Modular Sediment Barriers (Instream)

Similar documents
Filter Tube Barriers (Instream)

Temporary Watercourse Crossing: Culverts

Storm Drain Inlet Protection

Construction Best Management Practices Handbook BEST MANAGEMENT PRACTICES

PART 1 GENERAL REQUIREMENTS

Storm Drain Inlet Protection for Construction Sites (1060)

Straw Bale Barrier. - Along the face and at grade breaks of exposed and erodible slopes to shorten slope length and spread runoff as sheet flow

SECTION EROSION AND SEDIMENTATION CONTROLS

Application for resource consent Form B Damming and diversion of water

KDOT TEMPORARY EROSION - CONTROL MANUAL

Straw Bale Barrier. Parallel to a roadway to keep sediment off paved areas

Lyon Creek Cedar Way Stormwater Detention Dam Operation and Maintenance Manual

TEMPORARY SEDIMENT TRAP CODE

Created by Simpo PDF Creator Pro (unregistered version) Asst.Prof.Dr. Jaafar S. Maatooq

BMP 6.4.4: Infiltration Trench

Outline of Presentation. Inspecting Construction Site BMPs. Inspector. Back to Basics. Erosion Control. Erosion Control

Erosion and Sediment Control

LAYING IBSTOCK CLAY PAVERS FOR PERMEABLE PAVEMENTS

Installation and Maintenance of Erosion Control BMPs

Erosion & Sedimentation Control Policy

Best Practices for Building High-Performance Resource Roads. Road Drainage. Developed by: The Roads and Infrastructure Group

Mobile Treatment Units

Erosion and Sediment Control Plan for a Timber Harvesting Operation

CHAPTER 3 Environmental Guidelines for WATERCOURSE CROSSINGS GOVERNMENT OF NEWFOUNDLAND AND LABRADOR DEPARTMENT OF ENVIRONMENT AND LABOUR

SPECIFICATIONS FOR PRECAST MODULAR BLOCK RETAINING WALL SYSTEM (revised 5/8/7)

The Good, The Bad, and The Ugly

INDEX FOR SPECIFICATIONS FOR REMOVING CULVERTS AND PLACING CULVERTS SCOPE... 1

North Umpqua Hydroelectric Project (FERC 1927) Erosion Control Plan Site Remediation/ Assessment Form

Chapter 5 Hydraulic Structures

DIVISION VII SOIL EROSION AND SEDIMENTATION CONTROL

B. Install storm drain inlet protection to prevent clogging of the stormsewer and sediment loads to downstream stormwater facilities or waterbodies.

C. Foundation stabilization for pipe and utility structures.

Redi Rock Specification and Installation Manual

GRASS-LINED CHANNEL (acre) CODE 840

PERMEABLE INTERLOCKING PAVERS

Standards for Soil Erosion and Sediment Control in New Jersey May 2012 STANDARD FOR SLOPE PROTECTION STRUCTURES. Definition

Module 4 Regulatory requirements for Land Disturbing Activities

B. Subsurface data is available from the Owner. Contractor is urged to carefully analyze the site conditions.

CITY OF FARGO SPECIFICATIONS EROSION AND SEDIMENT CONTROL

Pahiatua Waste Water Treatment Plant Wetland Erosion and Sediment Control Plan (ESCP)

SCOTTISH ENVIRONMENT PROTECTION AGENCY PREVENTION OF POLLUTION FROM CIVIL ENGINEERING CONTRACTS: GUIDELINES FOR THE SPECIAL REQUIREMENTS

Box Culverts. Easy to install, suitable for very shallow or deep fill, ideal for use in a wide variety of civil engineering applications.

