Alec Kimber Australian Nuclear Science & Technology Organisation

Similar documents
A Radiation Protection Perspective- Decommissioning of the Moata Reactor. Biological Shield Dismantling

ANSTO s POLICY for MOATA & HIFAR. Prepared by John Rowling November 2007

PLAN FOR MOATA REACTOR DECOMMISSIONING, ANSTO

RESEARCH REACTOR FRJ-1 (MERLIN) THE CORE STRUCTURES OF THE REACTOR BLOCK ARE DISMANTLED

Best practices for preparing vessel internals segmentation projects

Decommissioning Group Ketut Kamajaya

Pham Hoai Phuong and Pham Van Lam NUCLEAR RESEARCH INSTITUTE, VAEC

PRESENT STATUS OF LEGAL & REGULATORY FRAMEWORK AND DECOMMISSIONING PLANNING FOR DNRR. Prepared by NUCLEAR RESEARCH INSTITUTE, VAEC.

Mark Ramsay BEng MSc MSRP, CRadP

International Perspective on non-heu Mo-99 Production

ADVANCED DECOMMISSIONING COSTING CALCULATION TOOLS FOR PILOT VIENNA TRIGA MARK-II RESEARCH REACTOR

New Swedish Regulations for Clearance of Materials, Rooms, Buildings and Land Efraimsson, Henrik Swedish Radiation Safety Authority, SWEDEN

Environmental Regulator's RWA Syllabus mapped to PHE's RPTS courses. RPTS coverage EA. No

C. Kennes - C. Mommaert - M. Van haesendonck (Bel V) H. Libon - A. De Backer (Belgonucleaire) Decommissioning of Belgonucleaire MOX plant

Planning for the Decommissioning of the ASTRA-Reactor

Decommissioning Planning

Development of Decommissioning Plan in Indonesia

2007 ANS Topical Meeting on Decommissioning, Decontamination and Reutilization September 2007, Chattanooga, TN, United States of America

STRUCTURAL RADIATION SAFETY AT A NUCLEAR FACILITY

The EnBW Strategyfor Decommissioningand DismantlingofNuclearPower Plants»

IAEA SAFETY STANDARDS for protecting people and the environment. Predisposal Management of Radioactive Waste from Nuclear Fuel Cycle Facilities

Experiences on a Regulatory Clearance of the Radioactive Wastes at KAERI

WM'99 CONFERENCE, FEBRUARY 28 - MARCH 4, 1999 RESEARCH REACTOR DECOMMISSIONING POTENTIAL BACK END OPTIONS

RADIOACTIVE GRAPHITE MANAGEMENT AT UK MAGNOX NUCLEAR POWER STATIONS. G. HOLT British Nuclear Fuels plc, Berkeley, United Kingdom 1.

Legislative Framework for the Regulation of Decommissioning at Egypt. Prof. Dr. Farouk M. A. Rahman

Applicability of EPRI Decommissioning Pre-Planning Manual to International Decommissioning Projects

IAEA SAFETY STANDARDS for protecting people and the environment. Predisposal Management of Radioactive Waste from Nuclear Fuel Cycle Facilities

Uranium mining legal and regulatory framework

The Chernobyl shelter industrial site, where the New Safe Confinement will be constructed (Photos: PMU)

Decommissioning of Nuclear Facilities. Waste Management

RESEARCH REACTOR DECOMMISSIONING PLAN

Packaging for Transport of the ILW-LL of EDF First Generation Power Plant Dismantling 16517

PROGRESS ON ANSTO S OPAL REACTOR PROJECT AND ITS FUTURE IMPORTANCE AS THE CENTREPIECE OF ANSTO S FACILITIES

Decommissioning and Site Release Problems for Georgian Nuclear Research Reactor IRT-M

Ghent University Research Reactor THETIS: Unloading and Conditioning of Spent Fuel

Berkeley Boilers Project. Studsvik Symposium April 2014

AUSTRALIA S NATIONAL RADIOACTIVE WASTE MANAGEMENT STRATEGY

Australia s Regulation of Low and Intermediate Level Radioactive Waste

Radiation Protection Adviser (RPA) Register

STURGIS Barge Decommissioning Project

Preliminary Lessons Learned from the Fukushima Daiichi Accident for Advanced Nuclear Power Plant Technology Development

Radiation Protection of the Public and Protection of the Environment

during Normal Operations

- 1 - Ingenieurgesellschaft für wissenschaftlich technischen Umweltschutz

Decommissioning three main strategies: Immediate dismantling, Safe enclosure (Deferred dismantling), Entombment

