Prepared by. Regd. Office: January, 2013

Similar documents
Annex F Scoping Checklist

Molvan- Chhamuchhal Group Gram Panchayat. Taluka- Mangrol, District- Surat. Ph. No

Form -1. [Vide Notification dated 1 st December 2009] FOR PROPOSED. COSTAL ROAD AT DRONAGIRI, NAVI MUMBAI Precast RCC Bridges On Holding Ponds-

FORM-1. Sr. No 1 Name of the Project Harbour Heights 2 S. No. in the Schedule 8(b) Townships and Area Development projects.

REPORT OF SAND STONE MINING PROJECT (KHATADARI Q.L. No. 178 FOR

Revised FORM - I & PRE-FEASIBILITY REPORT

FORM I I. BASIC INFORMATION S. No. Proposed Mixed Use Development Project SPR Binny 2 S. no. in the schedule 8 (b) 1 Name of the project

Centrade At Plot No. 1, Sector 140, NOIDA Noida, U.P FORM- I

Proposed Group Housing Project ATS Rhapsody At Plot No. GH 12/1, Sector -01, Greater Noida (U.P.) APPENDX (See paragr FORM 1

Sector D 1,Kanpur Road Yojna

Max. building height (m)

SIX MONTHLY COMPLIANCE REPORT JUNE- 2015

CONSERVATION OF ENVIRONMENT ENACTMENT 1996 CONSERVATION OF ENVIRONMENT (PRESCRIBED ACTIVITIES) ORDER 1999

FORM- I. Behrampur Gurgaon. Gurgaon, Haryana

4.0 ENVIRONMENTAL IMPACTS AND MITIGATION MEASURES. Negative or adverse impacts during the construction phase are:

STANDARD TEMPLATE & FORM-1 FOR KODIDRA LIMESTONE MINE AREA= 4.70 HECT. PROPOSED PRODUCTION: - 28,000 TPA OF LIMESTONE PROJECT COST: - 17.

Hind Energy & Coal Beneficiation (India) Ltd.

For PROPOSED IT PARK. By M/s.Balewadi Tech Park Pvt.Ltd. Submitted to State Environment Expert Appraisal Committee III, Maharashtra

*** Dated: May 2,2014

3 SCOPING 3.1 DEVELOPMENT OF SCOPING PROCESS Need for Scoping

Sandipbhai Shankarbhai Patel

SRI K. RAVI SHANKAR SURVEY NO.100, ODULAPALLI VILLAGE, TALPULA MANDAL, ANANTHAPURAMU DISTRICT, ANDHRA PRADESH

PRE-FEASIBILITY REPORT

Environmental Guideline on Stone crushing plant set up temporarily for the purpose of a project by a public department

Jayendrasinh Bharatsinh Jadeja

M/s Hind Energy & Coal Beneficiation Pvt. Ltd. is presently operating a 2 x 1.2 MTPA

Hind Energy & Coal Beneficiation (India) Ltd.

APPENDIX VIII. Form 1 M APPLICATION FOR MINING OF MINOR MINERALS UNDER CATEGORY B2 FOR LESS THAN AND EQUAL TO FIVE HECTARE

FORM - I-A CHECK LIST OF ENVIRONMENTAL IMPACTS

Submitted to. Expert Appraisal Committee (EAC), Mumbai Maharashtra. May 2017

FORM V ENVIRONMENTAL STATEMENT REPORT FOR THE FINANCIAL YEAR M/s Halki Lime Stone Mine (Unit: J. K. Cement Limited) PART A

APPLICATION FOR ENVIRONMENTAL CLEARANCE

Environmental Impact Assessment

SCHEDULE. FORM A (Rule 3(1)) THE CERTIFICATE OF ENVIRONMENTAL CLEARANCE RULES 2001 APPLICATION FOR A CERTIFICATE OF ENVIRONMENTAL CLEARANCE

FORM 1 & 1 A. Proposed Residential Project. Sr. No. 25/2/2A Kondhwa Bk. Tal. Haveli Dist. Pune. M/s. ANISHKA DEVELOPERS PVT. LTD.

