ONTARIO Policies. 1. Requiring SPC approval: LO SEW 3 LO FUEL 2

LESEDI ENVIRONMENTAL MANAGEMENT FRAMEWORK (EMF) PUBLIC MEETING 25 JANUARY 2006

Comprehensive Study Scoping Document. for Lower Mattagami Hydroelectric Complex Redevelopment CEAR Reference Number:

DRAFT ENVIRONMENTAL IMPACT ASSESSMENT REPORT FOR THE FOR BELA BELA FARMYARD ESTATE (PTY) LTD ON THE FARM NOODHULP 492 KR

Clifton Marsh Landfill Variation of planning permission 05/09/0376 & 06/09/0395 for the continuation of landfilling until Non Technical Summary

IAIAsa August 2014 Betty Mdala Department of Environmental Affairs

Transcription:

ENVIRONMENTAL SCOPING REPORT FOR THE PROPOSED COMBINED CYCLE GAS TURBINE (CCGT) POWER PLANT IN THE AMERSFOORT AREA, MPUMALANGA PROVINCE (DEAT REF 12/12/20/1074) DRAFT FOR PUBLIC REVIEW PROJECT OF ESKOM HOLDINGS LIMITED 28 FEBRUARY 2008

Amersfoort area, Mpumalanga Province DOCUMENT DESCRIPTION Client: Report name: Report type: Bohlweki Project number: Eskom Holdings Limited Environmental Scoping Report for the proposed Combined Cycle Gas Turbine (CCGT) power plant in the Amersfoort area, Mpumalanga Province Draft E02.JNB.000128 Compiled by: Author (s) Date / location Signature Prashika Reddy Reviewer Malcolm Roods Approval Document Control Sheet

EXECUTIVE SUMMARY 1. INTRODUCTION Eskom Holdings Limited (Eskom) has appointed Bohlweki Environmental (Pty) Ltd as independent environmental consultants to conduct the Environmental Impact Assessment (EIA) process for the proposed Combined Cycle Gas Turbine (CCGT) power plant in the Amersfoort area, in terms of the EIA regulations published in Government Notice R385 to R387 of 21 April 2006 - read with Section 24(5) and Section 44,of the National Environmental Management Act, 1998 (Act No 107 of 1998, NEMA )(as amended). Need and Justification of the Project Eskom has a mandate to satisfy potential customer and economic needs, which implies certain responsibilities. One of the most significant responsibilities is to find and maintain the balance between satisfying the needs of society and remaining within the capabilities of the environment. In order to achieve this, Eskom must continually re-assess its present infrastructure and take into account new developments to ensure that there is a continued supply of electricity, without significantly impacting on the environment. Eskom is the primary supplier of electricity in South Africa, providing approximately 95% of the electricity consumed. The decision to expand Eskom s electricity generation capacity was based on national policy and informed by on-going strategic planning undertaken by the national Department of Minerals and Energy (DME), the National Energy Regulator of South Africa (NERSA) and Eskom. Eskom applies an Integrated Strategic Electricity Planning (ISEP) process to identify long-term options regarding both the supply and demand sides of electricity provision in South Africa. The most recently approved ISEP (October 2005) identifies the need for increased peaking supply by about 2006/7 and base load by about 2010. Based on the above planning processes, and in order to meet the projected increase in the demand for electricity, various projects are underway and are at various stages of implementation. These include base load technologies such as coal fired plants, combined cycle gas turbines and conventional nuclear as well as peaking technologies such as pumped storage schemes and open cycle gas turbines. Eskom is committed to investigating and evaluating various options for the diversification of the energy mix over time (including renewable resources) and as part of an ongoing effort to assess the viability/feasibility of all supply-side options, a number of power generation technologies, not yet implemented in South Africa on a commercial basis, are being evaluated in terms of technical, socio-economic and environmental aspects. One such type of technology is Underground Coal Gasification (UCG), which has been successfully proven to be commercially viable, and Eskom plans to implement it as a fully commercially operating operation. In this current project, it is proposed that an Underground Coal Gasification- Combined Cycle Gas Turbine (UCG-CCGT) complex is constructed and operated. The current study only focused on the CCGT plant component of the complex. Executive Summary i 29/02/2007