Decommissioning of Nuclear Facilities. The Decommissioning Process. Lesson Objectives. Decommissioning. Decontamination. Decommissioning Objective

NUCLEAR FUEL AND REACTOR

Radioactive Waste Management at the NCSR Demokritos - Greece

Nuclear decommissioning challenges in the UK a rough guide for roboticists

Optimization of Reactor Pressure Vessel Internals Segmentation in Korea

TOPICAL SESSION MANAGEMENT OF DECOMMISSIONING WASTES

Radiation Protection and ALARA Program Highlights at Ontario Power Generation

SAFETY ANALYSIS AND ENVIRONMENTAL IMPACT ASSESSMENT FOR FOTON RTC DECOMMISSIONING

SoftWall Enclosures. Flexible In-plant Enclosure Systems An Excellent Alternative to Rigid Wall Systems

Peer Review of the RPII s Environmental Monitoring Programme Foundation Document. F. Exposure from Natural Sources in Ireland

News this quarter. Environment, Safety&Health Quarterly Performance Report. Reporting period: 1 April to 30 June 2015

Setting up the Medical Cyclotron Facility at Cochin, Kerala. M.R.A. Pillai Ph.D; D.Sc Molecular Cyclotrons Ltd. Cochin

WM2012 Conference, February 26 March 1, 2012, Phoenix, Arizona, USA

Radiation Environment and Shielding Design Optimization at MEIC

Occupational Radiation Protection in Radioactive Waste Management

BAE SYSTEMS Marine Ltd s strategy for the decommissioning of the Barrow nuclear licensed site

WM2014 Conference, March 2 6, 2014, Phoenix, Arizona, USA

Decommissioning Worldwide and NEA Activities

Low-Level Waste and Radiation Management

Joint ICTP-IAEA School on Nuclear Energy Management. 15 July - 3 August, Lecture Notes. I. Mele IAEA, Vienna, Austria

Nuclear Aircraft Carrier Inactivation Approach for Waste Management and Exposure Reduction 14201

P. Brennecke, S. Steyer Bundesamt für Strahlenschutz Willy-Brandt-Strasse 5, D Salzgitter, Germany

Joint ICTP-IAEA Essential Knowledge Workshop on Deterministic Safety Analysis and Engineering Aspects Important to Safety. Trieste,12-23 October 2015

WM2015 Conference, March 15-19, 2015, Phoenix, Arizona, USA

DRAFT National Framework for Radioactive Waste Management

THE ROLE OF THE WORLD'S LARGEST INTERIM STORAGE FOR WASTE AND FUEL WITHIN THE DECOM PROJECT OF 6 WWER REACTORS IN GREIFSWALD AND RHEINSBERG (GERMANY)

TROJAN DECOMMISSIONING STATUS. OPUC Meeting March 8, 2005 (draft)

S. Reyes. Lawrence Livermore National Laboratory. ARIES Meeting April 22-23, 2002 U. Wisconsin, Madison

Lessons Learned from Shut-Down to Decommissioning Plan at the Army Pulse Radiation Facility

RADIOLOGICAL PROTECTION

ENVIRONET Network on Environmental Management and Remediation. Terms of Reference

Experiments Carried-out, in Progress and Planned at the HTR-10 Reactor

German contribution on the safety assessment of research reactors

KIPT ADS Facility. Yousry Gohar 1, Igor Bolshinsky 2, Ivan Karnaukhov 3. Argonne National Laboratory, USA 2. Idaho National Laboratory, USA 3

Irradiated Hardware Characterization and Packaging During Decommissioning of the Ford Nuclear Reactor at University of Michigan

Gerhart Grinanger, NOELL GmbH, Postfach 6260, D-8700 Wizrzburg, Germany

Safety Assessment for Decommissioning of a Nuclear Power Plant

Status of the FRM-II Project at Garching. Hans-Jürgen Didier, Gunter Wierheim Siemens AG, Power Generation (KWU), D Erlangen

M. Laraia International Atomic Energy Agency Wagramerstrasse 5 P.O. Box 100 A-1400 Vienna Austria

Dismantling Techniques applied at MZFR

Excellence in Control of Radiation Exposures

Dismantling of nuclear facilities in France: what is at stake?

Texas A&M University, Department of Nuclear engineering, Ph.D. Qualifying Examination, Fall 2016

Radiation becomes dangerous when it becomes concentrated in some way by human activity.

