Environmental Assessment May 2007

Similar documents
Impact Assessment Methodology for the. Somerville Public Library August 4, 2008 Jason Ross, P.E. Harris Miller Miller & Hanson Inc.

Recommended Locations for Sound Barriers

1. Introduction Noise Analysis Results Figures. List of Tables

Development of the FXT Track System. presented by André Van Leuven Dynamic Engineering

LONE HILL TO WHITE DOUBLE TRACK STUDY Community Open Houses May 16 & 17

Noise Study Bristol Park Redevelopment Area

SOUND TRANSIT STAFF REPORT MOTION NO. M Link Noise Mitigation Policy

To: Hyoksang Kwon, COBE Construction From: Joshua Marcley, Mei Wu Acoustics

Traffic Noise Introduction to Traffic Noise Analysis and Abatement

TRANSIT PRODUCTS CATALOG

FEDERAL BOULEVARD (5 TH AVENUE TO HOWARD PLACE) PLANNING ENVIRONMENTAL LINKAGE STUDY TRAFFIC NOISE IMPACT ANALYSIS

Noise Analysis Study along I Tim Bjorneberg Project Development Program Manager SDDOT

APPENDIX 5.12-A PROJECT NOISE ANALYSIS: ARTESIAN SUBSTATION

Policy for the Assessment and Mitigation of Traffic Noise on County Roads

Non-Traditional Noise and Vibration Mitigation Strategies. Christopher Layman, Ph.D. Shannon McKenna Judy Rochat, Ph.D. ATS Consulting Pasadena, CA

Peak noise levels during any time period can be characterized with statistical terms.

5 INFORMATION UPDATE TRAFFIC NOISE ASSESSMENT TESTON ROAD CITY OF VAUGHAN

SOUND TRANSIT LIGHT RAIL VIBRATION ISSUES AT THE UNIVERSITY OF WASHINGTON

APPENDIX C NOISE STUDY TECHNICAL REPORT

LAFAYETTE RAILROAD RELOCATION, NORFOLK SOUTHERN CORRIDOR

NOISE AND VIBRATION FEASIBILITY STUDY 316 BLOOR STREET WEST CITY OF TORONTO, ONTARIO

Hamilton Rapid Transit Preliminary Design and Feasibility Study

MnDOT GREATER MN STAND ALONE NOISE BARRIER PROGRAM

Appendix D Environmental Noise Assessment

US 53 Noise Mitigation

TABLE OF CONTENTS Chapter 12 Noise

BRITISH COLUMBIA MINISTRY OF TRANSPORTATION AND INFRASTRUCTURE POLICY FOR ASSESSING AND MITIGATING NOISE IMPACTS

Cotton Belt Corridor. Area Focus Group (AFG) North Dallas September 11, John Hoppie, Capital Planning

Noise Assessments for Construction Noise Impacts

Noise Assessment Report Main Street, Residential Site Cambridge, ON

CROSSRAIL INFORMATION PAPER D10 GROUNDBORNE NOISE AND VIBRATION

UPRR criteria for sizing waterway openings under bridges and through culverts are as follows:

Virginia Department Of Transportation. Highway Traffic Noise Impact Analysis Guidance Manual

Fence and Wall Requirements

Traffic Noise Analysis

6.0 Indirect Effects and Cumulative Impacts

COMPONENTS OF THE NOISE ELEMENT

Floating Slabtrack Systems in Tunnels A case study with different FST systems Metro Lisbon Red Line Extension

TECHNICAL MEMORANDUM

Place Vanier Édifice AEFO

APPENDIX C NOISE STUDY TECHNICAL REPORT

GENERAL GUIDANCE FOR Low Noise and Low Vibration Slab Track

NOISE MITIGATION PROGRAM

State Route 8 Bridge Replacement Project

Appendix E Cost Estimating Methodology for High-Speed Rail on Shared Rightof-Way

12 November Ms. Winnie Lam Project Manager L.F. George Properties 159 El Camino Real Millbrae, CA 94030

Ballast Mats ATP-DR Profiled

Chapter 2: Foundation

Flagstone Development - Noise Assessment for Stage 1K and 1U

SEPTIC TANK CONSTRUCTION GUIDELINES

3.1 Noise Overlay District

Concrete Slab Track Test on the High Tonnage Loop. at the Transportation Technology Center. AREMA Annual Conference & Exposition