1.2. Overview of the Proposed Project It is anticipated that the CCGT power plant will have approximately 2100 MW of installed capacity. The proposed project will consist of the following components: the CCGT power plant (comprising up to 6 units of approximately 350 MW each); a compressor plant; ignition gas plant, for unit start-up (using commercial propane); weather and communication mast of up to 60 meters in height and air quality monitoring station; high voltage yard; a gas pipeline from the adjacent gas cleaning plant to the CCGT; a water supply pipeline from the Rietpoort Balancing Dam (for construction and operational water supply); electricity supply for construction; a water treatment plant as well as ancillary works such as other associated infrastructure; access roads; sewage treatment plant; storage facility for hazardous materials; storage facility for waste; and borrow pits. The CCGT plant and associated infrastructure are required to be constructed on a site that is environmentally, economically and technical feasible. A Screening Study (Site selection) encompassing a sensitivity mapping exercise was undertaken by independent consultants in order to establish the best possible sites to evaluate during the Scoping Phase of the project. The purpose of such an exercise was to identify suitable areas within the wider study area that could accommodate the CCGT plant and to pro-actively identify sensitive areas that should ideally be avoided (see Chapter 5 Site Selection Summary). 2. DESCRIPTION OF ALTERNATIVES In terms of the Environmental Impact Assessment (EIA) Regulations, feasible alternatives must be considered within the Environmental Scoping Study. All identified, feasible alternatives should be evaluated in terms of social, biophysical, economic and technical factors. Site alternatives Based upon the Screening/Site selection study, a total of ten candidate sites were identified for the possible location of the CCGT power plant and associated infrastructure. Executive Summary ii 29/02/2007

These farms included: Site 1 (Portions 3 and 4 of the farm Roodekopjes 67 HS) Site 2 Site 2a (Portion 7 of the farm Bergvliet 65 HS; Portion 4 of the farm Rietpoort 83 HS; Werda 116 HS) Site 2b (Portions 3 and 4 of the farm Rietpoort 83 HS and Werda 116 HS) Site 3 (Portions 3 and 4 of the farm Rietpoort 83 HS) Site 4 (Portion 1 of the farm Rietpoort 83 HS and Portions 2, 6 and 7 of the farm Welgedacht 82 HS) Site 5 (Portions 4, 5 and 8 of the farm Welgedacht 82 HS) Site 6 (Portions 1, 3 and 7 of the farm Palmietspruit 68 HS; Portion 6 of the farm Strydkraal 53 HS; Portion 1 of the farm Roodekopjes 67 HS ) Site 7 Site 7a (Portions 1, 2, 6, 10 and 11 of the farm Witkoppies 81 HS) Site 7b (Portions 1, 5 and 6 of the farm Witkoppies 81 HS) Site 7c (Portions 4, 5, 8, 9, 12, 13 and 14 of the farm Witkoppies 81 HS) With further input from the technical team, four sites were eliminated as they were located in the area earmarked for future UCG operations/expansion. Six alternative sites were then selected as being potentially the most viable of all the candidate sites investigated. The following six (6) sites will, therefore, be assessed during this Scoping Study: Site 1 (Portions 1, 3 and 7 of the farm Palmietspruit 68 HS; Portion 6 of the farm Strydkraal 53 HS; Portion 1 of the farm Roodekopjes 67 HS ) Site 2 Site 2a (Portion 7 of the farm Bergvliet 65 HS; Portion 4 of the farm Rietpoort 83 HS; Werda 116 HS) Site 2b (Portions 3 and 4 of the farm Rietpoort 83 HS and Werda 116 HS) Site 3 Site 3a (Portions 1, 2, 6, 10 and 11 of the farm Witkoppies 81 HS) Site 3b (Portions 1, 5 and 6 of the farm Witkoppies 81 HS) Site 3c (Portions 4, 5, 8, 9, 12, 13 and 14 of the farm Witkoppies HS) Other alternatives Alternatives relating to the CCGT power plant layout, technology selection, pipeline corridors as well as access roads and construction village positioning will be further assessed during the EIA phase. Executive Summary iii 29/02/2007