PROJECT FEASIBILITY REPORT

WATER CODE TITLE 2. WATER ADMINISTRATION SUBTITLE D. WATER QUALITY CONTROL CHAPTER 26. WATER QUALITY CONTROL SUBCHAPTER A. ADMINISTRATIVE PROVISIONS

Proposed Office Building at Plot no: 11 & 12 Sector 127, Noida, U.P.

Rajasthan State Pollution Control Board

(1) Bridge, Road and Railway (Adaptation Project) (2) Bridge, Road and Railway (BAU Development with Adaptation Options)

Dilipbhai D. Patel. BLOCK NO. 43, F.P. NO. 45,O.P NO. 40 T.P.S. No- 17 (PUNA), Ta: SURAT CITY, DIST: SURAT

GUIDE TO THE DEVELOPMENT OF A MINING AND RECLAMATION PLAN IN NEW BRUNSWICK

CHECK LIST OF DOCUMENTS / OTHER REQUISITES FOR OBTAINING VARIOUS CLEARANCES FROM THE STATE POLLUTION CONTROL BOARD, ODISHA.

FORM -1 CAPITAL CITY COMMERCIAL PROJECT. Plot No. 2B, Sector 94, Noida, District: Gautam Budh Nagar, Uttar Pradesh

Chemplast Sanmar Limited Marine Terminal Facility, Chitrapettai Village Cuddalore District, Tamil Nadu

Dust generation/ Air pollution. Noise and vibration. Water pollution. Drainage and sedimentation

PRE-FEASIBILITY REPORT. for

WATER CODE TITLE 2. WATER ADMINISTRATION SUBTITLE D. WATER QUALITY CONTROL CHAPTER 26. WATER QUALITY CONTROL SUBCHAPTER A. ADMINISTRATIVE PROVISIONS

WHS RISK REGISTER FOR THE DESIGN OF BUILDINGS AND STRUCTURES

PROPOSED TERM OF REFERENCE

.in Dated 9th August, Sharma ;

Consultant: M/s. SADEKAR ENVIRO ENGINEERS PVT. LTD.

Executive Summary 1. 1 Project Background 6

Environmental Information Worksheet

EXECUTIVE SUMMARY 1.0 PROJECT DESCRIPTION 1.1 INTRODUCTION

Viridor Waste Management. Proposed Development of an In-Vessel Composting Facility. Land at Exide Batteries, Salford Road, Bolton

9.3.9 Industry uses code

F.P.No.52, S.No.53/B, 54/2/B, D.T.P.S.No.80, Village: Bhat, Dist: Gandhinagar.

HINAUTI LIMESTONE MINE Mine Lease area ha. (A UNIT OF JAIPRAKASH ASSOCIATES LIMITED) JAYPEE VIHAR, SIDHI (M.P)

Existing vegetation with each tree detail like species, girth, canopy etc. Contours with levels Natural features like water body, stream etc.

Environment & Conservation Introduction

V.S LIGNITE POWER Pvt. Ltd AT VILLAGE-GURHA, KOLAYAT, BIKANER, RAJASTHAN

Bangalore Development Authority T. Chowdaiah Road Kumara Park West Bangalore

4. The ambient air quality monitoring stations We are monitoring the ambient air quality

Appendix A: Project Characteristics

HALF YEARLY COMPLIANCE REPORT OF ENVIRONMENTAL CLEARANCE CONDITIONS

LIST OF CONDITIONS FORPROPOSED SMART CITY AT TRIANON BY HERMES PROPERTIES LTD [ENV/DOE/EIA/1695]

CHAPTER 3 POLICY, LEGAL AND ADMINISTRATIVE FRAMEWORK

Summary of Preparatory Study

TERMS OF REFERENCE. Identification of the sources of pollution and assessing the impacts on the environment due to proposed project if any;

Subject: Environmental and CRZ clearance for expansion of Karaikal Port (Phase-II) at Puducherry by MIs. Karaikal Port Pvt. Ltd. - Reg.