DRAINAGE & DESIGN OF DRAINAGE SYSTEM

Builder s enviro guide

Concrete Slab-on-Ground

901 - TEMPORARY EROSION AND POLLUTION CONTROL SECTION 901 TEMPORARY EROSION AND POLLUTION CONTROL

4.8. Subsurface Infiltration

Installation Information 2016

E. STORMWATER MANAGEMENT

Understanding Stormwater Pollution Prevention Plans (SWPPPs) (SWPPPS)

Design and Installation Guidelines for Retaining Walls. 1 P age. Geo Products, LLC 8615 Golden Spike Lane Houston, TX Phone:

Construction Inspection Checklists

4 EXTREME FOUNDATION PANELS

E7. Taking, using, damming and diversion of water and drilling

Tasman Retaining Wall System

U.S. ARMY CORPS OF ENGINEERS. Little Rock District

LOW WATER CROSSINGS, fords, or drifts, as they

Town of Essex, Vermont January, 2017 Standard Specifications For Construction CHAPTER 3 EROSION AND SEDIMENT CONTROL

CITY UTILITIES DESIGN STANDARDS MANUAL

ESS EcoCell Ecological Tank Systems

Design Specifications & Requirements Manual

SECTION 19 - TRENCH EXCAVATION, BEDDING AND BACKFILL TABLE OF CONTENTS

SUBSURFACE INFILTRATION SYSTEM DESCRIPTION. Alternative Names: Sump, Drywell, Infiltration Trench, Infiltration Galleries, Leach Fields

Highway Drainage 1- Storm Frequency and Runoff 1.1- Runoff Determination

Med (3) Locator Information/GPS GPS shows 16 ft accuracy Lat: Impact Rating

4.8. Subsurface Infiltration

Construction of Dariali HEPP. Reinstatement Plan

Providing proper drainage system

INTERLOCK BETWEEN PARTICLES AT EACH PERFORATION

Sediment Basin. Fe= (Depends on soil type)

Section Soil Erosion Protection Tender No. [ ] Page 1

INSTRUCTIONS FOR SUBMITTING A COMMERCIAL SEWAGE DISPOSAL PERMIT APPLICATION

STORMCAPTURE. Installation Manual

SECTION TRENCHING & BACKFILLING

A.2.a Random Riprap... Table

SPECIFICATION FOR REINFORCED SOIL WALL

Minimum grade (%) Velocity at full flow (m s 1 )

Water Control Structures Selected Design Guidelines Alberta Environment Page 17-1

SECTION EXCAVATION AND BACKFILL FOR UTILITIES AND STRUCTURES

Visual Inspection Checklist

GRAY WATER RECYCLING SYSTEMS

SLAB ON GRADE Insul-Joint or Expansion Joint Material as Required by A/E Specifications AquaCheck Liquid Coating 400 (Waterproofing Membrane) with Aqu

CW 3615 RIPRAP TABLE OF CONTENTS

REROUTING DRAINAGE SYSTEMS

STREAMBANK RESTORATION DESIGN

CONCRETE SEGMENTAL RETAINING WALL SYSTEM

Section 8: Amended Soil Mounds. 8. Amended Soil Mounds

ITEM 506 Temporary Erosion Control

SAMPLE. Slab On Ground Construction. Carpentry - Residential Construction. Product Code: 5597

LANDSCAPE RETAINING WALLS

Homeowners Guide for Flood, Debris, and Erosion Control after Fires

4 EXTREME FOUNDATION PANELS

NOVEMBER 2016 MAGNUMSTONE. retaining walls installation manual

SECTION 19 - TRENCH EXCAVATION, BEDDING AND BACKFILL TABLE OF CONTENTS

Constructed Wetland Use in Nonpoint Source Control

Training on Roads for Water and Resilience

Sanitary and Environmental Engineering I (4 th Year Civil)

Anchorplex retaining wall construction guide. Building. Anchorplex. Retaining Wall Systems

INSTALLATION OF A STEP-SCREEN & VORTEX GRIT REMOVAL SYSTEM AT THE GRIFFITH SEWAGE TREATMENT PLANT. Peter Shanahan. Griffith City Council

Transcription:

