MANAGING UNDERGROUND RISKS: GEOTECHNICAL BASELINE REPORTS

Similar documents
GBR Fundamentals. Past Practices and Lessons Learned. Seminar on Geotechnical Baseline Reports. October 5, 2013

GEOTECHNICAL BASELINE REPORTS APPLYING THE GUIDELINES TO MICROTUNNELING

RISK MANAGEMENT. Harald Wagner PhD, PE

SEATTLE S BRIGHTWATER UNDERGROUND CONVEYANCE SYSTEM TUNNELING & UNDERGROUND CONSTRUCTION

April 7, Webster Street Sub-Surface Stormwater Storage System Bid No Bid Date: 4/13/17 ADDENDUM NO 1

Optimization of Supports in a Road Tunnel through Conglomerate during Construction

Soil conditioning for EPB tunnelling in choesionless soil, clay and rock masses and backfilling in shield tunnelling

Risk Evolution from Planning to Construction on the LA Metro Crenshaw/LAX Light Rail Transit Project

Experts in tunneling with Tunnel Boring Machines

King County Uses Trenchless Methods to Construct a Large Siphon Under Seattle s Ship Canal

Prof. Eng. Daniele PEILA

August 15, 2006 (Revised) July 3, 2006 Project No A

Wastewater Capital Projects Management Standard Construction Specification

Project Owners, especially in the public sector, are. Design-Build and Public-Private Partnerships: Risk Allocation of Subsurface Conditions

TBM Selection and Specification

Subsurface Investigations PDCA Professor s Driven Pile Institute. Loren R. Anderson Utah State University June 25, 2015

Injection Wells for Liquid-Waste Disposal. Long-term reliability and environmental protection

File No Supplemental November Geotechnical and Environmental Consulting Engineers

VERIFICATION OF GEOTECHNICAL GROUTING- STRATEGIES AND PLANNING. Michael J. Byle, D.GE, F. ASCE

Interpretation of Danish Chalk Parameters Applicable to Foundation Design

APPENDIX A DEFINITION OF PROFESSIONAL ENGINEERING CONSULTING SERVICES

SCG INTERNATIONAL TRINIDAD AND TOBAGO LIMITED COUVA CHILDREN S HOSPITAL

SITE INVESTIGATION. Foundation Engineering

Ardaman & Associates, Inc. Geotechnical, Environmental and Materials Consultants

Remote Monitoring of Gauge Cutter Wear in Pressurized Face Tunneling

Site Location. Figure 1: Site Location Map US-24 and I-275 Interchange Ash Township, Monroe County, Michigan

CONSTRUCTION SPECIFICATION FOR PIPELINE AND UTILITY INSTALLATION IN SOIL BY HORIZONTAL DIRECTIONAL DRILLING

Contracting Methods and Risk Management

Temporary Structures. Excavations and Excavation Supports

U.S. Army Corps of Engineers Jacksonville District Sediment Quality Control/Quality Assurance Plan For Maintenance Dredging with Beach Placement

Tunnelling and Underground Space Technology

Liquid Waste Coordination Committee

The Technical and Contractual Matters of Bored Piling Works. By Wallace Yeung Vibro (H.K.) Ltd.

Assessment of Tunnel Stability with Geotechnical Monitoring

Solutions for tunneling and mining TBM. Expanding Horizons Underground

I. Request for Proposal (RFP) submission REMAINS as June 26, 2017 at 5:00 PM (per preceding Addendum #1).

GEOTECHNICAL INVESTIGATION I-15 SIGN BRIDGES LAS VEGAS EA JANUARY

Ground Improvement. Martin G. Taube, P.E., P.G. February 4, 2003

Guidelines on Contractual Aspects. ITA - Working Group N 19 Conventional Tunnelling

Pipe Jacking/Microtunnelling. Dr. Mark Knight. Centre for Advancement of Trenchless Technologies (CATT) University of Waterloo.