PART A. M/s Shree Cement Ltd, (Grinding Unit) village - Udepur, Tehsil- Suratgarh, District -Shri Ganganagar, Rajasthan

Environmental Management Plan (EMP)

18 Cumulative Impacts and Interaction of Effects

Project Proponent: M/S FAITH BUILDTECH PVT. LTD. EIA Consultant:

9.2 Definitions. The following terms are defined, for purposes of Section 9, as follows:

WE EEN Wizard of the Environment: the Enterprise Europe Network. Eurosportello del Veneto Via delle Industrie 19/C Venezia

CAMLICA ELEKTRIK URETIM A.S. CAMLICA III RESERVOIR AND HYDROELECTRIC POWER PLANT (HEPP) ENVIRONMENTAL MANAGEMENT PLAN (EMP)

FORM-1 A (only for construction projects listed under item 8 of the Schedule) CHECK LIST OF ENVIRONMENTAL IMPACTS

PRE-FEASIBILITY REPORT

MIDC, Nagpur Expansion of Existing Butibori Industrial Area (BIA Phase II) - Form-1

12 Oct Virama Karya presentation on South Coast Highway. Therefore require a new route expressway

TABLE OF CONTENTS. Title page Table of contents List of tables List of figures Non- technical summary

CMPDI. 4.6 Mine Closure Plan

Environmental Guideline for Saskatchewan Asphalt Plants

JAYPEE NIGRIE SUPER THERMAL POWER PROJECT

Introduction. They can help ensure that all key issues and elements have been considered; They help ensure that the review process is systematic; and

Naubasta Lime Stone Mine ML - I Jaypee Rewa Plant Jaiprakash Associates Limited

Environmental and Social Considerations in Detailed Planning Survey. (Technical Cooperation for Development Planning)

Environmental Assessment Matrix

Yes: Y No: N (a) (b) (c) (d) (a) (a) (b) (c) (d) (e)

Guidance on use of Disposal and Recovery Codes (Waste Management Act, 1996 as amended)

North East Roofing Pvt. Ltd. Expansion of Asbestos Cement Sheets & Accessories Manufacturing Unit (50,000 TPA to 70,000 TPA)

ENVIRONMENTAL GUIDELINES FOR PREPARATION OF AN ENVIRONMENT MANAGEMENT PLAN. Environment Protection Authority, ACT May 2009

GENERAL SPECIFICATION FOR THE MANAGEMENT OF EXCESS MATERIALS

Expansion in. Environment Clearance Application. Shopping Mall. Mall of India

Activity Aspects Impacts/ Nuisances Construction phase - Site preparation. - Generation of excavated soil, debris and construction wastes

MARINE POLLUTION DEGRADATION MITIGATION MANAGEMENT IS ESSENTIAL FOR IMPROVING MARINE ENVIRONMENT

FINDING OF NO SIGNIFICANT IMPACT OWL CREEK GRAVEL PIT EXPANSION U.S. FOREST SERVICE

Prepared by: Vardan Environet, Gurgaon

Transcription:

[Vide CRZ tification dated 6 th January, 2011] FORM I For PROPOSED 5 STAR RESORT PROJECT VIVANTA BY TAJ AT HAVELOCK At (Plot : 149/1, 149/3, 150/3/2, 150/3/3, 150/3/4) Village - Radha Nagar, Gram Panchyat - Govinda Nagar, Havelock Island, Tehsil - Port Blair Dist. Andaman, A&N Islands Proposed by The Indian Hotel Company Limited Prepared by GREEN CIRCLE, INC. Integrated HSEQR Consulting Engineers, Scientists & Trainers (ISO 9001:2008, 14001: 2004 & OHSAS 18001: 2007 Certified organization & Recognized by Ministry of Environment & Forest, New Delhi under EPA 1986 & GPCB approved Environment Auditor Schedule II & provisionally accredited by QCI-NABET on 89 th AC meeting dated 17.10.2012) Regd. Office: Green Empire (Anupushpam), Above Axis bank, Near Yash Complex, Gotri Road, Vadodara - 390021 (Gujarat) Tel. +91-265-2371269; Fax: +91-265-2371269 E-Mail: info@greencircleinc.com, gccipl@rediffmail.com www.greencircleinc.com January, 2013

