Northport Berth 3 design and construction monitoring

Similar documents
UNDERPINNING A CRANE FOUNDATION

USE OF DIPP PILES FOR A NEW SUP BRIDGE IN WEST MELBOURNE

Numerical Analysis of a Novel Piling Framed Retaining Wall System

Static Response of Reinforced Soil Retaining Walls with Modular Block Facing

Behaviour of Various Support Systems for Deep Excavations, Changi Airport Underground MRT Station

NPTEL Course GROUND IMPROVEMENT USING MICROPILES

DESIGN AND INSTALLATION OF THE SHORING AND DECKING FOR TTC YONGE STATION

Challenges in Design and Construction of Deep Excavation With Case Studies - KVMRT in KL Limestone

Downloaded from Downloaded from /1

Nonlinear Modeling of Dynamic Soil-Structure Interaction: A Practitioner s Viewpoint

SCG INTERNATIONAL TRINIDAD AND TOBAGO LIMITED COUVA CHILDREN S HOSPITAL

GeoEng2000 An International Conference on Geotechnical & Geological Engineering

Testing of ground anchorages for a deep excavation retaining system in Bucharest

BACKGROUND: SUBSURFACE CONDITIONS:

Better ZSOIL, Better Geotechnical Analysis

SPECIFICATION FOR REINFORCED SOIL WALL

Jet Grouting to Increase Lateral Resistance of Pile Group in Soft Clay

PIANC UK Seminar Design Developments and Specification for Steel. Duncan Nicholson Arup Fellow 9/3/17 ICE London

Comparison of geotechnic softwares - Geo FEM, Plaxis, Z-Soil

1.364 ADVANCED GEOTECHNICAL ENGINEERING HOMEWORK No. 5

Lecture Retaining Wall Week 12

Temporary Structures. Excavations and Excavation Supports

FEM ANALYSIS OF ANCHORED SHEET PILE QUAY WALL: A CASE STUDY ON THE FAILURE OF WQ-7 BERTH OF VISAKHAPATNAM PORT

Numerical Analysis for High-rise Building Foundation and Further Investigations on Piled Raft Design

Case study of deep excavation in existing underground structure of three-story basement and diaphragm wall

CANTILEVER RETAINING WALLS - KOPPERS ROUNDWOOD POSTS FOR WALL HEIGHTS 0.3m to 1.8m

Behaviour of rigid retaining wall with relief shelves with cohesive backfill

Prof. Dipl.-Ing. H. Quick Ingenieure und Geologen GmbH provides geotechnical engineering services e. g. for high-rise buildings in Germany and abroad.

Combined Pile Foundation System for a Residential Complex

Deformation Behaviour of a Retaining Wall for a Deep Basement Excavation with Semi-Top Down Method

Design Illustrations on the Use of Soil Nails to Upgrade Loose Fill Slopes

Modelling of a pile row in a 2D plane strain FE-analysis

BERTHS 57, 58 AND 59 CONTAINER WHARF AT THE PORT OF OAKLAND

Case Studies on Soil Nailed Retaining Systems for Deep Excavations

Case study on a deep excavation in Baku: Flame Towers project earth retaining system

1970 s and. Site Location Map. and shed transform the. Gateway Project.

VOL. 11, NO. 16, AUGUST 2016 ISSN ARPN Journal of Engineering and Applied Sciences

Application of Vibro Techniques for Infrastructure Projects in India

APPROXIMATE ANALYSIS OF PILED RAFT. Rameez Gahlot1, Roshni J John2

Marina Bay Sands Hotel Arch 631 Kayla Brittany Maria Michelle

GROUND IMPROVEMENT USING DYNAMIC REPLACEMENT FOR NCIG CET3 COAL STOCKYARD

Finite Element Study Using FE Code (PLAXIS) on the Geotechnical Behavior of Shell Footings

Design of Anchored-Strengthened Sheet Pile Wall: A Case Study

Seismic Design of a Slope Stabilization Work Using Piles and Tendons

OPEN CELL. (800) SWC 120. SWC Weld-on. Charts and Pictures courtesy of: 120 o

Influence of unloading soil modulus on horizontal deformation of diaphragm wall

Application of Stress-Wave Theory to Piles

16. Design of Pipeline Structures.

Design and development of a decline shaft through poorly consolidated Kalahari deposits at Ghaghoo Diamond Mine.

Estimation of existing tall buildings pile foundations bearing capacity under seismic and wind loads. T.Davitashvili 1,a, I.

