NRDCA 300 PROCEDURES TO DETERMINE THE ACCURACY OF MATERIAL MEASURING EQUIPMENT FOR LIGHTWEIGHT INSULATING CONCRETE

Similar documents
Water Utility Science Water Math and Hydraulics 050. Name: Date:

MATERIAL ALLOWANCES AND UNIT PRICES

1 Exam Prep Chapter 64E -6 Questions and Answers

Lightweight insulating concrete (LWIC) is one of the most

CELCORE CELLULAR INSULATING CONCRETE SPECIFICATION FOR RETROFIT PLACEMENT OVER EXISTING ROOF MEMBRANES

Distribution System Basics Course Syllabus

Truck Mixer, Agitator and Front Discharge Concrete Carrier. Standards. TMMB Printing

Plant Address or Physical Location

Analysis 2: Greenroof Design

Trouble-Shooting Asphalt Content Problems

MEMORANDUM. The general findings of the assessment are as follows:

By Jerry Turrentine, NRCS Biologist USDA Natural Resources Conservation Service

ArcelorMittal Dofasco Scrap Specifications and Requirements

Calculate the Costs of Piping System Elements

DIVISION: THERMAL AND MOISTURE PROTECTION SECTION: PEDESTRIAN TRAFFIC COATINGS REPORT HOLDER: WESTCOAT

STANDARDS FOR MIXING WATER IN CONCRETE

Protecting Existing PCCP Subject to External Transient Loads. 200, Fort Worth, Texas 76109; phone (817) ;

T-145 batch vs. Continuous. Technical Paper T-145. batch vs. continuous. by E. Gail Mize and Greg Renegar

2010 FLORIDA BUILDING CODE TEST PROTOCOLS HVHZ (TAS)

SECTION 347 PORTLAND CEMENT CONCRETE CLASS 1 (NON-STRUCTURAL)

The GREENBOOK 2015 Standard Specifications for Public Works Construction

OMT Asphalt Plant Inspection Checklist

TESTING APPLICATION STANDARD (TAS) No TEST PROCEDURE FOR WIND AND WIND DRIVEN RAIN RESISTANCE OF DISCONTINUOUS ROOF SYSTEMS

Truck Mixer, Agitator and Front Discharge Concrete Carrier. Standards. Endorsed by and Affiliated with. TMMB Printing

SECTION CHAIN LINK FENCES AND GATES (GALVANIZED) A. Fence framework, fabric, gates, and accessories.

first flush water diverters water quality first downspout, post/wall mounted and in-ground diverters

Technical Information

VWEA Operations Challenge Roanoke, VA July 14, 2016

INTRODUCTION. Inspection Procedures oinitial Inspection Report. Visual Inspection Physical Sampling (Core and Slit Samples)

DOWNSTREAM DEFENDER TESTING USING MAINE DEPARTMENT OF ENVIRONMENTAL PROTECTION PROTOCOL UTILIZING OK-110 FEED SAND

THE SITUATION WITH STEEL DECKS

ADDITIONAL PRACTICE WITH WRITING CONVERSION FACTORS

There are many technologies available for

Manure Spreader Calibration. Jerry Martin, Senior Extension Associate, Penn State Crop & Soil Sciences

The following definitions apply with regard to requirements specified in this document:

Converting square ft to cubic yards concrete

SECTION 7 SEPARATION OF WATER MAINS AND SANITARY SEWERS

Tolerances- Section

SECTION CLAY BARREL TILE ROOFING. A. American Society for Testing and Materials (ASTM):

MOLDING, TESTING, AND EVALUATING ASPHALT BLACK BASE MATERIALS

SECTION PACKAGE BOOSTER PUMP STATIONS

September 1, 2003 CONCRETE MANUAL SPECIAL TYPES OF CONCRETE

Suggested Practices for Fluoride Design

NORTHWESTERN UNIVERSITY PROJECT NAME JOB # ISSUED: 03/29/2017

SAM HOUSTON STATE UNIVERSITY DIVISION 07 THERMAL & MOISTURE PROTECTION SECTION ROOFING SYSTEMS DESIGN AND CONSTRUCTION STANDARDS February 2016

Appendix A EXAMPLE COLLECTION SYSTEM PERFORMANCE INDICATOR DATA COLLECTION FORM

Concrete Plant Standards of the Concrete Plant Manufacturers Bureau

Contact Clark Public Utilities Construction Services department at (360) to initiate a request for service.