Form-I for seeking clearance for project attracting CRZ notification Basic information: Name of the Project: : Vivanta by Taj at Havelock Location or site alternatives Under consideration: Size of the project (in terms of total area) : Radha Nagar Beach, Village Radhanagar, Havelock Island, Andaman (11 0 59 8.76 N and 92 0 57 19.00 E : Total Plot Area: 1,82,834.741 sq.m Proposed Built-up area (FSI): 15796.57 sq.m n FSI area: 3175 sq.m Total Construction Built-up area (FSI+n FSI): 18972 sq.m CRZ classification of the area : ICRZ- III Expected cost of the project : 80 Crores Contact Information : The Indian Hotels Company Ltd., Oxford House 15 / 17, NF Road, Apollo Bunder, Mumbai-400001, India. (II) Activity 1. Construction, operation or decommissioning of the Project involving actions, which will cause physical changes in the locality (topography, land use, changes in water bodies, and the like) S.. Information/Checklist confirmation 1.1 Permanent or temporary change in land use, land cover or topography including increase in intensity of land use (with respect to local land use plan) / Details thereof (with approximate quantities /rates, wherever possible) with source of information data The proposed site is underdeveloped and covered with bushes and trees mostly areca nut. Permanent land use change is envisaged for 18972 sq. m area on which villas are to be constructed. Temporary land use change will be there only in construction phase which will be brought to almost original form after construction is completed. 1

Master Layout plan enclosed as Annexure III. 1.2 Details of CRZ classification as per the approved Coastal Zone Management Plan? 1.3 Whether located in CRZ-I area? 1.4 The distance from the CRZ-I areas. 1.5 Whether located within the hazard zone as mapped by Ministry of Environment and Forests/National Disaster Management Authority? 1.6 Whether the area is prone to cyclone, tsunami, tidal surge, subduction, earthquake etc.? 1.7 Whether the area is prone for saltwater ingress? 1.8 Clearance of existing land, vegetation and buildings? As per CRZ 2011 tification, and subsequent letter from MoEF in July 2012 for consideration of Havelock island under ICRZ. The proposed project comes under ICRZ III as per CRZ map of Havelock Island. CRZ map enclosed as Annexure - I Project comes under ICRZ - III. 50 m from HTL towards sea. Effects of Cyclone & tidal Surge may occur at site as it is near to sea. At the onset of monsoon, the islands are affected but usually not seriously by the cyclonic weather of Bay of Bengal. On an average 2-3 tropical cyclones form every year, of which one or two could be severe. Andaman & Nicobar islands are classified as Moderate Damage Risk Zone A. The basic wind speeds are applicable to 10 meters heights above the mean ground level in an open terrain cyclone seldom parts over the islands, though most of them form in Andaman sea. Area may be prone for saltwater ingress, as site is very close to sea (approx. 200-300 m) Few areca nut trees and other shrubs will be cut during site preparation. However economically important trees will be preserved and or replanted. 1.9 Creation of new land uses? Existing land will be used for construction of 5 star resort (villas) 2

1.10 Pre-construction investigations e.g. bore hole, soil testing? Soil samples were collected and analyzed from different locations at site and the results have been found satisfactory. Geotechnical study has also been carried out at the site and found to be satisfactory. Soil Analysis report enclosed as Annexure - II 1.11 Construction works? This project involves construction of a 5 star resort. It is proposed to begin commence operations with 50 keys, 16 public buildings and 18 staff accommodation buildings and raise the inventory to 100 keys in Phase II. 1.12 Demolition works? This is a new project 1.13 Temporary sites used for construction works or housing of construction workers? 1.14 Above ground buildings, structures or earthworks including linear structures, cut and fill or excavations 1.15 Underground works including mining or tunneling? Temporary shelter and sanitation facilities for construction workers are not required as majority of the labour will be hired from nearby villages. 50 keys (or rooms) will be constructed in Ist phase and rest 50 keys (or rooms) in 2 nd phase of the project. Construction will be done as per local town and country planning and not exceeding height of 9 meters with two floors (Ground and first floor) Sewage Treatment Plant (STP) and Rain Water Harvesting Tanks will be constructed underground. Master layout Plan is enclosed as Annexure-III. 1.16 Reclamation works? t applicable 1.17 Dredging/reclamation/land filling/disposal of dredged material etc.? t applicable 1.18 Offshore structures? Floating jetty, arrival pavilion and dive centre is proposed as offshore structure. 1.19 Production and manufacturing processes? NA 1.20 Facilities for storage of goods or materials? Raw materials required for construction shall be stored at the camp-sites during construction phase. 3