3. APPROACH TO THE ENVIRONMENTAL SCOPING STUDY (ESS) AND PUBLIC PARTICIPATION PROCESS Environmental Scoping Study The ESS aims to provide a description of how the environment may be affected by the development of the proposed project. Desktop studies making use of existing information, and ground-truthing during site visits, were used to highlight and assist in the identification of potential impacts (biophysical, social and economic) associated with the proposed project. Additional issues for consideration have been extracted from feedback obtained from the public participation process, which commenced at the beginning of the Scoping phase, and will continue throughout the duration of the project. All issues identified during this phase of the study have been documented within this issues-based Environmental Scoping Report. Thus, this Environmental Scoping Report provides a record of all issues identified, and a preliminary evaluation of the significance of the issues in order to make recommendations regarding the project and further studies required to be undertaken within the EIA phase of the proposed project. The Scoping Study aims to address the following: description of the sites selected for the proposed CCGT power plant and associated infrastructure; identification of potential positive and negative environmental (biophysical and social) impacts, and an evaluation of their significance in terms of the project; optimisation of positive impacts to the benefit of the local environment and community; and undertaking of a fully inclusive public participation process to ensure that Interested and Affected Party (I&AP) issues and concerns are recorded and form part of the scoping process. As the proposed project includes a number of listed activities from Government Notices R386 and R387 of April 2006, a full Environmental Impact Assessment process is being undertaken in a two-phased approach: Phase 1: Environmental Scoping Study (ESS) Phase 2: Environmental Impact Assessment and Environmental Management Plan (EMP) A number of specialist studies were conducted in order to comprehensively identify both potential positive and negative environmental impacts (biophysical, social and economic) associated with the project. These studies are presented in Table 1 below. Executive Summary iv 29/02/2007

Table 1 Specialist studies conducted in the Environmental Scoping Study Specialist Study Organisation Hydrogeology and Hydrology SRK Consulting Fauna and Flora Bathusi Environmental Consulting Air Quality Bohlweki Environmental Noise Jongens Keet Associates Social Environment MasterQ Research Heritage National Cultural History Museum Visual aspects and aesthetics MetroGIS Risk Riscom Traffic SSI Engineers and Environmental Consultants Approach to Scoping Study in terms of Site Preference The evaluation and nomination of a potential site for the CCGT power plant involves an interdisciplinary approach. The approach undertaken has involved a wide range of specialist studies (hydrogeology, hydrology, biodiversity; air quality; noise; social; visual; heritage; risk and traffic) which examined a number of different issues. In order to evaluate sites and determine a preferred site/s, the studies need to be comparative and therefore a site rating matrix was developed. The site preference rating system is applied to each discipline, and the rating of each site was conducted according to the following system: 1 = not suitable for development (impact of very high significance - negative) 2 = not preferred (impact of high significance - negative) 3 = acceptable (impact of moderate significance - negative) 4 = preferred (impact of low or negligible significance - negative) 5 = ideal site for development, or positive impact One of the outcomes of each specialist study was to have a Site Preference Rating, how they evaluated each site varied from discipline to discipline and the description of their specific approaches are outlined in each specialist report (refer Chapters 8 and 9). The site preference results for each site from each specialist study were entered into a matrix and added together. The site with the highest value is then considered the most preferable. The standard matrix as described above, gives equal importance to each variable. Therefore, a weighted matrix was also used. In a weighted matrix each variable is given a different importance weighting. Input from the project team and all specialists was utilised for the allocation of weightings to the different variables. Each member of the The project team was asked to rank each variable according to their significance: 1 low significance 2 medium significance 3 high significance Executive Summary v 29/02/2007

Once the average weighting for each variable was obtained, it was multiplied by the Site Preference Rating (SPR) to give a weighted SPR for each variable. Table 2 (overleaf) was obtained after the above process was completed. Executive Summary vi 29/02/2007