Modular Sediment Barriers (Instream) INSTREAM PRACTICES Flow Control No Channel Flow Dry Channels Erosion Control Low Channel Flows Shallow Water Sediment Control High Channel Flows Deep Water Symbol Photo 1 Modular sediment barrier Photo 2 Modular unit Modular sediment barriers as discussed within this fact sheet are a modification of the Sediment Weir technique presented within a separate fact sheet. It should be noted that a patented design exists ( WaterClean FilterBale by Star Water Solutions) for individual modular units containing replaceable filter cartridges and wrapped in filter cloth. Key Principles 1. Most filtration systems have only a limited ability to capture and retain clay-sized particles; therefore, operators should not expect a significant change in the colour or clarity of water passing through the structure, especially when working in clayey soils. 2. Sediment trapping is primarily achieved by the filtration of minor flows passing through the structure, however, sedimentation may also occur within the settling pond formed by the modular weir during high flows. 3. The critical design parameter for optimising particle settlement is the surface area of the settling pond. The hydraulic properties of the modular barrier are critical in achieving the desired stage-discharge relationship to achieve optimum settling pond conditions. 4. The allowable flow rate through the modular barrier is governed by the maximum allowable hydraulic head, the allowable flow rate per module, and the number of modules. 5. Sediment filtration and gravity-induced sedimentation can be improved by filling the modular units with compost or special pollutant-adsorbing filter bags (e.g. WaterClean FilterBale ), or attach one or more filter tubes to the weir (Figure 4). Design Information The following design procedure may not always be applicable due to the absence of productspecific head vs discharge relationships. Catchments & Creeks Pty Ltd Version 1 - May 2010 Page 1

Wherever possible, product-specific head vs discharge relationships should be obtained from the manufacturer or distributor. Preference must always be given to head discharge relationships determined from prototype testing rather than estimations based on standard permittivity testing typically based on a hydraulic head of 100mm. Design Procedure 1. Determine the primary design discharge (Q) for water passing through the modular barrier just prior to flows overtopping the units (Figure 1). This is normally set equal to the expected dry weather flow rate of the stream. 2. Determine the weir design discharge (Q WEIR ) for overtopping flows (Figure 2). The appropriate design event may be set by the licence conditions (set by State or local authority), otherwise choose a stream flood frequency of at least 10 times the expected operational life of the structure, but at least a 1 in 1 year channel flow. 3. Determine the desirable settling pond surface area (A s ) from Table 1 based on the design discharge (Q). Where practical, a critical particle size of 0.05mm should be chosen. 4. Determine the maximum allowable water level within the settling pond. This may be based on-site constraints, or related to flooding and/or public safety issues. 5. Determine the required width of the modular barrier (W). The width (perpendicular to the direction of flow) may be limited by site constraints, or controlled by the hydraulic management of overtopping flows. The hydraulic analysis of overtopping flows is normally based on weir equations refer to the separate fact sheet Chutes Part 1: General Information. 6. Select the required crest elevation of the modular barrier to achieve the desired settling pond surface area. Ensure the weir crest is sufficiently below the maximum allowable water elevation to allow for expected overtopping flows (possibly an iterative design step). Operators should avoid circumstances where the instream settling pond needs to be excavated (expanded) to achieve the required surface area as this can cause undesirable channel damage. 7. Determine the maximum allowable head loss (ΔH) through the modular barrier. If flow conditions downstream of the barrier are such that there is little or no backwater effects during the design discharge (Q), then assume ΔH is equal to the height of the barrier (H). If flow depths downstream of the modular barrier are expected to be significant, then the maximum allowable head loss (ΔH) should be taken as the expected variation in water level across the barrier during the design discharge. 8. Select an appropriate design blockage factor (B.F.). 9. If the available pond surface area is insufficient to settle the required particle size, then the efficiency of the sediment trap may be improved by incorporating additional filtration system into the modular units or incorporating Filter Tubes (refer to Filter Tube Barriers) into the structure. Note the filter tube intake pipes need to be set at an elevation above the expected settled sediment depth. 10. Determine the rock size required for the splash pad downstream of the modular barrier. Figure 1 Minimum design flow condition Catchments & Creeks Pty Ltd Version 1 - May 2010 Page 2