1.21 Facilities for treatment or disposal of solid waste or liquid effluents? 1.22 Facilities for long term housing of operational workers? 1.23 New road, rail or sea traffic during construction or operation? 1.24 New road, rail, air waterborne or other transport infrastructure including new or altered routes and stations, ports, airports etc? Temporary septic tanks will be made for disposal of sewage during construction phase. During Operation Phase, generated sewage will be treated in STP and treated water will be reused for land scape gardening and flushing toilets, Aircondition & DG cooling towers. Staff quarters will be provided on the project site. There will be increment in sea traffic during construction phase, as this is the only route to site. Approach road along with a bridge over the nalah in the project site will be constructed from the existing road. Master layout Plan enclosed as Annexure- III. 1.25 Closure or diversion of existing transport routes or infrastructure leading to changes in traffic movements? 1.26 New or diverted transmission lines or pipelines? 1.27 Impoundment, damming, culverting, realignment or other changes to the hydrology of watercourses or aquifers? There will not be any closure or diversion of existing transportation routes. t Applicable 1.28 Stream and river crossings? Fresh water stream is passing through one side the plot; however there will be no alteration in channel diversion or quality of water. 1.29 Abstraction or transfers of water from ground or surface waters? 1.30 Changes in water bodies or the land surface affecting drainage or run-off? NA Ground water will be utilized through Bore wells. Rain water harvesting will also be done to meet fresh water requirement. The existing drainage pattern may not change due to construction & operation activities, but there will be minor change as artificial ponds & water body will be created 4

1.31 Transport of personnel or materials for construction, operation or decommissioning? There will be transport of materials and personnel during both construction phase and operation phase. 1.32 Long-term dismantling or decommissioning or restoration works? 1.33 Ongoing activity during decommissioning which could have an impact on the environment? 1.34 Influx of people to an area in either temporarily or permanently? Construction phase: 300 persons (approx). Operation phase: 250 persons (approx). t Applicable There will be no impact on environment. Influx of people in construction phase: 300 persons (approx) temporarily. There will be influx of tourist during operation phase of the project 1.35 Introduction of alien species? There will be no introduction of alien species. 1.36 Loss of native species or genetic diversity? Few areca nut trees will be cut during site preparation and rest of the trees will either be preserved and or replanted. Native species will be protected. 1.37 Any other actions? other actions/activities envisaged 2. Use of Natural resources for construction or operation of the Project (such as land, water, materials or energy, especially any resources which are non-renewable or in short supply): S.. Information/checklist confirmation 2.1 Land especially undeveloped or agricultural land (ha) / Details thereof (with approximate quantities /rates, wherever possible) with source of information data 1,82,834.741 sq.m revenue land is undeveloped land allotted by ANIIDCO for resort project to IHCL. 2.2 Water (expected source & Source: Rain water and Ground 5

competing users) unit: KLD water. Total water requirement in construction phase: 60 KLD Total water requirement in operational phase: 480 KLD Domestic requirement: 250 KLD Swimming pool: 20 KLD Flushing requirement: 36 KLD Landscaping requirement: 114 KLD Air condition: 40 KLD D.G cooling tower: 20 KLD Water balance is enclosed as Annexure- IV 2.3 Minerals (MT) t Applicable 2.4 Construction material stone, aggregates, sand/soil (expected source MT) 2.5 Forests and timber (source MT) 2.6 Energy including electricity and fuels (source, competing users) Unit: fuel (MT), energy (MW) 2.7 Any other natural resources (use appropriate standard units) Construction materials such as stone, cement, sand, bricks, sheds, marble, paints, tiles, electrical ware, sanitary ware, glass, timber etc. will be taken up from authorized suppliers. Timbers will be procured from authorized vendor for construction of doors and windows. Electricity Source : DG set Construction: 100 KVA (1 no.) Operation: Power requirement: 720KW / 900 KVA Demand load: 720KW / 900 KVA Connected load: 985 KW/1230 KVA Backup power source & quantity: 100 % by diesel generators. t applicable 3. Use, storage, transport, handling or production of substances or materials, which could be harmful to human health or the environment or raise concerns about actual or perceived risks to human health. S.. Information/Checklist confirmation 3.1 Use of substances or materials, which are / Details thereof (with approximate quantities/rates, wherever possible) with source of information data Since this is a resort project, no hazardous chemical will be 6