ENVIRONMENTAL NOISE ASSESSMENT

Factor Potential Effects Mitigation Measures

FHWA/FTA/FRA Joint Project Procedures. Mark Ferroni Noise Team Leader July 22 25, 2007

Noise Reduction and Asphalt Rubber. Douglas D. Carlson RPA Deputy Director Asphalt Rubber Greenbook Workshop 08/22/02 UCSB, California

APPENDIX C. Environmental Noise Assessment

Buffer distances for surface roads and elevated highways correlated with pre-existing ambient noise

Evaluation of Highway. Noise Mitigation Alternatives. For Vail Colorado. Final Report October Prepared for. Vail, Colorado.

Jacksonville Port Authority Blount Island Marine Terminal Rail Improvements Jacksonville, Florida

ATD-G and RHEDA CITY GREEN The green tracks for urban traffic

Contact the Jurisdictional Engineer for materials allowed by each jurisdiction.

ASSESSMENT OF INWARD TRAFFIC NOISE IMPACT AT RESIDENTIAL DEVELOPMENT, WONDERFUL BARN, LEIXLIP, CO. KILDARE

California High-Speed Train Program FEIR/EIS

inter.noise 2000 The 29th International Congress and Exhibition on Noise Control Engineering August 2000, Nice, FRANCE

Northern Intermodal Transit Facility WHAT IS AN INTERMODAL TRANSIT FACILITY?

Noise Feasibility Study Proposed Residential Development Old Barber House 5155 Mississauga Road City of Mississauga, Ontario

Vibration Isolation by Floating Slab Track Systems

FIGURE N-1 LAND USE COMPATIBILITY FOR NEW DEVELOPMENT NEAR TRANSPORTATION NOISE SOURCES

Box Culverts. Easy to install, suitable for very shallow or deep fill, ideal for use in a wide variety of civil engineering applications.

THE SLAB TRACK SOLUTION FOR THE REQUIREMENTS OF TOMORROW LOW VIBRATION TRACK (LVT)

S-09: Auburn Station Access Improvements

COEXISTING: FREIGHT FACILITIES & COMMUNITIES. The Capital District Intermodal and Automotive Terminal Rick Crawford, Norfolk Southern April 24, 2013

ARCHITECTURAL AND STRUCTURAL NOISE CONTROL SOLUTIONS

Administrative Hearing Staff Report

CROSSRAIL INFORMATION PAPER D26 SURFACE RAILWAY NOISE AND VIBRATION

CASE STUDY OF THE SOUND REDUCTION OF VARIOUS RESIDENTIAL GLAZING TREATMENTS

ECMC Skilled Nursing Facility Architectural Engineering Senior Thesis AE 481W Thesis Proposal Dr. Ali Memari January 13 th, 2012

Metro Blue Line Improvements & Project Update

6 Draft Section 61 Findings and Mitigation Commitments

NORTH GILROY NEIGHBORHOOD DISTRICTS URBAN SERVICE AREA AMENDMENT EIR NOISE AND VIBRATION ASSESSMENT GILROY, CALIFORNIA

MBTA Green Line Extension Noise and Vibration Technical Report

9.0 Noise and Vibration

A CONCEPT FOR USING RECYCLED RUBBER GRANULES IN NOISE REDUCTION CONCRETE S PANELS

24 CFR Part 51 Noise Abatement and Control as part of a Part 58 HUD Environmental Review. November 19, 2013

Chapter Track Structure Design. Table of Contents

BAY MEADOWS PHASE II SPAR 2 SAN MATEO, CALIFORNIA

One and Two Family Additions

APPENDIX F: CALTRANS COST ESTIMATE TEMPLATE (included in Appendix AA of the CALTRANS Project Development Procedures Manual)

Presented By: Jim O Neill. Acoustics

MOA Project # Golden View Drive Intersection & Safety Upgrades

PENNSAFE BUILDING INSPECTION SERVICES LLC PERMIT APPLICATION

Project Steering Committee April 14, 2015

Civil Engineering and Architecture Detailed and Performance Objective Outline

SPACE TYPE: OUTSIDE PARKING (STRUCTURE)