Services for professional procurement. Be better informed, make better decisions. RISQS Audit Questions Network Rail On-Track Plant Operations

The Evolution of System Safety in the Canadian Nuclear Industry

2/14/2017. Introduction & Objectives. Radiation Safety Program Structure. Massachusetts DPH Radiation Control Program

Transporting radioactive material - Guidance on radiation and contamination monitoring requirements, and determining a Transport Index

ANSTO Nuclear Medicine: Reliable and Timely Mo-99 Supply Globally

Radiation Protection Challenges associated with the dismantling of Nuclear Power Plant

Accidental Melting of Radioactive Sources

EVALUATION OF SAFETY CULTURE IN WANO PRE-STARTUP REVIEWS

ACCESS CONTROL AND WORK AREA SETUP RCT STUDY GUIDE State responsibilities in using or initiating a RWP.

Niagara Falls Storage Site Safety Measures During Remediation

Interim Guidance on the Regulation of In-situ Disposals of Radioactive Waste and Residual Radioactive Contamination on Nuclear Authorised Premises

Transcription:

Decommissioning and Dismantling of the Moata Reactor Alec Kimber Australian Nuclear Science & Technology Organisation

A History of Moata Constructed at ANSTO in 1961 ARGONAUT type reactor Built as a 10 kw reactor, but modified in 1972 to 100 kw Graphite moderator / reflector Cooled by light water Shielding - high density and low density concrete

The Moata Reactor From 1961 to 1995: Neutron radiography Training Soil analysis Cancer treatment research Quality Control for HIFAR

Shutdown & Decommissioning Shutdown after 4,519 start-ups 1995 1997 1998 2008 2009 2010 Fuel unloaded Primary coolant (light water) drained Reactor Control System removed 2000 Decommissioning Licence Planning for Moata Dismantling Two phases of dismantling: Preliminary Dismantling the removal of the internal components of the reactor, including the steel core structures, graphite moderator and beam line facilities Structural (Biological Shield) Dismantling the cutting and removal of the concrete shielding and the floor area below the shielding. Containment tent installed Preliminary Dismantling July 2009 Biological Shield Dismantling began Biological Shield Dismantling Complete

Characterisation Survey Core samples extracted Radiological surveys carried out Determine dose rates Allow for waste reduction Data used to prepare a dose estimate for dismantling Internal reactor components Biological shield Radiological surveys allowed estimation of maximum individual and collective doses

Reactor Internals - Dismantling Control rod & drive assemblies Graphite moderator core & N, S, E & W cavities [approx 12 tonne] Aluminium core tanks Pipe work Steel framework graphite support Gamma curtain lead sheet [approx 750kg]

Structural (Biological Shield) Dismantling MOATA housed in a building used for AMS for C-14 dating A containment tent with HEPA filtered extraction system built around the reactor

Biological Shield - Dismantling

Challenge 1 An Australian first Challenge Nothing similar had ever been attempted previously Challenging to project team Slow start Mitigation Identifying and developing on-site expertise Explored use of external companies estimates: Turn key ($12M) Implementation ($8M) Partnership ($6M) Detailed planning we can do this

Challenge 2 Regulatory Challenge ARPANSA had never dealt with a reactor decommission / dismantle Regulatory caution Mitigation Communication Start early (Identification of requirements) Continuous Detailed planning Development of knowledge Developing organisational confidence They can do this

Challenge 3 Internal management Challenge Does ANSTO have the skills? Never undertaken a reactor decommission Easy to be less constructive Mitigation Project champion Staff training and expertise Detailed planning Development of knowledge Developing organisational confidence ANSTO can do this Stakeholder management Early communication Continual information

Challenge 4 External interest Challenge Pressures from external interest groups and stakeholders Politicians / government ANSTO Board IAEA Public Media Mitigation Communication Continuous Factual Managed Detailed planning Development of knowledge Developing organisational confidence Lets see if ANSTO can do this

Challenge 5 Project financial Challenge Decommissioning estimate developed from UK and US reactor dismantling Inherited a budget (AUS$3.8M) Minimal contingency Decommission within budget Mitigation Earned value analysis employed Job number allocation and control Early communication of cost overrun

Challenge 6 Tandem Accelerator Challenge Adjacent Tandem accelerator Sensitivity to carbon14 (1x10-14 ) [12 Tonne of graphite in MOATA] Risk to future of carbon dating program and research at LH Mitigation Localised tent and extract Fully enclosed and tented work area Double skinned Air inflow through tent skin Extract filtration Primary dust Secondary HEPA extract filtration

Challenge 7 Technology Challenge What methods were applicable? What technology was available and suitable? Lack of knowledge by project team Mitigation Research into methods Consultant advice sought Detailed planning Development of knowledge Developing organisational confidence ANSTO can do this