Geotechnical Engineering Report

Estimating and Reporting of

BLEINC. August 17, Black & Veatch Corporation 201 Brookfield Parkway, Suite 150 Greenville, SC 29607

GEOTECHNICAL REPORT B-1942

Analysis of the EPB-TBM Excavation Parameters Used in a Tunnel Construction in Istanbul

Geotechnical Engineering Report

ON THE BEHAVIOR OF A STUCK CURVED PIPE JACKING

Horizontal Geotechnical Investigations for Tunneling

Soil Conditioning with Artificial Soil and Foam in EPB-Tunneling

Partial Factors of Safety

Hudson River Tunnels, Mega Projects, and Risk A Designer s Perspective

Electrical Conductivity & Hydraulic Profiling. The Combining of Two Subsurface Investigation Methods (With More to Come)

Fracking Safety & Economics November 9, 2017 America 1 st Energy Conference, Houston Tx.

GEOTECHNICAL INVESTIGATION MDACC GUHN ROAD FLOOD MITIGATION PROJECT 5610 GUHN ROAD HOUSTON, TEXAS REPORT NO

PARSONS BRINCKERHOFF GENERAL GUIDELINES FOR DESIGN AND CONSTRUCTION OF CONCRETE DIAPHRAGM (SLURRY) WALLS. DECEMBER 2008 Revision 0

Design Guideline for Gravity Systems in Soil Type 1. January 2009

Study of the Permeability of Foam Conditioned Soils with Laboratory Tests

Consultant Specifications for Subsurface Investigation & Geotechnical Analysis and Design Recommendations

SEMINAR. Introduction to Continuous Flight Auger (CFA) piling Thursday 21/8/2013. Facilitator: Martin Larisch

Strata Energy. A Design-Build Success Story

Earth Mechanics, Inc. Geotechnical & Earthquake Engineering

SOURCES OF WATER SUPPLY GROUND WATER HYDRAULICS

Trenchless Technology

GEOTEK ENGINEERING & TESTING SERVICES, INC. 909 East 50 th Street North Sioux Falls, South Dakota Phone Fax

GEOTECHNICAL STUDY PROPOSED CONCRETE ROADWAY TIKI ISLAND COMMUNITY GALVESTON COUNTY, TEXAS PROJECT NO E

Implementation of this Special Provision requires a complete understanding of the following documents:

Challenges in Design and Construction of Deep Excavation With Case Studies - KVMRT in KL Limestone

Construction Family of Documents

GeoEng2000 An International Conference on Geotechnical & Geological Engineering

Case study on a deep excavation in Baku: Flame Towers project earth retaining system

Pipejacking Tunnel Boring Machines TBMs. Michael Frenke, LOVAT Inc.

CONSTRUCTION OF TWO MICROTUNNEL ACCESS SHAFTS USING THE CUTTER SOIL MIX (CSM) METHOD IN THE SAN JOAQUIN DELTA, CALIFORNIA

Water Well Decommissioning Guidelines

INDEX FOR SPECIFICATIONS FOR JACKING CULVERTS THROUGH EMBANKMENTS SCOPE... 2

Typical Subsurface Profile. November 28, 2016

Rock Tunnel Engineering INTRODUCTION. Tunnel a hole in the ground to provide for desired movement or as mobility channel.

An Interactive Case Study of a Differing Site Condition. Prepared by: William B. Dobbs MWH

CONSTRUCTION SPECIFICATION FOR PIPELINE AND UTILITY INSTALLATION IN SOIL AND ROCK BY HORIZONTAL DIRECTIONAL DRILLING (HDD)

GeoConstructability. An Owner s Guide to Obtaining Essential Geotechnical Information for Construction

Stabilization of Running Granular Soils in TBM Alignment with Sodium Silicate Grout

SAMPLE SPECIFICATION for CROSSHOLE SONIC LOGGING (CSL) September 2015

Pipe Jacking Association An introduction to pipe jacking and microtunnelling

PAUL ZICK, PE NORTH SHORE CONSTRUCTORS JV

Field and Equipment Problems and Recovery

Effective Stress Design For Floodwalls on Deep Foundations

Ground Improvement. A Discussion on Dynamic Compaction. Chris Woods, P.E., D.GE., LEED AP BD+C Vice-President

Design and Operation of Landfills

Foundation/Site Work Code Requirements

2

CROSSRAIL INFORMATION PAPER D8 TUNNEL CONSTRUCTON METHODOLOGY


DISPERSIVE SOILS. Dispersive soils are those in which the clay content has a high percentage of sodium.