BNSF RAILWAY COMPANY

CONSTRUCTION & INDUSTRIAL IMPACT INSULATION

This comparison is designed to satisfy the requirements of State CEQA Guidelines, Section (d), Evaluation of Alternatives, which state that:

National Housing Trust Fund Environmental Review and Funding Requirements

CITY OF CEDAR FALLS DEPARTMENT OF DEVELOPMENTAL SERVICES INSPECTION SERVICES DIVISION PHONE Residential Accessory Structures

Transcription:

jurisdictional waters. It is assumed that, at a minimum, a USACE Section 404 Nationwide Permit would be necessary to construct these features. The impacts of the fill into the floodplain cannot be fully assessed at this LEA/PE phase. A detailed hydraulic analysis will be conducted during final design. At that time, a full assessment of impacts would be determined and any mitigation treatments or further potential design modifications would be coordinated with the cities of Garland and Rowlett. 3.8.3 USACE/Section 404 Coordination As previously discussed, coordination with the USACE has been initiated and will continue through final design. This effort will include any needed coordination with the USACE on the issue of fill in the floodplains and impacts to jurisdictional waters, including wetlands, as a result of the proposed project. It will also be necessary to coordinate with the cities of Garland and Rowlett Public Works Departments in accordance with their floodplain regulations, permits and development conditions. 3.9 Noise and Vibration 3.9.1 Noise Impact Assessment The results of the noise analysis indicate that the existing noise environment at locations near the proposed alignment is dominated by noise from railroad operations and general community activities. Based on FTA criteria, it is predicted that without mitigation, the proposed LRT operations would cause noise impacts at 20 locations as shown in Table 3-9. None of these impacts are in the severe category. Detailed information regarding the impacts can be found in Appendix C. A number of noise mitigation treatments can be considered for the impacts listed in Table 3-9. The two most likely methods of noise mitigation are noise barriers and sound insulation. Sound insulation treatments are typically applied to buildings in areas where barriers would not be effective. These areas are primarily located near grade crossings, where additional noise impact is caused by train horns and grade-crossing bells. Relocation of crossovers away from noise-sensitive receptors would also reduce the noise impact. The selection of mitigation would depend on more detailed analysis during final design, including input from abutting neighbors. 3-40

Table 3-9: Summary of Noise Impacts Location Side of Number of Noise Impacts Track Moderate Severe Parker Circle S 13 0 Davidson Street S 0 0 Palomino Drive S 0 0 Vicinity of Main Street N 1 0 Rowlett North of Main Street N 1 0 Rowlett South of Main Street S 4 0 Totals 19 0 Potential mitigation treatments for reducing projected noise impacts resulting from the proposed are described below. Noise Barriers. This is a common approach to reducing noise impacts from surface transportation sources. The primary requirements for an effective noise barrier are that (1) the barrier must be high enough and long enough to break the line-of-sight between the sound source and the receiver, (2) the barrier must be of an impervious material with a minimum surface density of 4 pounds per square feet and (3) the barrier must not have any gaps or holes between the panels or at the bottom. Because numerous materials meet these requirements, the selection of materials for noise barriers is usually dictated by aesthetics, durability, cost and maintenance considerations. Depending on the proximity of the barrier to the tracks and on the track elevation, transit system noise barriers typically range in height from between four and eight feet. Relocation of Crossovers or Special Trackwork at Crossovers. Because the impacts of wheels over rail gaps at track crossover locations, or turn-outs for passing tracks, increases vibration by about 6 dba, crossovers are a major source of vibration noise impact when they are located in sensitive areas. If crossovers cannot be relocated away from residential areas, spring-rail or moveable point frogs in place of standard rigid frogs at turnouts allow the flangeway gap to remain closed in the main traffic direction for revenue service trains. Building Sound Insulation. Sound insulation to improve the outdoor-to-indoor noise reduction has been widely applied around airports and has seen limited application for transit projects. Although this approach has no effect on noise in exterior areas, it may be the best choice for sites where noise barriers are not feasible or desirable, and for buildings where indoor sensitivity is of most concern. Substantial improvements in building sound insulation (on the order of 5 to 10 dba) can often be achieved by adding an extra layer of glazing to the windows, by sealing any holes in exterior surfaces that act as sound leaks, and by providing forced ventilation and air-conditioning so that windows do not need to be opened. 3-41