Challenge 8 Drawing inaccuracies Challenge 1950 s drawings Imperial measurements Mitigation Expert draughtsman 3D CAD drawings produced Physical 3D model Uncertainty of asbuilt drawings Unknown details Known inaccuracies

Challenge 9 Radiation protection Challenge Doses likely to be encountered Shielding methods Self shielding Distance No dose-sharing ALARA Mitigation Characterisation Dose modelling Physical measurements Detailed planning Tooling PPE Shielding Contingency planning What if? Identification & removal of hottest items

Challenge 10 Safety Challenge Industrial safety Working at heights Wire cutting Manual handling Dust Mechanical plant Mobile crane Excavator Mitigation In-house safety expert OHS + Radiation PPE 3-day contractor safety training Daily safety checks walkabout Daily safety talks Contractor ANSTO personnel

Interfacing Challenge 11 Contractor Challenge ANSTO safety procedures ANSTO systems Fear of radiation Understanding the decommissioning process An Australian first Keeping the cost realistic engagement Mitigation Initial contractor evaluation Presentation to eligible contractors Detailed Specification Responsibilities table detailing contractor interfaces with ANSTO Final contractor evaluation

Challenge 12 Work systems methodology Challenge Day to day safe working Contamination minimisation Waste clearance methods Communication Mitigation Site function plan Safe Work Method Statements Commitment to safety Full time, on-site supervisor Daily safety checks ANSTO supplied PPE Health physics on call Daily safety meetings Weekly project meetings

Challenge 13 Waste removal and Challenge clearance Mitigation Waste handling processes Waste types Quantities Handling and transport Packaging Availability of staff Project vs operational needs Clearance processes Methods & Instrumentation location Knowledge of reactor Materials, characterisation, size and location Understand demolition processes Consultant advice Contractor advice Consult Waste Management Team Utilise suitable methods Model and calibrate instruments and processes

Challenge 14 Records Challenge Preparation (1995-2000) Operational records, drawings Preliminary planning incl DP Dismantling Project Project planning records Daily project records (log books, waste assessment and clearance, Health Physics) A story to be shared Mitigation Identified and collected all available historical records Team included former operators Engaged technical writer who also collated records Waste management group - Radioactive Waste Tracking System Contractor provides records of all wastes cleared from site. Project DVD

Final Survey Dose surveys carried out in grid pattern as per original survey Acceptance criteria of 0.5uSv/hr was met Samples taken and analysed for activity < clearance criteria Guides to determine the exemption and clearance criteria for the site IAEA No. RS-G.1.7 ARPANSA Reg 1999, Schedule 2, Part 2

Radiation Protection - outcomes Dismantling was completed safely and without incident Dose estimates higher than those recorded Overly conservative estimations Very detailed planning [ what if scenarios ] Concrete dismantling self shielding and greater distance Time taken to dismantle less than anticipated No surface or airborne contamination detected throughout the project No personal contamination events

Radiation Protection Dose results Estimated doses vs. actual doses: Dose ANSTO Estimated ARPANSA Constraint ANSTO Constraint Actual Collective 10,400 personμsv 13,000 personμsv 10,400 personμsv 1,679 personμsv Max. Individual 1444 μsv 1750 μsv 1500 μsv 252 μsv Daily - - 50μSv 46μSv (max)

Project - lessons learned Bridging the gap Telling the safety story in a way that the contractor can easily understand Documents The level playing field use of a single set of documents suitable for all purposes (regulator, contractor etc) Stakeholder A project champion Required to ensure early commitment from departments Operational v Project needs project requires rapid responses to maintain workflow. Thorough planning leads to success and constant review!

Project Achievements Setting Trends Ownership / Extending ANSTO department capabilities Procurement Adjusting their mandate to be more responsive to project requirements Survived it being a very high profile project Developed high quality stakeholder communication Regulatory approval and commendation Internal & External QA Audit incl Environmental Awards including National Best Small Project 2010 (Australian Institute of Project Management)

Project Achievements Site Function Plan Engagement of expert advice Comprehensive understanding of the project scope High quality specification of works Enhanced ability to deal with demolition contractor Significant savings on demolition contract Highly informed project team Development of in-house expertise Development of confidence for future needs Final cost within approximately 10% of budget

Project Achievements 3D Modelling including Physical Model Extremely powerful visualisation tool Aid to contractor understanding Enabled good understanding of the tasks ahead

Physical Model Project Achievements

Moving forward to HIFAR Experienced and highly informed project team in-house expertise now developed Engagement of expert advice Have a comprehensive understanding of the project scope Enhanced ability to deal with demolition contractor Organisation + project confidence in capabilities Proceed with detailed planning whilst local knowledge is available