Table 2 Environmental and social criteria matrix Unweighted Weighted Weighting Site 1 Site 2a Site 2b Site 3a Site 3b Site 3c Site 1 Site 2a Site 2b Site 3a Site 3b Site 3c Biophysical Criteria Hydrogeology 1.7 4 3 3 4 3 3 6.8 5.1 5.1 6.8 5.1 5.1 Hydrology 2 4 3 3 3 4 3 8 6 6 6 8 6 Flora 2 4 2 2 4 5 3 8 4 4 8 10 6 Fauna 2 3 1 1 3 5 3 6 2 2 6 10 6 Social Criteria Noise 1.8 3 2 2 3 3 3 5.4 3.6 3.6 5.4 5.4 5.4 Social 2.2 3 3 2 4 5 3 6.6 6.6 4.4 8.8 11 6.6 Visual 1.7 5 1 1 5 5 5 8.5 1.7 1.7 8.5 8.5 8.5 Heritage 1.2 3 3 3 3 3 3 3.6 3.6 3.6 3.6 3.6 3.6 Risk 2.3 3 3 3 3 3 3 6.9 6.9 6.9 6.9 6.9 6.9 Traffic 1.6 3 3 3 3 3 3 4.8 4.8 4.8 4.8 4.8 4.8 Total Score 35 24 23 35 39 32 64.6 44.3 42.1 64.8 73.3 58.9 Executive Summary vii 29/02/2007

Public Participation Process A public participation process has been undertaken as part of the Scoping process, and involved the consultation of individuals throughout the broader study area representing a range of sectors of society. To date, this consultation has included telephonic consultations, a Focus Group Meeting and documentation distributed via mail, background information documents and via the printed media. Issues and concerns raised during the Scoping process thus far have been recorded and captured within an Issues Trail (Appendix D). 4. CONCLUSIONS AND RECOMMENDATIONS Based on the specialist studies, no environmental fatal flaws have been identified as a result of the proposed project on any of the sites evaluated. However, a number of potentially significant environmental impacts have been identified that requires further in-depth study. Therefore, an EIA is to be undertaken in order to provide an assessment of these potential impacts and recommend appropriate mitigation measures, where required. In the consideration of the environmental, social and economic criteria along with the technical criteria, the nominated sites for further study within an environmental impact assessment would be: Sites 1 (Portions 1, 3 and 7 of the farm Palmietspruit 68 HS; Portion 6 of the farm Strydkraal 53 HS; Portion 1 of the farm Roodekopjes 67 HS); Site 3a (Portions 1, 2, 6, 10 and 11 of the farm Witkoppies 81 HS); and Site 3b (Portions 1, 5 and 6 of the farm Witkoppies 81 HS). Executive Summary viii

EXECUTIVE SUMMARY i 1. INTRODUCTION...1 1.1. Energy Policy Framework...1 1.1.1. White Paper on the Energy Policy of the Republic of South Africa 1998...1 1.1.2. 1.1.3. Integrated Energy Plan (IEP) 2003...2 National Integrated Resource Plan (NIRP) 2003/2004...2 1.1.4. Eskom Integrated Strategic Electricity Planning (ISEP) 2005...3 1.2. Overview of the Proposed Project...5 1.3. Environmental Legal Requirements...6 1.3.1. 1.3.2. The National Environmental Management Act...6 The Constitution of South Africa...9 1.3.3. Legal requirements in terms of other Acts...9 1.4. Environmental Study Requirements...10 2. TECHNICAL DESCRIPTION OF THE PROJECT...13 2.1. What is a Combined Cycle Gas Turbine (CCGT) Plant?...13 2.2. How does a Combined Cycle Gas Turbine (CCGT) work?...14 2.3. 2.4. Water and Cooling...17 Storage Tanks...19 2.5. Other Infrastructure...19 2.5.1. Access Roads...20 2.5.2. Construction Village...20 3. SCOPE OF ENVIRONMENTAL INVESTIGATIONS...21 3.1. Approach to Undertaking the Scoping Study...21 3.2. Authority Consultation...21 3.2.1. Consultation with Decision-making Authorities...21 3.2.2. Consultation with other Relevant Authorities...21 3.3. Application for Authorisation...22 3.4. Environmental Scoping Study...22 3.4.1. Specialist Studies...23 3.5. Overview of the Public Participation Process...23 3.5.1. Advertising...23 3.5.2. 3.5.3. Identification of Key Stakeholders and Interested and Affected...24 Briefing Paper...25 3.5.4. 3.5.5. Consultation and Public Involvement...25 Social Issues Trail...26 3.6. Review of the Draft Environmental Scoping Report and Plan of Study for EIA27 3.6.1. 3.6.2. Public Review of Draft Scoping Report and Plan of Study for EIA...27 Authority Review of Draft Environmental Scoping Report...27 3.7. Final Environmental Scoping Report...27 4. GENERAL DESCRIPTION OF THE STUDY AREA ENVIRONMENT...28 4.1. The Biophysical Environment...28 4.1.1. Locality...28 4.1.2. Climate and Rainfall...28 4.1.3. 4.1.4. Topography and Landscape...30 Geology...30 4.1.5. 4.1.6. Hydrogeology...31 Hydrology...32 4.1.7. Biodiversity...32 4.2. The Social Environment...33 4.2.1. Air Quality...33 4.2.2. Noise...35 4.2.3. Social...35 Table of Contents ix