Grade Separation, Quiet Zones or Closure of Grade Crossings. Because the sounding of horns is the dominant noise source for trains near grade crossings, the reduction or elimination of horn use can be an extremely effective noise mitigation measure. Grade crossing noise can be eliminated by grade separations, by closure of grade crossings or by implementation of Federal Railroad Administration (FRA) approved quiet zones. The FRA has published an Interim Final Rule on the Use of Locomotive Horns at Highway-Rail Grade Crossings that may allow this under certain conditions. The rule, described in 49 CFR Parts 222 and 229 (December 18, 2003), would permit local public authorities to establish quiet zones in which train horns may not be routinely sounded, provided that adequate supplementary safety measures (i.e., four quadrant gates and channelization arrangements) are applied at the crossings to compensate for the absence of the train horn. The rule also authorizes the use of automated wayside horns at crossings with flashing lights and gates as a substitute for the train horn. While activated by the approach of trains, these devices are mounted at the grade crossings, thereby limiting the horn noise exposure area to the immediate vicinity. Although the establishment of quiet zones or the use of wayside horns would be very effective noise mitigation treatments, considerable design analysis and coordination efforts with the railroad and local communities along the corridor would be required to determine if these measures are feasible. In addition to reducing the noise generated by the LRT operations, a quiet zone would also eliminate current horn noise from freight trains, providing an additional benefit to the surrounding community. FTA requires that severe impacts be mitigated unless there are no practical means to do so. While mitigation is encouraged at the moderate impact level, the implementation of such mitigation would depend on other project-specific factors. These other factors can include the projected increase over existing noise levels, the types and number of noise-sensitive land uses affected, existing outdoor-to-indoor sound insulation and the cost-effectiveness of mitigating noise to more acceptable levels. Consistent with DART policy on prior FTA-funded rail extensions, noise mitigation is only considered at locations where a noise exposure increase of three db or more is projected. Based on the results of the noise assessment, mitigation treatments have been identified for the moderate impacts where there is a projected three db increase in the noise level. The primary mitigation measure would be the construction of sound barrier walls to shield areas where impact is projected. Table 3-10 indicates the approximate noise barrier locations, lengths, and side of tracks as well as the number of impacts that would be reduced. Typical barrier height is about eight feet, and can be somewhat less on elevated structures. Exact height and configuration depend on specific conditions, and will be determined during final design. 3-42

Location Table 3-10: Noise Mitigation Locations Side Civil Height Length of Station (ft) (ft) Track Without Mitigation Impacts 1 With Mitigation Residence on Main Street N N 1162-1167 4 500 1 0 Residences North of Main Street (Rowlett) N 1181-1185 8 400 1 0 Residences South of Main Street (Rowlett) S 1175-1182 4/8 2 700 4 0 Total 6 0 Notes: 1 Impacts that are required to be mitigated in accordance with the DART noise mitigation policy. 2 The barrier should be 4 feet high on the elevated structure, with a transition to 8 feet high at grade. Mitigation Treatments After the noise analysis was completed, coordination with City of Rowlett revealed that the properties identified above are a part of the Downtown Rowlett Main Street Project. Each property will be incorporated into the TOD associated with this project, and therefore no mitigation would be required. In addition, environmental justice and community concerns, as well as the concerns of the City of Garland, necessitate a noise wall for the entire length of the corridor abutting the Rainbow Estates neighborhood. This wall will be approximately 2,270 feet in length. 3.9.2 Ground-borne Vibration Impact Assessment Other than very occasional low-speed freight train movements, there is not a significant source of existing vibration along the alignment. Based on FTA criteria, it is predicted that without mitigation, the LRT operations would cause vibration impacts at 13 locations as shown in Table 3-11. All of these impacts are related to annoyance effects and not to building damage effects. There are a number of options available for the mitigation of vibration impacts. The most common method is ballast mats. Ballast mats consist of pads made of rubber-like material placed on an asphalt or concrete base with the normal ballast, ties and rail on top. Because the vibration reduction provided by ballast mats is limited at lower frequencies, their effectiveness is dependent on the frequency content of vibration. Relocation of crossovers away from vibrationsensitive receptors would also reduce the vibration impact. Mitigation options would be evaluated in more detail during final design, and the most appropriate measures would be selected based on feasibility, cost effectiveness, and community input. 3-43