APPENDIX A - SIZING OF BRIDGE AND SUPPORT SYSTEM

LARGE DIAMETER PIPE ROOF BOX EXCAVATION FOR PASSENGER LINKWAY TUNNEL

Numerical Analysis of Piling Framed Tie-Down Concrete Retaining Wall

EN Eurocode 7. Section 8 Anchorages Section 9 Retaining structures. Brian Simpson Arup Geotechnics

DEPTH EFFECTS AND VIBRATIONS ASSOCIATED WITH DYNAMIC COMPACTION CASE STUDY


Timber piles to mitigate liquefaction and lateral spreading, Aotea Quay Wellington

COVERING THE HIGHWAY E12 IN THE CENTRE OF HÄMEENLINNA INNOVATIVE USE OF FOAMED GLASS AS LIGHT WEIGHT MATERIAL OF APPROACH EMBANKMENT

GROUND IMPROVEMENT SITE INVESTIGATON

[Kouravand Bardpareh* et al., 5(6): July, 2016] ISSN: IC Value: 3.00 Impact Factor: 4.116

The Effect of Ultra Large Container Vessels on Cranes and Infrastructure

Ground Improvement Techniques: Dynamic Compaction Martin Larisch & Tim Pervan

ENGINEERING DIRECTIVE

Modelling of RC moment resisting frames with precast-prestressed flooring system

COMPARISON OF EC7 DESIGN APPROACHES FOR NUMERICAL ANALYSIS OF DEEP EXCAVATIONS

MARINE SPECIALTY CONTRACTORS GENERAL TRADE KNOWLEDGE EXAMINATION CONTENT INFORMATION FOR COMPUTER BASED TESTING Revised March 2012

PILE SETTLEMENT ZONES ABOVE AND AROUND TUNNELLING OPERATIONS

Influence of Orientation of Piles on Seismic Response of Pile Groups

AAPA Facilities and Engineering Seminar. Robert Tolsma PE, PPM, D.PE Division Manager Atkins North America San Diego, CA Oct 22, 2015

Sheet Pile Retaining Walls Design and Construction in a Brown Fields Environment

Minimum Guidelines for the Design and Use of Underpins When Performing Foundation Stabilization and/or Supplementation UP-08

Bond Strength of Hollow-Core Bar Micropiles

THE RION ANTIRION BRIDGE DESIGN AND CONSTRUCTION

Using EPS Buffers for Diaphragm Walls

Table of Contents. July

Design of Semi gravity Retaining Walls

CHAPTER 11: PRESTRESSED CONCRETE

Construction Planning, Equipment, and Methods PILES AND PILE-DRIVING EQUIPMENT

Renovation of Buildings using Steel Technologies (ROBUST)

Retaining Wall Design

The designer shall also submit additional information required by the University as described and underlined below.

Oweninny Wind Farm. Oweninny Environmental Impact Statement Appendix 5. Turbine Foundation Construction Method Statement

Bi-Directional Static Load Testing of Driven Piles

Fagà, Bianco, Bolognini, and Nascimbene 3rd fib International Congress

COMPARATIVE STUDY ON NORMAL AND SKEW BRIDGE OF PSC BOX GIRDER

3.5 Tier 1 Analysis Overview Seismic Shear Forces

Box Culverts. Designers and manufacturers of engineered box culvert solutions

Bulk Liquids Berth 2 (Sydney): A case study in pile vibration monitoring and management

FE Review Mechanics of Materials

4D grouting pressure model of a bored tunnel in 3D Tunnel

DIAPHRAGM WALLS, CUT-OFF WALLS AND SLURRY WALLS

Ground Movement Analysis of Pipe Roof Construction in Soft Clay

TEMPORARY EXCAVATION SUPPORT SYSTEM FOR A NEW RAILWAY BRIDGE AND HIGHWAY UNDERPASS IN PITTSBURGH

Single Piles and Pile Groups

Selection of Proprietary Shoring Equipment

SEAU 5 th Annual Education Conference 1. ASCE Concrete Provisions. Concrete Provisions. Concrete Strengths. Robert Pekelnicky, PE, SE

Evaluation the Effectiveness of Rapid Impact Compaction (RIC) as a Ground Improvement Technique

Monitoring a Drilled Shaft Retaining Wall in Expansive Clay: Long-Term Performance in Response to Moisture Fluctuations

Transcription:

Proc. 18 th NZGS Geotechnical Symposium on Soil-Structure Interaction. Ed. CY Chin, Auckland Lucy Coe, Nicola Ridgley, Do Van Toan Beca Infrastructure Limited, Auckland, NZ Keywords: retaining wall, deflections, port, sheet piles ABSTRACT Berth 3, an extension to Northport Ltd s Marsden Point wharf facility, comprises a twin sheet pile wall to provide support to the new wharf deck and retain the adjacent reclamation. The wall type was selected to enable construction to proceed by walking a crane over the constructed wall, negating the need to use a large floating or jack up barge. The wall structure comprises twin king piles and intermediate sheet piles, 12.5m apart tied with steel bars at two levels and reinforced concrete deck top. Design was undertaken using finite difference software FLAC to predict displacement, movement, shear and anchor loads during various stages of construction. Deflection monitoring of the wharf performance was undertaken with survey and inclinometers. This paper describes the FLAC modelling for design of the twin wall and compares monitoring results from the performance of the wall both during construction and one year following completion with predicted displacements. 1 INTRODUCTION The project comprised development of Berth 3 at Northport's wharf facility at Marsden Point. The site is located 30km south-east of Whangarei and is adjacent to the NZ Refining Company facilities. The General Cargo Wharf is Northport's principal operating wharf and prior to the recent extension was 390m long, primarily supporting log handling and woodchip exports but capable of container handling with large container cranes. This wharf and reclamation was designed and constructed in 2000 by Beca Infrastructure Ltd (Beca) and The Fletcher Construction Company Ltd (Fletcher) when Northport had to relocate from further up Whangarei Harbour. In 2005 Northport procured another design and build (D & B) contract with Fletcher who engaged Beca as designer to extend its berth operation by 180m and reclamation by 30,000m². Construction using the jack-up barge previously used for Berths 1 and 2 was not possible as the spuds were not long enough as the harbour had been dredged from around -7 mcd to -13 mcd during construction of Berths 1 and 2. The D & B team therefore developed a new design and construction methodology for the wharf extension comprising of twin sheet pile walls with two tie levels. The design methodology, construction and post construction monitoring are detailed in this paper. 2 STRUCTURAL FORM Design requirements included a design dredge depth of -16 mcd, a 180m long berth, an integral back wall to provide retaining support to the adjacent reclamation, surcharge loadings of 50kPa for general port and container operation, and provision for supporting a future container crane. The design adopted comprised twin HZ775A king piles located at 1.79m centres with intermediate AZ26 sections for the front wall and lighter AZ17 sections for the rear wall. The two walls are tied together using two levels of steel rods attached to each king pile. The upper ties are 52mm in diameter and positioned at -2m CD and the lower ties are 80mm diameter steel bars positioned at -10 mcd. The wharf deck is a reinforced concrete flat slab spanning between the two sheet pile walls, creating a third top tie between the two walls. Two rows of steel ladder 1

anchor strips 20m long are also attached to the rear sheet piles to reduce lateral deflection under load. The steel ladder anchor strips consisted of two steel reinforcing bars 230mm apart running perpendicular to the wharf with short lengths of reinforcing bars 300mm long at 300mm spacing over the end 15m connecting the two main bars. Figure 1 shows the typical wall cross-section. 3 SOIL PROFILE Figure 1: Berth 3 typical twin sheet pile wall cross-section Geological Map Sheet 2A Whangarei describes geology of the Marsden Point area as comprising Quaternary aged foredunes, sedimentary deposits of undifferentiated sands, silts and clays with some peaty areas. Basement rock greywacke and argillite exist at large depths in the area and have not been encountered in investigations at this site. A number of site investigations have been undertaken in the harbour for the proposed development. The soil profile encountered in boreholes below Berth 3 comprises interbedded layers of silty sand, sandy silt, shelly sand and silt clay layers. A very dense sand layer (SPT N >50 blows/300mm) was encountered at the western end of Berth 3. Investigations indicated soil strengths to be variable immediately above this layer ranging from stiff sand silt to very dense sand with SPT values varying between 11 and 50+ blows. The very dense sand layer thins towards the east, becoming non-existent at the eastern end of Berth 3. Initially two soil profiles, a stiff profile representing the western end and a less stiff profile representing the eastern end of the site, were modelled to determine the effect of and sensitivity to the founding materials. The less stiff model was found to be critical and therefore selected for detailed design analyses. Table 1: Soil Profile Depth (mcd) Layer Description -13 to -22 SILTY SAND/SANDY SILT Loose; non-plastic. -22 to -25 SANDY SILT Very stiff, slightly to non-plastic. -25 to 36 SILTY SAND Medium dense; non-plastic. -36+ SILT, some clay Very stiff to hard; moderately to highly plastic. 2