1913 Lausanne, Switzerland

Instrumentation and Data Management for the Zurich Zimmerberg Railway Tunnel Construction Daniel Naterop Solexperts Ltd.

EJCDC Contract Documents for America s Infrastructure Buy online at

The Line 3 of the Metro of Cairo

CHALLENGES AND SUCCESSES OF OPEN SHIELD PIPE JACKING CONSTRUCTION IN A CONGESTED NEIGHBORHOOD

Cross Borehole Electrical Resistivity Tomography (ERT) Measurements

Transcription:

MANAGING UNDERGROUND RISKS: GEOTECHNICAL BASELINE REPORTS Randall J. Essex, PE Executive Vice President Tunnels Practice Breakthroughs in Tunneling Short Course August 14-16, 2017 Embassy Suites - O Hare, Chicago

Topics Historical Perspective Geotechnical Data Report GBR Fundamentals Risk Sharing Philosophy Concept of Baselines Lessons Learned Future Developments

Historical Perspective 1970s: Construction claims spiraled, industry got a black eye 1974: US National Committee on Tunneling Technology 1974: Better Contracting for Underground Construction Should spend at least 1% and up to 3% of the construction value on exploration 1989-1991: Underground Technology Research Council (UTRC) 1989: Silver book Avoiding and Resolving Disputes in Underground Construction 1991: Maroon book Avoiding and Resolving Disputes in Construction Differing Site Conditions Clause Geotechnical Baseline Report Escrow Bid Documentation Dispute Review Board

Historical Perspective 1970s: Construction claims spiraled, industry got a black eye 1974: US National Committee on Tunneling Technology 1974: Better Contracting for Underground Construction Should spend at least 1% and up to 3% of the construction value on exploration 1989-1991: Underground Technology Research Council (UTRC) 1989: Silver book Avoiding and Resolving Disputes in Underground Construction 1991: Maroon book Avoiding and Resolving Disputes in Construction Differing Site Conditions Clause Geotechnical Baseline Report Escrow Bid Documentation Dispute Resolution Review Board Board

Historical Perspective (cont d) 1995: Construction Dispute Review Board Manual 1997: GBRs for Underground Construction (Yellow Book) 2007: GBRs for Construction (2nd Edition Gold Book) 20XX: GBRs for Construction (3 rd Edition)

Geotechnical Data Report

Geotechnical Data Report Geologic setting of the project site Geomorphology Hydrologic Tectonic Site exploration program Aerial mapping, geophysics, drilling methods Geotech and environmental Boring location plan Sampling procedures Sample preparation Sample storage Field and laboratory testing programs Tests performed Test procedures Results of the exploration and testing programs Boring logs Tabulated field and laboratory test results Results from past programs The GDR is included in the Contract 7

GBR Fundamentals Tunneling Facts of Life What is a GBR? How is it used?

8 Underground Facts of Life Tunnel projects are linear and can extend for miles Subsurface conditions can vary significantly across the site Subsurface conditions influence construction methods and cost Underground surprises = commercial risk Contractors do not accept risk, they price risk Owners seek the lowest cost of construction It s cheaper to anticipate risks than be surprised Contracts that anticipate risks result in fewer claims and lower costs 9

8 Underground Facts of Life We prepare a Geotechnical Baseline Report to Describe the anticipated subsurface conditions Subsurface and conditions how influence they construction methods and cost will influence the construction Tunnel projects are linear and can extend for miles Underground surprises = commercial risk Subsurface conditions can vary significantly across the site Describe how they influenced the design Identify the key subsurface risks on the project Describe how those risks are allocated between the contractor and the owner Contractors do not accept risk, they price risk Owners seek the lowest cost of construction Describe how conditions beyond the baselines will be addressed It s cheaper to anticipate risks than be surprised Contracts that anticipate risks result in fewer claims and lower costs 10