4.2.4. Visual...36 4.2.5. Heritage...36 4.2.6. Risk...37 4.2.7. Traffic...38 5. SITE SELECTION SUMMARY...39 5.1. 5.2. Sensitivity Mapping and Selection of Sites...39 Sensitivity Indexes...43 5.3. Sensitivity Zoning...44 6. ALTERNATIVES...51 6.1. 6.2. Strategic Alternatives...51 The 'Do Nothing' Alternative...51 6.3. Site Alternatives...52 6.4. 6.5. Layout Alternatives...52 Technologies Alternatives...52 6.5.1. Cooling Technologies...52 6.5.2. Air Quality Abatement Technologies...54 6.6. Pipeline Alternatives...54 6.6.1. 6.6.2. Fuel Supply Pipeline...54 Water Supply Pipeline...54 6.7. Alignment of Access Roads...55 6.8. Construction Village...55 7. APPROACH TO SCOPING STUDY...56 7.1. Site Evaluation Field Studies...56 7.2. Specialist Studies...57 7.3. Rating Criteria...59 7.4. Assumptions and Limitations...60 8. ASSESSMENT OF THE BIOPHYSICAL ENVIRONMENT...61 8.1. Hydrogeology...61 8.1.1. Introduction...61 8.1.2. Methodology...61 8.1.3. Potential Impacts on Hydrology...63 8.1.4. 8.1.5. Site Preference Rating (SPR)...64 Conclusions...64 8.1.6. Recommendations...65 8.2. Hydrology...65 8.2.1. Introduction...65 8.2.2. 8.2.3. Methodology...66 Potential Impacts on Hydrology...67 8.2.4. Site Preference Rating (SPR)...67 8.2.5. 8.2.6. Conclusions...68 Recommendations...68 8.3. Flora...69 8.3.1. Introduction...69 8.3.2. Methodology...69 8.3.3. 8.3.4. Potential Impacts on Flora...71 Site Preference Rating...72 8.3.5. Conclusions and Recommendations...73 8.4. Fauna...73 8.4.1. Introduction...73 8.4.2. 8.4.3. Methodology...74 Potential Impacts on Fauna...76 8.4.4. Site Preference Rating...77 8.4.5. Conclusions and Recommendations...77 Table of Contents x