4 DESIGN ANALYSIS The sheet pile caisson structure was modelled using the numerical modelling software FLAC. FLAC incorporates both soil and structural elements, enabling the interaction effects between the sand internal fill, backfill, insitu material and the structural elements of the wharf structure to be modelled. FLAC was used to calculate bending moments and shear forces within the piles, axial loads within the tie and ladder elements, to predict the displacement of the sheet pile and expected movements within the sand fill. The soils were modelled using an inbuilt plasticity model with Mohr Coulomb strength parameters plus elastic stiffness parameters, input in terms of Bulk Modulus and Shear Modulus. All analyses were undertaken using effective stresses. All material above the toe of the structure was modelled as non-cohesive, with increasing stiffness over depth to take account of increased confining pressure. Soil stiffness is dependent on the effective confining stress and as such the soil stiffness (and interface stiffness) was increased to model the effect of the filling as construction proceeded. The stiffness profiles adopted for all stages are given in Table 2. Table 2: Design Soil Parameters Layer Density (kn/m3) Cohesion (kpa) Friction Angle (degrees) Elastic Modulus (MPa) (Prior to Filling) Elastic Modulus (MPa) (After Filling) Poisson s Ratio SAND FILL 17 0 30 N/A 50 to 80 0.3 (Internal) SAND FILL 17 0 30 N/A 17.5 to 0.3 (Reclamation Fill) 32.5 SILTY SAND/ 17 0 28 10 to 20 20 to 30 0.3 SANDY SILT SANDY SILT 18 0 34 35 45 0.3 SILTY SAND 18 0 33 35 45 0.3 SILT, some clay (Below Pile Toe) 17 5 32 500 500 0.3 The sheet piles, ties and wharf deck were modelled as elastic beam elements with appropriate end conditions and the steel ladders modelled as cable elements. The uncorroded sheet pile section was modelled for the construction phases and a corroded sheet pile section used in the final stage. The construction methodology and sequence was found to be critical in determining wall and tie demands. Variations on the construction sequencing were modelled and the following sequence was selected: Define geometry, soil properties and build structure (sheet piles and tie bars). Excavate to -14.5mCD in front of the sheet pile wall (Stage 1 design dredge level). Fill internally between sheet pile walls. Fill behind sheet pile walls and install steel ladders (consecutive stages fill to ladder, install ladder +2 mcd fill to next ladder, etc). Model tidal lag then build wharf deck. Apply 50kPa surcharge behind rear sheet pile wall then to wharf deck. Excavate to -16.0mCD in front of the sheet pile wall (Final design dredge level). 3

Remove 50kPa surcharge Fix back of steel ladders into crane beam and apply 50kPa surcharge. Apply crane loading (loads transferred in wharf deck into sheet pile sections). Reduce sheet pile wall stiffness to model 50-year corrosion case. 5 FLAC RESULTS Expected wall deflections have been predicted using FLAC for the various construction stages. The deflections of the wharf deck have been analysed for both a 50kPa and 35kPa live surcharge. The 50kPa load case is considered an extreme situation. The 35kPa surcharge is the serviceability case allowing for the likely maximum surcharge load taking into account layout, access ways and stacking weights. Table 3 shows the predicted movements during construction stages and surface loadings. Table 3: Estimated Horizontal Displacements Stage Description Estimated Front Sheet Pile Horizontal Displacements (mm) Serviceability Load Case Ultimate Load Case Total Incremental Total Incremental 4 Fill behind structure to RL5.0m 146-146 - 5 Tidal lag 151 5 151 5 6 Build wharf deck 154 3 154 3 7 35kPa/50kPa surcharge 182 (35kPa) 28 198 (50kPa) 44 8 Dredge to RL-16.0m 210 28 227 29 These results indicate the structure is likely to move 30mm under the area wide application of 35kPa surcharge and up to 45mm under the ultimate 50kPa surcharge. 6 CONSTRUCTION 6.1 General The construction of Berth 3 commenced in 2005 from the end of Berth 2. One of the challenges of the construction was access. A 200 tonne crane initially located on the end of Berth 2 was used to install the first driven piles for the wall. A platform system was developed by Fletcher using shallow steel bracing and sand fill to enable the crawler crane to advance over a 13m depth of water on the previously constructed length of wall. To enable the king piles to be driven at their correct location, a piling frame was constructed. This frame was supported by temporary locator king piles driven outside the works and the king piles were driven in sets of 7 at each set up. Intermediate sheets were driven following installation of the king piles. The temporary piles were removed and reused as the construction proceeded. The 33m long driven king piles were driven in one continuous length to minimise the requirement for onsite splicing. At the time of construction, these piles were the longest piles in Oceania to have been driven in a continuous length. Figure 2 below shows the installation of the sheet piles from the temporary platform system, dredging and reclamation process. The construction generally proceeded in accordance with the proposed sequence outlined in Section 4. However, the dredging to -14.5mCD was carried out by a separate contractor and was completed between installing the wall and constructing the wharf deck, and not necessarily prior to infilling between the sheets or backfilling behind the wall as originally designed. The 4