A GBR Is A Contract Document A set of realistic contractual assumptions regarding the anticipated subsurface conditions An aid to administering the Differing Site Conditions clause under the Contract A guidance document for bidding the project A means to help manage the construction The only set of binding interpretations in the Contract GBR takes precedence over the GDR 11

The GDR is A a compilation of data gathered during the site investigation(s) Contains factual information, no interpretation Is a Contract Document May be used to resolve a dispute if the GBR is silent on a matter or circumstance 13

Risk Sharing Philosophy Surface Vs Subsurface Construction Risk Sharing Vs Risk Shedding

Surface vs. Subsurface Construction Surface Works Complicated construction Simple constraints Can work-around delays Underground Repetitive construction Complicated constraints Linear = Limited Critical Path No work-arounds Risks and impacts are different 15

Risk Shedding vs. Risk Sharing Risk Sharing: Owner ultimately owns the ground Risks allocated to contractor for: Specified range of anticipated conditions Means and methods consistent with the anticipated conditions Workmanship Cost / Schedule Performance 16

Risk Sharing Goals Fairer basis for contracting Help avoid and resolve disputes Keep the lawyers out of our business 17

Concept of Baselines Baseline Philosophy Physical and Behavioral Baselines Design-Build and PPP

Baseline Philosophy Baselines describe anticipated conditions Baselines should be a realistic reflection of the available information Assume the baseline is a line in the sand Within the baselines Beyond the baselines Contractor s Risk Owner s Risk Can address conditions beyond the baselines with provisional payment terms 19

Physical and Behavioral Baselines Physical baselines properties and strength characteristics - independent of construction means and methods Behavioral baselines How the ground responds to excavation processes 21

Physical Baselines Soils Clays, silts, sands and gravels Strength, c/φ, K a unit weight, water content, grain size, Atterberg limits Abrasivity, stickiness potential Permeability (horizontal and vertical) Cobbles, boulders, obstructions Groundwater levels, artesian conditions Contaminated ground / groundwater Rocks Rock types - Sedimentary, Igneous, Metamorphic Strength - UCS, BTS, Point load, Punch penetration Mineralogy - Grain size, shape, interlock Boreability: DRI, CLI, Cerchar Abrasivity Stickiness potential (claystones beware of current vs future water contents) Rock Mass Defects - Joints, fractures, faults, shears, weathering, alteration Permeability, Gas, Contamination 22

Physical Baselines Other Considerations Baseline Representations Characteristics of ground types across project Percentage of ground types to be encountered At shaft locations By tunnel reach Ground conditions Mixtures of different strata Interlayered systems Soil over rock Soil mixtures Rock mixtures Conditions beyond excavation limits 23

Physical Baseline Representations Item Poor Better Best Geologic Profile Profile Information Data 24

Physical Baseline Representations Item Poor Better Best Geologic Profile None Profile Information None Data Tabulated results 25

Physical Baseline Representations Item Poor Better Best Geologic Profile None No stratum boundaries Profile Information None Stick logs Data Tabulated results Tabulated results with min, max, and average values 26

Physical Baseline Representations Item Poor Better Best Geologic Profile None No stratum boundaries Stratum boundaries Profile Information Data None Stick logs Soil logs with strength, plastic limits, water contents Rock logs with recovery, RQD, geophysics Tabulated results Tabulated results with min, max, and average values Histogram representation of data sets showing min, max, baseline values, and data set signature 27

Physical Baseline Representations Item Poor Better Best Geologic Profile None No stratum boundaries Stratum boundaries Profile Information Data None Stick logs Soil logs with strength, plastic limits, water contents Rock logs with recovery, RQD, geophysics Tabulated results Tabulated results with min, max, and average values Histogram representation of data sets showing min, max, baseline values, and data set signature 28