Figure 2 Maximum design flow condition Figure 3 Typical installation of modular units on channel bed Incorporating filter tubes into a modular sediment barrier (Figure 4) requires the modification of some of the modular units to house the connection pipes; however, once modified, these units can be reused on similar installations. Figure 4 Typical arrangement of filter tubes incorporated into a modular sediment trap Catchments & Creeks Pty Ltd Version 1 - May 2010 Page 3

It is important to ensure a good contact is achieved between the modular units and the ground surface to prevent leakage. When installing a modular sediment barrier into a concrete-lined drain, benefit may be obtained from using 50mm soft foam as a water seal between the units and the concrete surface (Figure 5). Figure 5 Typical installation of modular sediment barrier within a concrete drain Settling pond: Table 1 provides the required pond surface area per unit flow rate for various nominated critical sediment particle sizes. The critical sediment particle size for a modular barrier may be assumed to be 0.05mm unless otherwise directed. The chosen critical sediment size should reflect the environmental values of the receiving water body and the expected weather conditions. Ideally, the settling pond should have a length (in the main direction of flow) at least three times its average width. If the pond length is less than three times its average width, then the pond area should be increase by 20% from the values presented in Table 1. It is noted that achieving the minimum pond surface area may not be practical in all circumstances, in which case a greater focus should be placed on the design of additional filter medium and/or the incorporation of filter tubes (Figure 4). Design standard Table 1 Minimum settling pond surface area per unit inflow rate Critical sediment size Surface area of settling pond per unit discharge (m 2 /m 3 /s) [1] (mm) 10 C [2] 15 C [2] 20 C [2] Allowable throughvelocity (m/s) 0.50 6 5.2 4.6 0.3 Type 3 sediment trap 0.20 38 33 29 0.3 0.15 67 60 52 0.3 Type 2 0.10 150 130 115 0.2 sediment trap 0.05 600 525 460 0.2 Type 1 0.04 940 820 720 0.2 sediment trap 0.02 3700 3230 2860 0.2 [1] Pond area is based on a rectangular pond operating with uniform inflow conditions across its width. [2] Assume a pond temperature the same as the typical rainwater temperature during the time of year when the pond is likely to be operating at capacity. Catchments & Creeks Pty Ltd Version 1 - May 2010 Page 4

Description A sediment filtration barrier formed from modular units wrapped in filter cloth. Purpose Modular sediment barriers are a specialist sediment control system developed for specialist installation purposes. Originally developed to allow the formation of a Sediment Weir type structure within concrete lined drainage channels during construction and maintenance activities. Used as an alternative to a straw bale barrier. Limitations In the absence of an appropriate internal filter media, the filter cloth provides limited capture of clay-sized particles. Advantages Light, reusable and durable. Disadvantages Can be difficult and time consuming to install. Special Requirements It is important to ensure a good contact is achieved between the modular units and the ground surface to prevent leakage. Various anchoring systems can be employed (including the use of timber stakes) so long as the system is able to suitable restrain the units from movement. Site Inspection Check for leakage under or around the sediment trap. Check for excessive sedimentation around the entrance to the filter tubes (if used). Check for sediment crusting on the surface of the filter fabric. Materials Modular units: open mesh stackable cells (e.g. Atlantis Matrix Tank Modules or milk crates). Filter Fabric: heavy-duty, needlepunched, non-woven filter cloth minimum bidim A44 or equivalent. Aggregate: 15 to 25mm clean gravel or aggregate. Foam: minimum 50mm thick, soft foam. Installation 1. Prior to commencing any works, obtain all necessary approvals and permits required to conduct the necessary works including permits for the disturbance of riparian and aquatic vegetation, and the construction of all permanent or temporary instream barriers and instream sediment control measures. 2. Refer to approved plans for location and installation details. If there are questions or problems with the location or method of installation contact the engineer or responsible on-site officer for assistance. 3. If there is flow within the watercourse or drainage channel at the time of construction of the modular barrier, then install appropriate downstream sediment control devices and/or flow diversion systems prior to construction of the barrier. Such measures should only be installed if considered appropriate for the local conditions, and only if their installation is judged to provide a net overall environmental benefit. 4. To the maximum degree practical, construction activities and equipment must not operate within open flowing waters. 5. Where practicable, divert all surface water runoff from the adjacent construction site into stable, undisturbed, vegetated areas adjoining the watercourse so as to minimise the direct discharge of sediment-laden water into flowing channel waters. 6. Ensure clearing and excavation of access paths and the banks and bed of the watercourse are limited to the minimum practicable. 7. If flow diversion systems cannot be installed, then conduct bank excavations by pulling the soil away from the channel. 8. If dispersive, highly unstable, or highly erosive soils are exposed, then priority must be given to the prompt stabilisation of all such areas. 9. Clear the foundation area of the modular barrier of woody vegetation and organic matter. Delay any channel disturbances up-slope of the barrier until the barrier is able to act as a suitable sediment trap. Catchments & Creeks Pty Ltd Version 1 - May 2010 Page 5