hazardous (as per MSIHC rules) to human health or the environment (flora, fauna, and water supplies) generated nor used except HSD for power generation in DG sets. The spent oil will be carefully stored in HDPE drums under isolated storage, and periodically sold to authorized recyclers. All precautions will be taken to avoid spillage from the storage. 3.2 Changes in occurrence of disease or affect disease vectors (e.g. insect or water borne diseases) 3.3 Affect the welfare of people e.g. by changing living conditions? 3.4 Vulnerable groups of people who could be affected by the project e.g. hospital patients, children, the elderly etc., 3.5 Any other causes, that would affect local communities, fisher folk, their livelihood, dwelling units of traditional local communities etc. There will be no occurrence of any disease due to the proposed project. There will be positive impact due to proposed project. Direct or indirect employment opportunities for the local people will increase. The living condition and welfare of the people will improve. Tourism sector will get a boost. Since this is resort project, no significant impact on any vulnerable groups is envisaged due to construction and operation. t Applicable 4. Production of solid wastes during construction or operation or decommissioning (MT/month) S.. Information/Checklist confirmation 4.1 Spoil, overburden or mine wastes 4.2 Municipal waste (domestic and or commercial / Details thereof (with approximate quantities/rates, wherever possible) with source of information data t Applicable During construction phase, domestic Solid wastes generated will be 135 kg 7

wastes) /day approx which shall be properly collected, segregated and disposed off suitably as per norms. The construction debris shall be used for leveling and base course preparation. 4.3 Hazardous wastes (as per Hazardous Waste Management Rules) Approximately 63 Kg/day of solid waste will be generated during 4.4 Other industrial process wastes 4.5 Surplus product t Applicable operation phase of which biodegradable waste shall be 38 kg/day and non-biodegradable waste 25 kg/day. Biodegradable waste shall be treated in OWP and non biodegradable waste will be delivered to authorized vendors for further disposal/ Reused Spent oil from DG sets, Discarded oil, grease & paint containers (Category 5.1 and 33.3 of HW respectively (MH Trans boundary Movement) Rules 2008 t Applicable 4.6 Sewage sludge or other sludge from effluent treatment 4.7 Construction or demolition wastes 4.8 Redundant machinery or equipment 4.9 Contaminated soils or other materials The sewage generated will be treated through STP. Sludge of 0.63 KLD will be generated shall be handed over to authorized vendor. Soil excavation: 4500 m 3 shall be produced during Construction phase which will be used for back filling and leveling. demolition involved as this is a new project. Since this a resort project, redundant machinery is not applicable. The site will be cleared after construction is completed. There will be no contamination of soil as sewage will be treated in STP and solid waste will be segregated into biodegradable and non 8

biodegradable. Wet waste will be treated in OWP and dry waste shall be handed over to authorized vendors. 4.10 Agricultural wastes There will be no agricultural waste in this proposed project. 4.11 Other solid wastes t Applicable 5. Release of pollutants or any hazardous, toxic or noxious substances to air (Kg/hr) S.. Information/Checklist confirmation 5.1 Emissions from combustion of fossil fuels from stationary or mobile sources. 5.2 Emissions from production processes 5.3 Emissions from materials handling including storage or transport 5.4 Emissions from construction activities including plant and equipment / Details thereof (with approximate quantities/rates, wherever possible) with source of information data During Construction phase emissions shall be from use of Construction machineries, vehicles and DG Sets. During Operation phase emission will be from DG sets only. processes involving production. Dusting may occur during loading and unloading of cement bags, sand etc. however suitable mitigation measures like sprinkling of water etc will be done to control dusting to check air pollution. During Construction phase emission shall be from use of Construction machineries, vehicles and DG Sets only from stationary sources and fugitive emissions during handling. 9