modified dredge sequence was modelled and resulted in a relatively small change in long term predicted lateral deflections. 6.2 Deflection Monitoring Figure 2: Construction of twin king pile wall at Berth 3 The wall deflection behaviour was monitored during construction using inclinometers installed on the front sheet pile wall and surveying of the top of the front and rear sheet pile walls. Three inclinometers NP54, NP74 and NP102 were installed along Berth 3. These were positioned towards the eastern end as the soil profile was less stiff and where higher deflections were expected. Inclinometer casings were installed in steel pipes welded to the front of the king pile which were driven with the king pile. Inclinometer casing was installed in the steel pipe prior to infilling between the walls with sand. The inclinometers have been monitored during construction and re-surveyed one year following completion of the berth structure. Figure 3 below presents the measured deflections. The measured deflections at the top of the front wall were within the predicted range; however the deflected shape is different, with less displacement measured at seabed than predicted. The inclinometer readings indicate the actual soil stiffness below -20mCD is significantly higher than that modelled with measured deflections of less than 5mm recorded compared to the predicted deflections of 20 50mm. Subsequent back analyses were undertaken, matching the predicted displacements with the measured displacements, to find the actual stiffness of the founding material. These analyses indicate the stiffness is in the order of 500 MPa compared with the 35MPa adopted for design. This is considered to be attributed to the piles at the being founded within the very dense sand layer encountered towards the western end of the site and actual strains being much lower corresponding to a greater stiffness. In addition, the twin wall system above seabed is less stiff than predicted, this is probably due to the combination of the degree of compaction of the backfill between the sheet pile walls, lower degree of confinement provided by the walls and the ladder anchors creeping, allowing more movement than expected. It is noted ultimately the ladder anchors are to be connected to the rear crane beam to provide additional support and reduce differential movement between the two crane beams. 5

Measurements taken 1 year following construction indicate the wharf has shown about 20-30mm of further displacement. This is considered to be due to the result of the live surcharge from port operations and the additional loading during pavement construction. Predicted Front Wall Deflections Measured Deflections NP54 Measured Deflections NP74 5 0-5 y position (m CD) -10-15 NP54-06/06 - During 2 filling -20 NP54-09/06 - During 2/3a filling NP54-09/06 - Completed 2/3a NP74-09/06 - During 3a filling -25-30 2 - Infill between walls 3e- Fill behind rear wall 5 - Dredge to -14.5m CD 6b - Construct wharf slab 7b - 35kPa Surcharge NP54-10/06 - During 3c/3e NP54-11/06-6b completed NP54-01/07-6b completed NP54-02/09-1 year after completion NP74-10/06 - During 3c/e filling NP74-01/07-6b completed. NP74-11/06-6b completed. NP74-02/09-1 year after completion 0.00 0.05 0.10 0.15 0.20 0 0.05 0.1 0.15 0.2 0 0.05 0.1 0.15 0.2 x displacement (m) x displacement (m) x displacement (m) 7 CONCLUSIONS Figure 3: Predicted and measured wall deflections The Berth 3 extension to Northport s wharf facility at Marsden point was successfully developed by Beca and Fletcher. The wharf structural form, comprising twin king pile walls tied together with two levels of steel ties and sand infill, allowed construction access by walking the crane over the constructed wall. The design analyses were undertaken using FLAC to model the soil structure interaction. FLAC provided a tool to model the twin wall interaction and friction anchor ties within the sand backfill, which is typically outside the capabilities of standard retaining wall software. Analyses output included design loads for structural elements, deflected profiles for the walls and soil for each stage of construction. The model was sensitive to the soil stiffness properties. Deflections during construction were successfully monitored using inclinometers attached to the king piles. The survey monitoring indicated total displacements were in the order of that predicted, however the overall deflected shape differed indicating sand on the harbour or passive side to be stiffer than that modelled, and twin wall system with ladder anchors to be less stiff than that anticipated. 8 ACKNOWLEDGEMENTS The writers would like to thank The Fletcher Construction Company Ltd and Northport Ltd for permission to publish this paper. 6