10. Using minimum 2.4m wide fabric, lay the fabric on the ground with at least 200mm of the fabric placed upstream of the barrier. 11. If more than one sheet of fabric is used, then overlap the filter fabric a minimum of 600mm at all joints. 12. Place the modules end to end of the fabric with the upstream edge aligned with the down-slope edge of the trench. 13. Fold the remainder of the filter cloth over the modular units such that the end of the fabric extends at least 200mm upstream of the barrier. 14. Secure stakes immediately up-slope and downstream of each modular unit. The upstream stake should be used to both secure the modular units and anchor the fabric. 15. Using either a timber cross member or crisscrossed wire, secure the modular units to the stakes such that vertical movement is prevented. 16. Use a continuous layer of sand or aggregate to hold the fabric firmly on the channel bed. 17. Use geotextile fabric and/or minimum 200mm diameter rock to form a splash pad that extends downstream from the barrier a distance at least twice the height of the barrier. Alternative requirements for placement within a concrete channel: 1. Place a continuous layer of minimum 50mm soft foam across the channel at the proposed location of the sediment barrier. 2. Cover the foam with filter fabric before placing the central core of tightly packed modules. Sufficient length of fabric should exist upstream of the barrier to allow the fabric to eventually be placed over the modules to form a continuous sediment barrier. Overlap the filter fabric a minimum of 600mm at all joints, with the upstream strip laid over the downstream strip. 3. Place the modules end to end across the channel, then fold the filter cloth over the modules. 4. Place a solid timber beam on top of the sediment barrier and anchor the beam to the channel bed using rock bolts and heavy-duty wire ties. Maintenance 1. Inspect the modular barrier daily and after any changes in stream flow. Make repairs as needed. 2. Inspect the barrier for undercutting or undesirable seepage flows. 3. If flow through the structure is reduced to an unacceptable level, the filter medium should be removed and replaced. 4. If a greater degree of water treatment (filtration) is required, extra geotextile filter fabric should be placed over the upstream face of the structure. 5. Check the structure and surrounding channel banks for damage from overtopping flows and make repairs as necessary. 6. Immediately replace any rock displaced from the downstream splash pad. 7. Remove sediment and restore original sediment storage volume when collected sediment exceeds 10% of the specified storage volume. 8. Dispose of sediment and debris in a manner that will not create an erosion or pollution hazard. Removal 1. The modular barrier should be removed as soon as possible after they are no longer needed. 2. If there is flow within the watercourse or drainage channel at the time of removal of the modular barrier, then install appropriate instream sediment control devices and/or flow diversion systems prior to its removal. 3. All settled sediment upstream should be removed prior to removal of the modular barrier. Dispose of the sediment in a manner that will not create an erosion or pollution hazard. 4. Remove all materials used to form the modular barrier including the geotextile filter cloth and recycle or dispose of in a manner that will not create an erosion or pollution hazard. 5. Restore the watercourse channel to its original cross-section, and smooth and appropriately stabilise and/or revegetate all disturbed areas. Catchments & Creeks Pty Ltd Version 1 - May 2010 Page 6