5.5 Dust or odours from handling of materials including construction materials, sewage and waste Dusting will occur during transportation and handling of construction materials however suitable mitigation measures like sprinkling of water etc. will be done to control dusting. odour problem will occur due to solid waste since proper segregation and processing will be done using OWP. 5.6 Emissions from incineration of waste 5.7 Emissions from burning of waste in open air (e.g. slash materials, construction debris) 5.8 Emissions from any other sources t applicable as incineration will not be involved. burning of debris shall be allowed. t envisaged 6. Generation of ise and Vibration, and Emissions of Light and Heat: S.. Information/Checklist confirmation 6.1 From operation of equipment e.g. engines, ventilation plant, crushers / Details thereof (with approximate quantities/rates, wherever possible) with source of information data with source of information data. There will be slight increase in noise during construction phase due to operation of machineries however it will be mitigated through effective engineering and administrative measures. ise expected during operation of will be from DG set only but shall be below 75 db (A) at 1m from acoustic enclosure. Further proper acoustic measures shall be provided along with DG sets to reduce the noise and 10

vibrations. 6.2 From industrial or similar processes industrial or similar processes involved. 6.3 From construction or demolition Peak decibel level during construction phase shall be between 75 to 85 db (A), which may cause short term impact limited to the construction site only. demolition involved since this is a new project. 6.4 From blasting or piling blasting or piling involved. 6.5 From construction or operational traffic There will be marginal noise generation from vehicle movement. However, the noise levels from traffic will be less than 70 db (A). Further suitable mitigation measures shall be proposed to reduce the noise generated as a result of construction or operation traffic. 6.6 From lighting or cooling t Applicable systems 6.7 From any other sources t Applicable 7. Risks of contamination of land or water from releases of pollutants into the ground or into sewers, surface waters, groundwater, coastal waters or the sea: S.. Information/Checklist confirmation 7.1 From handling, storage, use or spillage of hazardous materials / Details thereof (with approximate quantities/rates, wherever possible) with source of information data The collection and disposal of hazardous waste will be as per hazardous waste (Management & Handling) amendment rule 2008 and adequate precautions will be taken to avoid adverse impact on land environment. Hazardous material 11

7.2 From discharge of sewage or other effluents to water or the land (expected mode and place of discharge) 7.3 By deposition of pollutants emitted to air into the land or into water like used oil, discarded containers will be handed over to authorized vendors. There will be no discharge of waste water onto land or water bodies as sewage will be treated in STP. Treated sewage will be used for gardening and flushing. Flue gas emissions from DG set will be within the prescribed limits of CPCB. Adequate stack height shall be provided for dispersion of the pollutants/ emissions. Water will be sprayed to mitigate dust pollution. 7.4 From any other sources t applicable 7.5 Is there a risk of long term build up of pollutants in the environment from these sources? The source of emissions is from construction machineries and DG set during construction phase which will be of short term and temporary. The source emissions id from only DG set during operation phase which shall be maintained as per CPCB standard. Thus there is no risk of long term build up of pollutants in the environment. 8. Risk of accidents during construction or operation of the Project, which could affect human health or the environment S.. Information/Checklist confirmation 8.1 From explosions, spillages, fires etc from storage, handling, use or production of hazardous substances / Details thereof (with approximate quantities/rates, wherever possible) with source of information data Fire protection measures & installations (passive and active) would include Fire Extinguishers, Hose reel, Fire Hydrant, Sand Buckets, Fire Alarm & fire water 12