9. ASSESSMENT OF THE SOCIAL ENVIRONMENT...78 9.1. Air Quality...78 9.1.1. Introduction...78 9.1.2. 9.1.3. Methodology...78 Baseline Assessment...79 9.1.4. Potential Impacts on Air Quality...80 9.1.5. Conclusions and Recommendations...82 9.2. Noise...83 9.2.1. Introduction...83 9.2.2. Methodology...83 9.2.3. Potential Noise Impacts...87 9.2.4. 9.2.5. Site Preference Ranking...90 Conclusions...93 9.2.6. Recommendations...93 9.3. Social Impact Assessment...94 9.3.1. Introduction...94 9.3.2. Methodology...94 9.3.3. Potential Impacts on the Social Environment...97 9.3.4. Site Preference Rating...105 9.3.5. 9.3.6. Conclusions...106 Recommendations...106 9.4. Visual...112 9.4.1. 9.4.2. Introduction...112 Methodology...112 9.4.3. Potential Visual Impacts...113 9.4.4. Site Preference Ranking...116 9.4.5. Conclusions...119 9.4.6. Recommendations...120 9.5. Heritage...120 9.5.1. 9.5.2. Introduction...120 Methodology...121 9.5.3. Potential Impacts on Heritage...121 9.5.4. Site Preference Rating...122 9.5.5. Conclusions and Recommendations...122 9.6. Risk...123 9.6.1. 9.6.2. Site Preference Rating...123 Recommendations...123 9.7. Traffic...123 9.7.1. Site Preference Rating...124 9.7.2. Conclusions and Recommendations...124 10. CONCLUSIONS AND RECOMMENDATIONS...125 10.1. Potential Environmental Impacts...127 10.2. Rating Matrix...134 10.3. Recommendations...139 11. PLAN OF STUDY FOR ENVIRONMENTAL IMPACT ASSESSMENT...140 11.1. Approach to Undertaking the Environmental Impact Assessment Phase of the Project...140 11.1.1. Authority Consultation...140 11.1.2. Application for Authorisation...141 11.2. The Environmental Impact Assessment Process...141 11.2.1. Aims of the Environmental Impact Assessment Phase...141 11.3. 11.4. Detailed Specialist Studies to be undertaken as part of the EIA...141 Public Participation Process...152 11.4.1. Advertising...153 11.4.2. Identification of and Consultation with I&APs and Key Stakeholders...153 Table of Contents xi

11.4.3. I&AP Database...153 11.4.4. Consultation and Public Involvement...153 11.4.5. Social Issues Trail...154 11.5. 11.6. Compilation of the Environmental Impact Assessment Report...154 Review of the Environmental Impact Assessment Report...156 11.6.1. Public Review of the draft Environmental Impact Assessment Report..156 11.6.2. Authority Review of the Environmental Impact Assessment Report...157 11.7. Environmental Authorisation...157 11.8. Environmental Management Plan...157 11.9. Environmental Study Team...158 12. REFERENCES...160 Table of Contents xii

LIST OF FIGURES Figure 1.1 Figure 1.2 Hierarchy of policy and planning documents...1 Project funnel...4 Figure 1.3 Locality map...12 Figure 2.1 A typical 3-in-1 CCGT power plant configuration, in model form...13 Figure 2.2 Schematic of a process of that a gas turbine undergoes in order to produce electricity....14 Figure 2.3 Figure 2.4 Layout of UCG-CCGT plant...16 Showing a direct dry cooling system...18 Figure 2.5 Showing an indirect dry cooling system...19 Figure 4.1 Map indicating the Pixley ka Seme Local Municipality and surrounding municipalities...28 Figure 4.2 Average monthly maximum and minimum temperatures recorded in the Majuba area (Weather Services Station, 2007)...29 Figure 4.3 Monthly rainfall figures for Majuba area (Weather Services Station, 2007).29 Figure 4.4 The period wind rose and wind frequency distribution for data taken at the UCG Pilot Plant and for modelled data received from the South African Weather Services respectively....34 Figure 5.1 Environmental sensitivity index...43 Figure 5.2 Environmental Sensitivity Zones...45 Figure 5.3 Ideal/preferred areas for development...46 Figure 5.4 Alternative sites identified in the Screening Study for the proposed CCGT power plant...48 Figure 5.5 Alternative sites identified for assessment in the Scoping Study for the proposed CCGT power plant in the Amersfoort area...50 Figure 6.1 Figure 6.2 Showing a direct dry cooling system...53 Showing a typical indirect dry cooling system...54 Figure 9.1 Map indicating 4 main noise measurement sites...85 Figure 9.2 Social waypoints...96 Figure 9.3 Potential visibility of Site 1...114 Figure 9.4 Figure 9.5 Potential visibility of Site 2A (left) and Site 2A (right)...114 Potential visibility of Site 3A (left) and Site 3B (right)...115 Figure 9.6 Potential visibility of Site 3C...115 Figure 9.7 Figure 9.8 Location of Site 1 (north of Majuba Power Station)...116 Location of Site 2a and 2b (east of Majuba Power Station)...117 Figure 9.9 Location of Site 3a; 3b and 3c (south of Majuba Power Station)...118 Figure 10.1 Showing the six (6) candidate sites evaluated in the Scoping Study...126 Table of Contents xiii