Table 3-11: Summary of Vibration Impacts Location Side of Track Impact Parker Circle S 13 Davidson Street S 0 Palomino Drive S 0 Vicinity of MAIN STREET N 0 Rowlett North of Main Street N 0 Rowlett South of Main Street S 0 Total 13 The assessment assumes that the vehicle wheels and track are maintained in good condition with regular wheel truing and rail grinding. There are several approaches to reduce groundborne vibration from LRT operations listed below. Ballast Mats. A ballast mat consists of a pad made of rubber or rubber-like material placed on an asphalt or concrete base with the normal ballast, ties and rail on top. The reduction in ground-borne vibration provided by a ballast mat is strongly dependent on the frequency content of the vibration and design and support of the mat. Tire Derived Aggregate (TDA). TDA or shredded tires consists of installing a layer of tire shreds, typically about one foot thick and encased in geo-textile material, in a trench and covering it with a one-foot thick layer of sub-ballast and a one-foot thick layer of ballast to support the track. Preliminary tests suggest that the vibration attenuation properties of the tire shreds are midway between that of ballast mats and that of floating slab track beds. Thus far, this treatment has only recently been installed on two U.S. LRT systems, in San Jose and in Denver. Although this is a low-cost option, the effectiveness of these shredded tire installations has not yet been tested under train operating conditions and the long-term endurance and vibration isolation performance of this treatment is unknown. Resilient Rail Fasteners. Resilient fasteners can be used to provide vibration isolation between rails and concrete slabs for direct fixation track on aerial structures or in tunnels. These fasteners include a soft, resilient element to provide greater vibration isolation than standard rail fasteners in the vertical direction. Relocation of Crossovers or Special Trackwork. Because the impacts of wheels over rail gaps at track crossover locations, or turn-outs for passing tracks, increases vibration by about 10 dba, crossovers are a major source of vibration impact when they are located in sensitive areas. If crossovers cannot be relocated away from residential areas, another approach is to use spring-rail or moveable point frogs in place of standard rigid frogs at turnouts. These devices allow the flangeway gap to remain closed in the main traffic direction for revenue service trains. 3-44

Floating Slabs. Floating slabs consist of thick concrete slabs supported by resilient pads on a concrete foundation; the tracks are mounted on top of the floating slab. Most successful floating slab installations are in subways, and their use for at-grade track is rare. Although floating slabs are designed to provide vibration reduction at lower frequencies than ballast mats, they are extremely expensive. Property Acquisitions or Easements. Additional options for avoiding noise and vibration impacts are for the transit agency to purchase residences likely to be impacted by train operations or to acquire easements for such residences by paying the homeowners to accept the future train vibration conditions. These approaches are usually taken only in isolated cases where other mitigation options are infeasible, impractical, or too costly. Vibration impacts that exceed FTA criteria are considered to be significant and to warrant mitigation, if reasonable and feasible. Table 3-12 indicates the locations along the proposed Corridor where mitigation has been recommended to reduce the vibration levels. At a minimum, mitigation would require the installation of ballast mats or TDA. However, more extensive mitigation may be required to adequately reduce the vibration levels to below the FTA vibration impact criterion. Vibration mitigation will be addressed in more detail during final design. The vibration mitigation locations in Table 3-11 are preliminary only, and will be refined based on a more complete vibration analysis with more detailed engineering information. Mitigation Treatments Table 3-12: Vibration Mitigation Locations Location Impacts Civil Station Length (ft) Parker Circle 13 994-1004 1,000 Total 1,000 Vibration Impacts would be mitigated between Civil Station 994 and 1004 to include 1,000 ft. of treatments to be developed during final design. 3.10 Air Quality This section describes the air quality assessment for the proposed. The purpose of this assessment is to identify potential air quality impacts for the proposed DART Rail to Rowlett as compared to the No-Build Alternative and to identify any mitigation treatments that may be required to reduce impacts to a level less than significant. 3.10.1 Air Quality Impact Assessment The potential for air quality impacts was evaluated by using an existing regional air quality emissions analysis, dispersion modeling, and evaluating any mitigation treatments determined 3-45