16. Design of Pipeline Structures.

Transmission Pipeline Opportunities. Advancing Project Development in India through Public Private Partnerships

2018 YEARLY BID FORMS SUPPLIER BID FORM. ITEM # 1: Fire Hydrants: 3 and 4 Bury, 3 ways, 5 ¼ valve opening, 6 mechanical joint shoe.

High Performance Material Additions for Batching

SECTION 4 - DESIGN STANDARDS FOR WATER DISTRIBUTION FACILITIES

METAL HANDRAILS AND RAILINGS. A. Properly identified manufacturer's literature, including shop and erection drawings before starting work.

DESIGNING WITH STEEL FORM DECK

DEPARTMENT OF ENVIRONMENTAL QUALITY WATER QUALITY DIVISION PERMIT APPLICATION FORM UNDERGROUND INJECTION CONTROL (UIC) CLASS V WELL

Property Condition Assessment

Asphalt Drum Mixers FULL LINE CATALOG MILEMAKER EX ROADBUILDER SPL COMPONENTS

READ ONLY. Adopting Agency BSC SFM. Adopt Entire Chapter X X X Adopt Entire Chapter as amended (amended sections listed below) X X X X X X

Rain Barrel Water Harvesting

Commonwealth of Pennsylvania PA Test Method No. 507 Department of Transportation October Pages LABORATORY TESTING SECTION. Method of Test for

TECHNICAL INFORMATION Bulletin NUMBER Thirty-Four

GUIDELINES FOR INSTALLATION OF ABOVEGROUND DIESEL FUEL TANKS

It s in the Pour Gla-Zit does so much for all types of new concrete projects no Pour should be without it. Gla-Zit.com

LIFE SCIENCES BUILDING STRUCTURAL CONCEPTS AND EXISTING CONDITIONS

Ivins City Standard Specifications for Design and Construction Part 2 Engineering and Design Standards

CONSTRUCTION PROCEDURES. AWWA D110 Type I Prestressed Concrete Tanks

Chapter 4.1. Estimating Manure Inventory. learning objectives

MASTERSPEC TECHNICAL SPECIFICATIONS DIVISION 22 PLUMBING

In order to get the maximum comfort out of a radiant system, it is paramount to go through a precise design phase (ref. UNI EN 1264).

Includes NEW Plant Mixer Performance Standards!

Cost Considerations of Asphalt Rubber Hot Mix

Allowable Loads for Round Timber Poles

Recommended Fastening Patterns for Rmax Insulation in Low Slope Roofing Applications

Dead Load Weight of Roof Trusses. Dead Load Weight of Floor Trusses

2015 DW Module 1: General Overview VOLUME III Answer Key

Moisture in Concrete Roof Decks and How to Evaluate its Effect on Roofing Systems

Flygt Advanced Low Pressure Sewer System Package

DIVISION: THERMAL AND MOISTURE PROTECTION SECTION: COATED FOAM ROOFING REPORT HOLDER: LAPOLLA INDUSTRIES, INC.

GUIDANCE MEMO NO : GUIDANCE CRITERIA FOR THE SEPARATION OF WATER MAINS AND NON-POTABLE PIPELINES

Design & Construction Standards, Revised January

Water Conservation in Poultry Processing. William C. Merka Extension Poultry Science Department The University of Georgia Athens, GA 30602

Strength and Durability for Life APPLICATIONS. Bridge Crossings with Ductile Iron Pipe

PORT OF SAN FRANCISCO PLUMBING CODE. Based on the 2010 California Plumbing Codes

MANHOLES, VAULTS AND CATCH BASINS SECTION A. Section Soil and Aggregate Materials. C. Section Storm Drainage Systems

CFFWA-20-1-U Chilled/Hot Water Universal Mount Fan Coil 2-Pipe Heat / Cool Fan Coil 60,000 BTUH

Attachment D-1: Civil/Structural Scope of Work

McIlvaine Hot Topics FGD Scrubber Components

Chapter 3: General Regulations

Asphalt Rubber Chip Sealing DRAFT MAINTENANCE SPECIFICATION. March 22, 2007

SECTION CAST-IN-PLACE CONCRETE

for plumbing regulations.