LIST OF TABLES Table 4.1 Table 5.1 Specialist studies undertaken as part of the previous Scoping process...23 Lithostratigraphy of the study area...31 Table 6.1 Description of the various categories used in the sensitivity mapping...39 Table 8.1 Specialist studies and the components investigated during the Environmental Scoping Phase...57 Table 9.1 Hydrogeology percentage relating to site preference rating class...62 Table 9.2 Table 9.3 Potential nature of impacts on groundwater regime...63 Site selection comparison...64 Table 9.4 Table 9.5 Hydrology percentage relating to site preference rating class...66 Site selection comparison...67 Table 9.6 Floral score relating to site preference rating class...70 Table 9.7 Site preference ranking according to floristic sensitivity...72 Table 9.8 Faunal score relating to site preference rating class...75 Table 9.9 Site preference ranking according to faunal sensitivity...77 Table 10.1 Main locations for noise measurements...84 Table 10.2 Site Rating Comparison...92 Table 10.3 Potential Impacts on the Social Environment...98 Table 10.4 Site comparison...105 Table 10.5 Terms of Reference for studies to be carried out in the EIA Phase...107 Table 10.6 Comparative table of the proposed CCGT power plant alternatives...119 Table 10.7 Potential impact on heritage during the construction and operation phase 122 Table 10.8 Site Comparison...122 Table 10.9 Site Comparison...123 Table 10.10 Site Comparison...124 Table 11.1 Potentially significant issues associated with the proposed CCGT power plant, identified within the Environmental Scoping Study. The area of potential impact and recommendations for investigations to be undertaken within the EIA phase are also specified...128 Table 11.2 Environmental and social criteria matrix...135 Table 11.3 Technical criteria...137 Table 11.4 Environmental, social and technical criteria matrix...138 Table 12.1 Criteria for the classification of environmental impacts...155 Table 12.2 Key milestones of the programme for the EIA phase of the project...158 Table 12.3 Proposed specialist team and their areas of expertise...158 Table of Contents xiv

LIST OF APPENDICES APPENDIX A: APPENDIX B: APPENDIX C: APPENDIX D: APPENDIX E: APPENDIX F: APPENDIX G: APPENDIX H: APPENDIX I: APPENDIX J: APPENDIX K: Applicable Legislation Acceptance Letter - DEAT Advertisements and Proof of Placement of Site Notices Issues Trail and I&AP Database Background Information Document and Letters to I&APs Advertisements Availability of Draft Scoping Report and Letter to I&APS Minutes of Meeting Screening Report Individual Specialist Maps Screening Study Specialist Reports Biophysical Environment Specialist Reports Social Environment Table of Contents xv

GLOSSARY OF TERMS Alternatives: means different means of meeting the general purpose and requirements of the activity, which may include site or location alternatives; alternatives to the type of activity being undertaken; the design or layout of the activity; the technology to be used in the activity and the operational aspects of the activity. Ambient sound level or ambient noise: means the totally encompassing sound in a given situation at a given time, and usually composed of sound from many sources, both near and far. Note that ambient noise includes the noise from the noise source under investigation. The use of the word ambient should however always be clearly defined (compare with residual noise). Combined Cycle Gas Turbine (CCGT): In a combined cycle power plant or CCGT plant, a gas turbine generator generates electricity and the waste heat is used to make steam to generate additional electricity via a steam turbine; this last step enhances the efficiency of electricity generation. Cumulative impact: means the impact of an activity that in itself may not be significant but may become significant when added to the existing and potential impacts eventuating from similar or diverse activities or undertakings in the area. Direct dry cooling: In the direct system, steam from the last stage turbine blades is channelled directly into radiator-type heat exchangers adjacent to the turbine hall of the power station (there are no cooling towers.). The heat is conducted from the steam to the metal tubes of the exchanger. Air passing through the exchanger is supplied by a number of electrically driven fans. The air removes the heat, thus condensing the steam back into water which will be used once again to produce steam in the boiler. Do-nothing alternative: The do-nothing alternative is the option of not undertaking the proposed activity. Environmental impact assessment, in relation to an application to which scoping must be applied, means the process of collecting, organising, analysing, interpreting and communicating information that is relevant to the consideration of that application as defined in NEMA. Environmental Screening Study: An exercise to identify suitable areas within the study area that could accommodate the CCGT plant and to pro-actively identify sensitive areas that should ideally be avoided. Gas turbine: The gas turbine (also called a combustion turbine) is a rotary engine that extracts energy from a flow of combustion gas and is the first stage in the process of producing electricity through the CCGT plant. Glossary of Terms xvi