Behavioral Baselines How the ground will respond to the excavation process Open/non-pressurized shields Pressurized shields SEM/NATM Tunnelman s classification (firm, raveling, running, flowing, squeezing) Rock tunnels: blocky, cutterhead plucking, slaking, overstress-related spalling and slabbing 29

Pressurized Face Tunneling Cohesive soils Consistency Index Function of LL, PL, and WC Granular soils response to different foam dosage rates 30

Cohesive Soils: Consistency Index (Stickiness, Clogging) Ball, Young, Isaacson, Champa, Gause (2009). Research in Soil Conditioning for EPB Tunneling through Difficult Soils. Rapid Excavation and Tunneling Conference Thewes and Burger (2004) Clogging risks for TBM drives in clay. Tunnels & Tunnelling International, pp.28-31. June. 31

Granular Soils Slump Tests Different conditioners Foam Injection Ratios High Density Limestone Slurry Bentonite Polymer Ball, Young, Isaacson, Champa, Gause (2009). Research in Soil Conditioning for EPB Tunneling through Difficult Soils. Rapid Excavation and Tunneling Conference 32

Design-Build and PPP Delivery Owner provides reference design only Design-builder responsible for design and construction PPP (and some DB) contracts have attempted to reverse history: All-risk You bid it, you build it demand Recommendation: Same risk-sharing philosophy as DBB Owner owns the ground Subsurface risks are shared GBR: three-step development process 33

GBR Approach for D-B and PPP Contracts GBR-B By GBR-C Owner GBR-C By Contractor Design Constraints Geologic Conditions Ratified by Owner Design Bases GBR to the Contract Means/Methods Physical Baselines Behavior Baselines 34

Lessons Learned

Terms Avoid ambiguous words, such as could, may, or might if it might be encountered, Contractor can assume that it won t Avoid qualitative descriptors high groundwater table frequent occurrence of boulders occasional joints short stand-up time Use quantitative terms where possible that can be measured and verified in the field 36

Data vs Baselines What if data is not representative? insufficient borings (number, location) insufficient testing non-representative data distribution uncertainty in between the borings Previous experience is an excellent baseline Baselines can / should consider more than just the data 37

Clarify how the Baselines Apply Are the strength parameters intended for design or for excavation planning? To what areal extent do the baselines apply if baselines are shown anticipating a 30 ft diam shaft, but the Contractor excavates a 50 ft shaft, do the baselines apply? Boulder UCS how is UCS intended to be used within the project? Clogging potential of claystones vs sticky clays 39

Fit within the Contract Page-Turning Consistency Check 3 C s Clear Concise Consistent General Conditions GDR GBR Contract Drawings Technical Specifications Payment Provisions 40

Additional Reading ASCE Book Dept.,ISBN 13: 978-0-7844-0930-5 www.amazon.com 41

Future Developments

Future Developments International Tunnelling Association Working Group on Contractual Practices Developing guidance documents for international applications Currently re-writing FIDIC to incorporate GBRs How to adapt GBRs to other forms of contract around the world (NEC, French, Swiss, HK, Singapore) Now used in US, Canada, New Zealand, Australia, Switzerland, Chile, Hong Kong, Singapore, UK, India, Abu Dhabi, South Africa Gold Book - translated into Japanese Will be translated into Spanish and Portuguese Third Guidelines document in planning Conclusion: GBRs can work, and are gaining acceptance around the world 43

Future Challenges - PPP Some PPP advisors believe that they can shed all risk to the developer/concessionaire/contractor Single price, single completion date All risks to single party, no risk sharing Underground industry needs to educate PPP advisors as we have owners over the last 40 years Risk Management Conference, DC, November 28-29, 2017 will address these and other topics 44

Summary Underground construction is unique Different contracting strategies are warranted GBR approach not perfect, but it works Write reasonable baselines and enforce them Benefit from the many lessons learned 45

Thank You! randall.essex@mottmac.com