tank will be installed. Emergency numbers will be displayed on the board. Do s and don ts will be displayed on board to minimize risk. Fire protection plan and evacuation alarm will be prepared. 8.2 From any other causes t applicable 8.3 Could the project be affected by natural disasters causing environmental damage (e.g., floods, earthquakes, landslides, cloud burst etc)? Flooding may occur in proximity at sea and worst case like tsunami. However adequate precautions will be taken for prevention and control of losses due to natural disasters. All of the Andaman & Nicobar Islands lie in Zone V. The entire island chain is also susceptible to tsunamis both from large local quakes and also from massive distant shocks. 9. Factors which should be considered (such as consequential development) which could lead to environmental effects or the potential for cumulative impacts with other existing or planned activities in the locality S.. Information/Checklist confirmation 9.1 Lead to development of supporting. Facilities, ancillary development or development stimulated by the project which could have impact on the environment e.g.: Supporting infrastructure (roads, power, supply, waste or waste water treatment, etc.) housing development extractive industries supply industries other. 9.2 Lead to after-use of the site, which could have an / Details thereof (with approximate quantities/rates, wherever possible) with source of information data Economic growth is envisaged as there will be more influx of tourists to Havelock island. This in turn will result in socio-economic development of the region. impact envisaged. 13

impact on the environment 9.3 Set a precedent for later developments The project shall set precedents for further development. 9.4 Have cumulative effects due to proximity to other existing or planned projects with similar effects III. Environmental Sensitivity cumulative effects due to other development (if any) envisaged. S.. Areas 1 Areas protected under international conventions, national or local legislation for their ecological, landscape, cultural or other related value 2 Areas which are important or sensitive for ecological reasons - Wetlands, watercourses or other water bodies, coastal zone, biospheres, mountains, forests 3 Areas used by protected, important or sensitive species of flora or fauna for breeding, nesting, foraging, resting, over wintering, migration 4 Inland, coastal, marine or underground waters Name/ Identity Aerial distance (within 15 km.) Proposed project location boundary Rani Jhansi Marine National Park at John Lawrance Island is located at a distance of more than 10 km from the proposed project site. This project comes under ICRZ III. The LTL towards sea at 200-300 meter approx from the project site and reserve forest is present within 300 meter approx. from the project site. One fresh water nalah is passing through the proposed site. Rani Jhansi Marine National Park at John Lawrence Island is located at a distance of more than 10 km from the proposed project site. This project comes under ICRZ - III 5 State, National boundaries state /national boundaries within 15 km. 6 Routes or facilities used by the public for access to recreation or other tourist, Public access is by means of road from Jetty to Radhanagar Beach, which is a tourist spot. pilgrim areas 7 Defence installations t present within 15 km 8 Densely populated or built-up t present area 9 Areas occupied by sensitive Primary Health Centre, Schools, 14

ANNEXURE I CRZ Map of Havelock Island

ANNEXURE I Landuse map and statistics of Havelock Island in 7 km radius around project site Sr.. Description Area in HA 1 AGRICULTURE 1211.65 2 BEACH 26.71 3 BUILT UP 76.23 4 CREEK 72.27 5 FOREST 5119.50 6 JETTY 0.48 7 MANGROVE 993.70 8 MARSHY 17.73 LAND 9 PLANTATION 105.87 10 SHEET ROCK 234.49 11 WATER BODY 2.94

ANNEXURE II Soil Investigation Report CHEMICAL ANALYSIS ON SOIL PROJECT : Soil Investigation of proposed TAJ EXOTICA at Havelock Island, Andaman & Nicobar Islands. Location : Port Blair Type of Sample : Soil GEO FOUNDATIONS & STRUCTURES PVT. LTD Sample Quantity : 1Kg Number of Sample : 1 BH. Depth m PH @ 25 C CHLORIDES SULPHATES as SO 4 ORGANIC MATTER BH-3 -- 8.72 1.120 g/kg 0.940 g/kg 1.8 %

ANNEXURE III Master Layout Plan

ANNEXURE - IV Water Balance Chart Central Reservoir supply 270 KLD aa Domestic use 250 KLD Swimming pool 20 KLD 233 KLD to sewage treatment plant Treated effluent available @90 % 210 KLD Sludge & Evaportion loss 23 KLD Toilets flushing 36 KLD Available for landscape purpose 114 KLD Air Condition 40 KLD D.G cooling Tower 20 KLD Central Utility Water Supply: 270 KLD Recycled water requirement: 210 KLD