Read Only Copy Not For Distribution. Chapter 17. Private Potable Water Supply Systems 17.1 GENERAL REGULATIONS 17.2 QUANTITY OF WATER REQUIRED

PROPORTIONING CONCRETE MIXES

Erect the weighing bins and hoppers on firm foundations to avoid settlement, which might affect the accuracy of the equipment.

SECTION CAST-IN-PLACE CONCRETE

ters them into a hammermill at a constant feedrate. The hammermill reduces the kernels to a powder that has the consistency of cornmeal. This discharg

Daytona Beach Pier Building Renovation Jun 2010

CHAPTER 11 CONDUITS AND FITTINGS

Transcription:

NRDCA 300 PROCEDURES TO DETERMINE THE ACCURACY OF MATERIAL MEASURING EQUIPMENT FOR LIGHTWEIGHT INSULATING CONCRETE I. Scope Lightweight insulating concrete is field produced with specialized mixing equipment. A conveying system transfers measured raw materials into the mixing equipment. The accuracy of the measuring equipment determines the consistency of the insulating concrete and whether the concrete meets manufacturer s specifications. This document establishes methods to determine the accuracy of the raw material measuring equipment. Repair and re-calibrate equipment before continued use in making insulating concrete, should it not meet the required accuracy limits established in this document. This document includes the methods of determining the accuracy and establishes accuracy limits for: Load Cell Water Meter Cast Density Scale Cast Density Calibrated Container II. Reference Documents A. Following are documents referenced in this document or that reference this document. 1. NRDCA 100 Guideline for Field Application of Aggregate Insulating Concrete Roof Deck Systems. All Rights Reserved Page 1

III. Load Cell 2. NRDCA 175 Guideline for Field Application of Cellular Insulating Concrete Roof Deck Systems. 3. NRDCA 250 Field Quality Control Procedures for Application of Insulating Concrete Roof Deck Systems. 4. NRDCA 400 - Guideline for Field Application of Lightweight Insulating Concrete Reroofing / Recover Systems. A. General: The load cell may be either a mechanical or electromechanical device to weigh the cement for the insulating concrete mix. A load cell may also measure the weight of the mixer and its components after all raw materials have been added. B. Frequency of Determining Accuracy and Accuracy Limits: The load cell must be checked for accuracy each time it is moved and set up in a new equipment site. The load cell may require accuracy testing more frequently if it shows erratic readings during normal operation. Should the average of three accuracy measurements show the load cell readings to be greater than 10% in error, it must be repaired and re-calibrated before continued use. C. Accuracy Procedure: This procedure requires the use of calibrated weights or a similar device shown in Attachment 1 and the following accuracy measuring steps. 1. Attach either a calibrated weight or the device shown in Attachment 1 to the load cell. Either device should apply a calibrated weight to the load cell approximately equal to 500 pounds. Load cell may be checked by a given volume of water for mixer weighing systems. 2. Record the scale reading in pounds and subtract the scale reading from the calibrated weight. If the difference is greater than 50 pounds, the load cell must be returned to a laboratory providing calibration service for repair and re-calibration. When continuing to use the current load cell for cement weight, increase or decrease the cement batch weight by the percent difference to complete the current project. IV. Water Meter A. General: The water meter is a mechanical device that measures the volume of water that flows through the meter. All Rights Reserved Page 2

B. Frequency of Determining Accuracy and Accuracy Limits: The water meter must be checked once every month to ensure the volume of water and the meter reading are in agreement. Should the meter reading be more than 5% different than a known volume, the meter should be repaired and re-calibrated. C. Accuracy Procedure: This procedure uses a container of known volume filled with water to compare to the water meter reading. Use either the water surge tank on the mixer or a 55-gallon drum to determine water meter accuracy. 1. Determine the volume of the calibrating container by measuring the inside diameter (inches) and inside length (inches) of the surge tank or 55-gallon drum. When using a surge tank, measure the inside diameter of the pipe from the tank to the dump valve and the length of the pipe. 2 Calculate the volume of the container in cubic inches using the formula below: Volume = Π D 2 X L 4 Where: Π = 3.14 D = Diameter in inches of tank or pipe L = Length in inches of tank or pipe 3. Divide the result by 231cubic inches/gallon to convert the calculated number in Section III. C. 2. from cubic inches to gallons. 4. Fill the calibrating tank three times and record the water meter reading each time. Average the three water meter readings. Calculate the difference between the average water meter reading and the calibrated tank volume. Determine the percent difference. If the average is more than 5% different than the know volume, have the meter repaired and re-calibrated. During the current water meter set up, the gallons of water required per batch can be increased or decreased by the calculated percent difference or another calibrated water meter can be installed to complete the current project. 5. Example of Calculating the Volume of a Surge Tank with Pipe: Tank outside dimensions: 24 diameter, 48 5/16 long Inside diameter of drain pipe: 5 Length of pipe from tank to center of valve: 4 7/8 All Rights Reserved Page 3