Indirect dry cooling: Indirect dry cooling systems have a condenser and turbine exhaust system as for wet systems, with the circulating water being passed through finned tubes in a natural draught cooling tower. Interested and affected party: any person, group of persons or organisation interested in or affected by an activity; and any organ of state that may have jurisdiction over any aspect of the activity. Outflow of labourers: Locals who secure employment with the contractors might also receive training, thereby enabling them to secure more permanent employment, which in turn might cause them to move out of the area and becoming part of the migrant labour force. Phase 1 Archaeological Survey: Walk through the entire footprint of the preferred site/s and document any/all heritage resources that exist on the site/s. Plan of study for environmental impact assessment: means a document which forms part of a scoping report and sets out how an environmental impact assessment must be conducted. Public participation process: means a process in which potential interested and affected parties are given an opportunity to comment on, or raise issues relevant to, specific matters. Red Data species: Species listed in terms of the International Union for Conservation of Nature and Natural Resources (IUCN) Red List of Threatened Species, and/or in terms of the South African Red Data List. In terms of the South African Red Data List, species are categorised as being extinct, endangered, vulnerable, rare, indeterminate, insufficiently known or not threatened. Site preference ranking: The approach involved a wide range of specialist studies examining a number of different issues. In order to evaluate sites and determine a preferred site/s, the studies needed to be comparative and therefore a site rating matrix was developed. The site preference rating system is applied to each discipline, and the rating of each site was conducted according to the following system: 1 = not suitable for development (impact of very high significance - negative); 2 = not preferred (impact of high significance - negative); 3 = acceptable (impact of moderate significance - negative); 4 = preferred (impact of low or negligible significance - negative) and 5 = ideal site for development, or positive impact. Underground coal gasification: UCG is a process carried out on unminable coal seams. These are coal seams that cannot be mined by using the conventional coal mining methods e.g. open cast or underground mining. UCG involves injecting steam and air (or oxygen) into a cavity created in an underground coal seam, to form a synthetic natural gas. Unweighted matrix: Each variable is given the same importance weighting. Vadose zone: The portion of Earth between the land surface and zone of saturation. It extends from the top of the ground surface to the water table. Glossary of Terms xvii

Vulnerable (vegetation): Vegetation types that have lost up to 20% of their original extent, which could result in some ecosystem function being altered. Weighted matrix: Each variable is given a different importance weighting. Glossary of Terms xviii

ABBREVIATIONS AND ACRONYMS CCGT Combined cycle gas turbine DEAT Department of Environmental Affairs and Tourism DME Department of Minerals and Energy DWAF Department of Water Affairs and Forestry EIA Environmental Impact Assessment EMP Environmental Management Plan ESS Environmental Scoping Study FGM Focus Group Meeting HRSG Heat recovery steam generator I&AP Interested and Affected Party IEP Integrated Energy Planning IEP Integrated Energy Planning ISEP Integrated Strategic Electricity Plan KSW Key Stakeholder Workshop MDALA Mpumalanga Department of Agriculture and Land Administration NEMA National Environmental Management Act (Act No 107 of 1998) NERSA National Energy Regulator of South Africa NGO Non-Governmental Organisation NHRA National Heritage Resources Act (Act No 25 of 1999) SAHRA South African Heritage Resources Agency SANRAL South African National Roads Agency Limited UCG Underground coal gasification Glossary of Terms xix