Inside dimensions of tank are approximately ¼ smaller than outside dimensions. Therefore, the inside dimensions of the tank are 23 ¾ diameter and 48 1/16 long. Volume of Tank: 3.1416 (23.75) 2 4 x 48.06 = 21,291.29 cubic inches Volume of Pipe: 3.1416 (5) 2 x 4.88 = 95.82 cubic inches 4 Total Volume of Tank with Pipe Converted Gallons of Water = V. Cast Density Scale = 21,387.11 cubic inches 21,387.11 cubic inches = 92.6 gallons 231 cubic inches/gallon A. General: The pound scale used to measure the cast density of insulating concrete may be either a platform scale or a hanging spring scale with a minimum weight capacity of 50 pounds or a capacity practical for the calibrated container. B. Frequency of Determining Accuracy and Accuracy Limits: The scale must be checked weekly. Repair and re-calibrate the scale should the scale accuracy measurements be greater than +/- 5.0%. C. Accuracy Procedure: Use a known calibrated weight of at least 25 pounds to calibrate the scale. 1. The calibrated weight must be attached to the scale or placed on the scale a minimum of three times. Record the scale reading for each weighing. 2. Calculate an average of the three scale readings. Subtract the average of the scale readings from the calibration weight. Calculate the percent difference between the two numbers. If the difference is greater than 5.0%, replace the scale or have it repaired before continuing to make cast density measurements. All Rights Reserved Page 4

VI. Cast Density Calibrated Container A. General: The volume of the cast density measurement container is critical to determining the cast density of the insulating concrete being placed. The cast density measurement container must be of solid construction in order to maintain its volume characteristics. Should the volume change because it is flexible when loaded with insulating concrete, the cast density measurement will not be accurate. A galvanized steel minimum 10-quart pail is recommended. B. Frequency of Determining Accuracy and Accuracy Limits: The container calibration factor should be measured once a month. If the pail volume changes due to bending of the container or leaving dried concrete inside the container, recalibrate the container or use a new container that has been calibrated. Should the container calibration factor change by more than 3%, the container must be replaced with a new container that has been calibrated. C. Accuracy Procedure: This procedure requires a scale with a minimum weighing capacity of 50 pounds and a cast density container. 1. Weigh the empty container in pounds. 2 Fill the container to the top with water. 3 Weigh the water filled container. 4. Subtract the empty container weight from the water filled container. 5. Divide the weight of water determined in Step 4 into 62.4 pounds/cubic foot. The resulting number is the calibration factor used in determining the concrete cast density. All Rights Reserved Page 5

D. Example of Determining Calibration Factor A 10 quart metal container will be used in measuring the cast density of insulating concrete. What is the container calibration factor? 1. Using a calibrated scale, the container empty weight = 2.00 Pounds. 2. The weight of the water filled container is = 23.50 Pounds 3. The net weight of water is (23.5-2.0) = 21.50 Pounds 4. The Container Calibration Factor is (62.4/21.5) = 2.90 Pails/ cubic feet (or by volume: 21.5/62.4 = 0.34 cubic feet) All Rights Reserved Page 6

Attachment 1: - Cement Load Cell Accuracy Measurement Using Water Weight I. The device shown below, when filled with water to the indicated level will result in a calibrated weight of approximately 500 pounds. The actual calibrated test weight for the unit filled with water is on the unit label. The device will hang directly from the load cell and has a valve installed to release the water after the calibration procedure is completed. This device provides a portable but accurate method to create the dead load required in Section III, Load Cell Accuracy Procedure. II. Design and Construction Details All Rights Reserved Page 7